PROGRESS FISIK PEKERJAAN

PEMBANGUNAN TPA SAMPAH


KAB. HALMAHERA TENGAH (LANJUTAN)

Realisasi Progress Fisik


Lapangan
72,78%
BACKUP QUANTITY MC 02

KONTRAK REALISASI

NO URAIAN PEKERJAAN
SA
VOL HARGA SATUAN TOTAL HARGA VOL BOBOT JUMLAH HARGA
T

1 PEKERJAAN PERSIAPAN

Mobilisasi dan
1,00 Ls 39,000,000.00 39,000,000.00 0.75 0.84 29,250,000.00
Demobilisasi

Direksikeet / Kantor
1,00 Ls 19,000,000.00 19,000,000.00 1.00 0.55 19,000,000.00
Proyek

Papan Nama Proyek 1,00 Ls 500,000.00 500,000.00 1.00 0.01 500,000.00

Laporan, Dokumentasi
1,00 Ls 10,500,000.00 10,500,000.00 0.71 0.22 7,500,000.00
Dan Asbuilt Drawing

Pembersihan Lokasi 1,00 Ls 14,000,000.00 14,000,000.00 0.75 0.30 10,500,000.00

Pengukuran Dan
1,00 Ls 7,000,000.00 7,000,000.00 0.60 0.12 4,200,000.00
Pemasangan Bouwplank

Listrik Dan Air Kerja 1,00 Ls 6,500,000.00 6,500,000.00 0.50 0.09 3,250,000.00

TOTAL 1 (PEKERJAAN PERSIAPAN) 95.500000.00 2.14 74,200,000.00


KONTRAK REALISASI
NO URAIAN PEKERJAAN
SA
VOL T
HARGA SATUAN TOTAL HARGA VOL BOBOT JUMLAH HARGA

2 PEKERJAAN TALUD

Galian Tanah 583.07 M³ 105,880.00 61,734,943.38 583.07 1.78 61,734,943.38

Timbunan Tanah Kembali 145.77 M³ 267,172.00 38,944,673.90 145.77 1.12 38,944,673.90

Pasir Urug 46.36 M³ 217,310.00 10,074,491.60 46.36 0.29 10,074,491.60

Pasangan Batu Karang


1,053.79 M³ 1,618,426.10 1.705.481.239.92 1,035.79 49.23 1.705.481.239.92
Gunung 1 : 4

Pekerjaan Pipa PVC 2" 319.65 M¹ 18,165.80 5,806,697.97 319.65 0.17 5,806,697.97

Pancang Kayu 1,200.00 M' 26,302.52 31.563.028.8 1,200.00 1.62 31.563.028.8

TOTAL 2 (PEKERJAAN TALUD) 1,853,605,075.57 53.51 1,853,605,075.57


KONTRAK REALISASI

NO URAIAN PEKERJAAN
SA
VOL T
HARGA SATUAN TOTAL HARGA VOL BOBOT JUMLAH HARGA

3 PEKERJAAN DRAINASE

Galian Tanah 567.00 M³ 105,880.00 60,033,960.00 567.00 1.73 60,033,960.00

Pasir Urug 40.77 M³ 217,310.00 8,859,728.70 40.77 0.26 8,859,728.70

Pasangan Batu Karang


217.44 M³ 1,618,426.10 351,910,571.18 217.44 10.16 351,910,571.18
Gunung 1 : 4

Plesteran 1 : 3 1,087.20 M² 129,207.40 140,474,285.28 - - -

TOTAL 3 (PEKERJAAN DRAINASE) 561,278,545.16 12.15 420,804,259.88


KONTRAK REALISASI
NO URAIAN PEKERJAAN
VOL SAT HARGA SATUAN TOTAL HARGA VOL BOBOT JUMLAH HARGA

4 PEKERJAAN DEUCKER

Galian Tanah 27.30 M³ 105,880.00 2,890,524.00 27.30 0.08 2,890,524.00

Urug Tanah Kembali 6.83 M³ 267,172.00 1,823,448.90

Pas. Batu Karang 1 : 4 11.97 M³ 1,618,426.10 19,372,560.42

Rabat Beton ad. 1 : 3 : 5 0.70 M³ 1,413,690.00 989,583.00

Beton K225 3.15 M³ 2,687,544.00 8,465,763.60

Tulangan 252.97 Kg 16,605.90 4,200,843.68

Bekisting 2.80 M² 102,005.00 285,614.00

Plesteran 13.30 M² 129,207.40 1,718,458.42

TOTAL 4 (PEKERJAAN DEUCKER) 39,746,796.01 0.08 2,890,524.00


KONTRAK REALISASI
NO URAIAN PEKERJAAN
VOL SAT HARGA SATUAN TOTAL HARGA VOL BOBOT JUMLAH HARGA

PEKERJAAN JALAN
5
HOTMIX
Mobilisasi/Demobilisasi 1.00 Ls 76,500,000.00 76,500,000.00
Alat Berat
Penyiapan Badan Jalan 1,170.00 M² 19,006.00 22,237,020.00

Lapis Pondasi Agregat 78.00 M³ 1,109,172.86 86,515,483.12


Kls. A
Lapis Pondasi Agregat 156.00 M³ 689,158.05 107,508,655.70
Kls. B
Lapis Resap Pengikat 624.00 Ltr 21,286.45 13,282,744.80

Lapis Perekat 234.00 Ltr 24,303.15 5,686,937.10

Lataston (HRS) Tebal 5 80.45 Ton 728,394.96 58,597,371.66


Cm
Aspal 5.22 Ton 21,000,000.00 109,582,200.00

Aditif anti pengelupasan 13.05 Kg 77,000.00 1,004,503.50

Bahan Pengisi (Filler) 1,304.55 Kg 2,260.00 2,948,283.00


Tambahan

TOTAL 5 (PEKERJAAN JALAN HOTMIX) 483,863,198.88


KONTRAK REALISASI
NO URAIAN PEKERJAAN
VOL SAT HARGA SATUAN TOTAL HARGA VOL BOBOT JUMLAH HARGA

6 JEMBATAN TIMBANG
a Pekerjaan Tanah Dan
Pasir

Galian Tanah 28.98 M³ 93,275.00 2,703,044.21

Urugan Pasir 3.79 M³ 217,310.00 824,039.52

Urugan Tanah Kembali 7.24 M³ 104,230.00 755,128.11

b Pekerjaan Pasangan
Dan Beton

Pondasi Batu Kali 1:4 2.52 M³ 1,618,426.10 4,078,433.77

Cor Lantai Kerja 1.90 M³ 1,413,690.00 2,680,356.24

Pondasi Poer Plat

1. Beton K225 2.19 M³ 2,687,544.00 5,885,721.36

2. Tulangan 626.83 Kg 16,605.90 10,409,029.80

3. Bekisting 19.20 M² 225,336.00 4,326,451.20


KONTRAK REALISASI
NO URAIAN PEKERJAAN
VOL SAT HARGA SATUAN TOTAL HARGA VOL BOBOT JUMLAH HARGA

Sloof 20/25
1. Beton K225 0.56 M³ 2,687,544.00 1,505,024.64

2. Tulangan 118.84 Kg 16,605.90 1,973,418.59

3. Bekisting 8.40 M² 238,836.00 2,006,222.40

Kolom 20/25    

1. Beton K225 1.26 M³ 2,687,544.00 3,386,305.44

2. Tulangan 188.28 Kg 16,605.90 3,126,499.07

3. Bekisting 12.15 M² 446,888.00 5,429,689.20

Ring Balok 20/30    

1. Beton K225 0.67 M³ 2,687,544.00 1,806,029.57

2. Tulangan 90.25 Kg 16,605.90 1,498,675.83

3. Bekisting 16.95 M² 455,888.00 7,727,301.60

Cor lantai Beton Bertulang    

1. Beton K225 10.06 M³ 2,687,544.00 27,043,411.50

2. Tulangan 1,391.87 Kg 16,605.90 23,113,238.76

3. Bekisting 21.00 M² 225,336.00 4,732,056.00


KONTRAK REALISASI
NO URAIAN PEKERJAAN
VOL SAT HARGA SATUAN TOTAL HARGA VOL BOBOT JUMLAH HARGA

a Pekerjaan Atap

Kuda-Kuda Kayu Klas I 0.61 M³ 8,662,200.00 5,305,424.26

Gording Kayu Klas II 8.40 M³ 4,735,320.00 39,776,688.00

Listplank Kayu Klas II 30.40 M³ 73,915.00 2,247,016.00

Atap Spandek Zincalume 52.00 M² 247,115.00 12,849,980.00

Nok atap spandeck 8.00 M' 115,578.00 924,624.00

d Jembatan Timbang 1.00 Ls 238,000,000.00 238,000,000.00 0.71 4.90 169,694,000.00


e Pekerjaan Perlengkapan

Komputer Merk HP 15” LCD


1.00 Unit 8,000,000.00 8,000,000.00
Monitor + Origina Windows 8

Dot Matric Epson Printer Lx-


1.00 Unit
310 + KertasNCR Continuous 4,000,000.00 4,000,000.00
Form 9-/12" x 11"/2

Meja & Kursi Komputer 1.00 Unit 3,000,000.00 3,000,000.00


TOTAL 6 (PEKERJAAN JEMBATAN
433,886,209.06 4.90 169,694,000.00
TIMBANG)
JUMLAH 3,464,107,422.92 72.78 2,399,446,122.67
PPN 10% 346,410,742.29 239,944,612.27
JUMLAH TOTAL 3,810,518,165.21 2,639,390,734.94
DIBULATKAN 3,810,518,000.00 2,639,391,000.00

PROGRESS REALISASI FISIK S/D PERIODE BULAN VI = 72.78 %


Papan Nama proyek
BACK UP PEK TALUD STA. 00+000 (AWAL) s/d STA. STA. 00+86
DOKUMENTASI TALUD STA. 00+000 (AWAL) s/d STA. STA. 00+86
BACK UP PEK TALUD STA. 00+096 s/d STA. STA. 00+200
DOKUMENTASI TALUD STA. 00+096 s/d STA. 00+200
BACK UP PEK TALUD STA. 00+200 s/d STA. 00+280
DOKUMENTASI TALUD STA. 00+200 s/d STA. 00+280
BACK UP PEK TALUD STA. 00+280 s/d STA. 00+410 (AKHIR)
STA. 00+280 s/d STA. 00+410 (AKHIR)
BACK UP PEKERJAAN GALIAN DRAINASE
DOKUMENTASI PEKERJAAN GALIAN DRAINASE
BACK UP PEKERJAAN PAS. BATU DRAINASE
DOKUMENTASI PEKERJAAN PAS. BATU DRAINASE
JEMBATAN TIMBANG
TERIMAKASIH