BTS HARDWARE/RF INSTALLATION PROCEDURES AND POWER UP PROCESS.


Wireless Case & Training Department
www.huawei.com

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Preface
This course will introduce the site Equipment (BTS), RF installation and power up procedures.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 1

Reference
BTS3900A (Ver.B) Quick Installation Guide(04)(PDF)-EN
<BTS3900 GSM V300R008 & R009 installation Guide product> TP48300-A Quick Installation Guide(V100R001_09) TP48200A-X3H4 & X3H5 Quick Installation Guide(V100R001_02)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 2

Objective
After this exercise, you can: . Understand the installation procedure for EMTS project. Master the key point of BTS installation

. Master wireless project implementation problem TOP 10


Understand the possible solutions to the problems.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 3

Chapter 1 Chapter 2

Installation procedure for EMTS project . The powering up of Equipment process.

Chapter 3 Snags after installation.


Chapter 4 Possible solutions.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 4

PART ONE

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 5

CHAPTER ONE: INSTALLATION PROCEDURE FOR EMTS PROJECT


If material arrive site, the SBC should use a checklist to check

the equipment and the ensure that the materials are complete as printed on the MR or DN.
If everything is confirmed ok, the SBC should unpack the

materials gently to avoid damaging of the equipment.


Ensure no damaged or missing item. If there is any damaged or

missing item, the SBC should inform Huawei engineer on site and indicate such on the check list. The SBC will get a corresponding amercement according to the damaged or missing item.
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 6

INSTALLATION PROCEDURE
The installation

procedure is best described in two folds:


The equipment (BTS)

part procedure
The RF part procedure

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 7

THE EQUIPMENT(BTS) PART PROCEDURE.

The installation

flow chart for this part is as follows:

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 8

INSTALLING THE BASE, RFC AND APM30H


Check the plinth and mark out according design.

The base of the Battery

cabinet and the RFC/APM30H cabinet must be separated by a distance of at least 10cm.
Ensure that you use

expansion bolt to make the base firm on the plinth.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 9

INSTALLING THE BATTERY & RFC CABINET


Ensure you install
IBBS battery banks set up.

the battery cabinet on the left side and the RFC cabinet on the right as shown in the picture below:

APM30H & RFC cabinet

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 10

INSTALLING EARTHING CABLES.


The grounding cable

of diameter 16mm^2 is used to interconnect the two cabinets and must be connected to the earthing terminal (Bar) as shown below:
To the earthing terminal onsite.
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 11

NOTES;
During this installation the SBC is not expected to

use short cables that may lead to joining of the cables.


The SBC should ensure tight connections at all

terminal points on the grounding bar.


The SBC must apply denso-paste at all the grounding

terminal points.
SBC must route the cable through a PVC pipe to

make the installation neat and protect the cables.


All earthing cables must be routed through the cable

hole accordingly.
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 12

CHECKING OF THE BOARDS AND MODULES


The SBC should check the boards e.g. DRFU,

modules e.g. PSU, PMU etc that are preloaded in the cabinet from factory, if they are complete and well positioned in the cabinet according to configuration. If at this stage and there is any alteration from the physical connection, please report to office.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 13

INSTALLING OF OTHER COMPONENTS.


The other components that

are installed are basically;


The environment monitoring

unit for outdoor (EMUA).


The transmission radio [IDU]

which can be RTN620 or RTN950 depending on MW config


The DDF for the termination of

both BTS and Microwave E1 cables

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 14

INSTALLATION OF CABLES
The cables that are installed are:
The APM30H power cable from

the ACDB to EPS


The battery cable from the battery

bank cabinet which must be red and black. RED(+) and BLACK(-)
The power cable of the EMUA

and the IDU which will run from the power ports of the components to DC voltage output terminal of the EPS.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 15

monitor port

Port NO. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

description Generator 1 on load Generator 1 Fault Fuel Low Level Fuel Tank Full Generator 2 on load Generator 2 Fault

Remark

INSTALLATION OF CABLES
The external alarm cables from tank, generator and other sensors like smoke The battery temperature sensor that is installed in the battery cabinet The pictures show the external alarm port that is physically terminated during installation for BTS3900A

S1+/S1S2+/S2S3+/S3S4+/S4S5+/S5S6+/S6S7+/S7S8+/S8S9+/S9S10+/S10S11+/S11S12+/S12S13+/S13S14+/S14S14+/S15Gate 12 VG Smoke 24VS

Rectifier Fuse alarm Rectifier SPD Fail Rectifier Battery LVD Rectifier SMR Fail Rectifier DC Low Rectifier AC Fail Rectifier PSU shutdown
Door Alarm Smoke alarm

spare spare Rectifier Rectifier Rectifier Rectifier Rectifier Rectifier Rectifier Indoor site only

External alarm Port on EMUA

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 16

Rectifier External alarm continued.


1.1 Rectifier alarms
In ET P6 we use TP48200A rectifier for outdoor site. Considering

TP48200A,there are 6 alarms in rectifier cabinet. 2 ports for each alarm,

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 17

Rectifier External alarm continued.


1.2 Rectifier alarms
In ET P6 we use TP48300 rectifier for indoor site. Considering

TP48300 ,there are 7 alarms in rectifier cabinet. 3 ports for each alarm, we just use port NO and COM

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 18

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 19

Rectifier External alarm continued.


In EMUA we use S9~S14 to monitor these alarms.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 20

Rectifier alarm continues.


Port mapping in EMUA:

Port in EMU

Port NO

Alarm Description in BSC

Severity

S9+/S9S10+/S10S11+/S11S12+/S12S13+/S13S14+/S14-

9
10 11 12 13 14

Rectifier Fuse alarm


Rectifier SPD Fail Rectifier Battery LVD Rectifier SMR Fail Rectifier DC Low Rectifier AC Fail

Critical Minor Minor Major Minor Critical

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 21

Special alarms
2.1 Installing Smoke sensor:

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 22

Special alarms
2.2 Installing Water Sensor:

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 23

Special alarms
2.3 Installing Humidity/Temperature Sensor:

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 24

Special alarms
2.4 Installing Door Status Sensor:

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 25

BTS E1 CABLE TERMINATION AND COLOR CODE

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 26

BTS MW CROSS CONNECTION OF 4E1 ON THE DDF FOR ONLY ONE IDU ON SITE
RTN620 & BTS 3900A

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 27

BTS MW CROSS CONNECTION OF E1 ON THE DDF FOR ONLY TWO IDU ON SITE

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 28

BTS MW CROSS CONNECTION OF 4E1 ON THE DDF FOR ONLY ONE IDU ON SITE
RTN950 & BTS 3900A

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 29

INSTALLATION OF BATTERIES [for back up]


The Engineer should

gently load batteries in the battery cabinet to provide a back up system for the BTS. The pictures shows the necessary steps which will be observed.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 30

Notes;
Ensure that the correct polarity is maintained in the

cabinet and on the EPS of the BTS.


Ensure that connecting plate between one battery

and the other battery is tightened well.


Ensure that temperature sensor off the battery is

connected and terminated on the correct port as shown by the picture.


Ensure that the output DC voltage after connection is

in the range 48v~53v


HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 31

PART TWO

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 32

PART TWO THE RF & MW PART PROCEDURE


Generally , the RF and MW part of the installation involves the

installation of the following:


The jumpers at the BTS end of the line. The feeder cable which can be 7/8 or 5/4 inch diameter coaxial cable

depending on the height of the tower.


The coaxial connectors at both ends of the cable which can be male or

female type.
The jumper cables at the antenna end on the tower The antenna which can be single band or dual band depending on

the configuration of the site.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 33

RF PROCEDURE
Couple your antenna and ensure

that then mechanical and electrical tilt angle is set according to design.
Put enough water proof and

Mechanical tilts angles set to 0

insulation tape to avoid water from entering the feeder connector joint.

Electrical tilts angles set to 2

Insulating & water proofing connectors

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 34

Antenna and Feeder Cable B, C


Commonly used three-sector mains and diversity antenna:
System Sector 1 The first set of system 2 3 1 Configuration of Colored Ring Labels Main and diversity: red, two rings Diversity: red, one ring Main and diversity: yellow, two rings Diversity: yellow, one ring Main and diversity: blue, two rings Diversity: blue, one ring Main and diversity: one white ring + two red rings Main and diversity: one white ring + one red ring The second set of system Remarks Cell default definition: cell 1 is in the north, and the cells in the clockwise direction are cell 2 and 3 respectively. When multiple systems share a site, the feeders of different systems need to be distinguished. For the second set of system, add a white ring besides the red, yellow, and blue rings. For the third set of system, add two white rings besides the red, yellow, and blue rings.

Main and diversity: one white ring + two yellow rings


Main and diversity: one white ring + one yellow ring

Main and diversity: one white ring + two blue rings Main and diversity: one white ring + one blue ring

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 35

RF PROCEDURE CONTINUED.
Hoist the antenna gently up the tower with a control line to avoid

the antenna from hitting the tower.


Cut the feeder cable according to the height of the tower in the

design specification
Make the connector perfectly to avoid impedance mismatch at

both ends of the cable.


Hoist the cable gently to avoid damage. Clamp the feeder from top to bottom, making sure that the

clamps are uniformly distributed with at least 2m spacing along the ladder.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 36

RF INSTALLATION continued.
Connect the single RF cable between the feeder and the BTS,

making sure that the joint is insulated and water proofed. The picture below depicts the scenario.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 37

RF INSTALLATION continued.
Ground the feeder cable at 3

points along the tower, ensuring that the lightening proof grounding cable are all terminated on the Bus bar mounted on the tower.

Feeder grounding kit

Groundin g bar

Grounding insulating & water proofing tapes

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 38

SWEEP TEST PROCEDURES FOR VSWR TEST STAGES

When the feeder cable connection is complete, the next step is to carry out sweep test for each line of both 900M and 1800M. Using

Step 1 : DTF , Return lost and Cable lost; 1.1 Press the MODE key. 1.2 Select FREQ-RETURN LOSS using the Up/Down arrow key and press ENTER. 1.3 Connect the calibrator Module to the RF port and calibrate the Site Master. 1.4 Select the appropriate frequency range, as describe in the procedure above. 1.5 860 MHz- 970 MHZ for M900 only and 1710MHz-1880MHZ for M1800 only 1.6 Press the START CAL key. Press ENTER, the calibration status indicator will change from calibrated to uncalibrated and after calibration turns back to calibrated in the display. 1.7 Connect the RF cable of the feeder to the RF port of the site master and check the signal pattern on the GUI 1.8 Press MARKER and then MARKER to PEAK to view the VSWR peak value of the feeder cable.

1.9 Repeat step 1.2 , for EMTS projects VSWR test reading must not be >1.3

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 39

PART THREE

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 40

CHAPTER THREE POWERING UP STAGES OF BTS 3900A OUTDOOR


Note: Make sure all necessary ATS setting for Generators and a 16mm 4 core, 4 wire power cable connecting from ATS to ACDB is well connected as design , check all phases for Generators 1& 2 in ATS if they are balanced and confirm the accuracy of the voltage needed to supply the equipment on-site using multimeter.

Step 1 : Check BTS 3-phases cables on ACDB if voltage supplied is according to range of AC voltage needed between 240V using millimeters to check . Make sure you switch ON AC breaker

For BTS inside ACDB.


Check also the 3-phases cables of BTS AC (EPS) box that came from ACDB ,make sure supplied voltage is according to range of AC voltage needed between 240V using multimeter to check.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 41

Power up process continued.


Step 2 : After you carefully check supplied voltages and confirmed accuracy AC voltage needed by BTS is okay then , you can now start powering up the BTS as specified. When you power up the AC breaker of the ACDB, Next you power up BTS 3900A AC breaker as shown. the rectifier modules (PSU) comes up also PMU. Ensure that the LED is green.

AC breaker to power up BTS 3900A

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 42

Power up process continued.


STEP 3: Power up the breaker in the battery cabinet

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 43

Power up process continued. STEP 4: Power up the battery switch on the EPS sub rack of the BTS cabinet and then the BBU DC breakers as shown.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 44

Power up process continued.

STEP 5:
Power up the BBU UPEU switch as shown

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 45

Power up process continued. STEP 6: Power up the switch for the boards on the RFC cabinet which can be DRFU or GRFU as shown

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 46

Power up process continued.

STEP 7:

After this step switch ON transmissions breakers from rectifier , then switch ON IDUs PXC Card pen switch and IF Card pen switch.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 47

Power up process continued. STEP 8: Wait for some minutes for the BTS boards to boot and register at the BSC, then check the alarm status of the boards and the modules. If there is any alarm, check the cause and troubleshoot.

if its a major alarm, escalate to the Huawei BSS Engineer in charge of the site.
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 48

PROCEDURE FOR POWERING UP OF INDOOR BTS 3900

STEP 1: Power ON rectifier from ACDB breaker controlling connecting point to Rectifier STEP 2: Power ON rectifier AC breaker under at a connecting point to ACDB, make sure you check voltage supplied not more range specified 240V using multimeter.

STEP 3: Power ON DC breaker connecting BTS 3900 connecting point on LP breaker , make sure you check voltage supplied not more range specified -48V using multimeter.

STEP 4: Power ON BTS 3900 indoor , first power ON BBU switch then power BBU, UPEU switch STEP 5: Power ON DRFUs and make sure all CPRI optical fibers were well connected and fixed tightly to CPRIs ports on DRFUs.

After this step switch ON transmissions breakers from rectifier , then switch ON IDUs PXC Card pen switch and IF Card pen switch.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 49

Pictures to show the position of the breakers on the TP48300A rectifier type..

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 50

Pictures to show the position of the breakers.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 51

CHAPTER 4 Wireless project problem


Feeder cables should be correctly adopted according to specifications. The azimuth and tilt angle of the installed antenna must accord with design specifications. The antenna connection and sector relationship are correct without reverse connection and misconnection. Waterproof and sealed measures for all outdoor jumpers and feeder cables should be correctly adopted according to specifications. The trunk cable should be correctly adopted according to specification without rosin joint.
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 52

Wireless project problem


The feeder cable should be earthed at three point at least, and has perfect waterproof treatments
The feeder windows should have correct sealed measures and waterproof bend. The RF connector needs to be installed perfectly. The lightingproof arrester must be earthed, all ground cables are connected to the outdoor protection ground bar of equipment room after collecting. Retain the additional engineering material for future use. There couldnt waste or throw away the engineering material optionally.
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 53

Chapter 4: Wireless Project Problem

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 54

Chapter 4 Hardware Quality Standard


4.1 General 4.2 Main Equipment 4.3 Antenna and Feeder Cable 4.4 Power Cable and Grounding Rule 4.5 Other

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 55

General

Requirements for rectifying: Violation of Class A clauses All problems must be rectified or else a memo must be signed with the Customer. If the Customer still does not agree to sign any memo although efforts have been made by multiple parties to coordinate with the Customer, a notice should be given to the related staff of Huawei such as the Engineering Management staff and a note must be indicated in the self-check report for future check. Violation of Class B or C clauses Problems of this project: Except for the quality problems that cannot be rectified this project (the specific cause must be indicated in the self-check report for future check), all the other problems must be rectified. Outstanding problems before this project: Such problems must be rectified if such rectification is rendered possible in this project.
Huawei Confidential Page 56

HUAWEI TECHNOLOGIES CO., LTD.

Chapter 4 Hardware Quality Standard


4.1 General 4.2 Main Equipment 4.3 Antenna and Feeder Cable 4.4 Power Cable and Grounding Rule 4.5 Other

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 57

Main Equipment

1. The RF cable connector needs to be installed perfectly to avoid the situation that the virtual connection would cause an abnormal VSWR and thus the normal system operation would be affected. (indoor, outdoor) 2. The external lightning-proof arrester of cabinet should be installed according to its design requirements. Its connection should be firm. (outdoor)
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 58

Main Equipment

3. The

cable connection of storage battery cabinet should be correct and reliable (check when an external storage battery exits). (outdoor)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 59

Main Equipment

4. For all kinds of cable connectors, they must be clean before installation. If necessary, they should be cleaned according to specification. (indoor, outdoor)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 60

Main Equipment
5. The connection of alarm cable should be correct and reliable (check when an external alarm box exits). (indoor, outdoor) 6. The parts of the rack should not be distorted. Which may be affect the equipment appearance. (outdoor) and the EMUA, DDF and RADIO(IDU) must be arranged in other as shown below:

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 61

Main Equipment
7.

The board can be plugged and unplugged smoothly. If there is any slot without board ensure to cover dummy slot.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 62

Main Equipment
8. The movable accessories of the cabinet work normal. (indoor, outdoor) 9. The collection cable of environment alarm connected to the base station should have reliable lightning-proof protection measures. (indoor) 10. The parts of the rack should not be distorted. Which may be affect the equipment appearance. (indoor) 11. Cabinet doors beside the main walkway should be aligned after they are installed. The installation error must be less than 5mm.(indoor) 12. The vertical errors of cabinet should be less than 3mm.(indoor, outdoor) 13. The gap between adjacent bases is not more than 3mm.(indoor)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 63

Main Equipment

14. The rigid cables should not be cross inside the cabinet. They cannot be pulled too tightly. Some redundancy must be reserved at their bend place. They also need to be bent in a tidy and consistent way. (indoor, outdoor)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 64

Main Equipment
15. The cable labels are filled in and pasted correctly and reliably. Their positions are orderly and in the same direction. Cable labels should be stuck at the place 2cm away from their connector. They can be made in a uniform way according to customer requirements. (indoor, outdoor) 16. The part of peeling of the on-site cable should be covered with protection tube or insulating tape. (indoor, outdoor)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 65

Main Equipment
short-circuit sheet metal

17. The PGND of main and slave cabinets must be interconnected by a copper wire when combining cabinets, the connection cable should be a yellow-green plastic insulating copper wire with a diameter of more than 10mm2, or using the short-circuit sheet metal to connect the metal shells of the two cabinets. The PGND of main and slave cabinets should be connected to the grounding bar in the equipment room respectively. When using the equipotential cable, its length should be less than 2m.(indoor)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 66

Main Equipment
18. When adjusting the level of the base by adjusting bolts, the pads should be added to its bottom to increase its stress area and avoid its distortion. (indoor) 19. The interconnecting piece on the top of the cabinet must be installed and tightened. (indoor) 20. PVC troughs should be installed on the wall for power and signal cables of alarm box. Redundant power and signal cables should be put under the floor or on the cabling ladder of alarm box side. (indoor)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 67

Main Equipment

21. Cables should be tied with uniform spacing and moderate tightness. Cable ties should be tied in a tidy way. Their redundant indoor parts should be cut from their bottom after they are tied without any spine. (indoor)
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 68

22. Jumpers are laid according to layers and sectors. (indoor, outdoor)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 69

24. The connection position of cable connector should reserve some redundancies. (indoor, outdoor)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 70

25. The

rack-mounting ear should be perfect. If some breakages occur on it, repair activities should be done with spray paint. (indoor, outdoor)

26. The upper plane of antistatic floor in the equipment room cannot be higher than the lower plane of the base to avoid to affect the ventilation. (indoor
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 71

Chapter 4 Hardware Quality Standard


4.1.1 General 4.2 Main Equipment 4.3 Antenna and Feeder Cable 4.4 Power Cable and Grounding Rule 4.5 Other

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 72

Antenna and Feeder Cable


1. The connection between antenna support and tower should be reliable and firm. The connection between antenna and its support should also be reliable and firm(indoor, outdoor) Antenna and feeder check: 1.1. The azimuth and tilt angle of the installed antenna must accord with design specifications ; 1.2. The antenna connection and sector relationship are correct without reverse connection and misconnection ; 1.3. The calibration test and sensitivity test indexes of base station accord to requirements ;

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 73

Antenna and Feeder Cable

2. The azimuth error of the directional antenna should not be more than 5 degrees. Its tilt angle error should not be more than 0.5 degrees. (indoor, outdoor)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 74

Antenna and Feeder Cable

3. When the feeder cable is bent on the top of a building and then extended downward along the wall, the protective means should be used for the parts of contact with the wall corner. When the feeder cable enter to room along the roof, the feeder clamps should be used to fix the feeder cable. (indoor, outdoor)
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 75

Antenna and Feeder Cable

4. When a feeder window is installed on the top of building to lead the feeder cable into the room, it must be sealed well. The antenna jumper and the feeder cable before the feeder winder must have waterproof bends. (indoor, outdoor)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 76

Antenna and Feeder Cable


5. The space between feeder clamps should be even and their direction should be same after installed. They should also be fixed firmly without any loose connection 6. The feeder cables can not cross after distributed. In the room they should be neat and straight with same bend.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 77

Antenna and Feeder Cable

7. The installation position of antenna should be accorded with the design document. (indoor, outdoor) 8. The distance between a directional antenna and the tower body should not be less than 1m. (indoor, outdoor)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 78

Antenna and Feeder Cable

9. Some redundancies 3~5mm should be reserved when cutting all of cable ties of outdoor. (indoor, outdoor)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 79

Antenna and Feeder Cable

10. The minimum bending radius of a feeder cable should not be less than 20 times of its diameter. (indoor, outdoor)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 80

Antenna and Feeder Cable


11. The jumper of the antenna should be tied along the rail of the support to the steel frame of the power. (indoor, outdoor)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 81

Chapter 4 Hardware Quality Standard


4.1 General 4.2 Main Equipment 4.3 Antenna and Feeder Cable 4.4 Power Cable and Grounding Rule 4.5 Other

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 82

Power Cable and Grounding

1. Each power cable or ground cable should be a whole section of copper core cable without any connector in between. It also should be connected firmly according to specifications. (indoor, outdoor)

2. When making copper lugs at the two ends of a power cable or ground cable, they should be soldered or crimped firmly. (indoor, outdoor)
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 83

outdoor power terminal for L1,L2 & L3

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 84

Power Cable and Grounding


(1) Cable (2) Nut

(3) Spring washer


(4) Flat washers (5) bolt

3. The grounding cable and power cable of equipment is connected correctly. Their flat washers, spring washers and nuts are installed in a right order. The nuts are tightened properly. (indoor, outdoor)
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 85

Power Cable and Grounding


4. The redundant part of a grounding cable or power cable should be cut and cannot be coiled. (indoor, outdoor)

5. The grounding of antenna and feeder cable on the top of a building without a tower should be connected to the nearby lightning-proof protection grounding net of the roof. (indoor, outdoor)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 86

Power Cable and Grounding

6. The handle of lug and bare wire of a power cable or grounding cable should be wrapped with the tube or insulating adhesive tape, the copper wire can not be bared. (indoor, outdoor) and remember to put denso paste.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 87

Power Cable and Grounding

7. The front door of cabinet should be connected to the grounding bolt of the door on the rack by the delivered or purchased cable. The grounding cable of the door should be connected firmly. (indoor, outdoor)
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 88

Power Cable and Grounding

8. The grounding bar must be wiped off rust and cleaned dirt before they are connected, in order to ensure their reliable connection. The outside grounding bar must be anticorrosion and antirust processed by using self-spray paint or other protection materials after they are connected in order to ensure their long-term good contact. Each connecting terminal should be installed correctly and firmly together with flat washers and spring washers. (indoor, outdoor)
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 89

Power Cable and Grounding


6. The space between a power cable/ground cable and a signaling cable outside the cabinet should be more than 3 cm. (indoor, outdoor)

3cm

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 90

Power Cable and Grounding


7. When the tower is more than 60 meters, add a grounding clip to the feeder in the middle of the tower. (indoor, outdoor) 8. If the length of feeder cable from the tower to the room on the roof (or cabling ladder) is more than 20 meters, a lightning-proof protection grounding clip should be added on the roof (or cabling rack). (indoor, outdoor) 9. The cable route for the power cable or ground cable should be accord with engineering document so that capacity expansion becomes easy. (indoor, outdoor) 10. The feeder cable goes into the room along the wall. If a cable ladder is used, it should be earthed. (indoor) 11. The grounding cable of feeder clips should extend from up to down. The angle between the grounding cable and the feeder cable should not be more than 15 degrees. (indoor, outdoor)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 91

Power Cable and Grounding


12. The diameter of the power cable, ground cable or equipotential cable between cabinets should meet the power distribution requirement. (indoor, outdoor) 13. The functions of power supply and fan are normal. (indoor, outdoor)

14. The power cable or grounding cable should be tied in a straight and tidy way with smooth bending. (indoor, outdoor)
15. The color of distributed power cables and ground cables should conform to the shipment, or satisfy requirements of the customer. (indoor, outdoor)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 92

Power Cable and Grounding Rule B,C

16. When connecting two or more cables to a wire pole, the cross or back-to-back installation method is generally adopted. When lugs are overlapped, they should be bent at an angle of 45 or 90 degrees, the bigger lugs should be put on the bottom and smaller one should be put on the top. (indoor, outdoor)
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 93

Chapter 4 Hardware Quality Standard


4.1 General 4.2 Main Equipment 4.3 Antenna and Feeder Cable 4.4 Power Cable and Grounding Rule 4.5 Others

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 94

Others
Retain the additional engineering material for future use. There couldnt waste

or throw away the engineering material optionally. A


The project should be implemented in compliance with related standards. for

construction behaviors, safety in production, power supply operations and equipment room of the customer. A
The engineering supervisor must upload the completion photographs for the

BTS along with Hardware Self-Check Report to the EPMS system. A

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 95

Thanks