Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Plan
1
Project Planning Steps:
SUMMARY
Develop Task List
(WBS)
Sequence Tasks
(Network Diagram)
Schedule Tasks
(Gantt Chart)
Schedule
Resources
2
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
PERT and CPM Networks
PERT
Program Evaluation and Review
Technique
Uses probabilistic (uncertain) estimates of
activity duration
CPM
Critical Path Method
Uses deterministic (certain) estimates of
activity duration
3
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
PERT and CPM Networks
Both PERT and CPM network
diagrams look similar
The difference is in how the
durations are determined
CPM: Use best choice for duration
PERT: Dur = (a + 4m + b)/6
a = most optimistic
b = most pessimistic
m = most likely
4
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
AOA / AON Network
Diagrams
Activity-on-Arrow (AOA)
C 3 D
Start 3 E Stop
1 G 0 4
1 A B 1 5 F 6
2 2 2
3
Activity-on-Node (AON)
1
C 3
D 1
Start E 2 Stop
A B F
2 3
5
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
6-1
6
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
6-3
Activity-on-Node Network
Fundamentals
<<
“Burst”
<< “Merge”
7
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
Example WBS
KOLL BUSINESS CENTER
B Construction plans A 15
C Traffic study A 10
H Occupancy E,G 35
8
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
6-5
B Construction plans A
C Traffic study A
D Service availability A
check
9
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
6-7
10
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
6-9
11
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
Task Start and Finish
Dates
Early Start (ES) – the earliest date a task can
begin, given the tasks preceding it
Early Finish (EF) – the earliest date a task can
finish, given the tasks preceding it
Late Start (LS) – the latest date a task can
begin without delaying the finish date of the
project
Late Finish (LF) – the latest date a task can
finish without delaying the finish date of the
project
12
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
Forward Pass: Determines
ES, EF
Working forward, add activity times
along each path in the network (ES +
Dur = EF)
Carry the EF to the next activity where it
becomes its ES, unless the next
succeeding activity is a merge activity
for a merge activity, select the largest EF of all
its immediate predecessor activities
ES ID EF
SL Act SL
LS Dur LF
13
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
Forward Pass
0 A 5 5 C 15
5 10
ES ID EF
SL Act SL
LS Dur LF
14
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
Forward Pass w/ Burst
5 B 20
15
0 A 5 5 C 15
5 10
5 D 10
ES ID EF 5
SL Act SL
LS Dur LF
15
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
Forward Pass w/ Merge
Larger = 20
5 B 20 20 E 35
15 15
5 C 15
10
ES ID EF
SL Act SL
LS Dur LF
16
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
6-11
17
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
Backward Pass: Determines
LS, LF
Working backward, subtract activity
times along each path starting with the
project end activity (LF – Dur = LS)
Carry the LS to the next preceding
activity to establish its LF, unless the
next preceding activity is a burst
activity
ES ID EF for a burst activity, select the smallest LS of all
SL Act SL its immediate successor activities to establish its
LF
LS Dur LF
(-) 18
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
Backward Pass
F G
20 10 30 30 170200
( -) ( -)
ES ID EF
SL Act SL
LS Dur LF
19
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
Backward Pass w/ Merge
B
5 15 20
( -)
C F
10 10 20 20 10 30
( -)
D ( -)
ES ID EF
SL Act SL 15 5 20
LS Dur LF ( -)
20
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
Backward Pass w/ Burst
B
5 15 20
A C(-)
0 5 5 10 10 20
( -) ( -)
D
ES ID EF 15 5 20
SL Act SL
( -)
LS Dur LF
21
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
6-13
22
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
Slack (or Float)
SL: total slack or float ES ID EF
SL Act SL
-)
-)
(
SL = LS – ES LS Dur LF
or SL = LF – EF
CRITICAL PATH: generally, the
path(s) for which SL = 0
ES ID EF
0 Act 0
LS Dur LF
23
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
6-15
Activity-on-Node Network with
Slack
24
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
Slack - Graphically
25
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
Finish to Start
Trench
Lay pipe
Refill
3 time units
26
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
(Using Finish-to-Start
Relationship)
Trench Trench Trench
1/3 1/3 1/3
27
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
Use of Lags
Lag: Minimum time a dependent
activity must be delayed to begin or
end
Why use lags?
To break a long activity into smaller ones
to avoid long delays to successor activity
To constrain the start and finish of an
activity
28
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
6-22
Finish-to-Start Relationship
Typical, generic network style
Ex: “design house, build
foundation”
29
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
6-23
Start-to-Start Relationship
Usually for performing a portion of one
activity and beginning a following
activity before competing the first
30
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
Use of Lags to Reduce
6-24
Detail
31
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
6-26
Finish-to-Finish Relationship
32
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
6-27
Start-to-Finish Relationship
33
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
6-28
Combination Relationships
Coding must be finished
before debugging can finish
35
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights
END
36