Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Shresth Suneja
M032
MBA TECH CIVIL
INTRODUCTION
India Bulls Real Estate Ltd is a leading real
estate company across India and the main aim
of the company is to construct residential and
commercial projects in each state of India.
Over the past years India Bulls has evolved as
a very successful company and promises to
continue to be at the top with high quality of
work and timely possession.
The company has been expanding since the
year 2000. The company generates an annual
turnover of Rs. 2000cr.
SYNOPSIS
GOALS
regional office of the Northern India
division
Two levels retail area at GF &FF
three main companies that will
operate from this commercial
complex will be :
Indiabulls Housing Finance
Limited( IBHFL), Indiabulls Real
Estate Limited (IBREL), and
Indiabulls Ventures Limited (IBVL).
Excavation
Ramp along front face external road
Three stages
1st cut : 5-6 m
2nd cut : 4-5m
3rd cut : primarily for tower area
SHOTCRETING
The pile wall surface to be treated shall be exposed
and loose soil shall be cleaned manually using trowels
Pre wetting of the earth surface between piles by
water spray
Prior to wetting of surface, steel wire mesh (100 mm x
100 mm x 3mm thick) shall be fixed
The shortcrete shall begin from top of cut slope and
proceed downwards
Specifications:
Water / Cement ratio 0.5
Water and Air pressure 1-1.5 kg/cm^2
Shotcrete Admixture used- Dr. Fixit integral waterproofing
powder Dosage : 500 gms per 50 kg of cement
Cement Portland Pozzolana ( Fly Ash Based)
Water Potable tap water
UPLIFT ANCHORS
Due to the water table being
too high (4 to 5m from NGL)
passive anchors were used to
counter uplift pressure of
underground water in nontower area, these anchors are
passive anchors in nature
having 3nos of 32mm dia of
TMT steel grouted in 200mm x
12mtr bore holes from PCC
bottom with neat cement and
non- shrinkage admixture
CEBEX-100, and lastly joint
with main reinforcement of raft.
Dewatering
Motors of 1.5 hp to
3.0 hp to be
provided and
operated for 24 hrs.
Total planned
capacity is 40-50hp
as per required and
as per water strata.
Providing all bores
and pumps
externally in line of
existing shore piles
to avoid damage
during execution of
soil retention work.
Dewatering shall be
carried out till
LAYING of PCC
A layer of 100mm
thickness of PCC was
laid by pouring
concrete after dressing
the soil to desired
level. The pouring was
done using concrete
pumps.
Foundation Drawings
RAFT FOUNDATION
PLACEMENT OF
CONCRETE
COMPACTION OF CONCRETE
Each layer of Fresh Concrete was compacted by
vibrators to the minimum practicable consolidated
volume
Immersion type Vibrators was inserted in a vertical
position at intervals of about 300mm to 450mm
The vibrators were withdrawn slowly out of the
Concrete, approximately at the rate of 75mm/sec
RMC plant
RMC plant was located
just 500 m from the
site for a regular and
timely delivery of
concrete to the site.
The working of the
RMC plant acts can be
shown with the help of
a flowchart.
THANK YOU