CONSTRUCTION SEQUENCE OF PC OUTER WALL FULL CONTANMENT LNG STORAGE TANK

Legend

: Outline of the tank


: Part under construction : Concrete part completed : Mechanical part completed : Insulation part completed

SOIL IMPROVEMENT OR PILING, BLINDING CONCRETE

Blinding concrete for staircase

Blinding concrete for slab

Soil improvement or piling

CONSTRUCTION OF CONCRETE SLAB AND STAIRCASE FOUNDATION

Slab heating conduit Staircase foundation Concrete slab Form work

PC OUTER WALL CONSTRUCTION, ERECTION OF BOTTOM VAPOR BARRIER

1st lift of PC wall Staircase Temporary opening Bottom vapor barrier Form work

PC OUTER WALL CONSTRUCTION, ERECTION OF BOTTOM VAPOR BARRIER

Staircase

2nd lift of PC wall Form work Bottom vapor barrier

PC OUTER WALL CONSTRUCTION, PREPARATION FOR ROOF ASSEMBLY

Intermediate lift of PC wall Staircase Temporary support for roof assembly Form work

PC OUTER WALL CONSTRUCTION, ROOF ASSEMBLY

Staircase

Intermediate lift of PC wall

Form work

Roof liner supporting frame

PC OUTER WALL CONSTRUCTION, ROOF AND SUSPENDED DECK ASSEMBLY

Staircase

Intermediate lift of PC wall

Form work

Suspended ceiling deck & hanger Roof liner

PC OUTER TANK WALL CONSTRUCTION, ASSEMBLY OF ROOF AND SUSPENDED DECK


Roof compression ring PC wall top haunch

Form work Top lift of PC wall

ASSEMBLY OF ROOF AND SUSPENEDED DECK, PREPARATION FOR ROOF RAISING

Staircase

Temporary blower for roof air-raise

ROOF RAISING

Air pressure

Temporary blower for roof raise

WELD GUSSET BETWEEN ROOF AND COMPRESSION RING, INSTALLATION OF ROOF PENETRATION
Roof nozzle & manhole dome roof penetration

Roof liner support, liner and suspended ceiling deck

CONSTRUCTION OF ROOF CONCRETE


Roof concrete

Air pressure

Temporary blower for roof concrete construction

CONSTRUCTION OF ROOF CONCRETE, ERECTION OF WALL VAPOR BARRIER (LOWER) AND BOTTOM INSULATION (LOWER)
Roof concrete

Wall vapor barrier (lower)

Bottom insulation (lower)

CONSTRUCTION OF PLATFORM AND ERECTION OF BOTTOM LINER


Platform

Bottom liner

CONSTRUCTION OF PLATFORM, RING BEAM FOUNDATION AND ERECTION OF ANNULAR PLATE


Platform

Annular plate Ring beam foundation

ERECTION OF INNER BOTTOM, WALL VAPOR BARRIER, CORNER PROTECTION, BOTTOM INSULATION, AND INSULATION FOR CORNER PROTECTION

Wall vapor barrier (upper)

Insulation for corner protection Corner protection wall Inner bottom Bottom insulation (top)

Temporary opening

ERECTION OF INNER TANK WALL, INNER TANK BOTTOM, WALL VAPOR BARRIER AND BOTTOM INSULATION

Wall vapor barrier (upper)

Automatic shell welding machine Inner shell 1st & 2nd course Inner bottom Bottom insulation (top)

ERECTION OF INNER SHELL AND PIPING

Inner shell intermediate

Temporary opening

INSTALLATION OF PIPE SUPPORT, PLATFORM, HANDRAIL, WALL VAPOR BARRIER, SUSPENDED DECK PENETRATION, ERECTION OF INNER TANK WALL / GIRDER, AND PIPING
Dome space ladder & walkway

Suspended ceiling deck nozzle & manhole penetration

Pipe support

Inner shell upper & top course Inner girder

Pipe rack or sleeper

INSTALLATION OF ESCAPE LADDER, PLATFORM AND HANDRAIL, AND PIPING


Platform & handrail PRV / VRV / instrument platform

Escape ladder

INSTALLATION OF PRV,VRV, INNER LADDER, CRANE, HOIST, AND PIPING


Pump loading / offloading crane or hoist

PRV / VRV

Inner ladder

Pump column

CLOSING TEMPORARY OPENING, AND PIPING

Corner protection temporary opening closure

Inner shell temporary opening closure

PC wall temporary opening closure

HYDROTEST, PNEUMATIC TEST AND PIPING

SHELL INSULATION - RESILIENT BLANKET, PIPING INSULATION, AND PAINTING

Shell insulation Resilient blanket

ROOF INSULATION, ANNULAR SPACE INSULATION - PERLITE, AND PIPING


Roof insulation

Shell insulation - Perlite

LNG PUMP INSTALLATION, COMMISSIONING OF INSTRUMENT AND ELECTRICAL,


LNG pump

LNG pump

FINAL BOX-UP OF THE TANK, DRYING AND N2 PURGING

Drying & N2 purging equipment

COOLDOWN

START OPERATION