PRESUPUESTO

obra : DISEÑO DE UNA BOCATOMA (BRAZO DEL RÍO CHANCAY)


¤ Item Descripción Und. Metrado Precio (S/.) Parcial (S/.)

1.0 OBRAS PRELIMINARES


1.1 CARTEL DE OBRA und 1.00 412.36 412.36
1.2 CAMPAMENTO PROVISIONAL PARA OBRA Y SUPERVISION GLB 1.00 350.00 350.00
1.3 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y HERRAMIENTAS GLB 1.00 2,230.00 2,230.00
2.0 CAPTACION
2.1 BOCATOMA CON BARRAJE FIJO Y MOVIL
2.1.1 TRAZO, NIVELACION Y REPLANTEO m2 74.40 1.14 84.82
2.1.2 ENCAUZAMIENTO PARA BOCATOMA m3 14.40 40.27 579.89
2.1.3 EXCAVACION MANUAL EN TERRENO ROCOSO m3 24.48 55.44 1,357.17
2.1.4 SOLADO PARA ESTRUCTURAS (F'C=100KG/CM2) m3 6.64 204.82 1,360.00
2.1.5 ACERO DE REFUERZO Fy=4200KG/CM2 Ø1/2" kg 145.55 3.26 474.49
2.1.6 ACERO DE REFUERZO Fy=4200KG/CM2 Ø3/8" kg 54.11 3.95 213.73
2.1.7 ACERO DE REFUERZO Fy=4200KG/CM2 Ø3/4" (ESCALERA TIPO GATO) kg 18.90 3.26 61.61
2.1.8 ENCOFRADO Y DESENCOFRADO m2 28.70 21.08 605.00
2.1.9 CONCRETO F'C=140 KG/CM2 + 40% P.G. (TAM. MAX. 8") m3 14.40 250.49 3,607.06
2.1.10 CONCRETO FC=175 KG/CM2 + 25% P.G (TAM. MAX. 6'') m3 5.81 282.71 1,642.55
2.1.11 CONCRETO F'c=210KG/CM2 + 40% P.G. (TAM. MAX. 8'') m3 3.35 324.09 1,085.70
2.1.12 CONCRETO FC=175 KG/CM2 m3 0.71 310.03 220.12
2.1.13 MAMPOSTERIA DE PIEDRA EMBOQUILLADA CON CONCRETO m2 36.00 82.64 2,975.04
2.1.14 BARANDA DE FIERRO GALVANIZADO D=2'' m 5.07 67.08 340.10
2.1.15 COMPUERTAS METALICAS TIPO ARMCO DE 1.83m X 1.83m und 1.00 1,747.29 1,747.29
2.1.16 COMPUERTAS METALICAS TIPO ARMCO DE 0.95m X 0.70m und 1.00 1,884.09 1,884.09
2.1.17 MIRAS LINNIMETRICAS m 1.90 126.15 239.69
2.1.18 JUNTA DE DILATACION CON WATER STOP 6'' m 2.60 43.96 114.30
2.2 CAPTACION
2.2.1 TRAZO, NIVELACION Y REPLANTEO KM 0.04 978.26 39.13
2.2.2 DEMOLICION Y ELIMINACION DE PAÑOS DETERIORADOS DEL CANAL m3 8.40 56.65 475.86
2.2.3 SOLADO PARA ESTRUCTURAS (F'C=100KG/CM2) m3 5.04 204.82 1,032.29
2.2.4 ACERO DE REFUERZO Fy=4200KG/CM2 Ø3/8" kg 720.56 3.95 2,846.21
2.2.5 ENCOFRADO Y DESENCOFRADO m2 58.80 21.08 1,239.50
2.2.6 CONCRETO FC=175 KG/CM2 m3 10.92 310.03 3,385.53
2.2.7 JUNTA DE DILATACION CON WATER STOP 6'' m 2.60 43.96 114.30
2.3 TRANSICION 0.00
2.3.1 TRAZO, NIVELACION Y REPLANTEO m2 3.30 1.14 3.76
2.3.2 DEMOLICION Y ELIMINACION DE PAÑOS DETERIORADOS DEL CANAL m3 0.25 56.65 14.16
2.3.3 SOLADO PARA ESTRUCTURAS (F'C=100KG/CM2) m3 0.83 204.82 170.00
2.3.4 ACERO DE REFUERZO Fy=4200KG/CM2 Ø3/8" kg 46.38 3.95 183.20
2.3.5 ENCOFRADO Y DESENCOFRADO m2 4.00 21.08 84.32
2.3.6 CONCRETO FC=175 KG/CM2 m3 1.07 310.03 331.73
2.3.7 JUNTA DE DILATACION CON WATER STOP 6'' m 2.90 43.96 127.48
31,632.48
PRESUPUESTO

SON : VEINTISIETE MIL TRESCIENTOS DOS CON SESENTA Y SEIS Y 00/100 NUEVOS SOLES
COSTO DIRECTO

6ASTOS GENERALES (6.00 %)

UTILIDAD (8.00 %)

SUB TOTAL

IGV (19.00 %)

VALOR REFERENCIAL

SUPERVISION Y LIQUIDACION (3.00%)

CAPACITACION

PRESUPUESTO TOTAL
SON : UN MILLON CUATROCIENTOS VEINTICINCO MIL CUATROCIENTOS CUARENTA Y 00/100 NUEVOS SOLES
1,012,983.63

60,779.02

81,038.69

-----------------

1,154,801.34

219,412.25

============

1,374,213.59

41,226.41

10,000.00

============

1,425,440.00