PREPARED BY
NG KAI CHUN (1101G13410) SHUM WEN JUN (0325151)
SOW WEI HENN (0324998) NGEOW YEE LING (0329178)
FIRZANA HASMI (0324838) SAHIL GUNESH (0328569)
PENNY LEUNG (0328245) HAROON FALEEL (0322197)
PROJECT FOR
DOUBLE STOREY HOUSE (TYPE B)
MEASUREMENT 4 - PRESENTATION
EMPLOYER
PELANGI HOME SDN BHD
NO. 604A, JLN SS9A/13, SERI M&E ENGINEER
SETIA ZATH PERUNDING SDN BHD
47300 PETALING JAYA, 8, HALA DATOH, JLN DATOH,
SELANGOR DARUL EHSAN 3000 IPOH,
PERAK DARUL EHSAN
ARCHITECT
CSP ARCHITECT
1F-3A,JLN SS26/9, QUANTITY SURVEYOR
TMN MAYANG JAYA, THL CONSULTANTS SDN. BHD.
SELANGOR DARUL EHSAN NO.2-2-2, JLN SEMARAK API 3,
DIAMOND SQUARE COMERCIAL
CENTRE,
C&S ENGINEER WILAYAH PERSEKUTUAN, 53000
K.L.CHAN & ASSOCIATES KUALA LUMPUR
36-B&C,JLN PETALING UTAMA 9,
PETALING UTAMA BATU 7,
OFF JLN KLANG LAMA, 46000 PETALING JAYA,
SELANGOR DARUL EHSAN
MEASUREMENT 4 - PRESENTATION
LOCATION
ADDRESS : JALAN
PUTRA PRIMA TENGAH,
47100, SELANGOR
DARUL EHSAN.
MEASUREMENT 4 - PRESENTATION
ROOF PLAN
MEASUREMENT 4 - PRESENTATION
SIDE ELEVATION
MEASUREMENT 4 - PRESENTATION
SECTION DRAWING
MEASUREMENT 4 - PRESENTATION
TENDER DOCUMENTS
MEASUREMENT 4 - PRESENTATION
DECLARATION OF NON-COLLUSION
FORM OF TENDER
• A form for
tenderer to insert
his “tender
amount” and
proposed
“completion
time” &
agreement to
validity period.
MEASUREMENT 4 - PRESENTATION
INSTRUCTIONS TO TENDERERS
CONDITIONS OF TENDERING
FORM OF CONTRACT
MEASUREMENT 4 - PRESENTATION
PRELIMINARIES
PREAMBLES
• Explanation of a tender
document
• Generally interprets the
tender document
• Generally define
descriptions in BQ
according to SMM2
clauses
• Background to the
document
MEASUREMENT 4 - PRESENTATION
CONTENTS
SPECIFICATIONS
Descriptions Page No.
• Documented requirements to be
satisfied by a material, design,
product, or service for the project
MEASUREMENT 4 - PRESENTATION
BILLS OF QUANTITIES
MEASUREMENT 4 - PRESENTATION
LISTS OF DRAWINGS
• It is the list of all the drawings which are found in the project
MEASUREMENT 4 - PRESENTATION
SCHEDULE OF FINISHES
• List of all prime cost and provision sum for easy reference.
• Prime cost sum is the sum included in the contract to cover specialist work and
supply of specific materials which is performed by nominated sub-contractors or
nominated suppliers.
• Provisional sum is for the works for which the full extent and character cannot be
determined precisely.
MEASUREMENT 4 - PRESENTATION
APPENDIX “F”
TO:
SIR,
BANK GUARANTEE
event of a successful This guarantee is effective from the date of the tender documents submitted by
tender. the tenderer, to wit ................................... and is to remain in force until ………………...
SIGN: ..........................................................................................................
ADDRESS: ..................................................................................................
DATE : .........................................................................................................
MEASUREMENT 4 - PRESENTATION
of business of Bank Company) (hereinafter called the “Guarantor” of the one Part and
PELANGI HOMES SDN BHD (hereinafter called the “Government”) of the other Part.
WHEREAS
Government ........................................................................................................
..........................................................................................................................
..........................................................................................................................
WE, the undersigned at the request of the Contractor irrevocably undertake a guarantee
The Guarantor has agreed to guarantee the due performance of the Contract in the manner
hereinafter appearing.
1. On the Government’s first written demand, the Guarantor shall forthwith pay to the
Government the amount specified in such demand not withstanding any contestation or
protest by the Contractor or Guarantor or by any other third party and without proof or
conditions. Provided always that the total of all demands so made shall not exceed the
sum of Ringgit Malaysia .....................................................................................
(state the amount of bond in words) (RM.......................................) and the total
amount recoverable against the Guarantor under this Agreement shall not exceed the said
sum.
MEASUREMENT 4 - PRESENTATION
2. The Government reserve the right to make any partial demands if it shall so desire and Signed for and on behalf of the )
........................................................
the total of all such partial demands so made shall not exceed the sum of Ringgit Malaysia
Said Guarantor in the presence of)
(state the amount of bond in words) (RM............................) and the liability of the Name : .............................................
Guarantor to pay the Government the aforesaid shall correspondingly be reduced Designation : .....................................
proportionate to any payment of partial demand having been made by the Guarantor. .......................................................
Bank Company
3. The Guarantor shall not be discharged or released from this Guarantee by any
arrangement between the Contractor and the Government with or without the
consent of the Guarantor or by any alteration in the obligation undertaken by the
........................................................
Contractor or by any forbearance, whether as to payment, time, performance or (Witness)
otherwise.
Name : .............................................
4. The Guarantee given by the Guarantor is a continuing guarantee. This Agreement Designation : .....................................
shall be irrevocable and shall initially remain in force and effect until …………….
.......................................................
(hereinafter referred to as the “Initial Expiry Date”) being the end of a period of
Bank Company
twelve (12) calendar months after either the expiry date of the Contract or the last
delivery of the Articles whichever is later. The Guarantor shall upon the request of
the Government extend the Initial Expiry Date of this guarantee for a further period
of one (1) calendar year from the Initial Expiry Date (hereinafter referred to as the Signed for and on behalf of the )
........................................................
“Extended Expiry Date”) and the Guarantee shall be so extended. The maximum
Said Guarantor in the presence of)
aggregate amount that the Government shall be entitled to under this Agreement
Name : .............................................
shall not exceed the said Sum of Ringgit: ................................................... Designation : .....................................
(state the amount of bond in words) (RM............................). .......................................................
Department’s Chop
5. All whatsoever obligations and liabilities of the Guarantor under this Agreement
shall cease upon the determination of this Agreement on the Initial Expiry Date or
the Extended Expiry Date as the case may be save to the extent that the
Government shall previously have called upon the Guarantor in writing to pay ........................................................
specified moneys payable under the Contract then remaining outstanding. (Witness)
6. ALL CLAIMS, IF ANY, INRESPECT OF THIS GUARANTEE MUST BE RECEIVED BY THE Name : .............................................
BANK COMPANY DURING THE VALIDITY PERIOD OF THIS GUARANTEE OR WITHIN Designation : .....................................
FOUR (4) WEEKS FROM THE EXPIRY DATE OF THIS GUARANTEE WHICHEVER IS .......................................................
THE LATER. IN WITNESS WHEREOF the parties hereto have hereunto set their Department’s Chop
hands the day and year first above written.