Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Resource Allocation
Activity Slope
Table 9-1
Table 9-2
Figure 9-1a
Figure 9-1b
Figure 9-1c
Figure 9-1d
Figure 9-1e
Cost-Crash Curve
Figure 9-2
Resource Allocation
It
Resource Loading
Resource
Resource A
Figure 9-6a
Resource B
Figure 9-6b
Resource Leveling
Less
hands-on management is
required
May be able to use just-in-time
inventory
Improves morale
Fewer personnel problems
Resource Leveling
When
Continued
An approach, such as a
rule of thumb, that yields
a good solution that may
or may not be optimal.
Heuristic Methods
The
soon as possible
As late as possible
Shortest task first
Most resources first
Minimum slack first
Most critical followers
Most successors
Arbitrary
Heuristic Methods
These
Continued
Optimization Methods
Finds
Schedule slippage
Resource utilization
In-process inventory
Schedule Slippage
The
Resource Utilization
The
In-Process Inventory
This
Heuristic Techniques
Multi-projects
scheduling method
Minimum late finish time
Greatest resource demand
Greatest resource utilization
Most possible jobs
Optimism
Capacity should be equal to demand
The Student Syndrome
Multitasking to reduce idle time
Assuming network complexity makes no difference
Management cutting time to motivate workers
Game playing
Early finishes not canceling out late finishes
Required
Find the
Given
theall-normal
followingschedule
information
and cost.
Find the all-crash
regarding
a construction
scheduleproject.
and cost.
Find the total cost required to expedite all
activities from all-normal to all-crash.
Find the least-cost plan for the all-crash
time schedule.
Activity
1-2
1-3
1-4
2-5
2-6
3-6
4-5
4-7
5-7
6-7
6-8
7-8
Normal schedule
Time
(weeks)
3
4
3
5
4
8
6
10
8
5
6
7
Cost
(000)
$15
26
21
15
12
20
15
25
20
15
18
28
Crash Schedule
Time
(weeks)
1
2
2
3
2
4
4
6
5
3
3
5
Cost
(000)
$25
32
30
24
20
28
20
40
28
21
24
38