Documentos de Académico
Documentos de Profesional
Documentos de Cultura
PROLOGUE
You are not the only one if you experience:
Equipment
suffers
unexplained
shutdown and failures or needs constant
repair.
PROLOGUE
Does
your
equipment
have
be
excess
easily
and
PROLOGUE
If
your
response
to
the
above
MAINTENANCE
or
processes
were
not
Critical
components
1935
1200
113
1960
2250
201
1970
2400
213
1980
2600
229
1990
2900
252
9
MAINTENANCE
10
11
12
GROWING EXPECTATIONS OF
MAINTENANCE
Third
Third Generation:
Generation:
Higher
Higher plant
plant
availability
availability
Greater
Greater safety
safety
Better
Better product
product quality
quality
No
No damage
damage to
to the
the
First
First Generation:
Generation:
Fix
Fix it
it when
when it
it
broke
broke
1940
Second
Second Generation:
Generation:
Higher
Higher plant
plant availability
availability
Longer
Longer equipment
equipment life
life
Lower
Lower costs
costs
1950
1960
1970
environment
environment
Longer
Longer equipment
equipment life
life
Greater
Greater cost
cost
effectiveness
effectiveness
1980
1990
2000
13
14
CHANGING MAINTENANCE
TECHNIQUES
Third
Third Generation:
Generation:
Condition
Condition monitoring
monitoring
Design
Design for
for reliability
reliability
and
and maintainability
maintainability
Hazard
Hazard studies
studies
Small,
Small, fast
fast computers
computers
Second
Second Generation:
Generation:
Scheduled
Scheduled overhauls
overhauls
First
First Generation:
Generation:
Fix
Fix it
it when
when it
it
broke
broke
1940
Systems
Systems for
for planning
planning
and
and controlling
controlling work
work
Big,
Big, slow
slow computers
computers
1950
1960
1970
Failure
Failure modes
modes and
and
effects
effects analyses
analyses
Expert
Expert systems
systems
Multiskilling
Multiskilling and
and
teamwork
teamwork
1980
1990
2000
15
Designing
equipment
with
much
greater emphasis on reliability and
maintainability.
16
Maintenance
Ensuring
that
physical
assets
or
restoring
it
to
serviceable condition.
17
OBJECTIVES OF MAINTENANCE
Elimination of
future defects
Prevent
breakdown
during operation
Forestall
rapid wear of
components
Enhance
performance
level
Productivity Improvement
through maximum
availability at
optimum cost
Reduce
maintenance cost
Ensure safety
during
operation
Maximize
operational
efficiency
Reduce idle hours
due to component
malfunctioning
18
1950
1960
1970
1980
Breakdown Maintenance
1990
Evolution of TPM
1951
Preventive Maintenance
1957
Corrective Maintenance
1960
Productive Maintenance
1971 TPM
Z D
G
R
O
U
P
(1965)
Condition-based era
J K
A
C
T
I
V
I
T
Y
(1969)
ZERO
A
C
C
A
C
M
I
P
D
A
E
I
N
G
T
N
(1971)
719
Category
Purpose
TQC
TPM
Improvement of corporate culture (improvement in actual
performance, creating a cheerful working environment)
Object
Quality
(Output side, Effect)
Equipment
(Input side, Cause)
Means to
achieve the
end
Functional organization
Demarcation
Reactive to
breakdowns
Equipment is the
Maintenance
Departments
responsibility
Necessary evil
Total Productive
Maintenance
Productive team
Multi-skilled and
operator-based
Preventive
maintenance
Operator ownership
and pride in
equipment by
everyone
Vitally important
21
TPM GOALS
TPM has two goals:
Zero Breakdowns
Zero Defects
The closer one gets to these objectives,
the lower the costs become, reserves are
reduced and work productivity increases.
22
of
the
intervention
costs
To
develop
complete
maintenance system.
production
24
25
Total
production
maintenance:
The
activation of maintenance prevention (in
the planning phase), of preventive
maintenance and of a lower maintenance
requirement (by corrective maintenance
during the life of the installation).
26
of
maximize
activities
the
which
exploitation
tend
of
to
the
Total participation:
The constitution of
company
structure,
production
and
the
design
administrative
28
29
30
In Japanese, the
(Kosho) means:
word
for
breakdown
DEFINITION OF TPM
JIPM VERSION
Because early TPM activities were
targeted at production departments, TPM
was
originally
defined
by
the
Japan
32
DEFINITION OF TPM
Involve
all
employees
from
management to frontline workers.
Promote
TPM
through
motivation
management i.e. autonomous small group
activities.
33
top
DEFINITION OF TPM
the
following
strategic
DEFINITION OF TPM
Conduct
zero-loss
activity
through
overlapping small group activities.
35
OBJECTIVES OF TPM
TPM aims at the improvement of
enterprise through radical reforms
equipment and personnel.
(1)
an
in
OBJECTIVES OF TPM
to
Maintenance
man
should
posses
ability to do maintenance of all types
of equipments
OBJECTIVES OF TPM
(2)
Improvement of Equipment
38
4.
2.
5.
3.
Motivation
Department
leaders
Pride in
ones work
Changing
the
equipment
Effects
Reduction of
defects and
breakdowns
Changing
the
people
Changing attitudes
Breakdowns and
defects should be
seen as an
embarrassment
Effects
Achievement
of Zero
breakdown
Changing attitudes
goals
Changing
(invigorating)
the work
place
Breakdowns and
defects should be
seen as lost profit
40
41
TRADITIONAL
MANUFACTURING
Breakdown
Defects
Setting
Breakdown
Adjustment
Misc.
stoppage
8 hrs.
42
Operators
meet
10 Mins.
8 hrs.
Equipment
cleaning/checkin
g
10 Mins.
43
Kairyo
Innovation in the
systems and
machines as a feed
back effect towards
design
Kai Fuku
Restoring design
normality (speed,
pressure etc. )
44
45
FROM PRODUCTION-DEPARTMENT
TPM TO COMPANYWIDE TPM
TOP MANAGEMENT
Planning
Finance
Personnel
General
Affairs
Administration
Development
Production
Plant
Plant
Plant
Sales
Plant
TPM Stage 1
TPM Stage 1: Production-department TPM
TPM Stage 2
46
47
SIGNIFICANT TANGIBLE
RESULTS
Companies
practicing
TPM
invariably
equipment
breakdowns,
defects
and
claims,
boosting
Shutdown accidents 0
Pollution incidents 0
49
Intangible Benefits
51
activities
improving
involvement
suggestions
52
inside
manufacturing
of
losses
which
reduce
the
53
FAMILY OF
LOSS
Loss from
Breakdown
OBJECTIVE
To
reduce
stoppages
breakdown to a minimum
due
to
Set up Loss
Production
Adjustment
Loss
Small
To reduce them to zero
Stoppage Loss
54
FAMILY OF
LOSS
Defect Loss
Start up Loss
OBJECTIVE
To make acceptability
tight, 0.1 percent to 0.
limits
very
56
57
September
September 1988
1988 Target
Target
(relative
(relative to
to April
April 1986
1986 baseline)
baseline)
Number
Number of
of failure:
failure:
1/100
1/100 or
or less
less
Number
Number of
of minor
minor
stops:
stops:
1/20
1/20 or
or less
less
(Mean
(Mean time
time between
between
minor
minor stops):
stops):
(4
(4 h
h or
or more)
more)
Processing
Processing Productivity:
Productivity:
at
at least
least 50%
50% higher
higher
Materials
Materials wastage
wastage rate:
rate:
1/3
1/3 or
or less
less
Total
Total cost:
cost:
60%
60% or
or less
less
Number
Number of
of shutdown
shutdown
Accidents:
Accidents:
0
0
59
Early Management
Quality Maintenance
Planned Maintenance
Autonomous Maintenance
Focused Improvement
PILLARS OF TPM
5S
60
Equipment management
61
Focused Improvement
In addition to major losses, experienced in
fabrication
and
assembly
industries
process industry sustain three additional
types of losses:
Autonomous Maintenance
When tailoring autonomous maintenance to
individual process environments planning
team must
Allocate
responsibilities
appropriately
between
production
and
specialized
maintenance personnel.
63
Planned Maintenance
Planned
or
scheduled
maintenance
embraces three forms of maintenance
Breakdown
Preventive
Predictive
64
Quality Maintenance
Quality
characteristics
are
mainly
influenced by the four production inputs
Equipment
Materials
Methods used
65
66
Early Management
Early equipment management concerns
equipment users, engineering companies
and
equipment
manufacturers
and
addresses the following areas:
Process design
Equipment design,
construction
Test operation
Start up management
fabrication
and
67
Its
availability
levels
maintainability etc.)
Establish budgets
achieve them
and
(reliability,
schedule
to
68
Implemented
this function
and boasts
improving
process
Administrativ
e Environment
Activities
here
remove
obstacles to effective work
hidden
in
the
physical
69
environment.
step-by-step
reduces costs
efficiency by
administrative
70
given
rigorous
safety
72
73
EXAMPLE OF TPM
EFFECTIVENESS
Good
400
300
Year 1
200
Year 2
Year 3
100
1
9 11
9 11
9 11
Months
74
Manufacturing costs
Reduced by 30%
( D ) Delivery
Inventory
Reduced by 30% to
50%
( S ) Safety
( M ) Morale
accidents
Implemented employee
suggestion
Reduced to zero
5 to 8 per month per
75
employee
Overall equipment
effectiveness
Productivity
Program Chart
(Progress Chart of
number of
breakdowns
76
Performance
Measure
Quality rejects per
million parts
Setup time
World
Class
2nd Class
3rd Class
< 500
1000
2000
< 10 min
< 20 min
< 30 min
90%
75%
55%
Breakdown losses
1%
5%
19%
On schedule
production
Engineering
change process
response time
Annual training
days per employee
100%
90%
80%
1 Day
5 Days
10 Days
20
10
<5
Utilized capacity
77
78
79
the
defects
in
equipment,
tools,
81
82
faulty
sensors,
material
materials
or
resetting
components.
83
higher
operating
speeds,
quality
85
up
defects
operating
losses
result
associated
from
with
conditions
quality
stabilizing
at
the
87
losses,
because
they
reflect
lost
Losses
are
grouped
in
three
major
categories:
Down Time
Speed Losses
Defect Losses
88
Loss Categories
Down Time
(Lost availability)
Speed Losses
(Lost performance)
Defect Losses
(Lost quality, sometimes
also called Yield Losses)
90
Most
industries
have
some
kind
of
and
sometimes
even
the
production speed.
important
if
our
goal
is
improvement.
93
94
OEE METRIC
Availability Rate =
rate
reflects
Equipment failures
Setup and adjustments
be in operation
The performance rate is the
quantity produced during the running Performance Rate =
time versus the potential quantity,
given the designed speed of the
Total output
equipment.
A low performance rate reflects Potential output at rated speed
speed losses:
Idling and minor stoppages
96
OEE METRIC
Performance Rate (Contd)
There are, however,
where only few parts are
per day or per week or
month or year.
situations
produced
even per
Performance =
Time Run Minor Stoppage
Reduced speed
Time Run
Performance figure can be
calculated in either way, but it is
usually simpler to use the first
formula
when
reasonable
quantities
and
standard
throughput rates are available.
Quality Rate =
Amount Produced Amount
Defectives Amounts
reprocessed
97
98
Quality
Performance
B Running Time
C
Target Output
Actual Output
Actual Output
Minor stoppage
Reduced speed
Lost Effectiveness
Scrap rework
Startup losses
OEE =
B/A
x
D/C
x
Availability Rate Performance Rate
Good
F
Output
F/E
Quality Rate
99
100
OBJECTIVES OF OEE
OEE
is
(machine
used
or
to
identify
equipment)
stream
process
related
purpose
of
improving
a
and
single
/
or
losses
asset
single
for
total
the
asset
101
OBJECTIVES OF OEE
OEE
provides
improvement
the
basis
priorities
for
and
setting
beginning
OBJECTIVES OF OEE
and
improve
collaboration
jointly
reduce)
identify
the
major
and
eliminate
causes
of
(or
poor
103
104
involved in
tracking
OEE
and in
to
reduce
lost
effectiveness.
105
Teach
the
equipment.
operator
about
the
Focus the
losses.
operators attention on
106
107
108
Example 1
OEE EXAMPLES
= 20 Minutes
Loading Time
Downtime Encountered
Percentage Availability
Output
= 400 Components
Percentage Performance
= 8
Percentage Quality
OEE
Actual Output
Potential Output
x 100
x 100
x 100
OEE EXAMPLES
Example 2
Loading Time
Downtime Encountered
Percentage Availability
Output
= 2,20,000 units
Theoretical Output
Percentage Performance
= 2050
Percentage Quality
OEE
Actual Output
Potential Output
x 100
x 100
x 100
110
with
conventional
production
to
ascertain
totally
the
level
is
clearly
defined
with
111
113
One
traditional
together
the
facilitys
physical
performance
Equipment
referred
measure
Efficiency
to
Effectiveness)
as
aspects
is
pulls
of
Operating
(OEE),
Overall
which
that
also
Equipment
gauges
how
115
117
Equipment,
People,
and
be
made
on
how
to
allocate
118
119
Capacity
Usage
Annual
Non
Capacity
EmpoLabour
x
x
x Absenteeism x
Usage
wered %
Retention
%
%
%
120
identified
by
Industry
Week
121
OPE of Approximately
48%
OEE
84%
LOE
72%
82%
Turnover Rate
10%
Absenteeism
2%
Capacity Usage
79%
122
available
capacity.
The
quick
27%
labour
based
turnover,
absenteeism
and
on
8%
10%
33%
LOE 85%
based on 90%
empowerment, 5% turnover and
1% absenteeism.
Maintains an OPE of 51%. Clearly plant B
has been doing a far better job of optimizing
the equipment, and people it has and
though it does not have as much unused
capacity as plant A, it should be rewarded
the new production.
125
126
127
MEASURES OF EFFECTIVENESS
OF FACILITIES
Example 1:
Hand Assembly
Example 2:
Semi Automated
Assembly
Example 3:
Processing System
128
this
example
we
look
at
the
HAND ASSEMBLY
1.
HAND ASSEMBLY
2.
HAND ASSEMBLY
3.
132
HAND ASSEMBLY
4.
133
HAND ASSEMBLY
5.
HAND ASSEMBLY
6.
HAND ASSEMBLY
7.
136
HAND ASSEMBLY
8.
137
HAND ASSEMBLY
9.
138
HAND ASSEMBLY
139
HAND ASSEMBLY
HAND ASSEMBLY
HAND ASSEMBLY
HAND ASSEMBLY
Total
8 x 60 mins (No. 1) +
3 x 60 mins x 2 (No. 2) +
12 mins x 5 x 8 (No. 4) +
15 mins x 5 x 8 (No. 5) +
20 mins x 2 x 8 (No. 7) +
6 x 60 mins (No. 9) +
5 x 60 mins (No. 10) +
8 x 60 mins (No. 12)
3380 mins during the
assembly
Performance losses =
Total
10 mins x 5 x 8 (No. 3) +
15 mins x 10 (No. 13)
550 minutes during the
assembly
143
HAND ASSEMBLY
Quality losses
30 mins x 2 x 8 (No. 6) +
5 x 60 mins x 3 (No. 8) +
4 x 60 mins x 2 (No. 11)
Total
144
EXAMPLE 2.
SEMI-AUTOMATED
ASSEMBLY
assembly
machine
which
and
welds
automotive
SEMI-AUTOMATED ASSEMBLY
SEMI-AUTOMATED ASSEMBLY
SEMI-AUTOMATED ASSEMBLY
3.
cannot
be
causes a
time the
operated,
an
148
SEMI-AUTOMATED ASSEMBLY
4.
One of
the fixtures is slightly
misaligned and can sometimes cause
one of the welds to be out of position,
220 units per week are lost.
The
misaligned
fixture
inconsistent
quality
of
resulting in the rejection of
of units. Therefore, this is
loss.
causes
products
a number
a quality
149
SEMI-AUTOMATED ASSEMBLY
5.
SEMI-AUTOMATED ASSEMBLY
6.
151
SEMI-AUTOMATED ASSEMBLY
7.
SEMI-AUTOMATED ASSEMBLY
8.
SEMI-AUTOMATED ASSEMBLY
Total
Performance losses
Total
Quality losses
Total
=
=
=
1 x 60 mins (No. 2) +
5 x 60/4 mins (Av.No.3) +
2.25 x 3 x 60 mins (No.5) +
6 x 60/6 mins (Av. No. 8)
600 minutes per week
2 mins x 5 x 7.5 x 5 (No.1) +
15 mins x 5 (No. 6) +
5 mins x 2 x 5 (No. 7)
500 minutes per week
1 unit x 5 x 7.5 x 5 (No.1) +
30 units (No. 2) +
220 units (No. 4) +
24 units x 3 (No. 5)
510 units per week
154
this
example
we
take
food
water
tank
valves
and
interconnecting
pipe
work.
Working
conditions are three shift working, 24 hours
a day, 7 days per week; throughput capacity
= 300 kg/hour (batches of 75 kg); actual
output = 43 000 kg. The following is a list of
losses encountered during production:
155
PROCESSING SYSTEM
1.
PROCESSING SYSTEM
2.
PROCESSING SYSTEM
PROCESSING SYSTEM
4.
PROCESSING SYSTEM
5.
PROCESSING SYSTEM
6.
PROCESSING SYSTEM
162
PROCESSING SYSTEM
7.
PROCESSING SYSTEM
If we now add up all of the losses we find:
Availability losses
Total
Performance losses
Total
Quality losses
Total
=
=
=
=
=
4 x 60 mins (No. 3) +
8 x 60 mins/2 (No. 5)
480 minutes per week
8 mins x 10 (No. 1) +
3 mins x 12 x 3 x 7 (No. 4) +
15 mins x 4 (No. 6) +
10 mins x 6 (No. 7)
956 minutes per week
3 kg x 3 x 7 (No. 2) +
50 kg (No. 3) +
37.5 kg/2 (No. 5) +
75 kg x 4 (No. 6)
431.75 kg per week
164
PROCESSING SYSTEM
PROCESSING SYSTEM
166
PROCESSING SYSTEM
167
90
Total
Losses
80
Lost
Earnings
Rs
Percentage
70
60
50
40
Available
for
operation
Output
Good
Quality
Output
Effective
operation
Rs
100
Lost
Availability
Earnings
30
20
10
0
Rs
availability
performance
quality
overall
effectiveness
earning
capacity
Rs
actual
losses
168
PROCESSING SYSTEM
169
OVERALL EFFECTIVENESS
The effectiveness of facilities has a
direct bearing upon the competitiveness and
profitability of a business and maximizing
their effectiveness means that the best
possible return is generated by each capital
asset owned by the business. It is possible to
calculate a percentage figure for each
of losses, thus percentage availability
group
is the
170
OVERALL EFFECTIVENESS
X 100
% availability =
8 (1 + 1)
8
X 100 =
6
8
= 75%
171
OVERALL EFFECTIVENESS
OVERALL EFFECTIVENESS
quantity produced
time run x capacity/given time
X 100
173
OVERALL EFFECTIVENESS
% performance =
500
6 X 100
X 100 =
500
600
X 100 = 83%
174
OVERALL EFFECTIVENESS
OVERALL EFFECTIVENESS
% performance =
6-
6
X 100 =
5
6
X 100 = 83%
176
OVERALL EFFECTIVENESS
OVERALL EFFECTIVENESS
% quality =
X 100
500 50 50
500
X 100 =
400
500
X 100 = 80%
178
OVERALL EFFECTIVENESS
way
of
calculating
OVERALL EFFECTIVENESS
% quality =
X 100
% quality =
6-
6
X 100 =
5
6
X 100 = 83%
180
OVERALL EFFECTIVENESS
in
OVERALL EFFECTIVENESS
75%
% performance
83%
% quality
80%
overall effectiveness
182
OVERALL EFFECTIVENESS
183
% availability =
(8 x 60) + (3 x 60 x 2) + (12 x 5 x 8) +
(15 x 5 x 8) + (20 x 2 x 8) + (6 x 60) +
(5 x 60) + (8 x 60)
=
480 + 360 + 480 + 600 + 320 + 360 +
300 + 480
=
3380 mins/assembly
19200 3380
Performance losses
19200
=
=
X 100 =
15820
19200
X 100 = 82%
HAND ASSEMBLY
% performance =
Quality losses
% Quality
15820 550
15820
X 100 =
15270
15820
X 100 = 97%
= (30 X 2 X 8) + (5 X 60 X 3) + (4 X 60 X 2)
= 480 + 900 + 480 = 1860 mins/assembly
15820 1860
15820
X 100 =
13960
15820
X 100 = 88%
OAE = 70%
185
HAND ASSEMBLY
on an
losses
186
100
90
Lost
Output
Loss
Availability
Total
Losses
Lost
Earnings
Good
Quality
Output
Effective
operation
Earnings
quality
overall
effectiveness
earning
capacity
80
Percentage
70
60
50
40
30
Available
for
operation
Output
20
10
0
availability
performance
actual
losses
187
EXAMPLE 2. SEMI-AUTOMATED
ASSEMBLY
loading time = 7.5 X 5 = 37.5 hours/wk = 2250 mins/wk
availability losses
=
=
% availability =
Performance losses
% performance =
2250 600
2250
=
=
X 100 =
1650
2250
X 100 = 73%
(2 X 5 X 7.5 X 5) + (15 X 5) + (5 X 2 X 5)
375 + 75 + 50 = 500 mins/wk
1650 500
1650
X 100 =
1150
1650
X 100 = 70%
188
HAND ASSEMBLY
% performance =
Quality losses
% quality =
2875
(1650/60 X 150)
X 100 =
2875
4125
X 100 = 70%
2875 510
2875
X 100 =
2365
2875
X 100 = 82%
OME = 42%
189
HAND ASSEMBLY
190
Lost
Availability
Lost
Output
Lost
Output
Percentage
70
Total
Losses
Lost
Earnings
Effective
operation
Earnings
overall
effectiveness
earning
capacity
60
50
40
30
Available
for
operation
Output
Good
Quality
Output
20
10
0
availability
performance
quality
actual
losses
191
% availability =
Performance losses
% performance =
=
=
10080 480
10080
X 100 =
9600
10080
X 100 = 95%
=
(8 X 10) + (3 X 12 X 3 X 7) + (15 X 4) + (10
X 6)
=
80 + 756 + 60 + 60 = 956 mins/wk
9600 956
9600
X 100 =
8644
9600
X 100 = 90%
192
HAND ASSEMBLY
% performance =
Quality losses
% quality =
43000
(9600/60 X 300)
X 100 =
43000
48000
X 100 = 90%
43000 413.75
43000
X 100 =
42586.25
43000
X 100 = 99%
OPE = 85%
193
HAND ASSEMBLY
194
Lost
Availability
Lost
Output
Lost
Output
90
Total
Losses
Lost
Earnings
Effective
operation
Earnings
overall
effectiveness
earning
capacity
80
Percentage
70
60
50
Available
for
operation
Output
Good
Quality
Output
availability
performance
quality
40
30
20
10
0
actual
losses
195
HAND ASSEMBLY
HAND ASSEMBLY
Overall effectiveness
used just as a means of
should not be
comparing one
198
and
and
arising
from
the
199
value
and
is
200
= Rs. 5000
= Rs. 7000
= Rs. 2000
= Rs. 2000 X 50
= Rs. 100,000/hour
201
= Rs. 100,000 x
70
100
= Rs. 70,000/hour
and therefore the major losses represent a loss of
added value equal to Rs. 30,000/hour.
202
203
100
70
per
per
cent
cent
Rs. 50.4m
30%
= Rs. 1.68m/percent
The
introduction
of
autonomous
maintenance activities which are all
production-led activities, will lead to a
rapid improvement in overall effectiveness
of at least 5 percent, but more usually of
the order of 10 percent. Therefore, for the
example
of
the
press,
autonomous
maintenance activities would be expected
to increase its earning capacity by at least
Rs 8.4m and most likely the figure would be
Rs 16.8m.
206
8 hours/day x
5 days/week for
8 weeks
=
320 hours in
total
If each man hour is sold at Rs 2500 (assembly
processes are often priced on the man hours
required to complete the assembly) then the
estimated cost of the
calculated as follows:
assembly
can
be
207
HAND ASSEMBLY
= 457 hours
208
HAND ASSEMBLY
1% improvement =
Rs 3.425m
30%
= Rs 1,14,166 /year
COMPLETED EFFECTOGRAM
FOR EXAMPLE 1
Percentage
70
60
50
40
Available
for
operation
Output
Good
Quality
Output
Earnings
Effective
operation
30
20
Rs 2500
457
320
Addl
Cost
10/yr
80
Total
Losses
Rs 800,000
Rs.1.1425 m
90
Lost
Output
Lost
availability
Rs 1,14,166/yr/1%
100
Lost
Output
10
0
availability
performance
quality
overall
effectiveness
earning
capacity
actual
losses
210
Example 2. SEMI-AUTOMATED
ASSEMBLY
Loading = 7.5 hours/day x 5 days x 48 weeks =
1800 hours/year
Planned throughput = 150 units/hour
Value added to each unit = Rs 15
Therefore, the theoretical earning capacity for
the machinery can be calculated thus:
Earning capacity = 1800 hrs x 150 units/hr x Rs
15/unit = Rs 40,50,000/year (Rs
4.05m)
overall effectiveness = 42%
211
SEMI-AUTOMATED ASSEMBLY
losses = Rs 4.05m x
and 1% improvement =
58
100
= Rs 2.349m/year
Rs 2.349m
58%
= Rs 40,500
212
SEMI-AUTOMATED ASSEMBLY
213
Percentage
60
40
30
Available
for
operation
Good
Quality
Output
Output
Earnings
20
Effective
operation
10
0
availability
performance
quality
overall
effectiveness
earning
capacity
Rs 2250
Total
Losses
70
50
Lost
Earnings
Rs 945
80
Lost
Output
Lost
Output
1800
90
Lost
availability
Rs 40,500/yr/1%
100
Rs 1.701 m Rs
4.05m
COMPLETED EFFECTOGRAM
FOR EXAMPLE 2
actual
losses
214
overall effectiveness =
215
PROCESSING SYSTEM
losses = Rs 75.6m x
15
100
= Rs 11.34m/year
Rs 11.34m
= Rs 7,56,000/year
and 1% improvement =
15%
in overall effectiveness
216
PROCESSING SYSTEM
An
improvement
in
overall
217
Lost
Output
100
Total
Losses
Lost
Earnings
90
80
Percentage
70
60
50
40
Available
for
operation
Output
Good
Quality
Output
availability
performance
quality
Effective
operation
Earnings
overall
effectiveness
earning
capacity
30
20
Rs 9000
Rs 7,650
Lost
Output
8400
Lost
availability
Rs 7,56,000/yr/1%
Rs 75.6m
Rs 64.26m
10
0
actual
losses
218
PROCESSING SYSTEM
just
apply
to
the
production-led,
219
220
Enhanced
factory
floor
personnel,
improved motivation and morale, arising
from
a
much
improved
working
environment, greater participation and
training.
224
225
reduced
effectiveness
of
packaging
226
World Class
Availability
90.0%
Performance
95.0%
Quality
99.9%
Overall OEE
85.0%
228
229
230
FOCUSED IMPROVEMENT
As a result of autonomous maintenance
activities, the TPM team discover
inherent faults in either design and
construction of machinery and / or in the
methods of operation which support the
process.
Quite often, they will not be able to
rectify these faults as part of everyday
TPM activities as these faults require a
great deal of effort and resources.
232
FOCUSED IMPROVEMENT
at which
project be
the
set
233
FOCUSED IMPROVEMENT
small
project
team,
comprising
OVERALL EQUIPMENT
EFFECTIVENESS
Availability
Changeover /
setup time
reduced. Study
& improve
Reliability
improvement
Redesign for
maintainability
Performance
Chronic loss
analysis and
Quality
improvement
Process
improvement
Study and
improve
method of
operation
Process
capability
study and
improvement
POKA YOKE
design
Redesign for
operational
stability
235
FOCUSED IMPROVEMENT
The
key
to
the
successful
implementation of focused projects is
that they should be approached in a
structured way, i.e. undertaken in a
logical sequence, step by step. Some
guidelines to the implementation of
different kinds of focused projects are
as follows:
236
AVAILABILITY IMPROVEMENT
PROJECTS
Changeover Time Reduction:
There are three major aspects of
changeover from part to part which need to be
considered in this kind of project:
237
AVAILABILITY IMPROVEMENT
238
AVAILABILITY IMPROVEMENT
Reliability Improvement:
Where
machinery
is
frequently
239
AVAILABILITY IMPROVEMENT
On
many
occasions,
however,
the
240
AVAILABILITY IMPROVEMENT
cause
the
majority
of
241
PERFORMANCE IMPROVEMENT
PROJECTS
Reducing Cycle Time:
Where the throughput of the process is
significantly below what is expected, the
project team will initially need to establish the
possible causes of the problem. To accomplish
this the early stages are:
PERFORMANCE IMPROVEMENT
Based
on
this
analysis,
the
particularly
significant
problems
which are besetting the operation of
the machinery can be identified.
243
PERFORMANCE IMPROVEMENT
244
POKA
YOKE
of
is
many
POKA YOKE or
approach to the
process
particularly
quality
relevant
to
QUALITY IMPROVEMENT
occur, alongwith
the
type
of
problems encountered.
QUALITY IMPROVEMENT
247
QUALITY IMPROVEMENT
then
the
team
asks
the
question:
248
QUALITY IMPROVEMENT
249
QUALITY IMPROVEMENT
250
QUALITY IMPROVEMENT
or
visual
alarm
to
be
actuated.
251
QUALITY IMPROVEMENT
A
well
executed
Focussed
Improvement
programme
should
deliver the following six major
results:
252
Q (Quality)
1.
1.
2.
Increased equipment
productivity
2.
Reduced customer
complaints
3.
Increased value-added
productivity
3.
4.
5.
4.
5.
D (Delivery)
1.
2.
2.
3.
3.
Increased inventory
turnover rate
4.
Reduced spare-parts
inventories
4.
253
S (Safety)
M (Morale)
1.
1.
Increased number of
improvement suggestions
2.
2.
Increased frequency of
small-group activities
3.
Elimination of pollution
incidents
3.
4.
Degree of improvement on
statutory environmental
requirements
4.
Increased number of
irregularities detected
254
255
Maintenance
is
geared
OPERATORS ROLE
Policy
Uninterrupted
equipments.
operation
of
Step-wise
implementation
Autonomous Maintenance.
of
257
OPERATORS ROLE
Targets
Reduce
oil
consumption
by
50
percent.
258
OPERATORS ROLE
Assembly
industry
is
constantly
and
micro-electronic
OPERATORS ROLE
OPERATORS ROLE
operating or the
261
OPERATORS ROLE
in
OPERATORS ROLE
OPERATORS ROLE
Unfortunately,
traditional
and
conservative ideas regarding operators
still exist within the leadership of many
companies, even though the relationship
between human beings and machinery is
changing daily.
Some
managers
may
think
it
unnecessary to educate the shop floor
personnel because production in a fully
automated plant can be conducted
simply by following the computers
instructions.
264
OPERATORS ROLE
OPERATORS ROLE
account all
or indirectly
OPERATORS ROLE
Success
will
be
evasive
careful
consideration,
unless,
these
by
same
and
roles
among
all
these
departments.
267
OPERATORS ROLE
TPM,
with
the
participation
of
all
employees,
means
reviewing
the
function and roles of all the personnel
and analyzing the interfaces of
various departments.
the
268
equipment
as
well
as
be
269
equipment
and
prior
to
the
270
so
as
of
to
from
the
beginning
of
the
of
equipment,
through
practice
and
on
later
actual
equipment.
273
to
achieve
remarkable
benefits.
274
control,
to
prepare
for
275
TRAINING OPERATORS
their
plant
skills
by
studying
operations
shut-down
and
procedures
276
TRAINING OPERATORS
certain
redundancy
of
human
intervention.
risk
and
cost
in
plant
TRAINING OPERATORS
TRAINING OPERATORS
Autonomous
maintenance
fostering the development
knowledgeable operators.
aims
at
of these
279
280
PLANNED MAINTENANCE
It
is
aimed
to
have trouble
free
products
for
total
customer
satisfaction.
281
TYPES OF MAINTENANCE
Daily checks
Periodic checks
TBM
Periodic Inspection
Periodic servicing
PM
CBM
Rotating machinery
diagnostics
Static equipment diagnostics
PLANNED
BM
Approach to
Maintenance
CM
PM:
Preventive Maintenance
UNPLANNED
BM:
Breakdown Maintenance
CM:
Corrective Maintenance
282
PLANNED MAINTENANCE
In TPM planned maintenance is based
on the twin foundations of
Autonomous
maintenance
by
the
by
the
Production Department.
Specialized
maintenance
Maintenance Department.
283
PLANNED MAINTENANCE
Within
the
planned
maintenance
activities
should
evolve
Improving Maintenance
Technology and Skills
Improving equipment
Autonomous maintenance
support
Corrective maintenance
Maintenance prevention
Predictive maintenance
285
failures
and
process
Quality abnormalities
Capacity reductions
286
Obvious Problems
& Losses
1. Equipment failures
or process
problems causing
shutdown
2. Quality
abnormalities
3. Unit-consumption
abnormalities
Common
Problems
& Their
Causes
Static Equipment
Equipment
Disorders
& Hidden
Defects
4. Capacity reductions
5. Safety and
environmental
problems
Rotating Machinery
POLICY
Achieve
and
sustain
availability
of
machines.
Improvement
in
reliability
and
maintainability of machines.
288
TARGET
289
SIX STEPS IN
PLANNED MAINTENANCE
290
STEP-BY-STEP IMPLEMENTATION OF
PLANNED MAINTENANCE
Step 1:
Step
2:
Restore deterioration
weaknesses.
and
Step
3:
Build an
system.
management
information
correct
Step 4:
Step 5:
Step 6:
292
QUALITY MAINTENANCE
As equipment takes over the work of
production, quality depends increasingly
on the condition of the equipment. Quality
Maintenance evolved as a major TPM
activity in fabrication and assembly
industries that are becoming increasingly
automated.
In
environments
where
human
intervention is decreasing, the goal of
Quality Maintenance is to maintain and
constantly
improve
quality
through
effective equipment maintenance.
293
QUALITY MAINTENANCE
QUALITY MAINTENANCE
Quality
Maintenance
consists
of
activities
that
establish
equipment
conditions that do not produce quality
defects, with a goal of maintaining
equipment in perfect condition to
producing perfect products.
Quality
defects
are
prevented
by
checking and measuring equipment
conditions periodically and verifying that
the measured values lie within the
specified range.
295
QUALITY MAINTENANCE
QUALITY MAINTENANCE
297
QUALITY MAINTENANCE
ABOLISH ACCELERATED
DETERIORATION
When equipment is subject to accelerated
deterioration,
its
modules
and
is
unstable
and
fails
unexpectedly.
Progress towards zero quality defects is
painfully
slow
when
equipment
is
QUALITY MAINTENANCE
ABOLISH ACCELERATED DETERIORATION
deterioration
and
unexpected
must
be
failures
Maintenance,
and
Planned
Operation
and
300
QUALITY MAINTENANCE
Process
industries
are
plagued
by
Focused
Improvements
operator-initiated
Maintenance
Improvements.
or
Autonomous
Only
then
QUALITY MAINTENANCE
We
have
discussed
training
of
discuss
Operating
and
the
issue
Maintenance
under
Skills
Training.
302
303
CAUSES OF QUALITY
DEFECTS
304
RELATIONSHIP BETWEEN
EQUIPMENT & QUALITY
305
EQUIPMENT CONTROL
CONDITIONS
306
QUALITY MAINTENANCE
establish
the
equipment
control
quality
characteristics
are
QUALITY MAINTENANCE
Prevent
defects
from
occurring
by
308
309
responsible
for
promoting
Quality
310
311
TPM
aims
to
create
corporate
the
changing
technological
sophistication
business
advances,
and
climate,
equipment
management
innovation.
312
Essential
in
this
environment
are
Meanwhile,
maintenance
personnel
and
skills
training
invite
equipment-originated
quality
314
engineering
desperately
departments
to
commission
conditions,
awkward
to
difficult
maintain
and
to
use,
regularly
316
317
WHAT IS SKILL?
318
Noticing
Noticingaa
certain
certain
phenomenon
phenomenon
Assessing
Assessingthe
the
phenomenon
phenomenonaccurately
accurately
(cause
(cause
action)
action)
Perception
Judgment
Five senses
Intellect
Training,
experience
and
information
Function of Time
Acting
Acting
reflexively
reflexively
Action
Body
319
WHAT IS SKILL?
and
information
enables
320
to
identify
the
level
of
knowledge,
321
Level
1:
Lacks
both
theoretical
knowledge and practical ability
(needs to be taught)
Level 2:
Level 3:
Level 4:
EQUIPMENT-COMPETENT
OPERATORS
EQUIPMENT-COMPETENT OPERATORS
1.
Equipment-competent operators
detect equipment abnormalities
effect improvements.
can
and
Understand
the
importance
of
lubrication
and
can
lubricate
correctly, and check the results
Understand
the
importance
of
cleaning as inspection and can do it
correctly
324
EQUIPMENT-COMPETENT OPERATORS
Understand
the
importance
of
minimizing
the
scattering
of
and
can
develop
Correct
or
improve
irregularities
they detect
325
EQUIPMENT-COMPETENT OPERATORS
2.
Equipment-competent
operators
understand equipment structure and
functions and are able to discover the
causes of abnormalities.
They must be able to:
EQUIPMENT-COMPETENT OPERATORS
Understand
abnormalities
Diagnose
extent
the
failures
causes
to
of
certain
327
EQUIPMENT-COMPETENT OPERATORS
3.
Equipment-competent
operators
understand the relationship between
equipment and quality and can predict
quality abnormalities and discover
their causes.
They must be able to:
Understand
the
relationship
between equipment and product
quality characteristics
328
EQUIPMENT-COMPETENT OPERATORS
329
EQUIPMENT-COMPETENT OPERATORS
4.
Replace components
EQUIPMENT-COMPETENT
MAINTENANCE PERSONNEL
In many industries, equipment quality
significantly affects productivity, product
quality, safety and so on. This is why
excellent maintenance skills are so badly
needed.
To
meet
this
demand,
331
Improve
reliability,
equipment
lengthen
and
component
equipment
life
333
AS
equipment
sophisticated
becomes
and
more
automated,
the
operation,
low
energy
334
336
Design
program
for
improving
Implement
operating
and
337
Design
and
develop
skill-
environment
that
development system.
Foster
an
encourages self-development.
338
339
EARLY MANAGEMENT
As products diversify and their life cycles
become shorter, finding ways to make
new product development and equipment
investment
decisions
more
efficient
grows in importance.
The goal in Early Management is to
reduce dramatically the time from initial
development to full-scale production and
to achieve vertical startup (a startup that
is fast, free of bugs, and right the first
time).
340
quality
that
anticipate
users
343
life
cycle
costs)
and
344
LIFE-CYCLE COSTING
DEFINED
The life-cycle cost of a product,
equipment item, or system is its total cost
over the whole of its life. In U.S, it is
defined as:
345
The
sum
recurring,
of
the
direct,
non-recurring,
indirect,
and
other
generated
development,
during
production,
the
design,
operation,
346
systematic
technique
that
decision-making
incorporates
life-cycle
all
possible
trade-offs
to
347
Step 1:
Step
2:
Step 3:
Step 4:
Step 5:
As
user
competition
needs
on
diversify
quality,
and
price
and
plan,
schedule,
develop,
satisfy
customer
quality
349
losses
from
manufacturing
Poor
design
reduced
is
major
profitability,
cause
of
impaired
351
design,
and
production
departments
must
cooperate
involve
these
353
354
and
to
outperform
the
company
developments
accomplish
that
senior
the
strategic
management
envision.
355
Their
third
preceding,
task,
is
based
to
win
on
the
customer
issues
must
we
address
to
357
its
particular
function
Decision Making
Communication
Data Processing
359
IMPLEMENTING TPM IN
ADMINISTRATIVE & SUPPORT
DEPARTMENTS
The
approach
systematizes
the
described
experiences
below
of
many
administrative
and
support
360
creating
to
361
362
The first
step in
breaking down
Each
department
has
an
essential
363
the
what
365
366
ESTABLISHING DEPARTMENTAL
VISION & MISSION
If
the
functions
of
different
gaps
or
discontinuities,
367
ESTABLISHING DEPARTMENTAL
VISION & MISSION
Processing loss
Accuracy loss
Time
spent
information
on
retrieval
of
368
ESTABLISHING DEPARTMENTAL
VISION & MISSION
Communication channel
telephone and fax lines
breakdown,
369
ESTABLISHING DEPARTMENTAL
VISION & MISSION
from
departmental
the
visions
rest.
Establish
and
missions
370
ESTABLISHING DEPARTMENTAL
VISION & MISSION
1.
2.
Integrate
the
departments
consensus.
3.
Obtain
the
management.
proposals
and
build
approval
of
all
an
of
the
overall
top
371
372
IMPLEMENTING THE
FIVE CORE ACTIVITIES
and
the
Focused Improvement
Autonomous Maintenance
Flexible Staffing
Performance Measurement
373
374
FOCUSED IMPROVEMENT
After establishing a vision and mission
for the department, eliminate chronic
losses and pursue efficiency in all
aspects of departments existing work.
Departmental work rarely takes place
in a vacuum, it usually closely involves
other departments as well. Start by
selecting a task that affects other
departments and appears likely to yield
significant improvement results.
375
376
AUTONOMOUS MAINTENANCE
Administrative Function
Administrative Environment
AUTONOMOUS MAINTENANCE
378
379
Developing
people
with
superior
380
Establishment
programme
of
detailed
that
specializations
and
training
covers
all
grades,
set
and
skills,
and
devise
381
382
383
PERFORMANCE MEASUREMENT
achieve
certain
results,
some
areas
of
cost
effectiveness,
384
PERFORMANCE MEASUREMENT
385
386
388
389
Increase Productivity
(Eliminate Losses)
TPM Activity
Autonomous Maintenance
Focused Improvement
Maintain Reliability
Develop Competent People
Create Safe, Pleasant Workplace
Make Equipment Safe
Develop Safety-Conscious People
Planned Maintenance
Early Management
Prevent Accidents
390
391
392