Está en la página 1de 4

CALCULO DEL FLETE

OBRA:

CONSTRUCCIN, AMPLIACION Y EQUIPAMIENTO DE LA I.E.P. N 38071 DE MANCO CAPAC DE PANTIPAMPA SUYO

1- DATOS GENERALES

A- POR PESO
MATERIALES

UNIDAD

ALAMBRE NEGRO N 16

KG

ALAMBRE NEGRO N8
ACERO DE REFUERZO FY=4200KG/CM2 GRADO 60
CLAVOS
LADRILLO CORRIENTE DE ARCILLA DE 22x11x8 CM.
CEMENTO PORTLAND TIPO I (42.5KG)
MADERAS EN GENERAL
LADRILLO P/TECHO DE 8x30x30 CM 4 HCOS.
PINTURAS Y OTROS

KG
KG
KG
Und
BOL
P2
UND
GL

MAYOLICA DE 0.20X0.20M BLANCO


EQUIPOS IDA Y VUELTA

M2
KG

OTROS

KG

CANTIDAD

PESO.UNIT.

PESO.TOTAL

272.98

1.00

69.87
4,447.87
139.38
20,202.33
1,216.00
3,763.59
2,612.21
295.52

1.00

69.87

1.00

4,447.87

272.98

1.00

139.38

3.00

60,606.99

42.50

51,680.00

2.80

10,538.05

4.90

12,799.83

4.00

1,182.08

19.66
800.00

8.00

157.28

1.00

800.00

1,000.00

1.00

1,000.00

PESO TOTAL

143,694.33

B- POR VOLUMEN
EN AGREGADOS Y MADERA
DESCRIPC.
ARENA FINA
ARENA GRUESA
PIEDRA MEDIANA
PIEDRA GRANDE
MADERA
PIEDRA ZARANDEADA DE 1/2"
HORMIGON

UNIDAD
M3
M3
M3
M3
P2
M3
M3

AFECTO IGV

VOLUMEN TOTAL
CAPACIDAD DEL CAMION (M3)
NUMERO DE VIAJES
REDONDEO

EN TUBERIA
CAPACIDAD DEL CAMION EN TUBOS / VIAJE
Tub, 1"
Tub,1 1/2"
Tub 2:"
Tub, 3"
Tub 4":
Tub 6:" U-PVC
Tub 8" U-PVC
Tub 10' U-PVC
Tub 8'; CSN

SIN IGV

0.00
0.00

UNIDAD DE (2.20 M. x 3.00 M.) DE CARROCERIA, CON H= 1.50 M.


ML
No de tubos
No VIAJES
3,360.00
U
0.00
0.00
0.00
1,690.00
U
0.00
0.00
0.00
994.00
U
0.00
0.00
0.00
470.00
U
0.00
0.00
0.00
259.00
U
0.00
0.00
0.00
110.00
U
0.00
0.00
0.00
75.00
U
0.00
0.00
0.00
55.00
U
0.00
0.00
0.00
80.00
U
NUMERO TOTAL DE VIAJES
REDONDEO
TUBERIA EN VOLUMEN

2- FLETE TERRESTRE
UNIDAD DE TRANSPORTE
UNIDAD QUE DA COMPROBANTE
CAPACIDAD DEL CAMION ( M3 )
COSTO POR VIAJE S/.
CAPACIDAD DEL CAMION (KG)
FLETE POR KG

UNIDAD QUE NO DA COMPROBANTE


10.00 CAPACIDAD DEL CAMION ( M3 )
800.00 COSTO POR VIAJE S/.
10,000.00 CAPACIDAD DEL CAMION (KG)
0.080

CALCULO DEL FLETE


OBRA:

CONSTRUCCIN, AMPLIACION Y EQUIPAMIENTO DE LA I.E.P. N 38071 DE MANCO CAPAC DE PANTIPAMPA SUYO


AFECTO IGV
11,495.55

FLETE POR PESO


FLETE POR VOLUMEN

SIN IGV

AGREGADO
TUBERIA
COSTO FLETE TERRESTRE

FLETE POR PESO =Peso Total * Flete por peso


FLETE POR VOLUMEN=No viajes*costo por viaje
COSTOS PUESTO EN OBRA

11,495.55

3- FLETE FLUVIAL
UNIDAD DE TRANSPORTE QUE DA COMPROBANTE
UNIDAD DE TRANSPORTE QUE NO DA COMPROB.

N
S

CAPACIDAD DEL BOTE EN PESO


(KG)
CAPACIDAD DEL BOTE EN VOLUMEN (M3)
COSTO POR VIAJE
COSTO POR PESO
AFECTO IGV
0.00

FLETE POR PESO


FLETE POR VOLUMEN
AGREGADO
TUBERIA

SIN IGV

0.00
0.00
FLETE POR PESO =Peso Total * Flete por peso
FLETE POR VOLUMEN=No viajes*costo por viaje

0.00
0.00

COSTO FLETE FLUVIAL

4- FLETE EN ACEMILA
La tubera ser transportada por peones
Costos de transporte por viaje
Acemila S/.
0.00
Peon S/.
0.00
Cantidad
Peso total tubera de agua
Peso total tubera desague CSN
Peso total tubera desague PVC
Numero bolsas de cemento
Peso resto de materiales
Agregados Total en Kilos

1,216.00
92,014.33

Unidades de
Carga
2
2
1
1
1
1

Capacidad de
Carga
80
80
35
1
43
150

Nmero de
Viajes

1,216.00
2,139.87

COSTO TOTAL DEL FLETE EN ACEMILA S/.

RESUMEN DE FLETE TOTAL


FLETE TERRESTRE
FLETE FLUVIAL
FLETE RURAL O ACEMILA
FLETES TOTALES S/.

AFECTO IGV
11,495.55

11,495.55

SIN IGV

FLETE TOTAL:

11,495.55

Flete no
Afecto a IGV

0.00
0.00

CALCULO DEL FLETE


OBRA:

CONSTRUCCION, AMPLIACION Y EQUIPAMIENTO DE LA I.E.P. N38071 DE PANTIPAMPA SUYO

1- DATOS GENERALES

A- POR PESO
MATERIALES

UNIDAD

ALAMBRE NEGRO N 16

KG

ALAMBRE NEGRO N8
ACERO DE REFUERZO FY=4200KG/CM2 GRADO 60
CLAVOS
LADRILLO CORRIENTE DE ARCILLA DE 22x11x8 CM.
CEMENTO PORTLAND TIPO I (42.5KG)
MADERAS EN GENERAL
LADRILLO P/TECHO DE 8x30x30 CM 4 HCOS.
PINTURAS Y OTROS

AFECTO IGV

PESO.UNIT.

PESO.TOTAL

272.98

1.00

KG
KG
KG
Und
BOL
P2
UND
GL

69.87
4,447.87
139.38
20,202.33
1,216.00
3,763.59
2,612.21
295.52

1.00

69.87

1.00

4,447.87

PLANCHA DE FG DE 1/27"
EQUIPOS IDA Y VUELTA

PLN
KG

OTROS

KG

272.98

1.00

139.38

3.00

60,606.99

42.50

51,680.00

2.80

10,538.05

4.90

12,799.83

4.00

1,182.08

19.66
800.00

8.00

157.28

1.00

800.00

1,000.00

1.00

1,000.00

PESO TOTAL

143,694.33

B- POR VOLUMEN
EN AGREGADOS Y MADERA
DESCRIPC.
ARENA FINA
ARENA GRUESA
PIEDRA MEDIANA
PIEDRA GRANDE
MADERA
PIEDRA ZARANDEADA DE 1/2"
HORMIGON

UNIDAD
M3
M3
M3
M3
P2
M3
M3

AFECTO IGV

VOLUMEN TOTAL
CAPACIDAD DEL CAMION (M3)
NUMERO DE VIAJES
REDONDEO

EN TUBERIA
CAPACIDAD DEL CAMION EN TUBOS / VIAJE
Tub, 1"
Tub,1 1/2"
Tub 2:"
Tub, 3"
Tub 4":
Tub 6:" U-PVC
Tub 8" U-PVC
Tub 10' U-PVC
Tub 8'; CSN

SIN IGV

0.00
0.00

UNIDAD DE (2.20 M. x 3.00 M.) DE CARROCERIA, CON H= 1.50 M.


ML
No de tubos
No VIAJES
3,360.00
U
0.00
0.00
0.00
1,690.00
U
0.00
0.00
0.00
994.00
U
0.00
0.00
0.00
470.00
U
0.00
0.00
0.00
259.00
U
0.00
0.00
0.00
110.00
U
0.00
0.00
0.00
75.00
U
0.00
0.00
0.00
55.00
U
0.00
0.00
0.00
80.00
U
NUMERO TOTAL DE VIAJES
REDONDEO
TUBERIA EN VOLUMEN

2- FLETE TERRESTRE
UNIDAD DE TRANSPORTE
UNIDAD QUE DA COMPROBANTE
CAPACIDAD DEL CAMION ( M3 )
COSTO POR VIAJE S/.
CAPACIDAD DEL CAMION (KG)
FLETE POR KG

UNIDAD QUE NO DA COMPROBANTE


10.00 CAPACIDAD DEL CAMION ( M3 )
800.00 COSTO POR VIAJE S/.
10,000.00 CAPACIDAD DEL CAMION (KG)
0.080

CALCULO DEL FLETE


OBRA:

CONSTRUCCION, AMPLIACION Y EQUIPAMIENTO DE LA I.E.P. N38071 DE PANTIPAMPA SUYO


AFECTO IGV
11,495.55

FLETE POR PESO


FLETE POR VOLUMEN

SIN IGV

AGREGADO
TUBERIA
COSTO FLETE TERRESTRE

FLETE POR PESO =Peso Total * Flete por peso


FLETE POR VOLUMEN=No viajes*costo por viaje
COSTOS PUESTO EN OBRA

11,495.55

3- FLETE FLUVIAL
UNIDAD DE TRANSPORTE QUE DA COMPROBANTE
UNIDAD DE TRANSPORTE QUE NO DA COMPROB.

N
S

CAPACIDAD DEL BOTE EN PESO


(KG)
CAPACIDAD DEL BOTE EN VOLUMEN (M3)
COSTO POR VIAJE
COSTO POR PESO
AFECTO IGV
0.00

FLETE POR PESO


FLETE POR VOLUMEN
AGREGADO
TUBERIA

SIN IGV

0.00
0.00
FLETE POR PESO =Peso Total * Flete por peso
FLETE POR VOLUMEN=No viajes*costo por viaje

0.00
0.00

COSTO FLETE FLUVIAL

4- FLETE EN ACEMILA
La tubera ser transportada por peones
Costos de transporte por viaje
Acemila S/.
0.00
Peon S/.
0.00
Cantidad
Peso total tubera de agua
Peso total tubera desague CSN
Peso total tubera desague PVC
Numero bolsas de cemento
Peso resto de materiales
Agregados Total en Kilos

1,216.00
92,014.33

Unidades de
Carga
2
2
1
1
1
1

Capacidad de
Carga
80
80
35
1
43
150

Nmero de
Viajes

1,216.00
2,139.87

COSTO TOTAL DEL FLETE EN ACEMILA S/.

RESUMEN DE FLETE TOTAL


FLETE TERRESTRE
FLETE FLUVIAL
FLETE RURAL O ACEMILA
FLETES TOTALES S/.

AFECTO IGV
11,495.55

11,495.55

SIN IGV

FLETE TOTAL:

11,495.55

Flete no
Afecto a IGV