Adjustments for Changes in Cost

Prepared by :- Under supervision :-


Eng / Hatem Shalaby Dr / Reda Sabry

Logo Goes Here 1


What is Red Book
(FIDIC 99)opinion ?

EMAIL US:
sales@slidestore.com
But

Logo Goes Here 2


Why sub-clause 13.8 (FIDIC 1999 Red book) ?

Eliminate volume of disputes


Fair Determination for Parties
Reduce Uncertainty
Increase Transparency between Parties

How does it Play ?

Logo Goes Here 3


Case Study << Caesar Project >>

P =a+bM /M +cS /S +dE /E .


n n o n o n o

Also ;

1. Mn .. Materials Cost @ Period of Time (n)


2. Mo .. Materials Cost @ Base Date (o)
3. Sn .. Subcontractors Cost @ Period of time(n)
4. So .. Subcontractors Cost @ Base Date
5. En .. Equipments Cost @ Period of Time (n)
6. Eo .. Equipments Cost @ Base Date.
Logo Goes Here 4
Assumption for Formula

Logo Goes Here 5


Change Analysis

Materials Cost
Increased by 45 %

Subcontractors Cost
Increased by 20 %

Equipment's Cost
increased by 40 %

Overall (Indirect Cost & Profit)


It may be changed but not according
to sub-clause (13.8) ,
Under sub-clause (13.7)

Logo Goes Here 6


Applying for Formula

Logo Goes Here 7


Case for Discussion ?

*** Contractor compensate all available floats of the


project. The owner didn`t use any , but he caused
delay about 50 days up on critical activities And Cost
of Materials , Subcontractors and Equipment is OR NOT ?
decreased within these 50 days (Contractor procured to And Why ?
required resources with high value ) Formula can be
applied ?
Logo Goes Here 8
QUESTIONS !!!