Documentos de Académico
Documentos de Profesional
Documentos de Cultura
A workshop towards PMP certification Preparation using PMIs PMBOK 3rd edition
Session VI
Information Distribution
Deliverables
Requested changes
Implemented change requests Implemented corrective actions Implemented preventive actions Implemented defect repair Work performance information
The project manager, along with the project management team and the project team directs the performance of the planned project objectives, and manage the various technical and organizational interfaces in the project Deliverables are produced as outputs from the processes performed to accomplish the project work planned and scheduled in the project management plan This process also includes implementation of approved corrective, preventive actions and approved defect repair requests.
Requested changes
Recommended Corrective actions Organizational process assets( updates) Project management plan( updates)
Resource availability
Staffing management plan updates
Acquisition
Hiring contractors or Subcontracting a piece of work to another organization
Virtual Teams
Different geographic areas of same org Specific experts in different geographical zones Home office Different time zones and shifts People with mobility handicaps
Examples
Assisting one another when workloads are unbalanced Communicating in ways that fit individual preferences Sharing information and resources
Outputs
General management skills (Inter-personal skills / soft skills) Training Team building activities Ground rules
Co-location
Recognition and rewards
Team building
The project manager brings them the big picture perspective, and facilitates to concentrate on overall project goals
Forming
Storming
Norming Performing
Adjourning
Storming
Characteristics: Hostility, infighting, major moaners,
blaming, and poor communications.
Norming
Characteristics: Willingness to solve problems,
confronting issues, constructive feedback.
Performing
Characteristics: Collaboration, enthusiasm, trust,
self motivation, and clean fights.
Classifiers
Harmonizers thing.
Summarizers
Gatekeepers
Blockers
The withdrawer
Recognition seeker Seeks the attention by monopolizing the discussions Topic jumpers Dominators Continually changes the subject Tries to takeover the discussion
WENT WRONG
WENT RIGHT
Brainstorming
Early and accurate identification of trends and problems Accurate picture of contract status
What is EVMS?
that integrates the technical, schedule, and cost parameters of the contract. The project manager is the primary tool in the EVMS toolbox.
Basic Elements
PV
EV AC BAC EAC
Planned Value
Earned Value Actual cost Budget at Completion Estimate at Completion
Total Budget
Its my pleasure to award you this contract for a new railroad track
Month 1 PV = $1,000
Month 2 PV = $1,000
Month 3 PV = $1,000
Month 4 PV = $1,000
Month 5 PV = $1,000
Total PV or (BAC)
Total Budget = $5,000
Total PV = $5,000
Month 1 PV = $1,000 Month 2 PV = $1,000 Month 3 PV = $1,000
Month 4 PV = $1,000
Month 5 PV = $1,000
$
$ $ $ $ $ $ $
time
when all work has been phased, cumulative PV = BAC e.g., $5,000 = $5,000
VALUE concept
Were at the end of the second month, but only 1 section of track is complete. Value of work performed = $1,000
Schedule Variance
SCHEDULE VARIANCE is the difference between work scheduled and work performed (expressed in terms of budget dollars) SPI is the ratio between work performed and work scheduled
formula:
example:
SV $ = EV - PV
SV = EV - PV = $1,000 - $2,000 SV= -$1,000 (negative = behind schedule)
5,000
PV the baseline
sv
EV earned value TIME
5 months
At the end...
At the end of the contract, when all work has been completed:
Ive earned all of my budget ($5,000)
EV (cumulative) = PV (cumulative) = therefore, schedule variance ($) =
$5,000 $5,000
0
Labor came to $1,300, and materials cost $1,100. That first section of track cost $2,400!
Cost Variance
COST VARIANCE is the difference between
Earned Value and actual cost
formula: CV $ = EV - AC
example: CV = EV - AC = $1,000 - $2,400 CV= -$1,400 (negative = cost overrun)
cv
$
EV earned value
TIME
5 months
AC + ETC = EAC
Common EAC Formulae: EAC = BAC/ CPI Example = 5000/0.4 = 12500
ANSWER
Planned Value
ACRONYM
PV
Earned Value
EV
Actual Cost
AC
Budget at Completion
BAC
Estimate at Completion
EAC
EVM - Summary
5,000
BCWS ACWP
cv sv
BCWP
TIME
5 months
Performance Indices
GOOD
1.2
SCHED PERF INDEX (SPI) = EV PV
1.1
TIME
1.0 BAD .9
CPI
SPI
.8
Schedule Status
TIME NOW
PV
compare
% completed = EV x 100% BAC
EV
MONTHS BEHIND
Budget Status
budget status
% spent = AC x 100% BAC
compare:
% spent
example:
vs.
% complete
Questions?