Está en la página 1de 5

UNIVERSIDAD NACIONAL SAN CRISTOBAL DE HUAMANGA

COSTOS Y PRESUPUESTOS IC-549

Hoja de Metrados
ITEM
03.00
03.01
03.01.01

DESCRIPCION

UND

# VECES

ANCHO

LARGO

ALTO

PARCIAL

TOTAL

ARQUITECTURA
MUROS Y TABUIQUES DE ALBAILERIA
MUROS DE LADRILLO KING KONG CARAVISTA, DE CABEZA

m2

457.41

primera planta
EJE C-C

1.00

7.30

2.65

EJE D-D, G-G y J-J

3.00

0.70

2.65

19.35
5.57

EJE F-F, I-I y L-L

3.00

7.30

2.15

47.09

EJE 11-11

3.00

area

7.97

23.91

EJE 9-9

3.00

area

7.97

23.91

EJE 9-9 / C-C y D-D

3.00

area

5.87

17.61

EJE 11-11 / C-C y D-D

3.00

area

3.09

9.27

EJE A-A

2.00

area

7.74

15.48

EJE B-B

1.00

area

9.08

9.08

ENTRE EJE B-B y C-C

1.00

area

5.51

5.51

EJE 9-9

1.00

area

8.33

EJE 10-10

1.00

EJE 11-11

1.00

servicios higienicos

3.50
area

8.33
2.65

11.60

9.28
11.60

segunda planta
EJE C-C, F-F, I-I y L-L

4.00

7.30

2.95

EJE D-D, G-G y J-J

3.00

0.70

2.95

EJE 9-9

6.00

area

6.40

EJE 9-9 / C-C y D-D

3.00

area

3.74

11.22

EJE 11-11 / C-C y D-D

3.00

area

7.68

23.04

EJE 11-11

6.00

2.98

86.14
6.20
38.40

1.10

19.67

servicios higienicos

03.01.02

03.02
03.02.01

EJE A-A

2.00

area

8.85

17.70

EJE B-B

1.00

area

10.10

10.10

ENTRE EJE B-B y C-C

1.00

area

6.15

6.15

EJE 9-9

1.00

area

9.40

EJE 10-10

1.00

EJE 11-11

1.00

PARAPETOS (placa de concreto, E=10cm)

3.50
area

9.40
2.95

13.10

10.33
13.10

m2

149.00

segunda planta

1.00

38.70

0.80

30.96

azotea

1.00

101.00

0.80

80.80

escalera

8.00

4.90

0.95

37.24

REVOQUES Y REVESTIMIENTOS
TARRAJEO EN INTERIORES, e=1.5 cm

m2

457.41

primera planta
EJE C-C

1.00

7.30

2.65

EJE D-D, G-G y J-J

3.00

0.70

2.65

19.35
5.57

EJE F-F, I-I y L-L

3.00

7.30

2.15

47.09

EJE 11-11

3.00

area

7.97

23.91

EJE 9-9

3.00

area

7.97

23.91

EJE 9-9 / C-C y D-D

3.00

area

5.87

17.61

EJE 11-11 / C-C y D-D

3.00

area

3.09

9.27

EJE A-A

2.00

area

7.74

15.48

EJE B-B

1.00

area

9.08

9.08

EJE B-B / 11-11 y 10-10

1.00

area

5.51

5.51

EJE 9-9

1.00

area

8.33

EJE 10-10

1.00

EJE 11-11

1.00

servicios higienicos

3.50
area

8.33
2.65

11.60

9.28
11.60

segunda planta
EJE C-C, F-F, I-I y L-L

4.00

7.30

2.95

EJE D-D, G-G y J-J

3.00

0.70

2.95

EJE 9-9

6.00

area

6.40

EJE 9-9 / C-C y D-D

3.00

area

3.74

11.22

EJE 11-11 / C-C y D-D

3.00

area

7.68

23.04

EJE 11-11

6.00

Pgina 1

2.98

86.14
6.20
38.40

1.10

19.67

ITEM

DESCRIPCION

UND

# VECES

ANCHO

LARGO

ALTO

PARCIAL

EJE A-A

2.00

area

8.85

17.70

EJE B-B

1.00

area

10.10

10.10

EJE B-B / 11-11 y 10-10

1.00

area

6.15

6.15

EJE 9-9

1.00

area

9.40

EJE 10-10

1.00

EJE 11-11

1.00

TOTAL

servicios higienicos

03.02.02

TARRAJEO EN COLUNMAS, e=1.5 cm

3.50
area

9.40
2.95

13.10

10.33
13.10

m2

242.48

primera planta
C-1

12.00

perimetro

1.4

2.65

44.52

C-2

6.00

perimetro

1.8

2.65

28.62

C-3

2.00

perimetro

1.5

2.65

7.95

C-4

4.00

perimetro

1.05

2.65

11.13

C-5

6.00

perimetro

1.25

2.65

19.88

C-6

1.00

perimetro

1.00

2.65

2.65

C-1

12.00

perimetro

1.4

2.95

49.56

C-2

6.00

perimetro

1.8

2.95

31.86

C-3

2.00

perimetro

1.5

2.95

8.85

C-4

4.00

perimetro

1.05

2.95

12.39

C-5

6.00

perimetro

1.25

2.95

22.13

C-6

1.00

perimetro

1.00

2.95

2.95

segunda planta

03.02.03

TARRAJEO EN VIGAS, e=1.5 cm

m2

343.98

primera planta
V-2101
En voladizo
V-2102
En voladizo
V-2103
En voladizo

3.00

perimetro

0.85

8.90

3.00

perimetro

1.05

2.50

22.70
7.88

3.00

perimetro

0.85

8.90

22.70

3.00

perimetro

1.05

2.50

7.88

1.00

perimetro

0.85

8.90

7.57

1.00

perimetro

1.00

2.50

2.50

V-2104
En voladizo
V-2105

2.00

perimetro

0.25

1.25

0.63

12.00

perimetro

1.05

2.98

37.55

6.00

perimetro

1.05

2.30

14.49

V-2106

4.00

perimetro

0.95

3.70

14.06

V-2107

1.00

perimetro

0.92

29.55

27.19

V-2108

1.00

perimetro

0.15

1.25

0.19

V-2109

1.00

perimetro

0.85

2.50

2.13

V-2110

1.00

perimetro

1.15

2.70

3.11

V-2111

1.00

perimetro

0.55

2.65

1.46

3.00

perimetro

0.85

8.90

22.70

3.00

perimetro

1.05

2.50

7.88

3.00

perimetro

0.85

8.90

22.70

3.00

perimetro

1.05

2.50

7.88

1.00

perimetro

0.85

8.90

7.57

1.00

perimetro

1.00

2.50

2.50

segunda planta
V-2101
En voladizo
V-2102
En voladizo
V-2103
En voladizo
V-2104
En voladizo
V-2105

03.02.04

03.02.05

2.00

perimetro

0.25

1.25

0.63

12.00

perimetro

1.05

2.98

37.55

6.00

perimetro

1.05

2.30

14.49

V-2106

4.00

perimetro

0.95

3.70

14.06

V-2107

1.00

perimetro

0.92

29.55

27.19

V-2108

1.00

perimetro

0.15

1.25

0.19

V-2109

1.00

perimetro

0.85

2.50

2.13

V-2110

1.00

perimetro

1.15

2.70

3.11

V-2111

1.00

perimetro

0.55

2.65

1.46

segunda planta

1.00

2.00

38.70

0.80

61.92

azotea

1.00

2.00

101.00

0.80

161.60

escalera

8.00

2.00

4.90

0.95

74.48

TARRAJEO EN MUROS DE CONCRETO

m2

VESTIDURA DE DERRAMES

298.00

452.84

primera planta
V-1

6.00

perimetro

8.26

49.56

V-2

6.00

perimetro

9.66

57.96

V-3

14.00

perimetro

2.40

33.60

V-4

2.00

perimetro

6.40

12.80

P-1

5.00

perimetro

7.90

39.50

P-2

5.00

perimetro

5.40

27.00

P-3

1.00

perimetro

6.00

6.00

Pgina 2

ITEM

DESCRIPCION

UND

# VECES

ANCHO

LARGO

ALTO

PARCIAL

V-1

6.00

perimetro

8.26

49.56

V-2

6.00

perimetro

9.66

57.96

V-3

14.00

perimetro

2.40

33.60

V-4

2.00

perimetro

6.40

12.80

P-1

5.00

perimetro

7.90

39.50

P-2

5.00

perimetro

5.40

27.00

P-3

1.00

perimetro

6.00

6.00

TOTAL

segunda planta

03.02.05

03.02.06

BRUAS

119.46

Corredor de aulas

1.00

103.38

103.38

Corredor de ss.hh

3.00

5.36

16.08

4.90

64.68

2.55

20.40

1.50

18.00

TARRAJEO EN FONDO DE ESCALERAS, e=1.5 cm

m2

64.68
8.00

03.02.07

PREPARACIN DE GRADAS DE CONCRETO

1.65

20.40
8.00

03.02.08

PREPARACIN DE DESCANSOS, e=1.5 cm

m2

18.00
8.00

03.03
03.03.01

1.50

CIELOS RASOS
CIELOS RASOS CON MEZCLA DE CONCRETO, e=1.5 cm

m2

677.83

primera planta
SERVICIO HIGIENICO(H)

1.00

area

17.00

17.00

SERVICIO HIGIENICO(M)

1.00

area

18.62

18.62

CORREDOR VAO

3.00

0.92

1.76

4.86

CORREDOR

1.00

2.18

1.94

4.23

6.00

2.18

3.46

45.26

2.00

2.18

2.32

10.12

1.00

2.18

2.46

5.36

1.00

2.49

2.68

6.67

AULA C-101

1.00

area

75.60

75.60

AULA C-102

1.00

area

75.60

75.60

AULA C-103

1.00

area

75.60

75.60

SERVICIO HIGIENICO(H)

1.00

area

17.00

17.00

SERVICIO HIGIENICO(M)

1.00

area

18.62

18.62

CORREDOR VAO

3.00

0.92

1.76

4.86

CORREDOR

1.00

2.18

1.94

4.23

6.00

2.18

3.46

45.26

2.00

2.18

2.32

10.12

1.00

2.18

2.46

5.36

1.00

2.49

2.68

6.67

AULA C-101

1.00

area

75.60

75.60

AULA C-102

1.00

area

75.60

75.60

AULA C-103

1.00

area

75.60

75.60

segunda planta

03.04

PISOS Y PAVIMENTOS

03.04.01

CONTRAPISOS

m2

2,034.77

primera planta
Serv. Hig. H

1.00

area

16.59

16.59

Serv. Hig. M

1.00

area

18.53

18.53

corredor

1.00

area

95.85

95.85

Aula C-101 ,Aula C-102 , Aula C-103

3.00

area

230.78

692.33

Cuarto de limpieza

1.00

area

1.18

1.18

Serv. Hig. H

1.00

area

16.59

16.59

Serv. Hig. M

1.00

area

18.53

18.53

corredor

1.00

area

95.85

95.85

Aula C-201 ,Aula C-202 , Aula C-203

3.00

area

230.78

692.33

Cuarto de limpieza

1.00

area

1.18

1.18

azotea

1.00

area

385.84

385.84

segunda planta

03.04.02

PISOS

03.04.02.01

CERMICOS

m2

1,629.99

primera planta
Serv. Hig. H

1.00

area

16.59

16.59

Serv. Hig. M

1.00

area

18.53

18.53

corredor

1.00

area

95.85

95.85

Aula C-101 ,Aula C-102 , Aula C-103

3.00

area

230.78

692.33

Pgina 3

ITEM

DESCRIPCION

UND

# VECES

ANCHO

LARGO

ALTO

PARCIAL

Serv. Hig. H

1.00

area

16.59

Serv. Hig. M

1.00

area

18.53

corredor

1.00

area

95.85

95.85

Aula C-201 ,Aula C-202 , Aula C-203

3.00

area

230.78

692.33

1.00

area

386.07

386.07

30.13

30.13

TOTAL

segunda planta

03.04.02.02

PISO DE CEMENTO PULIDO

m2

azotea
03.04.03

18.53

SARDINELES

386.07

30.13
1.00

03.05

ZOCALOS Y CONTRAZCALOS

03.05.01

ZOCALOS

03.05.01.01

ZOCALOS DE MADERA, h=10 cm

m2

21.84

AULA C-101, C-201


Eje C-C, entre Eje 9'-9' y 11'-11'

2.00

6.90

0.10

1.38

Eje F-F

2.00

8.40

0.10

1.68

Eje D-D

2.00

1.90

0.10

0.38

Eje 9'-9'

2.00

9.60

0.10

1.92

Eje 11'-11'

2.00

9.60

0.10

1.92

Eje F-F

2.00

6.90

0.10

1.38

Eje I-I

2.00

8.40

0.10

1.68

Eje G-G

2.00

1.90

0.10

0.38

Eje 9'-9'

2.00

9.60

0.10

1.92

Eje 11'-11'

2.00

9.60

0.10

1.92

Eje I-I

2.00

6.90

0.10

1.38

Eje L-L

2.00

8.40

0.10

1.68

Eje J-J

2.00

1.90

0.10

0.38

Eje 9'-9'

2.00

9.60

0.10

1.92

Eje 11'-11'

2.00

9.60

0.10

1.92

2.00

25.90

1.50

77.70

AULAS C-102, C-202

AULAS C-103, C-203

03.05.01.02

ZOCALOS DE MAYOLICA, 20x30 cm

m2

Servicio Higienico
03.05.02

CONTRAZOCALOS

m2
2.00

area

34.55

69.10

Eje 11'-11' entre eje A-A y eje L-L

2.00

area

34.55

69.10

P-1

10.00

1.00

2.95

29.50

P-2

10.00

0.60

2.10

12.60

P-3

2.00

0.70

2.30

3.22

V-1

12.00

2.98

1.15

41.12

V-2

12.00

2.98

1.85

66.16

V-3

28.00

0.60

0.60

10.08

V-4

4.00

2.30

0.90

8.28

CARPINTERIA DE MADERA

03.07.01

PUERTAS

m2

03.08

CARPINTERA METLICA Y HERRERA

03.08.01

VENTANAS DE ALUMINIO

03.11.01

45.32

m2

BARANDAS METALICAS, tubo negro 2"

125.64

235.90

segunda planta

1.00

38.70

38.70

azotea

1.00

101.00

101.00

escalera

8.00

4.90

39.20

114.00

0.50

57.00

entre parapetos
03.11

138.20

Eje 9'-9' entre eje A-A y eje L-L

03.07

03.08.02

77.70

PINTURA
PINTURA DE CIELOS RASOS, VIGAS, COLUMNAS Y PAREDES

971.60

Cielos rasos
Aulas Primer y segundo nivel

6.00

area

80.64

483.84

Servivicio Higuienico primer y segundo nivel

2.00

area

36.69

73.38

Viga en eje C-C, F-F, I-I, Y L-L

8.00

area

6.68

53.44

Viga en eje D-D, G-G y J-J

6.00

area

7.12

42.72

Viga en voladizo

14.00

area

28

Viga en eje 9-9

2.00

area

23.88

47.76

Viga en eje 11-11

6.00

area

7.93

47.58

Vigas Primer y segundo nivel

Pgina 4

ITEM

DESCRIPCION

UND

# VECES

ANCHO

LARGO

ALTO

PARCIAL

C-1

12.00

perimetro

1.4

5.6

94.08

C-2

6.00

perimetro

1.8

5.6

60.48

C-3

2.00

perimetro

1.5

5.6

16.8

C-4

4.00

perimetro

1.05

5.6

23.52

19.35

TOTAL

Columnas Primer y segundo nivel

Paredes
primera planta
EJE C-C

1.00

7.30

2.65

EJE D-D, G-G y J-J

3.00

0.70

2.65

5.57

EJE F-F, I-I y L-L

3.00

7.30

2.15

47.09

EJE 11-11

3.00

area

7.97

23.91

EJE 9-9

3.00

area

7.97

23.91

EJE 9-9 / C-C y D-D

3.00

area

5.87

17.61

EJE 11-11 / C-C y D-D

3.00

area

3.09

9.27

segunda planta

03.11.01

03.11.02

EJE C-C, F-F, I-I y L-L

4.00

7.30

2.95

EJE D-D, G-G y J-J

3.00

0.70

2.95

EJE 9-9

6.00

area

6.40

EJE 9-9 / C-C y D-D

3.00

area

3.74

11.22

EJE 11-11 / C-C y D-D

3.00

area

7.68

23.04

EJE 11-11

6.00

PINTURAS DE PUERTAS

2.98

86.14
6.20
38.40

1.10

19.67

m2

90.64

P1

10.00

1.00

2.95

59.00

P2

10.00

0.60

2.10

25.20

P3

2.00

0.70

2.30

6.44

PINTURAS DE BARANDAS

m2

298.00

segunda planta

1.00

38.70

0.80

61.92

azotea

1.00

101.00

0.80

161.60

escalera

8.00

4.90

0.95

74.48

Pgina 5