Está en la página 1de 2

FEATURE

Construction of the Boyne Bridge


Nigel King
Environmental constraints prevented this very large cable-stayed bridge from being assembled by normal
techniques. It had to be put together on one side and launched across the valley.

enclosure. The innovative launch scheme was


still viable and was proposed as an integral
part of the design. The proposals proved
attractive to the client and were accepted early
in the contract.
Being in control of the erection scheme and
permanent works design allowed the
designers to optimise the sections of the
longitudinal girders by choosing the stress
condition for the girders at the end of the
launch and the finished cable stay loads. All
design work was done in-house with a small
team of engineers.

Launching
It was proposed to launch the assembled main
and back span deck steelwork, weighing 1,600
tonnes and 210m in length, through the A-
frame pylon and across the river to meet the
north deck. The north deck would be erected
independently prior to the launch.
The development of the launch scheme
considered various options for the rolling
support of the steelwork behind the abutment
and at the pylon, along with those for
Ireland’s largest cable stay bridge is under Venture submitted the winning bid. positioning the temporary cable stay
construction in the peaceful Boyne Valley on At the time of tender it was realised that the attachments and strand jacks. Detailed
the outskirts of Drogheda, an historic town innovative space frame design still had operational and risk assessments resulted in
situated 30 miles north of Dublin. This significant technical, cost and time risks the selection of the following arrangements:
landmark steel structure will carry the M1 attached to it. In order to address these risks, • Multi-axle trailers carrying, driving and
motorway linking Dublin and Belfast across Cleveland Bridge and its internal design steering the rear end of the steelwork on the
the River Boyne. consultant, Dorman Long Technology, began approach to the southern abutment.
The contractor for the € 34m project is SIAC to develop an alternative design based on the • Rollers fixed to the steelwork running on
Cleveland Bridge Joint Venture, consisting of use of a combination of twin longitudinal plate steel tracks along the southern abutment
Irish contractor SIAC Construction Ltd. and girders and cross girders. and recycled as the launch progressed.
Darlington based Cleveland Bridge UK Ltd. Throughout the tender period, a considerable • Rollers fixed to the pylon cross beam over
The completed Boyne Bridge will consist of an amount of effort was put into deriving the best which the girders passed.
asymmetric 56 cable stayed structure with a method of erecting the cable-stayed • Lateral guide systems at the souther n
main span of 170m across the two channels of superstructure. Ground level access into the abutment and pylon.
the river. A series of shorter approach spans main span was prohibited for environmental • Temporary cable stays attached at ²⁄₅ and ⁴⁄₅
constructed on piers carry the bridge over the reasons, thus r uling out any support or points on the main span with strand jacks
northern slopes of the river valley. delivery of material from below. Difficulties mounted and operated at deck level.
were envisaged with the adoption of the • A hauling line running from the launch
Design traditional progressive cantilever method front to a fixed point behind the northern
The client, Meath County Council, and its normally used for cable stayed bridges, by abutment and operated by strand jacks.
consultant, Northconsult, were determined to erecting the tubular steelwork piece-small or To facilitate the launch temporary works, an
deliver a structure of aesthetic and technical in sub-assembled units. This led to the area of approach road, 160m in length, was
merit. An innovative feature of the design is innovative method of assembling the main and prepared with compacted stone behind the
the GRP (Glass Reinforced Plastic) enclosure back span deck behind the southern abutment southern abutment. A series of steel support
which surrounds and protects the steelwork of and launching it across the river. stillages were set up to the pre load camber of
the superstr ucture whilst providing an By the time the client was ready to place a the completed deck. The pre-fabricated
aerodynamically and aesthetically enhanced contract for the Boyne Bridge, the alternative longitudinal and cross girders were shipped
profile. The detailed design continued the design was completed in order to present it for from Cleveland Bridge and set up on the
innovation with the use of a tubular steel consideration. The scheme had advantages of stillages.
space frame within the GRP enclosure to maximum off-site fabrication under controlled At the souther n abutment and pylon
support the concrete deck slab. The tenders conditions and reduced technical, cost and crossbeam, temporary steel posts were cast
for the contract were invited on the basis of time risk. However, the appearance remained into the concrete works to support the deck in
this design and SIAC Cleveland Bridge Joint unaltered as all changes were within the GRP both lateral and horizontal movement. On the
FEATURE

north deck, the hauling line jacking system ste elwork. These were included with a Analysis of the surveys following cable
was cast into the concrete deck and anchored comprehensive method statement and the tensioning was completed in the same
by means of embedded blocks behind the detailed temporary works drawings. morning allowing adjustments, if any, to be
northern abutment. All designs were independently checked and made that afternoon with no break in the
Prior to launch operations, a series of verified and a design team presence on site construction work. Again the comparisons
checking points were set up along the deck to throughout the launch ensured accurate between actual and predicted geometry and
monitor the geometry of the deck at any stage. implementation. The check surveys cable loads were excellent.
The pylon verticality was also checked for undertaken at regular intervals throughout the
deflection at each stage. launch showed excellent agreement with Completion
Once the deck was pulled past the southern predicted profiles.
The launch of the back and main span deck
abutment, the temporary beams were installed
was completed successfully, followed by
to enable the whole deck to be lowered down Cable installation concreting of the deck. The in-situ concrete
into the final position at the souther n
The final involvement of the design team was deck slab was poured incrementally in
abutment. With the aid of two ‘A’ frames as
during permanent cable stay installation. conjunction with the installation of the
support, the deck was jacked down and then
Control of deck geometry during cable permanent cable stays. Installation of the
pulled back into the final position. After
installation is one of the key features of this barriers and asphalting, etc. is now well
lowering down, the north deck was jacked
form of structure. Completion of the steelwork underway and the bridge is due to be
back on the pier bearings to align with the
prior to any deck slab or cable work had the completed by the end of April 2003.
launched steelwork. The final north and south
advantage of eliminating the potential errors
deck connections were then welded.
in constructing the required unstressed girder Nigel King is a Project Manager with
shape usually present when erecting piece by Cleveland Bridge UK Ltd.
Control of the launch piece in cantilever. Nevertheless considerable The following people contributed to
A step-by-step non-linear structural analysis analytical effort was put into the prediction of this article:
produced the detailed step-by-step geometry, cable loads and deck stresses and Simon Hill, Survey Manager, Cleveland Bridge
adjustments required at the strand jacks to their sensitivity to variables such as UK Ltd.
control the launch prog ress whilst temperature, weight errors and geometric David Taylor, Principal Engineer, Dorman
maintaining acceptable stresses in the construction tolerances. Long Technology.

También podría gustarte