Documentos de Académico
Documentos de Profesional
Documentos de Cultura
W S William
Cost Estimation
Ballpark (order of magnitude) 30% Comparative 15% Feasibility 10% Definitive 5%
8-2
External factors
Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall
8-3
Cumulative cost
At project definition
Time
Estimating Process Estimating Methods 1. Expert opinion 2. Analogy + compensation for differences 3. Parametric: Formula or Cost Function, e.g.,
Cost, engine A = (Cost, engine B)
Thrust, engine A
Thrust, engine B
0.7
Cost, cabling = 150 (total area + 10%) + 300 (number of rooms) + 125 (number of floors)
Estimation Process
Procedure for larger projects, steps 1-3
1. PM: Uses WBS to identify work packages 2. FM: Subdivide work packages into identifiable tasks; determine labor, material, facilities, and resources requirements for each 3. Supervisors/team leads: Estimate number of labor hours and quantities of materials needed
Project Management WBS 1. information 2. Functional Management
3. Work team
Project Management
Estimation Process
WBS information
Functional Management
6.
4., 5.
4. FM: check and aggregate time and material estimates 5. FM: convert time estimates into costs
Work team
6. PM: checks over and approves all estimates aggregates costs; added in overhead costs:
Project Management
7., 8..
Functional Management
Work team
8. PM: Compares bottom-up estimates to top-down targets or goals. Attempt to reconcile differences.
project
work package
task
Project Budget
$ 356,755
Basic design
Hardware $179,868
Software $122,118
J $31,362
Final Tests
$10,857
User Test
Cost Accounts
Materials
Installation
Procedures
M $138,571 V
Y $20,352
Assembly $20,945
Q $100,846
Specifications
X $6,622
System Test
$21,272
W $4,235
Project Budget The best project budgets are time-phased to allow cost tracking vs. time
Budget Contingencies
The allocation of extra funds to cover uncertainties and improve the chance of finishing on time.
Estimating Pitfalls
Misinterpretation of the statement of work Improperly defined scope Overly optimistic schedule Inaccurate WBS Applying improper skill level to tasks Failure to account for risks Failure to account for cost escalation and inflation Failure to use correct estimating technique
Thank you