CONSTRUCCION DE

EDIFICACIONES
TEMA:
METRADO Y
PRESUPUESTO DE UN
CERCO PERIMETRICO

MG. ING. SAULO N. ROMERO CASTILLO


PLANOS DE
CERCO
PERIMETRICO
ARQUITECTURA

1 2
3.80 m

MURO
0.25 m A

COLUMNA COLUMNA

0.25 m
ACTIVIDAD:
•METRADO DE DE MUROS
•METRADO DE TARRAJEO DE MUROS Y COLUMNAS
ELEVACION
1 2
3.80 m

VIGA
C C
O O
L L
U U
4.20 m M M
N N
A A
S S
N.P.T: + 0.15
CIMENTACION
1 2
3.80 m

C-1 C-1

1
Z-1 Z-1

ACTIVIDAD:
•METRADOS DE COLUMNAS Y ZAPATAS
•METRADO DE CIMIENTO CORRIDO Y SOBRECIMIENTO
DETALLE DE CIMIENTO CORRIDOS
0.13

N.P.T : + 0.15
0.55 N.T.N: + - 0.00

0.09 h
0.60

0.24 L 0.13 A

N.F.C : - 0.80

0.50
1-1
DETALLE 0.15
DE
ZAPATAS
RECUBRIMIENTOS:
•COLUMNAS: 2.50 cm
• ZAPATAS: 7.50 cm.

4.20 m
Z-1:
1.00 m x 1.00 m x 0.50 m

N.P.T : + 0.15 N.P.T : + 0.15


N.T.N: + - 0.00

0.30
0.50
N.F.Z : - 1.30

1.00 ACERO EN ZAPATAS:


1Ø 1/2; 1@0.20 (EN AMBOS
SENTIDOS)
DETALLE DE COLUMNAS

0.25

0.25

6 Ø 5/8”

ESTRIBOS:
1Ø 3/8; 1@0.05 ; 2@0.10 ;
3@0.15
RTO@0.20m
DETALLE DE VIGAS

0.25

0.20

4 Ø 1/2”

ESTRIBOS:
1Ø 3/8; 1@0.05 ; 2@0.10 ;
3@0.15
RTO@0.20m
METRADO DE
CERCO
PERIMETRICO
01.00.00 MOVIMIENTO DE TIERRAS

01.01.00 EXCAVACION EN ZAPATAS:

VOL EXC. = 1.00 m x 1.00 m x 1.40 m x 2

VOL EXC. = 2.80 m3

01.02.00 EXCAVACION EN CIMIENTO CORRIDO:

VOL EXC. = 2.80 m x 0.50 m x 0.60 m

VOL EXC. = 0.84 m3


01.03.00 RELLENO EN ZAPATAS: (CON MATERIAL PROPIO)

VOL RELL. = 0.75 m2 x 0.80 m x 2

VOL RELL. = 1.20 m3 / 0.80

VOL RELL. = 1.50 m3

01.04.00 RELLENO EN CIMIENTO CORRIDO: (CON MAT. PRO)

VOL RELL. = 3.55 m x 0.37 m x 0.20 m

VOL RELL. = 0.26 m3 / 0.80

VOL RELL. = 0.325 m3


01.05.00 ELIMINACION DE MATERIAL EXCEDENTE:

VOL ELIM. = ( (2.80 + 0.84) * 1.25) – ( 1.50 + 0.325)

VOL ELIM. = 2.73 m3


02.00.00 CONCRETO SIMPLE

02.01.00 CONCRETO EN CIMIENTO CORRIDO:

VOL CON. = 3.55 m x 0.50 m x 0.60 m

VOL CON. = 1.07 m3

02.02.00 CONCRETO EN SOBRECIMIENTO:

VOL EXC. = 3.55 m x 0.13 m x 0.55 m

VOL EXC. = 0.25 m3


02.03.00 CONCRETO EN SOLADO EN ZAPATAS:

VOL EXC. = 1.00 m x 1.00 m x 0.10 m

VOL EXC. = 0.10 m3


03.00.00 CONCRETO ARMADO
03.01.00 ZAPATAS:
03.01.01 CONCRETO F’c: 210 Kg/Cm2 EN ZAPATAS:

VOL CON. = 1.00 m x 1.00 m x 0.50 m x 2

VOL CON. = 1.00 m3

03.01.02 ACERO F’y: 4200 Kg/Cm2 EN ZAPATAS:

( Ø ½” )

LONG. = ( 0.85 m x 5 x 2 ) x 2 = 17.00 m

PESO = 17.00 m x 0.94 kg/m = 16.90 kg


03.02.00 COLUMNAS:
03.02.01 CONCRETO F’c: 210 Kg/Cm2 EN COLUMNAS:

VOL CON. = 0.25 m x 0.25 m x 5.15 m x 2

VOL CON. = 0.64 m3

03.02.02 ENCOFRADO EN COLUMNAS:

AREA = ( 0.85 m x 5 x 2 ) x 2

AREA = 17.00 m
03.02.03 ACERO F’y: 4200 Kg/Cm2 EN COLUMNAS:
* LONG. = 6.00 m x 6 x 2
LONG. = 72.00 m (Acero Longitudinal)

* PESO = 72.00 m x 1.552 kg/m


PESO = 111.74 kg (Acero Longitudinal)

* PESO = 0.95 m x 32 x 0.56 kg/m


PESO = 17.02 kg (Acero Transversal – Estribo)

PESO TOTAL = 111.74 kg + 17.02 kg


PESO TOTAL = 128.76 kg
03.03.00 VIGAS:
03.03.01 CONCRETO F’c: 210 Kg/Cm2 EN VIGAS:

VOL CON. = 3.55 m x 0.25 m x 0.20 m

VOL CON. = 0.18 m3

03.03.02 ENCOFRADO EN VIGAS:

AREA = 3.55 m x 0.50 m

AREA = 1.78 m
03.03.03 ACERO F’y: 4200 Kg/Cm2 EN VIGAS:
* LONG. = 6.00 m x 6 x 2
LONG. = 72.00 m (Acero Longitudinal)

* PESO = 72.00 m x 1.552 kg/m


PESO = 111.74 kg (Acero Longitudinal)

* PESO = 0.95 m x 32 x 0.56 kg/m


PESO = 17.02 kg (Acero Transversal – Estribo)

PESO TOTAL = 111.74 kg + 17.02 kg


PESO TOTAL = 128.76 kg
04.00.00 MUROS Y TABIQUERIA
04.01.00 MURO DE SOGA:

AREA MURO = 3.55 m x 3.80 m

AREA MURO = 13.49 m3

05.00.00 REVOQUES Y REVESTIMIENTO


05.01.00 TARRAJEO EN MUROS:

AREA TARR. = 3.55 m x 3.80 m x 2

AREA TARR. = 26.98 m3


CALCULO DE
INSUMOS PARA
CERCO
PERIMETRICO
RESUMEN DE METRADOS

01.00.00 MOVIMIENTO DE TIERRAS

01.01.00 EXCAVACION EN ZAPATAS……. 2.80 m3

01.02.00 EXCAVACION EN CIMIENTO C… 0.84 m3

01.03.00 RELLENO EN ZAPATAS………… 1.50 m3

01.04.00 RELLENO EN CIMIENTO C……..0.325 m3

01.05.00 ELIMINACION DE MAT. EXC........ 2.73 m3


02.00.00 CONCRETO SIMPLE

02.01.00 CONCRETO EN CIMIENTO……. 2.80 m3

02.02.00 CONCRETO EN SOBRECIM…… 0.84 m3

02.03.00 CONCRETO EN SOLADO ZAP… 1.50 m3

03.00.00 CONCRETO ARMADO

03.01.00 ZAPATA

03.01.01 CONCRETO EN ZAPATAS ………. 1.00 m3

03.01.02 ACERO EN ZAPATAS……….…… 16.90 m3


03.02.00 COLUMNAS

03.02.01 CONCRETO EN COLUMNAS.…… 0.64 m3

03.02.02 ENCOFRADO EN COLUMNAS… 17.00 m3

03.02.02 ACERO EN COLUMNAS….…… 128.76 m3

03.03.00 VIGAS

03.03.01 CONCRETO EN VIGAS…………… 0.18 m3

03.03.02 ENCOFRADO EN VIGAS……….... 1.78 m3

03.03.03 ACERO EN VIGAS….…………... 128.76 m3


04.00.00 MUROS Y TABIQUERIA

04.01.00 MUROS DE SOGA…………...……. 2.80 m3

05.00.00 REVOQUES Y REVESTIMIENTO

05.01.00 TARRAJEO EN MUROS ………... 28.96 m3


PROPORCIONES EN EL CONCRETO

• TARRAJEO MUROS: 1:5 C: A


• MORTERO DE MURO: 1:4 C:A
• CIMIENTO CORRIDO: 1:10 + 30%PM C: H
• SOBRECIMIENTO: 1:8 + 25% PM C: H
• SOLADO ZAPATAS : 1:12 C: H
• CONCRETO ZAPATAS : 1: 2 : 2 C: A : P
• CONCRETO COLUMNAS: 1: 2 : 2 C: A : P
• CONCRETO VIGAS : 1: 2 : 2 C: A : P
PRECIOS

MANO DE OBRA
•CAPATAZ: S/. 24.20

•OPERARIO: S/. 22.00

•OFICIAL: S/. 19.00

•PEON: S/. 16.80

•OPERADOR EQUIPO LIVIANO: S/. 22.00


PRECIOS

MATERIALES
•CEMENTO TIPO MS: S/. 25.00 / Bolsa

•CEMENTO TIPO I: S/ 23.50 / Bolsa

•ARENA GRUESA: S/ 45.00 / m3

•PIEDRA CHANCADA: S/. 48.00 / m3

•HORMIGON : S/. 35.00 / m3

•PIEDRA MEDIANA : S/. 38.00 / m3


•AGUA : S/. 5.50 / m3
PRECIOS

EQUIPOS Y MAQUINARIA
•CAMION VOLQUETE: S/. 120.00 / HM

•CARGADOR FRONTAL: S/ 220.00 / HM

•MEZCLADORA: S/ 15.00 / HM
CALCULO DE LA CANTIDAD DE HORA HOMBRE
CUADRILLA x JORNAL

CANT. M.O =

RENDIMIENTO

CALCULO DE LA CANTIDAD DE HORA MAQUINA


CUADRILLA x JORNAL

CANT. M.O =

RENDIMIENTO
CALCULO DE COSTOS
EN INSUMOS
•M.O
•MATERIALES
•EQUIPOS
01.01.00 EXCAVACION EN ZAPATAS:
CALCULO DE LA CANTIDAD DE MANO DE OBRA

CUADRILLA x JORNAL

CANT. M.O =

RENDIMIENTO

0.10 x 8

CANT. CAPATAZ = = 0.32 HH

2.50
1.00 x 8

CANT. PEON = = 3.20 HH

2.50
CALCULO DEL PRECIO
PRECIO M.O = CANT. M.O x PRECIO UNT.

MANO DE OBRAS

CANT. CAPATAZ = 0.32 HH x S/. 24.20 = S/. 7.74

CANT. PEON = 3.20 HH x S/. 16.80 = S/. 53.76

S/. 61.50
HERRAMIENTAS MANUALES

HERRAMIENTAS M. = 3 % DE LA M. O.

HERRAMIENTAS M. = 0.03 x S/. 61.50

HERRAMIENTAS M. = S/. 1.84


PRECIO DE LA PARTIDA EXCAVACION EN ZAPATAS

EXC. ZAPATAS = PRECIO DE M.O + PRECIO DE H.M

EXC. ZAPATAS = S/. 61.50 + S/. 1.84

EXC. ZAPATAS = S/. 63.34 / m3

COSTO DE EXC. = EXC. ZAPATAS x METRADO


ZAPATAS
COSTO DE EXC. = S/. 63.34 / m3 x 2.80 m3
ZAPATAS
COSTO DE EXC. = S/. 177.35
ZAPATAS
01.02.00 EXCAVACION EN CIMIENTO C.:
CALCULO DE LA CANTIDAD DE MANO DE OBRA

CUADRILLA x JORNAL

CANT. M.O =

RENDIMIENTO

0.10 x 8

CANT. CAPATAZ = = 0.229 HH

3.50
1.00 x 8

CANT. PEON = = 2.286 HH

3.50
CALCULO DEL PRECIO
PRECIO M.O = CANT. M.O x PRECIO UNT.

MANO DE OBRAS

CANT. CAPATAZ = 0.229 HH x S/. 24.20 = S/. 5.54

CANT. PEON = 2.286 HH x S/. 16.80 = S/. 38.40

S/. 43.94
HERRAMIENTAS MANUALES

HERRAMIENTAS M. = 3 % DE LA M. O.

HERRAMIENTAS M. = 0.03 x S/. 43.94

HERRAMIENTAS M. = S/. 1.32


PRECIO DE LA PARTIDA EXCAVACION EN CIMIENTO CORRIDO

EXC. C. C = PRECIO DE M.O + PRECIO DE H.M

EXC. C. C = S/. 43.94 + S/. 1.32

EXC. C. C = S/. 45.26 / m3

COSTO DE EXC. = EXC. C. C x METRADO


C. C
COSTO DE EXC. = S/. 45.26 / m3 x 0.84 m3
C. C
COSTO DE EXC. = S/. 38.02
C. C
01.03.00 RELLENO EN ZAPATAS :
CALCULO DE LA CANTIDAD DE MANO DE OBRA

CUADRILLA x JORNAL

CANT. M.O =

RENDIMIENTO

0.10 x 8

CANT. CAPATAZ = = 0.114 HH

7.00
1.00 x 8

CANT. PEON = = 1.143 HH

7.00
CALCULO DEL PRECIO
PRECIO M.O = CANT. M.O x PRECIO UNT.

MANO DE OBRAS

CANT. CAPATAZ = 0.114 HH x S/. 24.20 = S/. 2.76

CANT. PEON = 1.143 HH x S/. 16.80 = S/. 19.20

S/. 21.96
HERRAMIENTAS MANUALES

HERRAMIENTAS M. = 3 % DE LA M. O.

HERRAMIENTAS M. = 0.03 x S/. 21.96

HERRAMIENTAS M. = S/. 0.66


PRECIO DE LA PARTIDA RELLENO EN

ZAPATAS

RELL. ZAP. = PRECIO DE M.O + PRECIO DE H.M

RELL. ZAP. = S/. 21.96 + S/. 0.66

RELL. ZAP. = S/. 22.62 / m3

COSTO DE RELL. = RELL. ZAP. x METRADO


ZAP.
COSTO DE RELL. = S/. 22.62 / m3 x 1.50 m3
ZAP.
COSTO DE RELL. = S/. 33.93
ZAP.
01.04.00 RELLENO EN CIMIENTO CORRIDO :
CALCULO DE LA CANTIDAD DE MANO DE OBRA

CUADRILLA x JORNAL

CANT. M.O =

RENDIMIENTO

0.10 x 8

CANT. CAPATAZ = = 0.114 HH

7.00
1.00 x 8

CANT. PEON = = 1.143 HH

7.00
CALCULO DEL PRECIO
PRECIO M.O = CANT. M.O x PRECIO UNT.

MANO DE OBRAS

CANT. CAPATAZ = 0.114 HH x S/. 24.20 = S/. 2.76

CANT. PEON = 1.143 HH x S/. 16.80 = S/. 19.20

S/. 21.96
HERRAMIENTAS MANUALES

HERRAMIENTAS M. = 3 % DE LA M. O.

HERRAMIENTAS M. = 0.03 x S/. 21.96

HERRAMIENTAS M. = S/. 0.66


PRECIO DE LA PARTIDA RELLENO EN
CIMIENTO CORRIDO

RELL. C. C = PRECIO DE M.O + PRECIO DE H.M

RELL. C. C = S/. 21.96 + S/. 0.66

RELL. C. C = S/. 22.62 / m3

COSTO DE RELL. = RELL. C .C. x METRADO


C. C
COSTO DE RELL. = S/. 22.62 / m3 x 0.325 m3
C. C
COSTO DE RELL. = S/. 7.35
C. C
01.05.00 ELIMINACION DE MATERIAL
EXCEDENTE:
CALCULO DE LA CANTIDAD DE MANO DE OBRA

CUADRILLA x JORNAL

CANT. M.O =

RENDIMIENTO

0.10 x 8
CANT. CAPATAZ = = 0.0017 HH

480.00
2.00 x 8
CANT. PEON = = 0.03333 HH

480.00
CALCULO DE LA CANTIDAD DE EQUIPO PESADO
CUADRILLA x JORNAL

CANT. E.P =

RENDIMIENTO

1 x 8
CANT. CARGADOR = = 0.0167 HH

480.00
8.00 x 8
CANT. VOLQUETE = = 0.1333 HH

480.00
CALCULO DEL PRECIO
PRECIO M.O = CANT. M.O x PRECIO UNT.

MANO DE OBRAS

CAPATAZ = 0.0017 HH x S/. 24.20 = S/. 0.04

PEON = 0.0333 HH x S/. 16.80 = S/. 0.56

S/. 0.60
EQUIPOS Y H.M

HERRAMIENTAS M. = 3 % DE LA M. O.

HERRAMIENTAS M. = 0.03 x S/. 0.60

HERRAMIENTAS M. = S/. 0.018


CARGADOR F. = 0.0167 HH x S/. 220.00 = S/. 3.67

VOLQUETE. = 0.1333 HH x S/. 120.00 = S/. 16.00

PRECIO DE LA PARTIDA ELIMINACION DE MAT. EXCENDETE

ELI. MAT. EXC. = PRECIO DE M.O + PRECIO DE EQU. Y H.M

ELI. MAT. EXC. = S/. 0.60 + S/. 0.018 + S/. 3.67 + S/. 16.0

ELI. MAT. EXC. = S/. 20.29 / M3


COSTO ELI. = PRECIO DE M.O + PRECIO DE EQU. Y H.M

COSTO ELI.. = S/. 0.60 + S/. 0.018 + S/. 3.67 + S/. 16.0

COSTO ELI. = S/. 20.29 / M3


02.00.00 CONCRETO SIMPLE

02.01.00 CONCRETO EN CIMIENTO CORRIDO:


CALCULO DE LA CANTIDAD DE MANO DE OBRA

0.10 x 8
CANT. CAPATAZ = = 0.032 HH

25.00
1.00 x 8
CANT. OPERARIO = = 0.32 HH

25.00
2.00 x 8
CANT. OFICIAL = = 0.64 HH

25.00
8.00 x 8
CANT. PEON = = 2.56 HH

25.00
1.00 x 8
CANT. OPER. EQ = = 0.32 HH

25.00
CALCULO DE LA CANTIDAD DE EQUIPO PESADO

CUADRILLA x JORNAL

CANT. E.P =
RENDIMIENTO

1 x 8
CANT. MEZCLAD. = = 0.32 HH

25.00
CALCULO DE LA CANTIDAD DE MATERIALES
CIMIENTO CORRIDO (1 : 10 + 30%PG)

1 m3 Concreto = 0.70 m3 (cemento + Horm.) +


0.30 m3 Piedra Grande
CEMENTO
0.70 35.3147 P3
• CANT. CEMENTO
10 = 1 m31 x
m3
x

CANT. CEMENTO = 2.47 P3

CANT. CEMENTO = 2.47 Bls


CALCULO DE LA CANTIDAD DE MATERIALES
1 m3 Concreto = 0.70 m3 (cemento + Horm.) + 0.30 m3
Piedra Grande
HORMIGON

• CANT. HORMIGON = 0.70


1 m3 x

CANT. HORMIGON = 0.70 m3 1

PIEDRA GRANDE
• CANT. PIEDRA G. = 1 m3 x 0.30

CANT. PIEDRA G. = 0.30 m3


CALCULO DEL PRECIO
PRECIO M.O = CANT. M.O x PRECIO UNT.

MANO DE OBRA

CAPATAZ = 0.032 HH x S/. 24.20 = S/. 0.77

OPERARIO = 0.320 HH x S/. 22.00 = S/. 7.04

OFICIAL = 0.640 HH x S/. 19.00 = S/. 12.16

PEON = 2.560 HH x S/. 16.80 = S/. 43.01

OPER. EQ. = 0.320 HH x S/. 22.00 = S/. 7.04

S/. 70.02
MATERIALES

CEMENTO TIPO MS = 2.47 bls x S/. 25.00 = S/. 72.50

HORMIGON = 0.83 m3 x S/. 35.00 = S/. 29.05

PIEDRA M. 6” = 0.30 m3 x S/. 38.00 = S/. 11.40

AGUA = 0.135 m3 x S/. 5.50 = S/. 0.74

S/. 113.69
EQUIPOS Y H.M

HERRAMIENTAS M. = 3 % DE LA M. O.

HERRAMIENTAS M. = 0.03 x S/. 70.02

HERRAMIENTAS M. = S/. 2.10

MEZCLADORA = 0.32 HH x S/. 15.00


MEZCLADORA = S/. 4.80
PRECIO DE LA PARTIDA CONCRETO EN CIMIENTO CORRIDO

PRECIO CIMIENTO = PRECIO DE M.O + PRECIO DE


MATERIALES + PRECIO DE EQU. Y H.M

PRECIO CIMIENTO = S/. 70.02 + S/. 113.69 + S/. 4.80 + S/. 2.10

PRECIO CIMIENTO = S/. 190.61 / M3


PRESUPUESTO
CERCO
PERIMETRICO
APORTE UNITARIO EN ENCOFRADO
PARA SOBRECIMIENTO
APORTE UNITARIO EN ENCOFRADO
PARA SOBRECIMIENTO
APORTE UNITARIO EN ENCOFRADO
PARA SOBRECIMIENTO