Documentos de Académico
Documentos de Profesional
Documentos de Cultura
DESCRIPCION
UNIDAD
ALAMBRE NEGRO # 16
ALAMBRE NEGRO # 8
CLAVOS
PERNO DE 1/4" X 2 1/2"
PERNO DE 3/8" X 4"
CLAVOS PARA CALAMINA
ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60
ACCESORIOS PARA INSTALACION ELECTRICA
CEMENTO PORTLAND TIPO I (42.5 kg)
TOPE DE NEOPRENO DE 0.15 X 0.30 X 0.025M
YESO
OCRE
PINTURA ANTICORROSIVA
SOLDADURA
LACA DESMOLDEADORA
ADITIVO PLASTIFICANTE
ADITIVO INCORPORADOR DE AIRE
JUNTA FLEXIBLE DE NEOPRENE
NEOPRENE SHORE DE 0.35 X 0.40 X 0.05 m
LAMINA REFLECTORIZANTE
MEDICINA, EXTINTORES, ETC.
GASOLINA 84 OCTANOS
SOGA DE 3/4" NYLON
GIGANTOGRAFIA DE 3.60X2.40M.
SEAL INFORMATIVA (incl. colocacion y accesorios)
SEAL PREVENTIVAS (incl. colocacion y accesorios)
MADERA TORNILLO
MADERA 3"X4"X10
MADERA 2"X3"X10
MADERA 2"X3"X10 (03 Usos)
PALO ROLLIZO DE 6"X5.00M.
PALO ROLLIZO DE 5"X3.00M.
PALO ROLLIZO DE 5"X1.50M.
PALO ROLLIZO DE 5"X3.50M.
ESTACA DE MADERA
TRIPLAY DE 4' X 8' X 10 mm
TRIPLAY DE 4' X 8' X 19 mm (02 usos)
MADERA NACIONAL PARA ENCOFRADO 11/2"x8"x10' (03 Usos)
ANGULO DE ACERO LIVIANO DE 3" X3" X 1/4" X 6 m
TUBO CUADRADO DE ACERO LIVIANO 1/2"
DISOLVENTE THINER
PINTURA ESMALTE SINTETICO
PINTURA DE TRAFICO
PLANCHA ACERO 3.2mm X 1.22m X 2.40 m
PLANCHA ACERO 400X400X12.5
PLANCHA ACERO 175X175X12.5
CALAMINA GALVANIZADA ZINC 28 CANALES 1.83 X 0.830 m X 0.4 mm
SUMIDERO F. G DE 3"X0.85M. INCLUYE FABRICACION
TUBO DE FIERRO NEGRO DE 3" X 6.4 m
BARANDA METALICA SEGUN DISEO FABRICACION
PLACA RECORDATORIA
kg
kg
kg
pza
pza
kg
kg
u
bls
pza
QQ
kg
gal
kg
gal
kg
gal
m
pza
p2
glb
gal
kg
u
u
u
p2
p2
p2
p2
u
u
u
u
p2
pl
pl
p2
pza
m
gal
gal
gal
pl
pl
pl
pl
u
u
m
pza
CANTIDAD
1351.5415
170.5084
209.3714
2
2
9.36
28407.1315
390
4654.2548
8
4.9153
1.9897
0.15
90.44
63.7008
488.49
73.38
34.4
8
6
1
70.9245
6.6
1
2
2
375.2
430.32
594
3691.776
2
198
198
78
28.6608
93.6
197.3224
1715.256
22.9792
137.6
0.1236
0.481
0.4944
0.54
4
4
101.4
4
0.5
15.9
1
PESO
UNITARIO
1
1
1
0.1
0.15
1
1
0.01
42.5
6
30
1
4
1
4
1
4
3
12
1
1
4
1
5
12
12
1
1
1
1
30
20
10
20
1
12
20
1
12
1
4
4
4
30
12
6
3
8
12
8
25
PESO PARCIAL
1,351.54
170.51
209.37
0.20
0.30
9.36
28,407.13
3.90
197,805.83
48.00
147.46
1.99
0.60
90.44
254.80
488.49
293.52
103.20
96.00
6.00
1.00
283.70
6.60
5.00
24.00
24.00
375.20
430.32
594.00
3,691.78
60.00
3,960.00
1,980.00
1,560.00
28.66
1,123.20
3,946.45
1,715.26
275.75
137.60
0.49
1.92
1.98
16.20
48.00
24.00
304.20
32.00
6.00
127.20
25.00
TOTAL
250,298.15
1.-
Tiempo de Transporte
La distancia de Echarati a Quellomayo Palma Real es de 40.00 km. (por el tipo de carretera se asume los siguientes tiempos)
El tiempo de transporte de Echarati a Quellomayo Palma Real es de aproximadamente 2:00 horas
2.-
Cantidad de Viajes
Cantidad de Viaje
1
Cantidad de Dias/unidad
N de unidades
Dias requeridos
Capacidad (kg)
8,000.00
31.29
1.00
31
N de Viajes
31.29
Canter y/o Fuso
2.-
3.-
Combustible
4.-
Cantidad
12.00
Total
Parcial
40.00
40.00
60.00
60.00
200.00
Total
Parcial
168.00
168.00
Precio
14.00
Combustible
200.00
168.00
368.00
Costo tonelada
46.00
B.-
3 Gln/ Hora
Descripcion
Petroleo D-2
4.-
Hrs
2.00
2.00
3.00
3.00
TOTAL COSTO
TRANSPORTE
11,514.72
2.- UBICACIN
3.- ZONAL
4.- DISTRITO
CALCULO DEL PRECIO DE M3 DE AGREGADO PUESTO A PIE DE OBRA
Usando Camion Volquete de 15 m3
Debido a la topografia de la zona asumiremos que el camion volquete va cargado con 10 m3 de agregado
A.-
1.-
2.-
3.-
Combustible
Parcial
144.00
144.00
288.00
Total
Parcial
134.40
134.40
4 Gls/h
Descripcion
Petroleo D-2
4.-
Hrs
1.20
1.20
Cantidad
9.60
Precio
14.00
Costo de 1 m3 de agregado
Costo maquina seca
288.00
Combustible
134.40
B.-
1.-
Tiempo de Maquina
Costo Volquetada
422.40
3.-
Total
Parcial
54.00
54.00
Cantidad
2.50
Total
Parcial
35.00
35.00
Precio
14.00
Costo de 1 m3 de agregado
Costo maquina seca
54.00
B.-
Combustible
Descripcion
Petroleo D-2
4.-
Hrs
0.30
Combustible
35.00
Costo Volquetada
89.00
S/. 50.00
42.24
8.90
51.14
ARENA FINA
m3
32.9487
ARENA GRUESA
m3
15.7113
GRAVA
m3
10.5000
HORMIGON
m3
48.7740
HORMIGON
m3
76.2008
PIEDRA GRANDE
m3
40.6635
m3
18.9105
m3
12.5070
256.2158
S10
1401001
Subpresupuesto
001
Fecha
Lugar
02/07/2012
080902
Cdigo
Recurso
Unidad
INGENIERO CON
ESPECIALIDAD
EN
OPERARIO
IMPACTO
OFICIAL AMBIENTAL
PEON
mes
hh
hh
hh
1.5000
2,419.5558
2,749.1464
6,496.7445
5,250.00
12.94
10.04
8.37
ALAMBRE NEGRO # 16
ALAMBRE NEGRO # 8
CLAVOS
PERNO DE 1/4" X 2 1/2"
PERNO DE 3/8" X 4"
CLAVOS PARA CALAMINA
ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60
ACCESORIOS PARA INSTALACION ELECTRICA
CEMENTO PORTLAND TIPO I (42.5 kg)
TOPE DE NEOPRENO DE 0.15 X 0.30 X 0.025M
YESO
OCRE
PINTURA ANTICORROSIVA
SOLDADURA
LACA DESMOLDEADORA
ADITIVO PLASTIFICANTE
ADITIVO INCORPORADOR DE AIRE
JUNTA FLEXIBLE DE NEOPRENE
NEOPRENE SHORE DE 0.35 X 0.40 X 0.05 m
LAMINA REFLECTORIZANTE
MEDICINA, EXTINTORES, ETC.
GASOLINA 84 OCTANOS
SOGA DE 3/4" NYLON
GIGANTOGRAFIA DE 3.60X2.40M.
SEAL INFORMATIVA (incl. colocacion y accesorios)
SEAL PREVENTIVAS (incl. colocacion y accesorios)
MADERA TORNILLO
MADERA 3"X4"X10
MADERA 2"X3"X10
MADERA 2"X3"X10 (03 Usos)
PALO ROLLIZO DE 6"X5.00M.
PALO ROLLIZO DE 5"X3.00M.
PALO ROLLIZO DE 5"X1.50M.
PALO ROLLIZO DE 5"X3.50M.
ESTACA DE MADERA
TRIPLAY DE 4' X 8' X 10 mm
TRIPLAY DE 4' X 8' X 19 mm (02 usos)
MADERA NACIONAL PARA ENCOFRADO 11/2"x8"x10' (03 Usos)
ANGULO DE ACERO LIVIANO DE 3" X3" X 1/4" X 6 m
TUBO CUADRADO DE ACERO LIVIANO 1/2"
DISOLVENTE THINER
PINTURA ESMALTE SINTETICO
PINTURA DE TRAFICO
PLANCHA ACERO 3.2mm X 1.22m X 2.40 m
PLANCHA ACERO 400X400X12.5
PLANCHA ACERO 175X175X12.5
CALAMINA GALVANIZADA ZINC 28 CANALES 1.83 X 0.830 m X 0.4 mm
SUMIDERO F. G DE 3"X0.85M. INCLUYE FABRICACION
TUBO DE FIERRO NEGRO DE 3" X 6.4 m
BARANDA METALICA SEGUN DISEO FABRICACION
PLACA RECORDATORIA
kg
kg
kg
pza
pza
kg
kg
u
bls
pza
QQ
kg
gal
kg
gal
kg
gal
m
pza
p2
glb
gal
kg
u
u
u
p2
p2
p2
p2
u
u
u
u
p2
pl
pl
p2
pza
m
gal
gal
gal
pl
pl
pl
pl
u
u
m
pza
1,351.5415
170.5084
209.3714
2.0000
2.0000
9.3600
28,407.1315
390.0000
4,654.2548
8.0000
4.9153
1.9897
0.1500
90.4400
63.7008
488.4900
73.3800
34.4000
8.0000
6.0000
1.0000
70.9245
6.6000
1.0000
2.0000
2.0000
375.2000
430.3200
594.0000
3,691.7760
2.0000
198.0000
198.0000
78.0000
28.6608
93.6000
197.3224
1,715.2560
22.9792
137.6000
0.1236
0.4810
0.4944
0.5400
4.0000
4.0000
101.4000
4.0000
0.5000
15.9000
1.0000
5.20
5.20
5.00
0.60
0.75
8.50
4.96
1.88
28.00
500.00
16.50
12.00
52.00
14.56
95.00
8.00
12.00
250.00
2,500.00
22.50
1,000.00
15.00
18.00
300.00
1,500.00
650.00
3.50
2.50
2.50
2.50
30.00
18.00
10.00
20.00
2.00
90.00
135.00
2.50
225.00
5.00
30.50
42.00
62.25
325.00
150.00
80.00
20.00
75.00
45.00
420.00
450.00
Cantidad
Precio S/.
MANO DE OBRA
0147000039
0147010002
0147010003
0147010004
MATERIALES
0202000010
0202000015
0202010022
0202080039
0202080040
0202170001
0203020003
0210140077
0221000001
0226050011
0229060006
0229150009
0229200012
0229500091
0230110008
0230120021
0230190012
0230650001
0230650023
0230670002
0230760073
0234000000
0239020008
0239090071
0239900100
0239900101
0243040000
0243110009
0243110010
0243110016
0243600006
0243600012
0243600013
0243600014
0244010001
0244030016
0244030019
0245010007
0251010017
0251070002
0253050007
0254010001
0254450070
0256020010
0256020084
0256020085
0256900002
0265000108
0265170006
0265220010
0279560003
EQUIPOS
0337010001
0337040034
0337580100
0337580101
0337580102
0337900005
0348010011
0348040034
0348080000
0348600001
0349030013
0349040010
0349040034
0349040092
0349070004
0349070050
0349080097
0349080098
0349080100
0349080101
0349080102
0349090000
0349880016
0349880020
HERRAMIENTAS MANUALES
MOTOSIERRA DE 16"
ESTUDIO DE CANTERAS
DISEO DE MEZCLAS CONCRETO 175, 210 Y 280 KG/CM2.
PRUEBAS DE CALIDAD DE CONCRETO ROTURA
BROCHA DE 4"
MEZCLADORA DE CONCRETO DE 9 -11p3
CAMION VOLQUETE 12 m3
MOTOBOMBA 10 HP 4"
TIRFOR DE 3 ton
RODILLO LISO VIBRATORIO AUTOPROPULSADO 70-100 HP 7-9 ton
CARGADOR SOBRE LLANTAS 125-155 HP 3 yd3
TRACTOR DE ORUGAS DE 190-240 HP
EXCAVADOR SOBRE ORUGA 220 HP 1.1-2.75 yd3
VIBRADOR DE CONCRETO 4 HP 2.40"
MOTOSOLDADORA DE 250 A
TRANSPORTE DE TRACTOR SOBRE ORUGAS (IDA) EN PLATAFORMA
TRANSPORTE DE MOTONIVELADORA (IDA) EN PLATAFORMA
TRANSPORTE DE RODILLO COMPACTADOR (IDA) EN PLATAFORMA
TRANSPORTE DE EQUIPOS MENORES (IDA Y VUELTA)
TRANSPORTE DE CARGADOR FRONTAL (IDA) EN PLATAFORMA
MOTONIVELADORA DE 125 HP
NIVEL OPTICO
ESTACION TOTAL
%MO
hm
u
u
u
pza
hm
hm
hm
hm
hm
hm
hm
hm
hm
hm
vje
vje
vje
vje
vje
hm
hm
hm
70.6789
1.0000
3.0000
30.0000
8.1092
451.9735
24.7848
399.5150
35.1978
89.2008
19.5246
23.2937
41.2112
217.1175
48.5323
1.0000
1.0000
1.0000
2.0000
1.0000
89.2008
70.1383
17.0791
10.00
5,000.00
500.00
40.00
6.00
10.00
283.00
5.00
8.00
115.00
210.00
280.00
280.00
6.50
70.00
9,000.00
8,000.00
7,000.00
2,000.00
8,000.00
192.00
8.00
18.75
Total
S/.
S/.
La columna parcial es el producto del precio por la cantidad requerida; y en la ltima columna se muestra el Monto Real que se est utilizando
Parcial S/.
Presupuestado S/.
7,875.00
31,309.05
27,601.43
54,377.75
121,163.23
7,875.00
31,198.72
27,565.87
54,400.58
121,040.17
7,028.02
886.64
1,046.86
1.20
1.50
79.56
140,899.37
733.20
130,319.13
4,000.00
81.10
23.88
7.80
1,316.81
6,051.58
3,907.92
880.56
8,600.00
20,000.00
135.00
1,000.00
1,063.87
118.80
300.00
3,000.00
1,300.00
1,313.20
1,075.80
1,485.00
9,229.44
60.00
3,564.00
1,980.00
1,560.00
57.32
8,424.00
26,638.52
4,288.14
5,170.32
688.00
3.77
20.20
30.78
175.50
600.00
320.00
2,028.00
300.00
22.50
6,678.00
450.00
651,955.31
7,028.01
883.91
1,046.88
1.20
1.50
79.56
140,953.31
733.20
130,319.20
4,000.00
78.64
26.53
7.80
1,316.94
6,051.57
3,907.92
880.56
8,600.00
20,000.00
135.00
1,000.00
1,063.88
118.80
300.00
3,000.00
1,300.00
1,313.20
1,075.80
1,485.00
9,229.44
60.00
3,564.00
1,980.00
1,560.00
57.32
8,424.00
26,638.53
4,288.14
5,170.32
688.00
3.77
20.20
30.78
175.50
600.00
320.00
2,028.00
300.00
22.50
6,678.00
450.00
652,007.53
3,242.59
706.79
5,000.00
1,500.00
1,200.00
48.66
4,519.73
7,014.10
1,997.57
281.58
10,258.09
4,100.17
6,522.24
11,539.14
1,411.26
3,397.26
9,000.00
8,000.00
7,000.00
4,000.00
8,000.00
17,126.55
561.11
320.23
116,747.07
3,242.59
698.59
5,000.00
1,500.00
1,200.00
48.67
4,520.71
7,014.59
1,995.02
281.82
10,265.14
4,104.88
6,520.62
11,537.85
1,410.11
3,397.23
9,000.00
8,000.00
7,000.00
4,000.00
8,000.00
17,135.91
562.64
319.44
116,755.81
889,865.61
889,803.51
889,803.51
S10
1401001
Subpresupuesto
001
Fecha
Lugar
02/07/2012
080902
Cdigo
Recurso
Unidad
INGENIERO CON
ESPECIALIDAD
EN
OPERARIO
IMPACTO
OFICIAL AMBIENTAL
PEON
mes
hh
hh
hh
ALAMBRE NEGRO # 16
ALAMBRE NEGRO # 8
CLAVOS
PERNO DE 1/4" X 2 1/2"
PERNO DE 3/8" X 4"
CLAVOS PARA CALAMINA
ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60
ARENA FINA
PIEDRA CHANCADA DE 1/2"
PIEDRA GRANDE DE 8"
MATERIAL CLASIFICADO GRANULAR # 1
PIEDRA MEDIANA
ARENA GRUESA
ACCESORIOS PARA INSTALACION ELECTRICA
CEMENTO PORTLAND TIPO I (42.5 kg)
TOPE DE NEOPRENO DE 0.15 X 0.30 X 0.025M
YESO
OCRE
PINTURA ANTICORROSIVA
SOLDADURA
LACA DESMOLDEADORA
ADITIVO PLASTIFICANTE
ADITIVO INCORPORADOR DE AIRE
JUNTA FLEXIBLE DE NEOPRENE
NEOPRENE SHORE DE 0.35 X 0.40 X 0.05 m
LAMINA REFLECTORIZANTE
MEDICINA, EXTINTORES, ETC.
FLETE TERRESTRE DE ECHARATI A LA OBRA
GASOLINA 84 OCTANOS
COMBUSTIBLE, LUBRIC. Y FILTROS
HORMIGON DE RIO
SOGA DE 3/4" NYLON
AGUA
GIGANTOGRAFIA DE 3.60X2.40M.
SEAL INFORMATIVA (incl. colocacion y accesorios)
SEAL PREVENTIVAS (incl. colocacion y accesorios)
MADERA TORNILLO
MADERA 3"X4"X10
MADERA 2"X3"X10
MADERA 2"X3"X10 (03 Usos)
PALO ROLLIZO DE 6"X5.00M.
PALO ROLLIZO DE 5"X3.00M.
PALO ROLLIZO DE 5"X1.50M.
PALO ROLLIZO DE 5"X3.50M.
ESTACA DE MADERA
TRIPLAY DE 4' X 8' X 10 mm
TRIPLAY DE 4' X 8' X 19 mm (02 usos)
MADERA NACIONAL PARA ENCOFRADO 11/2"x8"x10' (03 Usos)
ANGULO DE ACERO LIVIANO DE 3" X3" X 1/4" X 6 m
TUBO CUADRADO DE ACERO LIVIANO 1/2"
DISOLVENTE THINER
PINTURA ESMALTE SINTETICO
kg
kg
kg
pza
pza
kg
kg
m3
m3
m3
m3
m3
m3
u
bls
pza
QQ
kg
gal
kg
gal
kg
gal
m
pza
p2
glb
kg
gal
%EQ
m3
kg
m3
u
u
u
p2
p2
p2
p2
u
u
u
u
p2
pl
pl
p2
pza
m
gal
gal
Cantidad
Precio S/.
MANO DE OBRA
0147000039
0147010002
0147010003
0147010004
1.5000
2,419.5558
2,749.1464
6,496.7445
5,250.00
12.94
10.04
8.37
1,351.5415
170.5084
209.3714
2.0000
2.0000
9.3600
28,407.1315
0.7950
296.2918
164.6260
3,466.5470
8.9760
188.5964
390.0000
4,654.2548
8.0000
4.9153
1.9897
0.1500
90.4400
63.7008
488.4900
73.3800
34.4000
8.0000
6.0000
1.0000
281,892.0900
70.9245
5.20
5.20
5.00
0.60
0.75
8.50
4.96
100.00
120.00
60.00
30.00
60.00
90.00
1.88
28.00
500.00
16.50
12.00
52.00
14.56
95.00
8.00
12.00
250.00
2,500.00
22.50
1,000.00
0.15
15.00
158.6790
6.6000
332.0047
1.0000
2.0000
2.0000
375.2000
430.3200
594.0000
3,691.7760
2.0000
198.0000
198.0000
78.0000
28.6608
93.6000
197.3224
1,715.2560
22.9792
137.6000
0.1236
0.4810
50.00
18.00
5.00
300.00
1,500.00
650.00
3.50
2.50
2.50
2.50
30.00
18.00
10.00
20.00
2.00
90.00
135.00
2.50
225.00
5.00
30.50
42.00
MATERIALES
0202000010
0202000015
0202010022
0202080039
0202080040
0202170001
0203020003
0204000000
0205000003
0205000009
0205000015
0205000032
0205010004
0210140077
0221000001
0226050011
0229060006
0229150009
0229200012
0229500091
0230110008
0230120021
0230190012
0230650001
0230650023
0230670002
0230760073
0232000056
0234000000
0234000003
0238000002
0239020008
0239050000
0239090071
0239900100
0239900101
0243040000
0243110009
0243110010
0243110016
0243600006
0243600012
0243600013
0243600014
0244010001
0244030016
0244030019
0245010007
0251010017
0251070002
0253050007
0254010001
0254450070
0256020010
0256020084
0256020085
0256900002
0265000108
0265170006
0265220010
0279560003
PINTURA DE TRAFICO
PLANCHA ACERO 3.2mm X 1.22m X 2.40 m
PLANCHA ACERO 400X400X12.5
PLANCHA ACERO 175X175X12.5
CALAMINA GALVANIZADA ZINC 28 CANALES 1.83 X 0.830 m X 0.4 mm
SUMIDERO F. G DE 3"X0.85M. INCLUYE FABRICACION
TUBO DE FIERRO NEGRO DE 3" X 6.4 m
BARANDA METALICA SEGUN DISEO FABRICACION
PLACA RECORDATORIA
gal
pl
pl
pl
pl
u
u
m
pza
0.4944
0.5400
4.0000
4.0000
101.4000
4.0000
0.5000
15.9000
1.0000
62.25
325.00
150.00
80.00
20.00
75.00
45.00
420.00
450.00
HERRAMIENTAS MANUALES
MOTOSIERRA DE 16"
ESTUDIO DE CANTERAS
DISEO DE MEZCLAS CONCRETO 175, 210 Y 280 KG/CM2.
PRUEBAS DE CALIDAD DE CONCRETO ROTURA
BROCHA DE 4"
MEZCLADORA DE CONCRETO DE 9 -11p3
CAMION VOLQUETE 12 m3
MOTOBOMBA 10 HP 4"
TIRFOR DE 3 ton
RODILLO LISO VIBRATORIO AUTOPROPULSADO 70-100 HP 7-9 ton
CARGADOR SOBRE LLANTAS 125-155 HP 3 yd3
TRACTOR DE ORUGAS DE 190-240 HP
EXCAVADOR SOBRE ORUGA 220 HP 1.1-2.75 yd3
VIBRADOR DE CONCRETO 4 HP 2.40"
MOTOSOLDADORA DE 250 A
TRANSPORTE DE TRACTOR SOBRE ORUGAS (IDA) EN PLATAFORMA
TRANSPORTE DE MOTONIVELADORA (IDA) EN PLATAFORMA
TRANSPORTE DE RODILLO COMPACTADOR (IDA) EN PLATAFORMA
TRANSPORTE DE EQUIPOS MENORES (IDA Y VUELTA)
TRANSPORTE DE CARGADOR FRONTAL (IDA) EN PLATAFORMA
MOTONIVELADORA DE 125 HP
NIVEL OPTICO
ESTACION TOTAL
%MO
hm
u
u
u
pza
hm
hm
hm
hm
hm
hm
hm
hm
hm
hm
vje
vje
vje
vje
vje
hm
hm
hm
70.6789
1.0000
3.0000
30.0000
8.1092
451.9735
24.7848
399.5150
35.1978
89.2008
19.5246
23.2937
41.2112
217.1175
48.5323
1.0000
1.0000
1.0000
2.0000
1.0000
89.2008
70.1383
17.0791
10.00
5,000.00
500.00
40.00
6.00
10.00
283.00
5.00
8.00
115.00
210.00
280.00
280.00
6.50
70.00
9,000.00
8,000.00
7,000.00
2,000.00
8,000.00
192.00
8.00
18.75
EQUIPOS
0337010001
0337040034
0337580100
0337580101
0337580102
0337900005
0348010011
0348040034
0348080000
0348600001
0349030013
0349040010
0349040034
0349040092
0349070004
0349070050
0349080097
0349080098
0349080100
0349080101
0349080102
0349090000
0349880016
0349880020
Total
S/.
S/.
La columna parcial es el producto del precio por la cantidad requerida; y en la ltima columna se muestra el Monto Real que se est utilizando
Parcial S/.
Presupuestado S/.
7,875.00
31,309.05
27,601.43
54,377.75
121,163.23
7,875.00
31,198.72
27,565.87
54,400.58
121,040.17
7,028.02
886.64
1,046.86
1.20
1.50
79.56
140,899.37
79.50
35,555.02
9,877.56
103,996.41
538.56
16,973.68
733.20
130,319.13
4,000.00
81.10
23.88
7.80
1,316.81
6,051.58
3,907.92
880.56
8,600.00
20,000.00
135.00
1,000.00
42,283.81
1,063.87
24,111.51
7,933.95
118.80
1,660.02
300.00
3,000.00
1,300.00
1,313.20
1,075.80
1,485.00
9,229.44
60.00
3,564.00
1,980.00
1,560.00
57.32
8,424.00
26,638.52
4,288.14
5,170.32
688.00
3.77
20.20
7,028.01
883.91
1,046.88
1.20
1.50
79.56
140,953.31
79.50
35,555.01
9,877.56
103,996.41
538.56
16,973.68
733.20
130,319.20
4,000.00
78.64
26.53
7.80
1,316.94
6,051.57
3,907.92
880.56
8,600.00
20,000.00
135.00
1,000.00
42,283.81
1,063.88
24,111.51
7,933.95
118.80
1,660.63
300.00
3,000.00
1,300.00
1,313.20
1,075.80
1,485.00
9,229.44
60.00
3,564.00
1,980.00
1,560.00
57.32
8,424.00
26,638.53
4,288.14
5,170.32
688.00
3.77
20.20
30.78
175.50
600.00
320.00
2,028.00
300.00
22.50
6,678.00
450.00
651,955.31
30.78
175.50
600.00
320.00
2,028.00
300.00
22.50
6,678.00
450.00
652,007.53
3,242.59
706.79
5,000.00
1,500.00
1,200.00
48.66
4,519.73
7,014.10
1,997.57
281.58
10,258.09
4,100.17
6,522.24
11,539.14
1,411.26
3,397.26
9,000.00
8,000.00
7,000.00
4,000.00
8,000.00
17,126.55
561.11
320.23
116,747.07
3,242.59
698.59
5,000.00
1,500.00
1,200.00
48.67
4,520.71
7,014.59
1,995.02
281.82
10,265.14
4,104.88
6,520.62
11,537.85
1,410.11
3,397.23
9,000.00
8,000.00
7,000.00
4,000.00
8,000.00
17,135.91
562.64
319.44
116,755.81
889,865.61
889,803.51
889,803.51