STANDARD CHECK LIST STATION : NTPC - Ramagundam Stage III (1 X 500 MW) PLANT ITEM : HFO PIPE LINE

PLANT NOMENCLATURE: LOCATION: REF: Sl.No.


1

SHEET 1 OF 3

ACTIVITY / CHECKS
General conditions satisfy the site Standing Instructions as listed in the Plant Item Commissioning Essential Pre-requisites".

STATUS YES / NO

REMARK

The nameplate legend agrees with the approved NTPC Plant Nomenclature and is clearly visible, securely fixed, durable and correlates with remote labels.

The installation is complete and correct in accordance with the latest approved drawings and specification.

4 5

Access for adjustments maintenance and repairs is satisfactory. Check that all bosses, flanges and tapping points have been adequately made off.

Verify, if appropriate, that all compression couplings have been inspected on site to confirm that the couplings comply with drawings showing approved locations.

Check that all fittings on the pipework comply to the requirements of the relevant India Standard for that system.

Check that all pipe falls to drainage points are satisfactory. Check that steam traps are correctly fitted with bypass and test connections.

Agency Elect. Mech. C&I Elect. Mech. C&I Contractor

Name

Signature

Date

NTPC Comg.

NTPC Erec.

STANDARD CHECK LIST STATION : NTPC - Ramagundam Stage III (1 X 500 MW) PLANT ITEM : HFO PIPE LINE PLANT NOMENCLATURE: LOCATION: REF: Sl.No.
9

SHEET 2 OF 3

ACTIVITY / CHECKS
Confirm that all blanks still required in the system are adequately identified and recorded in the Blanks Schedule.

STATUS YES / NO

REMARK

10

Confirm that all pipework that can be touched from walk ways etc, and that reaches a temperature of 60 deg C or over is adequately lagged.

11

Check that the pipework system, including supports, is free to expand and contract within its constraints, including floor collars and wall boxes.

12

Check that adequate number of vents are provided on the pipe at highest points.

13

Check that all supports are undamaged, fixed and mounted vertically, (Except where design requires the support at a specified angle).

14 15

Check that all support loadings have been correctly set. Verify that galvanised sheet weather-hoods have been fitted where pipes pass through roofs.

16

Check that all thrust/anchor points are correctly installed.

Agency Elect. Mech. C&I Elect. Mech. C&I Contractor

Name

Signature

Date

NTPC Comg.

NTPC Erec.

STANDARD CHECK LIST STATION : NTPC - Ramagundam Stage III (1 X 500 MW) PLANT ITEM : HFO PIPE LINE PLANT NOMENCLATURE: LOCATION: REF: Sl.No.
17

SHEET 3 OF 3

ACTIVITY / CHECKS
Confirm, where possible, that there is a radial clearance between the pipe and the support clip.

STATUS YES / NO

REMARK

18

Check that all roller and sliding supports are clean, free to move and so constructed that dirt and water cannot accumulate.

19

Flush the pipe line properly to open drain to clear all debris from pipe.

20

Test the pipeline hydraulically to the relevant standard in presence of Boiler Inspector if required.

21 22

Check that all temporary supports have been withdrawn. Confirm adequate support for small bore, horizontal pipes that may be stood upon (or adequate protection for the pipes and supports for system not strong enough to withstand additional loads).

23

A pressure relieving device has been provided between valves on each fuel oil line and that each relief, drain and vent valve is piped to a suitable disposal / recovery point.

24

Pipework trace heating, if appropriate, has been provided and proven.

Agency Elect. Mech. C&I Elect. Mech. C&I Contractor

Name

Signature

Date

NTPC Comg.

NTPC Erec.