PART-I
ELECTRIFICATION
Page 1 of 89
Page 2 of 89
01.00
INTRODUCTION M/s Hindustan Petroleum Corporation Limited is setting up green field Petroleum Storage cum Distribution Installations at Bihta, near Patna. The Depot at Bihta, near Patna shall have receipt facility by Rail Wagons and onward distribution by Road Tankers. The storage and distribution facilities at Bihta have been planned for both White Oils (MS/HSD/SKO/Ethanol/Additives) and Black Oil (Furnace Oil/ Bitumen). The white Oil facility shall be fully automated (except Wagon Unloading Siding & Pumps) whereas the Black Oil facility shall be Manually operated with A/G Tanks key parameters inputs to Automation system for monitoring purpose.
02.00
INTENT OF THE SPECIFICATION The intent of this specification is to describe in detail the entire Electrification, Illumination & Communication system required for the above Depot, which the Bidder shall undertake in full compliance with the contract documents. This document elaborates the Bidders work involved in erection, testing and commissioning of the electrical Equipment supplied by owner/ testing and commissioning of the motors and other items to be installed by other agency. This document also includes Bidders scope of work involved for items to be supplied, erected, tested and commissioned. These items are elaborated under different schedules under this Technical Specification.
03.00
GENERAL a) These instructions shall be read in conjunction with all the commercial documents appended to this document. In case of contradictions in the clauses under TS the most stringent one shall prevail. b) All the equipment supplied by the contractor shall be new and conforming to relevant latest BIS, safe engineering practices and codes. These shall be tested and commissioned as required and no separate payment shall be made unless otherwise specified in the schedule of rates. c) Any work not conforming to the execution drawings, Specification or codes shall be rejected forthwith and the contractor shall carryout the rectification at his own cost. d) The contractor shall carry out the various tests as enumerated in the technical specification and the technical documents, which, may be furnished to him during the performance of the work. e) Before an electrical system is made live, the electrical contractor shall carry out suitable tests to establish to the satisfaction of owner that installation of all equipment, wiring and connections have been correctly done and are in good working condition and will operate as intended. f) All tests shall be conducted in the presence of the Engineer-in- charge or his authorized representative unless he waives this requirement in writing. All the testing equipment required, to carry out the tests must be supplied by the contractor. The tests shall be recorded on approved pro-forma and certified records of the tests shall be submitted to the owner / Engineer in- charge.
Page 3 of 89
j)
k) Following Items shall require inspection and clearance by Third Party Inspection Agency (EIL/BV/DNV/PDIL/ Mecon / Llyod) as per approved QAP prior to dispatch to site. The quoted rate by bidder is deemed to be inclusive of the TPI charges. a. All FLP Items. b. HV and MV Cables c. EPABX, PA System and VHF System l) Although every required item of work may not be explicitly described in the specification, it is the owner's intention to furnish the Bidder with every detail necessary to complete the specified work with the exception of those items of work listed under "work by others".
m) It is the responsibility of the Bidder to assess the type and magnitude of work involved based on information furnished by the owner / in the schedules of this document and general field conditions. n) It is the Bidders responsibility to specially list out in his quotation, all items and any other items left out in the schedule of units, but which are necessary for the completion of work assigned, along with unit prices. If the unit price is not already indicated then all such items are deemed to be included in Bidders scope. o) Bidder shall clearly indicate deviation, if any, from this specification, along with unpriced bids. p) Bidder shall quote for complete work specified in the document. q) Bidder shall obtain from Owner / additional details / data, if any, required to submit proper quotation. The Bidder is advised to visit site and assess the conditions prevailing before submitting the offer. r) The word 'installation' wherever mentioned in this document shall mean erection, testing and handing over of item /equipment after successful commissioning. s) Information and documents furnished by the Bidder for each item of work shall be complete, without any cross reference to other parts.
Page 4 of 89
u) The Successful Bidder has to make his own arrangements for construction power, water, workshop office etc., at site. The cost of the same is deemed to be included in the offer. 03.01 Data / Information to be furnished by Bidder with tender a. List of works executed similar to the one covered under this tender along with contract value and the period of completion. b. List of tools and tackles, testing / handling equipment available with Bidder and required for completion of job detailed in this specification. c. Bar chart indicating schedule of manufacture, delivery at site, erection, testing and commissioning of individual equipment. d. Copy of the License for 11kV issued in name of the company / personnel of the bidders organization. e. Documents required towards fulfillment of Technical and financial Bid Qualification criteria. 03.02 Price Prices quoted shall be firm without any escalation till completion of the job assigned and shall be inclusive of all incidental charges/expenses whatsoever including safe storage at site, handling /transportation, erection, testing, commissioning, documentation etc as required for the completion of job in line with the scope of work. All consumables and spares, required for the installation, testing and commissioning, shall be supplied by the contractor till the stage of handing over. Unit rates for installation shall include such consumable. Bidder shall furnish list of consumable / spares recommended by manufacturer for each equipment, for two years normal operation. The contractor's responsibility shall be for the complete work including supply of materials as per Scope and he shall not absolve him-self of any unintentional errors or omissions in the description of the scope. Prices indicated by the Bidder shall also be deemed, to include and cover, but not limited inter-alia, the following: Providing touch up final paint etc., wherever required after installation. Handling & transportation of materials, at stores/ place of work, temporary connections/disconnection, Cost of tools & tackles, security till handing over etc. 03.03 Training Contractor shall train the work force of customer with his technical and supervisory personnel for safe and efficient operation and maintenance of the equipment and system installed by the contractor. The Number of personnel to be trained and the duration and structure of the training shall be mutually discussed and finalized. 03.04.00 Spares
Page 5 of 89
03.09
L.
CONTRACTORS SCOPE OF SUPPLY The broad scope of supply shall be as under: A. B. C. D. HV, MV XLPE POWER CABLES & CONTROL CABLES. FLP LIGHTING FIXTURES WITH CONTROL GEARS IN STRUCTURAL SHEDS SUCH AS. WATCH TOWER TT GANTRY(S) PRODUCT PUMP HOUSE(S) CALIBRATION TOWER FIRE WATER PUMP HOUSE SEALING PLATFORM FOAM SHED LUBE WARE HOUSE GREASE DRUM YARD TRANSFORMER AREA 2 POLE STRUCTURE AREA SAMPLE ROOM IN ADMN BLDG TANK TRUCK PARKING AREA OTHER PLACES AS DIRECTED FLP LIGHTING & POWER DISTRIBUTION BOARDS WITH INCOMING AND OUTGOING FEEDERS AND CONTROLS IN ABOVE SHEDS LIGHTING POLES WITH LIGHTING FIXTURES & CONTROL GEAR.
Page 8 of 89
04.01
SCOPE OF WORK a) Drawing preparation, approval from owner, procurement, shop testing,(TPI inspection for selected items as per tender) supply, transportation, transit insurance, unloading, handling, temporary storage, erection, testing, commissioning, documentation and handing over of Supply Items as per scope of supply, schedule of rates, enabling works ,specification, terms and conditions. b) Design and preparation of Overall Lighting and Earthing layout including Lighting and earthing design/ drawings for individual Structural Sheds. Lighting Design and drawing of RCC Building and Car Parking Shed is outside the scope of the Bidder. c) Shifting from owners store, erection, testing and commissioning of owner supplied HT & LT switchgears and transformers. d) HT & LT power, control and signal cable laying in RCC trenches, cable trays, buried cable trenches, on steel & RCC structures etc including jointing, testing, end termination and commissioning. e) Installation of Plant earthing network with GI flat and GI pipe earth electrode including local grid for Building, structures, lightning protection grid all complete as per IS-3043, OISD standard, IE rules and the tender specification. f) Supply of all labor, supervision, tools and tackles, testing equipments, consumables, materials and all other erection accessories not specifically mentioned herein but required to complete in all respect, installation, testing and commissioning of all equipments covered under this contract. g) All liaison work with CEA/ Local electrical Inspectorate right from submission of application, drawings, test certificates to Inspection of Plant and until receipt of approval and completion of energization of entire plant equipment. All Statutory Deposits made to CEA in this regard shall be reimbursable on production of receipt. h) As Built documentation: This shall comprise of submission of 6 sets ( 1 original + 5 copies) of following documents in hard form including one set in soft form (CD/DVD) in pdf/ Autocad format. (i) Cable Schedule (ii) Overall Lighting & Earthing Layout (iii) Lighting and Earthing layout of individual Building/ Structure (iv) All field Test records (v) All OEMs Test certificate, CMRI Certificates etc (vi) All OEMs drawing, catalogues (vii) Fire Alarm system drawing (viii) PA System Drawing (ix) Termination Details (x) Plant Cable layout (Outdoor) (xi) Final Approval from CEA
Page 9 of 89
04.02
The cable glands (WP/FLP), plugs (WP/FLP) for all equipments supplied by the contractor shall be in the scope of contractor and no extra payment shall be made for those glands/plugs. Construction of suitable covered equipment storage building / sheds and site construction office with all required facilities, illumination etc. shall be done by the agency at their own cost. Watch & ward at contractors store / working place, working place at plant site, erection sites for safe custody of equipment erected by contractor till the equipment are handed over to purchaser. Contractor shall be held responsible for any theft of equipment, components etc. kept under their custody. Transportation of equipment and materials from plant / contactors stores to the site for erection and commissioning purpose. Provision of proper handling equipment e.g. winches, lifting jacks, slings, pulleys, ropes etc. as well as all erection tools and tackles, welding and gas cutting machines, power tools, hand lamps, pipe bending machine, cable crimping tools, gauges, scaffoldings, ladders, local illumination etc. including cables required for connection of these items. Provision of construction power supply including supply of construction power supply boards, cables etc. & maintenance of same during contract period. Purchaser shall not provide any construction power but shall be arranged by contractor. The scope of work of the contractor shall also include co-ordination with other contractors at site, pre-commissioning no load / load tests, integrated on load testing & commissioning, handing over, conducting PAT / FAT and liquidating defects etc. for the complete installation work carried out by the contractor. Obtaining Statutory approvals for the entire electrical installation Supplied, installed, tested and commissioned or owner supply items installed, tested and commissioned under this Contract. DELETED
04.03
04.04
04.05
04.06
04.07
04.08
05.00
06.00
TECHNICAL SPECIFICATIONS OF CABLES (H.T. / L.T. / CONTROL / LIGHTING) AND ACCESSORIES GENERAL CONSTRUCTION The cables shall be suitable for laying in trays, trenches, ducts and conduits and for underground buried installation with uncontrolled backfill and possibility of flooding by water and chemicals. Also cables shall be suitable for system particulars, site conditions and environment conditions specified. The conductor shall be stranded and compacted circular / shaped for all cables. Outer sheath of all PVC and XLPE cables shall be black in colour. In addition suitable chemicals shall be added in to the PVC compound of the outer sheath to protect the cable against rodent and termite attack. The outer sheath of PVC and XLPE cables shall possess ST-2 PVC properties meeting requirements as per IS. Sequential marking of the length of the cable in metres shall be provided on the outer sheath at every one-metre. The embossing shall be legible and indelible.
06.01
Page 10 of 89
Page 11 of 89
06.04
FLAME RETARDANT LOW SMOKE (FRLS) These shall be as per specification mentioned above but with protective system of inner and outer sheath specially designed with thermoplastic or thermosetting materials, superior resistance to ignition and flame propagation with smoke emission and toxicity or corrosive characteristics.
06.05
CABLES / WIRES FOR ILLUMINATION WORKS FOR FIXED WIRING : i) Type I : Single core :1100 grade Cables With Copper conductor, PVC insulated and Unsheathed. Minimum 1.5 Sq. MM Size.
ii) Type II : Single core :1100 V grade cables with copper conductor, PVC insulated and PVC sheathed. iii) Type III: Circular multicore: 1100 V grade cables with copper conductor, PVC insulated and PVC sheathed. iv) Type IV: Same as Type I above but having aluminum conductor. Minimum 4 Sq. mm Size v) Type V : Same as type II above but having aluminium conductor.
FLEXIBLE CORD : i) Type I: Single core: 1100 V grade cables with copper conductor, PVC insulated and unsheathed. Minimum 1.5 Sq. Mm size
ii) Type II : Single core : 1100 V grade cables with copper conductor, PVC insulated and PVC sheathed. iii) Type III: Two core twisted: 1100 V grade cables with copper conductor, PVC insulated and unsheathed. iv) Type IV: Circular, Multicore: 1100 V grade with copper conductor, PVC insulated and PVC sheathed.
CONDUCTOR Conductor shall be composed of plain annealed high conductivity copper wires or aluminium wires. Wires up to 1.5.mm2 shall be either solid or stranded in case of copper conductor and solid in case of aluminium conductor. Wires above 1.5 Sq. mm shall have stranded conductors. Conductors having cross sectional area up to 25 mm2 shall be circular and above 25 mm2 may be circular or shaped. INSULATION
Hindustan Petroleum Corporation Limited Page 13 of 89
1. Core: Red, Black, Yellow, Red, Black, Yellow, blue, white or blue, white or gray gray 2. Cores: Red & Black 3. Cores: Red, Yellow & Blue Red & Black Red, Black & Yellow / Green
4. Cores: Red, Yellow, Blue & Red, Yellow, Blue & Yellow / Green Black
SHEATHING i) Sheathing of black, white or grey shall be applied by extrusion over the insulation in case of single core cables and over the laid up cores in other cases.
ii) The colour of sheath shall be Black, white or grey. 06.06 Cable Accessories The termination and straight through jointing kits for use on the systems shall be suitable for the type of cables. Heat shrinkable type or cold setting type of kits offered shall be mentioned in the offer clearly. The accessories shall be supplied in kit form. Each component of the kit shall carry the manufactures mark of origin. The kit shall include all stress grading, insulation and sealing materials apart from conductor fittings and consumable items. An installation instruction sheet shall also be included in each kit. The contents of the accessories kit including all consumable shall be suitable for storage without deterioration at a temperature of 450 C, with shelf life extending to more than 5 years. 06.07 TERMINATION KITS The termination kit shall be suitable for termination of the cables to an indoor switchgear or to a weatherproof cable box of an outdoor mounted transformer. For outdoor terminations, weather shields / sealing ends and any other accessories required shall also form part of the kit. The termination kits shall be one of the makes / types mentioned in the preferred make. 06.07.01 JOINTING KITS The straight through jointing kits shall be suitable for installation on overhead trays, concrete lined trenches, and ducts and for underground burial with uncontrolled backfill
Hindustan Petroleum Corporation Limited Page 14 of 89
D) Routine test 06.08.02 Conductor resistance test Partial discharge test for HT cables. High voltage test Insulation resistance test
Cable Accessories Type tests shall be carried out to prove the general qualities and design of a given type of termination / jointing system / kits as per IS: 13573. The type test certificates shall be submitted along-with the offer. In case type test certificates are older than 5 years, vendor shall carry out the type at his own cost.
06.09
PACKING AND MARKING Cables shall be dispatched in non-returnable wooden drums of suitable barrel diameter, securely battened, with the take-off end fully protected against mechanical damage. The wood used for construction of the drum shall be properly seasoned, sound and free from defects. Wood preservatives shall be applied to the entire drum. Ferrous parts used shall be treated with suitable rust preventive finish or coating to avoid rusting during transit or storage. Cable drums shall be suitable for storage in the open yard at site where it will be subjected to rains and other climatic variations. The wooden drums shall not deteriorate and collapse during storage for at least 2 years. On the flange of the drum, necessary information such as project title, manufacturers name, type, size, voltage grade of cable, length of cable in metres, drum No., cable code, BIS certification mark, gross weight etc. shall be printed. An arrow shall be painted on the drum with suitable instructions to show the direction of rotation of the drum.
Page 16 of 89
06.10
DESIGN CRITERIA
Page 17 of 89
40 degrees C XLPE Aluminium/Copper Copper Steel Wire armour. Round wire armour. Extruded inner and outer sheath, type ST2
Voltage variation + or -10% Frequency variation + or 3% Cable size As specified in BOQ and drgs. Voltage rating of the cable 11kV (UE) 1.1 kV Number of cores 3 core 4 / 3 core
1.1 kV Multicore
06.11
SELECTION Size and type of cables for specific applications shall be selected giving due consideration for the following : The size selection of HV cable shall be done on the basis of system fault level in addition to current rating of the cable and voltage drop on the cable. Thermal heating effect / permissible current carrying capacity Allowable voltage drop as per Technical specification Short time current / overload requirement Protection system grading and short circuit current carrying capacity Ambient conditions Cable grouping factors Cross-sectional area of the cables used in LT power circuits shall be Minimum 10 sq mm per core with aluminium conductor or 6 sq mm per core with copper conductor Maximum core size shall be 185 sq mm for motors and 240/300 sq mm for incomers
Page 18 of 89
- Sequential length marking shall be provided in outer sheath of all power and control cables. - Standard drum length for all types of power and control cable shall be offered. ISI marking at every meter of cable length shall be provided. Cores of multi-core control cables shall be serially numbered. The wires shall be suitable for voltage up to and including 1100 V with copper / aluminium conductor (as specified), PVC insulated, PVC sheathed or unsheathed as specified, unarmoured.
07.00 07.01
L.T Equipment Design Criteria Ambient conditions 1 2 3 4 Maximum ambient temperature Humidity Height Environment 45 degrees C 100% not occurring with maximum temperature Less than 1000 M Completely laden with dust & gases
: 1 Voltage Power supply system 415V +/- 10% 3 phase and neutral
Page 19 of 89
08.00 FEEDER PILLAR AND LDB / SDB / DB 08.01 LDB/SDB/DB 08.02 Suitable for 415 / 230V with Aluminum / copper TPN & E busbar. Totally enclosed, nondrawout, front operable Enclosure IP: 65. Incomer chamber housing MCCB / SFU / MCB / ELCB / Contactors/ Busbars, indicating lamps. Outgoing chambers housing SP/DP/TP/TPN MCBs /TIMER/SFU Shrouding of all live parts. Suitable mounting bracket / pedestal / base frame. Continuous earth bus with earthing studs, Phase barriers. Aluminum / copper busbars as per approved SLD. Neoprene gasket for all door and frame shutters. Link between neutral and earth. Hinged door with pad locking arrangement. Brass cable-glands for all incoming and outgoing feeders. Double Door construction. SLD to be pasted inside the door. Board designation plate to be fixed. Danger board to be provided. Inscription plate with inscriptions for all feeders. The finish paints for the boards shall be indicated during approval of GA drawing. FEEDER PILLAR Shall be suitable for 415 / 240V with aluminium TPN & E busbars Suitable for plinth mounting. The frame work and door shutters shall be CRCA sheet steel of 2.0 mm and 1.6 mm thick respectively with double door construction. The enclosure shall have a protection class of IP: 65. Suitable canopy for rain water protection. Cable entry and exit from top or bottom with removable undrilled gland plate of 3 mm thick shall be provided. Continuous earth bus with extended earthing stand. Incomer shall have separate chamber for housing TPN SFU / MCCB and provision for terminating multi-core cables. Outgoings for Fittings- SFU / MCB / ELCB / Timer / Contactor
Page 20 of 89
MOULDED CASE CIRCUIT BREAKERS 1. 2. 3. 4. Type Reference standard Rated current Feature required : : : : Motor/feeder duty as required IS:13947 (Pt-3), 1993, IS:2516 As per approved SLD Adjustable inverse time (O/L) and/or instantaneous magnetic releases as per approved SLD : Yes : : Yes Yes
Page 21 of 89
6. 7. 08.04
HRC FUSES 1. 2. 3. 4. Type Rated Voltage Rated current Operation indicator : : : : Link type 500 V AC As specified in SLD Required
08.05
AC CONTACTORS 1. Service : Indoor within steel cubicle for maximum system voltage, starting of motors and miscellaneous loads. :3 : 415V +/- 10% voltage : 50 Hz +/- 5% : 110 V +/- 10% l phase 50 Hz +/-5% derived from 415 / 110 V control transformer : AC2/3 for unidirectional motors AC4 for bi-directional motors Minimum 2 NO. + 2 NC contacts
2. 3. 4. 5.
6.
Utilisation category
7. 8.
: 85% to 110% : Shall not be higher than 75% and lower than 10% of rated control supply voltage : 16 A or 125% of rated motor current whichever is Higher
9. 08.06
Rating
CURRENT TRANSFORMERS 1. 2. Service System : Indoor : 415V, 3 phase, 4 wire, 50 Hz, Solidly earthed neutral : Resin cast encapsulated, window type, primary bar
3.
Type
Page 22 of 89
4. 5.
: 415 V +/- 10% : As per requirements of individual feeders or as mentioned in the specification : CT secondary rating shall be 5 Amperes, Burden 15VA : 5P10 or better for protection and Class - 1 for Metering : 2.5 kV (RMS) for one minute
6.
7.
Accuracy
8.
9.
08.07
CONTROL TRANSFORMER 1. 2. Service Primary Voltage : : Indoor 415V, 3 phase, 4 wire, 50 Hz solidly earthed neutral Cast resin, dry type 110 V 1 Phase 50 Hz As per requirement. Minimum 5 kVA 10% on Primary side in steps of 2.5 % Primary 2.5 kV for 1 Minute stand voltage Secondary 1.0 kV for 1 Minute Bottom of panel with Air Blow Louvres As per approved SLD
3. 4. 5. 6. 7.
Type Rated secondary voltage Rated burden Tappings Power frequency with
: : : : :
8. 9. 08.08
Mounting Quantity
: :
ELCBs The ELCB shall be current operated type 4 pole with sensitivity of 30 to 300 mA sensitivity quick break trip free rating and provision to connect cable as per approved single line diagram.
08.09.
Name Plates Name plates showing switchgear / feeder designation shall be provided of anodised aluminium of 3 mm thick. Individual panel nos. / designation plate shall be fixed both at back and front of the panel on fixed portion. All components shall have distinct labels.
08.10
TESTS
Page 23 of 89
09.00 09.01
TABLE B SL. NO. 1 AREA Tank farm & other area lighting ILLUMINATION Maintenance LEVEL (LUX) Factor 60 0.6 TYPE OF LIGHT FITTINGS 400W flood light fittings (Non FLP) with HPSV lamp 250W SON/400W flood light fittings (Non FLP) with HPSV lamp FLP, 3x26W, CFL well glass fittings Decorative / rail / Trough type fluorescent tube light fittings Surface/recess mounting type fluorescent tube light fittings Vapour proof fluorescent tube light fittings FLP, 3x26W, CFL well glass fittings FLP, 3x26W, CFL/250W HPMV well glass fittings Non FLP, 70W/150 W, HPSV Street Light Fittings FLP, 3x26W, CFL well glass fittings / Flourescent tube light, fittings WP, 3x26W, CFL well glass fittings well glass fittings/street lighting
20
0.6
Pipe Manifolds Electrical rooms / offices / LT substations, Amenities Block, Security Room
60
0.6
250-300
0.8
400
0.8
Battery room
100
0.7
Lubricant Go-down TLF shed& Gantry calibration shed, meter room etc
100
0.7
300
0.65
Periphery of buildings
20
0.5
Product pump houses /Water 10 pump house/ General Stores/ Drivers Rest Room
150
0.7
11
Transformer yard
60
0.6
12
Watch Tower/Water tank/ watchman Kiosk/Gate Complex and any other open area within the battery Limits
NOTE : The quantities indicated in the SOR are tentative and may increase/ decrease to meet the lux requirement. The successful bidder shall design the Lighting and earthing system. 09.02 LIGHT FIXTURES, LAMPS AND ACCESSORIES
09.02.01 GENERAL All the luminaires shall be designed, manufactured and tested in accordance with relevant IS specifications so far as they are applicable. All the luminaires shall be commercial / industrial type as per specific requirement. Specification for the various types of incandescent, mercury vapour, sodium vapour and fluorescent fittings mentioned in the schedule of quantities shall be followed. All the lighting fixtures shall be complete with all parts, including earthing arrangement and accessories for efficient performance whether specifically asked in the specification or in the schedule of items or not. Individual light fittings shall be provided with suitable arrangements for GI threaded conduit entry of 19 mm dia unless otherwise specified. Terminals of all fittings shall be suitable for taking 2.5 sq. mm flexible, copper conductor PVC insulated, PVC sheathed cable. Fittings shall be supplied with all inter connections made and fully wired upto the terminal block and shall be suitable for mounting on wall / column / ceiling / suspension (from the ceiling including suitable bracket). All types of light fittings shall be supplied with lamps. All live parts shall be provided with suitable sleeves to prevent accidental contacts. The earthing terminal in the fitting shall effectively earth the body of the entire luminaires. The clearance between the live parts and the enclosures earthing and other safety factors shall be governed by the latest revisions of the relevant IS specification and IE rules. The fixing arrangement of various components and lamps shall be in such a way that the maintenance and replacement jobs can be easily carried out. The luminaires shall be suitably designed to provide economically the required level of illumination on the working plane when mounted at normal standard height in accordance with the type of fixtures. The luminaires shall be suitable for operating at normal supply voltage of 240 V, single phase, 50 Hz with voltage variation of +/- 6% or at voltages as specified. The lamp holders of the fittings shall be suitable to take the lamp supplied. All types of Flourescent lamp fittings shall be supplied with necessary controlgear housing polyester filled copper wound ballast/ electronic ballast. P.F improvement capacitor spring loaded rotary lamp holders starter holders metallic starters all pre wired to suitable terminals
Page 26 of 89
09.02.02
STREET LIGHT LUMINAIRE (SUITABLE FOR HPSV LAMPS) The integral type street light fittings shall be of single piece construction from die cast aluminium. The control gear compartment shall have the necessary ballast, ignitor, p.f. improvement capacitor and connector block apart from the brackets for fixing the fitting to the mast / arm.
09.02.03
STEEL TUBULAR POLE (FOR MOUNTING STREET LIGHT / FLOOD LIGHT) Shall be as per drawing attached with the tender
09.02.04
FLOOD LIGHT LUMINAIRE (SUITABLE FOR HPSV LAMPS) The flood light fitting shall be of non integral type, complete with suitable weather proof control gear box made of cast aluminium. The fitting shall consist of a cost aluminium lamp holder housing a reflector made of spun aluminium electro-chemically brightened and anodised. Flat toughened front glass suitable to withstand the high temperature and humid conditions shall be fixed to the housing using neoprene gasket. Focusing knob to help in adjusting the lamp centre shall be provided. Mild steel cradle shall be mounted on the control gear. The control gear shall consist of heavy duty polyester filled copper choke suitable for lamp wattage specified, p.f improvement condensors, connector and fitting is duly wired with provision of cable
Page 27 of 89
09.02.05
POST TOP LANTERNS: Post top lanterns shall be suitable for taking GLS/blended light (MLL) / HPMV / HPSV lamp as specified in the schedule of items. The fitting shall include all the necessary accessories for efficient working. The fitting suitable for HPMV lamp should include copper wire wound ballast, power factor improvement capacitor and fittings for HPSV lamp should include electronic ignitor in addition to ballast and capacitor. In the integral type of fitting, the control gears shall preferably housed in a cast aluminium spigot which apart from housing the control gears shall be suitable for mounting to the GI pipe post. The lamp housing shall be different types as specifically indicated in the schedule of items. It shall be either double conical or spiral opal white acrylic domes or an opal white crylic bowl with top spun aluminium canopy or of purely decorative designs. If the type of the lamp housing is not clearly indicated in the schedule of items, the contractor in his offer shall indicate these details he has considered in the offer. All the joints shall be gasketed using neoprene gaskets and the fitting shall be suitable for outdoor use. The protection for lamp compartment shall not be less than IP : 43 and that for the control gear compartment not less than IP : 33. All the hardwares shall be corrosion resistant preferably be of stainless steel / brass. Post top lanterns are envisaged on all gate Pillars
09.02.06
5A / 15A, 5A, 240V, single phase, 3 pin (two pole and one earth) socket outlet shall be flush / surface mounting type along with decorative control type switch. If indicated, the socket shall be 5A / 15A combined (universal type) having 6 pin with suitable piano type switch. Adequate No. of Socket outlets shall be provided in areas like control rooms Sub-station, office, amenities block and similar other buildings. 09.02.07 JUNCTION AND OUTLET BOXES Junction and outlet boxes fabricated with sheet steel shall having a minimum thickness of 1.6 mm unless otherwise specified The JB shall have earthing terminals & terminal block, number of knockouts for cable entry etc., as required. The exact size of knockout and cable gland shall be as per actual requirement. 09.02.08 CONTROL SWITCHES DECORATIVE TYPE Single pole decorative type, 5A, or 15A switches shall be used for light/fans/socket outlets points in office premises / non plant buildings and shall be of approved type, make and colour. All branch switches shall be placed in line conductor of the circuit and no single switch or fuse shall be inserted in the neutral conductor of the circuit. 09.02.09 SWITCH BOARDS (for decorative switches and sockets) The switch board shall be made of 1.6 mm thick sheet steel & painted including supports for switches, sockets, fan regulator etc., but excluding front cover in case of decorative switches & sockets which will be of FRP sheet of approved quality, design and colour. Clear depth of the box shall not be less than 60 mm, but adequate for easy mounting of fan regulators. All fittings shall be in flush pattern in case of concealed wiring. The FRP cover sheet thickness shall not be less than 3 mm. 09.02.10 CEILING FAN Ceiling fans shall be 3 Blades type. Ceiling fans shall be hung at 150mm above the light fitting level or as per as per layout DRGS. The length of the down rod supplied shall be suitable for this purpose. 1 No. 1200mm Sweep Ceiling fan for every 15 Square meter area (max) shall be provided wherever required. 09.02.11 EXHAUST FAN
Exhaust fan shall have totally enclosed highly efficient heavy duty motor mounted on ball bearing, precisely dynamically balanced blades/impeller to ensure smooth & trouble free operation, rigid frame with rubber frames for silent operation finished with stove enamelled/epoxy powder coated for better chemical, mechanical & corrosion resistant. The exhaust fan shall be supplied with wire guard/bird-mesh screen, and earthing terminal. The exhaust fan shall be provided with earthing terminal. 09.02.12 Flame Proof Push Button Stations for motors, Light Fittings and Accessories like Boards switches Junction Boxes, cable glands etc.,
Page 29 of 89
Incoming isolator with fuses and neutral links with RYB on / off LED lamps (22.5mm), CTs with ammeter and ammeter selector switch, voltmeter with selector switch and fuses etc. Local / selector switch, control MCB, Contactors etc. as required for automatic tap changer and automatic bypass of the unit in case of problem in unit / abnormal under voltage/fuse failure etc. If the unit offered is forced cooling type then the starter for the fans shall also be included in the panel. The rating of the unit with fan failed condition shall also be indicated in the offer. Contractor shall indicate the assured / guarantee amount of saving in the system. The system will be checked for the same at manufacturers works. The vendors reference list where such units are supplied and amount of energy being saved shall be indicated with users certificates, The vendor shall submit all the relevant drawing for our approval before manufacture. HAZARDOUS AREA
10.00
Page 30 of 89
These lamps shall be suitable for universal burning positions and shall have E-40 with ES/GES threaded cap. These lamps shall be of ovoid shaped outer glass bulb and the inner surface is coated with phosphor. SWITCHES SOCKETS AND OTHER ACCESSORIES The enclosures shall be of cast iron construction having an integral terminal chamber. The front cover shall be secured to the body either by a threaded joint or by special type screws. The box shall have minimum two earthing provision outside and preferably one more inside. The switches and sockets shall be supplied with suitable double compression FLP type cable gland and cable entry / exit provisions shall be as per specific requirements. The enclosure shall have suitable provision for mounting on wall / column. The contact of the switches shall be suitable for heavy duty and shall be able to make and break the specified rated current effectively. The enclosure shall be suitable to contain the spark / arc created during the operation of the switch effectively from the outside atmosphere. The entire equipment shall conform to the relevant standards and certified by the appropriate authorities for use in hazardous areas having flamable gases or vapour and explosive dust. All the accessories such as Pull/anchor/ceiling/junction/outlet boxes specified for use in hazardous areas should conform to the relevant standards and certified by CMRS, Dhanbad. The body of all the above boxes shall be made of cast iron or cast aluminium alloy and shall have a removable cover plate. The cover plate shall have either a threaded joint or a screwed joint with the body. The number of cable entries shall be as per the requirement. FLAME PROOF EXHAUST FAN Exhaust fans shall have flame proof, highly efficient heavy duty motor mounted on ball bearing, precisely dynamically balanced blades / impeller to ensure smooth to trouble free operation, rigid frame with rubber pads for mounting to reduce vibrations for silent operation, finished with stove enameled epoxy powder coated for better chemical, mechanical and corrosion resistant. The exhaust fan shall be supplied with wire guard / bird mesh screen as required. FLAME PROOF MCB DISTRIBUTION BOARDS All equipments shall be designed suitable for operation in hazardous areas having flammable gases or vapour and explosive dust. The distribution board shall be wall / floor mounted type made of cast iron / cast aluminium LM6 with anti corrosive and light grey epoxy coated finish. The incoming cable terminals, outgoing cable terminals and the switch are all housed in separate chambers. The operating handle of the incomer shall be suitably inter locked mechanically with the door of the incomer. The boards are provided with neoprene gasket. Suitable cable entries shall be provided for incomer and outgoing. The boards are provided with 2 Nos. external and 1 no internal earth terminals. The entire equipment shall conform to the relevant standards and certified by the appropriate authorities for use in hazardous areas. 10.03 WIRING GENERAL For general requirements for wiring refer to the details stipulated under specifications for wiring for Ordinary (non-hazardous) area elsewhere in this specification.
Hindustan Petroleum Corporation Limited Page 33 of 89
ii)
iii)
iv)
v)
vi)
vii) The rate quoted shall include the cost of accessories required like FLP junction boxes, saddles, consumables, etc., for supply and installation of complete wiring system. B) WIRING USING PIPES i) Wiring in the hazardous areas can be carried out using 1100V grade PVC insulated PVC sheathed cable with copper conductor in surface laid solid drawn or ERW welded pipe, if specified, for connecting from distribution board to other equipments in flame proof areas.
ii) Conduits shall be supported at a minimum distance of 1000mm horizontally and 500mm vertically, Nylon / rawl plugs shall be used for fixing conduits on wall / ceiling. The plugs shall be fixed using correct size of drills and screws as specified by the suppliers. Using of wooden plugs are not permitted. iii) Conduits shall be laid in such a manner to avoid crossing of conduits. iv) Metal conduits are to be screwed tight to the apparatus. Conduit unions only are to be used for jointing and couplers are not allowed. v) Flexible conduits are NOT allowed for use in hazardous areas. vi) Cables with multistrand conductors only are permitted for use in conduit wiring system for hazardous areas. vii) The rates quoted for the conduit system shall include the cost of accessories required for supply and installation of a complete conduit system eg., saddles, consumables etc., CONTROL OF ELECTRICAL SUPPLY CIRCUITS
Hindustan Petroleum Corporation Limited Page 34 of 89
3. All exposed metal parts such as HT / LT switchgear / power distribution board/Lighting boards/feeder pillar enclosure, metal clad switches enclosure, lamps brackets, lamp holder, plug sockets enclosure, lighting poles, junction box etc., shall be properly earthed by connecting these to the earth electrode by means of bare GI wire/flat or single core cable of approved size to pass the fault current safely to earth in case of leakage at the apparatus or in the system. The minimum size of earthing wires is indicated below: a) Main earthing ring (connecting the earth pits) 50 x 6mm GI strip or equivalent, laid at a depth of not less than 700 mm. b) Loop earthing ring for main distribution board/LDB/ sub distribution board earthing - minimum size of 20 x 3 mm GI strip buried in floor/wall/trench etc., in side the shop.
c) Light point earthing - same size as point wiring single core PVC insulated copper wire / bare copper wire in case of GI / MS conduit wiring of same size or equivalent. 4 A common grounding system network will be made underground by using 50 mm x 6 mm GI earthing strip connected to earth electrodes in loop-in & loop-out system and connecting the electrical equipment to network. In RCC cable trench one number earth strip of size 50 x 6 mm shall be run throughout the length of the trench. The ring earthing system around each building shall be laid at a distance of approximately 1.5 m from the building and at a depth of approximately 0.8m. The ring shall be bonded at intervals to the building steel structures, reinforcement of building columns and also to pipes, wherever they are crossing. The earth ring shall further be connected at intervals to deep earthing electrodes to achieve a combined earth resistance of less than one ohm. For the purpose of dimensioning the earthing lines / conductors, the duration of the earth fault current shall be taken as 0.3 seconds.
Page 35 of 89
The power supply cables (LT) from the sub-station and the distribution cables to individual motors shall have 4 / 3.5 cores. LT power supply cables shall have four cores and the fourth core shall have crosssectional area of 50% of the other cores generally. The fourth core of the main supply lines shall be connected to the solidly earthed neutral bar in the substation switchgear as well as at the earth bars in power distribution boards. All the equipment will be connected to earthing grid by using conductors as per Table given elsewhere in the tender.
9.
11.02
EARTH STATIONS A. EARTHING ELECTRODES All the earth electrodes will be made of test pit type made with B-class GI pipe ( 3.0 m long 65mm dia) driven to ground, pit filled with charcoal and salt. Bottom half of the pipes shall have holes drilled at intervals on its surface. Removable caps shall be provided at the top of the pipes to facilitate pouring of water. Suitable clamps shall be provided with the electrodes for connecting earth conductors. Funnel to be handed over for facilitating water pouring B. EARTHING PITS The pit for an earth electrode will be of size not less than 600 mm x 600 mm x 4000 mm and will be dug with its centre at minimum 2.5 metres away from the edge of any building/masonry work. Homogeneous mixture of charcoal, salt and sand shall be made on ground and poured into pit covering the electrode. The minimum requirement shall be 20 kg charcoal and 30 kg salt per pit. The space above the salt/charcoal layers will be filled with loose sandy soil, upto a level of 550 mm from ground level. A cement concrete chamber of inner dimension 350 x 350 mm will be erected around the top of the earth electrode so that top surface of the chamber is flushed with the outside finished ground level. Earth pits shall be located as per approved grounding layout drawing. Distance between two earth pits shall not be less than 6 Meters. Masonry work of the earthpit shall be carried out only after well ramming of riddled soil and complete settling of loose soil. As such, electrodes shall be fixed in ground before commencement of any other work of the installation and masonry work shall be taken only at the end after completion of all other works in the installation. C. RESISTANCE OF EARTHING ELECTRODE The earth resistance of each electrode will be measured by an approved earth testing apparatus and recorded. In case the earth resistance is more than the required value, as per IS: 3043 additional earth pits, earthing ring as required shall be installed. The resistance of earth grid shall be less than 1 (ohm) . D. CHECKING PROCEDURES TO BE FOLLOWED
Page 36 of 89
The contractor shall keep ready the pit of proper dimensions and various materials for the earthing installation, for checking by the engineer. The contractor shall also arrange all measuring/testing instruments at his cost for testing. In case the pipe is buried without the above check being carried out, the contractor will be liable to open out filled up earth and re-do after proper check at his own cost. The earth pit is to be erected in all kinds of soil including rocky soil and the party shall quote their rate accordingly. 11.03 EARTHING RING MAIN The earthing ring shall be made by GI strip/wire of specified size. The ring shall be laid in the cable trench along with lighting cable and connected to all the earthing pits as shown in the drawing. Installation of Earthing Circuit. Earthing of HT/LT switch gear, Power Transformer, PDB/MLB/DB/DFB Etc. Each of the above equipment shall be provided with two separate earth terminals. An earth busbar of appropriate cross section shall be provided inside the equipment board and connected to the earth terminals provided on either side of the board. Adequate number of holes/terminals shall be provided on earth bus with suitable provision for terminating the earth wire. GI strip / Armored Aluminum conductor single core cable of suitable size shall be used for connecting the two earth terminals of the equipment independently to the earthing main in the shop. 11.04 EARTHING OF LIGHT FIXTURES AND SOCKET OUTLETS The single core PVC insulated/bare coper wire of same size as the phase conductor or 8 SWG GI wire and the third core of the flexible wiring cable shall be used for earthing the light fixtures and single phase socket outlets etc. Earthing of metal boxes and brackets Not less than 14 SWG GI wire shall be used for earthing all metal boxes and brackets. 11.05 LIGHTNING PROTECTION All buildings and plant structures vulnerable to lightning strokes owing to their height or exposed situation shall be protected against atmospheric flash-overs and lightning strokes in such a manner as to eliminate any danger to the personnel employed therein. The installation shall conform to IS:2309-1969 as amended up to date. Conductors on parapet: The conductors shall be coursed along ridges, parapets, edges of the flat roof, over flat roof where necessary in such a way as to join each air terminal to the rest. The conductors shall be fixed securely with galvanized iron staples 40mm (1 1/2") long and spaced not more than 4' (1.3m) apart. Vertical down conductors: These conductors, shall originate direct from earth station, shall be connected to parapet conductors or air terminals and shall be coursed through shortest possible routes without abrupt turns or kinks. While passing through cornices, these shall pass through GI pipe (Class 'B') having adequate bore. These conductors shall be fixed securely with galvanized iron staples 40 mm (1 1/2") long and spaced not more than 3' (1.0 m) apart.
Hindustan Petroleum Corporation Limited Page 37 of 89
Page 38 of 89
SPECIFICATIONS
S.NO. 1 2 Details of the Test Tensile Strength Elongation Unit N/mm2 % Poly Electro safe, 2.0 mm thickness 22.40 318.50
Page 39 of 89
7 8 9.
a) Color : Blue or Grey without Metallic Derivatives b) Thickness Tolerance + 10% II. SIZE : 2.5 MM THICK SUITABLE 3.3 KV TO 11 KV CLASSB INSULATION WITH ISI MARK & CPRI TESTED.
SPECIFICATIONS
S.NO. 1 2 3 4 5 6 Details of the Test As per IS:15652-2006 Tensile Strength Elongation Insulation Resistance Die Electric withstand Test Breakdown test Effect of fire Effect of Acid, Alkali, Diesel & Transformer Oil Unit N/mm2 % Mega Ohm KV KV Second % Poly Electro safe, 2.5 mm thickness (Tested Values) 25.10 336.50 11, 88, 370 45 KV for 1 min 75.0 1.0 -19.8 & + 2.31 of Original value
Page 40 of 89
Front to front clearance between boards Clearance between two panel boards in a row Clearances between front of the panel to the wall of the room Clearance between the wall & end of Switchgear / PDB Back to back clearance Back to front clearance -
Minimum 1000 mm
Clearance between the bottom of the ventilation duct & top of the electrical equipment 12.04 HT / LT SWITCHGEAR
Scope under equipment erection shall include: a) b) Physical inspection and handling Installation on the foundations or supports as the case may be as per general guidelines given in section. Assembly and instructions. interconnection of shipping sections as per supplier's
c)
d) e) f)
Mounting and connection of wiring of loose supplied items if any. Checking of components, wiring and interlocks as per approved drawings. All moving parts shall be checked for easy and free movement.
Page 41 of 89
Fixing / foundation bolts, nuts, lock nuts, washers etc., shall be properly fixed/ grouted in the pockets already provided or to be provided by the contractor. HT / LT switchboards,/ PCC / power distribution boards shall be tack welded to steel bars / plates provided in the floors. Cross support structures, if required be welded to inserts. If tack welding is done, foundation bolts are not required for the equipment. The equipment shall be installed on the foundations / supports / floors firmly in such a way that there will not be any vibration during operation of the components on the boards. Normally equipment like remote push button stations will be supplied without pedestals. The push button stations shall be mounted at convenient places like walls, columns, cable rack supports etc. Pedestals wherever required, shall be fabricated from the steel sections used for fabrication of cable supports/racks and installed properly. For mounting of equipment like SFUs, Plug and Sockets on the walls/ column suitable support brackets shall be fixed/grouted by the contractor. After installation of equipment, all interconnected wiring shall be checked thoroughly for correct connections, with the wiring and schematic drawings of the manufacturer and the drawings supplied by the engineer/owner before energizing. All cable/bus bar connections shall also be thoroughly inspected and checked for correctness, absence of foreign materials, tightness etc., before energizing the equipment. All labeling shall be checked against drawings. Distinct duplicate earthing shall be done for the metallic bodies of the equipment. All components within the main equipment shall be tested for proper performance & correct operation before commissioning of the equipment. 12.05 LIGHTING BOARDS MAIN LIGHTING DISTRIBUTION BOARD / FEEDER PILLAR The main distribution board shall be floor-mounting type. Suitable base channel shall be supplied and the floor inserts if necessary, incorporated in the civil works by the contractor. G.A drawing shall indicate foundation details and insert requirement also along with general arrangement of panel boards for approval. Contractor has to carry out chipping of floor etc., without any extra cost, installation of equipment includes supply and installation of necessary hooks/arms for cable support and all other connected works. Feeder Pillars shall be installed on Civil foundations to be constructed by the contractor. There shall be pipe inserts for taking the cable in/out of the feeder panel. This shall be included in price quoted for installation of Feeder Pillar. 12.06 MLDB / Lighting Distribution Boards / Sub-distribution boards The lighting distribution boards/sub-distribution boards shall be generally mounted on wall or structural column. The distribution board shall be mounted in such a way that
Hindustan Petroleum Corporation Limited Page 42 of 89
Supporting vertical racks and horizontal hooks shall be of 50 x 50 x 6 mm MS angles. Cable racks and hooks shall be welded construction. To avoid damage during cable laying, cable structures shall have no scales, abrasive or rough surfaces for cutting edges. If galvanizing is spoiled at any place, the same shall be painted with cold galvanized paint. 12.11 CABLING INSTALLATION The cables shall be laid in RCC cable trenches / GI pipes / cable trays / directly buried in the ground. In paved area cable shall be laid in GI pipes only. Except civil work of RCC cable trenches, Excavation of trenches of required width and depth in all types of soil Clearing natural obstructions including rock cutting if any required along the cable routing , Laying of cable on 8 cm of riddled sand and covered with 8 cm of riddled sand providing 75mm thick RCC cover slabs back filling with earth (after cable laying), and finally compacting to original ground level of cable trenches, all other equipment, materials and components required for cable laying is included in the scope of work. The maximum trench depth shall normally be 1.5m If the trench is to cross railway tracks / roads or any load bearing area the cables shall betaken through suitable GI conduits/ pipes / ducts. Installation of cables directly buried in ground shall generally conform to the requirements given in IS:255. Cables laid directly in underground trenches ( where permitted by owner/consultant) shall be in one layer only, more than one layer is not permissible. For crossing the road / rail track, cables shall be laid in concrete cable ducts/ hume pipes/ GI pipes. 25% spare duct /pipe openings / pipes shall be available. The scope includes but not limited to,
Hindustan Petroleum Corporation Limited Page 44 of 89
ii) Laying, meggering, termination, dressing and clamping of cables. iii) Tagging and marking of cables. iv) HT/LT tests on cable. v) Identification of phases. vi) Connection of equipment. vii) Making of cabling ready for charging after completing all associated works. 12.12 IMPORTANT NOTE For cable installation/laying, if cutting of foundations or structures is required, prior permission shall be obtained from the owner/ engineer. Wherever a cable crosses a temperature expansion joint in structure, a sufficient sag shall be provided. Cables of different voltage levels and noise classification if any, shall be taken on different trays/racks (or other means specified). When cables of different voltage levels or noise classes are installed on the same tray/ rack/place, the same shall be separated by grounded steel barrier. In no case instrument cables are to be run along with power cables. Cable trays / racks shall not be used as a walkway or ladder either during installation or while cable pulling or at any other time of installation. 12.13 CABLE INSPECTION AND HANDLING On receipt of cable drums at site, the contractor shall inspect each cable drum and check for size, length and type with respect to supplier's seal and marking / documents. Loading and unloading of cable drums shall be done by crane and drums shall be carefully lifted and deposited on ground. If crane is not available then the drum shall be carefully rolled down on a suitable ramp of rails. The drum shall be rolled as per the direction indicated by the arrow on the drum in order to prevent the turns of the cable from loosening on the drum. Under no circumstances shall a drum be dropped to the ground as the shock may cause serious damage to the inner layer of cables. No cable drum shall be slung, except, by a bar or spindle through the center of the drum. In no case, the drum be stored on the flat i.e with the flanges horizontal.
Only cable jacks shall be employed for removing the cable from the drum. For removing the cables from the drums, the drum should be properly mounted on jacks on a cable wheel, making sure that the spindle is strong enough to carry the weight without bending and that it is laying horizontally in the bearings so as to prevent the drum creeping to the one side or the other while it is rotating. The drums should be mounted such that when the drum is turned against the direction of arrow, the cable
Hindustan Petroleum Corporation Limited Page 45 of 89
12.16
CABLING ON TRAYS/RACKS Cabling may have to be carried out a) b) c) d) e) on ladder type (GI/FRP) cable trays/slotted channels; in rigid steel conduits; in perforated type GI trays; in duct banks or embedded conduits; and buried underground/in concrete cable trenches.
Lighting, Power and control cables shall be properly segregated and clamped on the trays/racks. A clearance equal to one diameter of the bigger cables shall be maintained between two adjacent higher rated power cables on the trays/racks/ risers and clamped by separate clamps which shall follow the profile of the cable. Common clamping/ strapping shall be done for a bunch of control cables and small power cables. Cables shall be clamped at every 1.5 meters on the trays/racks slotted channels in trenches.
Hindustan Petroleum Corporation Limited Page 46 of 89
Cable leading to cable box of an equipment shall be supported at a distance of 450 mm from cable gland/cable box and cable gland shall be suitably earthed. Cable shall be clamped only after the cables are neatly arranged, dressed and kept in position. 12.17 CABLING IN CONDUITS/PIPES Cables through floor slabs/walls are to be passed through rigid, galvanized steel conduit. Cables entering or leaving the conduits shall be sealed with non-hardening silicon compounds. It is also contractor's responsibility to satisfy him-self regarding the conditions of the embedded conduits. Prior to pulling cables, each duct shall be rodded by suitable means. After rodding a 8 gauge pulling wire is to be left in each duct. The ends of the conduits shall be plugged when work is halted for any period of time. Laying of cables (in trenches in ground subject to owners Consultants permission) Cables shall be laid direct in ground in all kinds of soil or in the prepared RCC ducts. If required, 100 mm dia (min.) GI pipe shall be provided wherever these cables cross the roads/water lines, sewerage lines etc. GI pipe shall also be provided wherever the cables enter the building. Cables terminating to any equipment shall also be encased in a GI pipe raising from the ground level to the equipment connection. Cable racks for cable trays shall be fixed at a maximum interval of 1.5m Cables leaving the ground / floor shall be protected upto 2m height by conduits / metallic guards. Ladder type cable racks and trays shall be provided to lay cables. Cables shall be laid in separate racks according to the voltage / application classification. All necessary frame works and fixings for the support of cables And accessories shall be supplied. Cables shall be suitably protected against heat & Mechanical damages. 12.18 The sizes of GI pipes shall be as given below :
Size of cable Upto 4 x 50 sq.mm 3 1/2 x 70 - 3 1/2 x 90 sq.mm 3 1/2 x 120 - 3 1/2 x 185 sq.mm 3 x 240 to 400 sq.mm
Approximately 3 m of surplus cable shall be left on each end of the cable, on each side of the underground joint, at entries and places as may be decided by the engineer-in-charge. The surplus cable shall be left in the form of a loop. The trench cut through the road-ways or other paved areas inside building shall be restored to the same density and materials as in the surrounding areas at no extra cost. Black-toping of the road will, however, be not done by the contractor.
Hindustan Petroleum Corporation Limited Page 47 of 89
Cable route markers shall be provided along straight runs of the cable and at locations approved by the engineer-in-charge, at intervals generally not exceeding 30 meters. Wherever cables are taken in conduits both ends of the conduits shall be sealed after laying the cable to avoid the ingress of water. All associated materials like sand, bricks, clamps and route markers etc., shall be supplied by the contractor. The cost for laying of cables shall be inclusive of all these items. Laying of cables on walls/columns/ceiling/structures All the lighting cables are to be neatly bunched and laid on surface of walls/ columns/ ceiling / structures. All the cables laid on surface of walls / columns / ceiling shall be supported by using clamps / rawl plugs and screws / cable hooks. No wooden plugs shall be used. All the cables laid on structures shall be fixed with suitable clamps. Cables are to be supported at minimum regular intervals of 0.5 m horizontal and 1 m vertical run. Care is to be taken while laying/pulling so that insulation of cables does not get damaged. 12.19 CABLE ENTRY AT BUILDINGS Pressure seals and fire barriers shall be provided at the places where cables enter pressurized electrical rooms. All wall openings shall be effectively sealed after installation of cables to avoid water leakage. Wherever buried cables enter the buildings the same shall be taken through GI pipes embedded at the entry portion. After taking cables through the above pipes, the same shall be sealed by using suitable compound so as to avoid ingress of water. 12.20 CABLE JOINTING Cable joints shall not be allowed, unless permitted by the owner / engineer in very exceptional cases. 12.21 CABLE TERMINATION: Scope of Erection shall include cable termination to all equipment supplied by contractor as well as to field equipment likes motors, stations, I/o cabinets etc. Unit rates shall be applicable for temperature equipment not supplied by the contractor. Cable shall enter motor terminal boxes through the bottom if this is not practical through the side. Top entry to motors to be avoided. Connection of feeders in motor terminal boxes shall be done in accordance with standards. Cable shall enter switch boards, distribution boards etc., from top or bottom depending on equipment feature. Drops/ risers to individual cubicles shall be neatly laid out and may be supported on channel type frame work.
Page 48 of 89
12.26
CONDUIT SYSTEM a) G.I conduit Conduit shall be of galvanized iron, rigid, screwed type. The internal bore of all conduits must be smooth and the ends free from burrs. The conduits upto 32 mm dia shall be 1.6 mm thick and conduits above 32 mm shall be of 2mm thick. b) M.S. Conduits Conduit shall be of mild steel, rigid, screwed type and should be stove enameled. The internal bore of all conduits must be smooth and free from burrs. The conduits shall be 1.6 mm thick upto 32 mm dia and above 32 mm, it shall be 2 mm thick. c) PVC conduit Rigid PVC conduit suitable for electrical wiring may also be used wherever approved by Engineer. It will be of approved make of minimum 1.8 mm thickness. The length of the conduit (MS/GI/PVC) will also include all accessories like joints, bends, junction/pull box etc., required as per site conditions and fish wire for drawing-in cables.
Page 50 of 89
12.27
Casing N capping The casing N capping wiring shall be done in accordance with the specification laid down as per standard practice.
12.28
USE OF PIPES All the GI pipes supplied shall be suitable for cable drawing, without any internal burrs, smooth internal surface and threaded at both ends with coupling at one end. The installation work of cable includes making the necessary bends using suitable bending machine without damage to the pipe, making additional threading at cut ends, jointing with coupling including supply and installation of all required accessories like junction/pull box etc. Class `B' type GI pipes as per IS: 1239 shall be used at the following locations: a) b) Cables running on floor shall be laid in buried GI pipes. All cables laid upto a level of + 2000 mm from floor pipes. Cables crossing road, entering buildings wall/foundations etc., shall be laid in GI pipes. level shall be laid in GI
c)
from outside
through
d)
GI pipes shall be used for taking the cable to feeder foundation or for taking cable to street light poles.
pillar
through
e) All GI pipes laid shall have a suitable fish wire for drawing in cable. Number of wires in a conduit/radius of conduit bending The number of wires in each conduit shall be as per relevant IS. Draw-in-boxes must be provided so that the wires are not drawn round more than two right angle bends or their equivalent. The radius of ends must not be less than the standard normal bend. The standard radius of normal bends shall be as tabulated below (For single core wires): Normal radius of conduit bends Outside dia. Of conduit 20 mm 25 mm 32 mm 40 mm 50 mm Radius of Normal bends 50 mm 60 mm 80 mm 95 mm 125 mm Remarks
12.29
INSTALLATION OF TRANSFORMERS In case of transformer, the accessories shipped loose by the manufacturer shall be assembled by the contractor at site
Page 51 of 89
TESTING AND COMMISSIONING GENERAL The successful Bidder, based on the broad outline procedure indicated in this specification, shall finalize with owner / engineer, the detailed procedure for testing and commissioning along with time schedules for both. The contractor shall adhere to the general guidelines given for testing & commissioning of the equipment/items implicitly covered under heading special instructions to contractor general condition of contract and technical specification. The intention of specifying below, the procedure for testing and commissioning and different tests to be conducted, are only to give guideline to the contractor. The contractor shall not restrict himself in carrying out only the tests specified here, but all tests as per relevant Indian Standards shall satisfactorily be conducted on each equipment. On successful completion of erection of each item /equipment, a final inspection will be carried out at site by owner /engineer, for correctness and completeness of erection. The successful Bidder shall provide adequate supervisory/ skilled personnel and all tools and tackles, testing equipment and instruments required for complete checking of installations and testing and commissioning of all equipment and accessories. The Bidder shall furnish with the offer a complete list of equipment, tools and tackles, instruments etc. which he intends bring in to site for erection, start up, testing and commissioning of equipment. The testing and commissioning of all equipment under the scope of the Bidder shall be carried out in accordance with the latest edition of relevant Indian Standards and IE Rules. The testing of all sub systems as well as the equipment as a whole shall be carried out to ensure that the equipment and its components are in satisfactory condition and will successfully perform their functional operation. Test reports shall be submitted in required number of copies duly signed by the BIDDER, and OWNER. The results of all tests shall confirm to the requirements of the specification as well as any specific performance data guaranteed during finalisation of the contract.
Page 53 of 89
i)
HT / LT switchgear power distribution boards, distribution fuse boards, plug and sockets, switch fuse and like equipment All interconnected wiring shall be checked thoroughly for correct connections with the wiring and schematic drawings of the manufacturer and the drawings supplied by the owner before energizing. All cable / bus bar connections shall also be thoroughly inspected & checked for corrections, foreign materials, tightness etc., Before energizing the equipment, all labeling shall be checked against Drgs All components within the main equipment shall be tested for proper performance & correct operation before commissioning the equipment. Continuity and insulation tests shall be conducted. Switchgear/ MCC rated 415 volts shall be tested with a 1000 volts megger. Auxiliary wiring rated less than 415 volts shall be tested with 500 volts megger. Equipment giving insulation resistance readings of less than 10 mega Ohms shall not be energized. Necessary steps shall be taken for improving the I.R value. All protective relays shall be tested at sufficient points to establish their proper functioning in accordance with the manufacturer's specification.
13.04
AC MOTORS 1. IR test of stator and rotor windings 2. Heating of both windings with heating curve (only for HT motors) 3. Ensure that checking / testing of associated switchboard, cables, relays / meter interlocking as mentioned in relevant chapters are completed. 4. Check tightness of cable connection 5. Winding resistance measurement of stator and rotor. 6. Checking continuity of winding 7. Check tightness of earth connections 8. Check space heaters and carryout heating of winding (if required) 9. Check direction of rotation in de-coupled condition during kick-start 10. Measure no load current for all phases 11. Check for temperature rise of body in no load and on load conditions 12. Check for tripping of motor from local / remote switches and from electrical / technological protection including differential protection 13. Checking of vibration
Page 55 of 89
14. Checking of noise level during load running, 15. Measurement of stator and bearing temperatures (if applicable) for every Half an hour interval till saturation comes 16. Checking tightness of foundation bolts 17. Check operation of speed switch (if there) 18. Check continuity of temperature detectors 19. Check alignment, paralleling of shafts, level of lubricating oil etc. as per manufacturer's manual 20. Check contact of slip ring brush and measure brush pressure 21. For CACW drive check cooling water and system piping, availability of pressure, cleaning and pressure testing of pipelines etc. 22. Check for polarization index of stator winding. R10 / R1 by motorised megger (The value should not be less than 1.5). 23. Dielectric test (only for HT motors) 13.05 PRE-COMMISSIONING TESTS All pre-commissioning tests at site on all the equipment/items shall be carried out as per relevant standards and as directed by the owner/ engineer. High voltage tests and primary and secondary injection tests on all components/ equipment shall form part of pre-commissioning tests. All cables, heating cable units, immersion type heaters, correction type unit heaters and metallic conduits shall be tested to ensure electrical continuity. Circuit breakers, contactors, relays, remote devices and other electrical operation equipment shall be functionally tested. Relays, thermisters, photo-cells and other equipment requiring operational setting shall be set and checked. 13.06 OPERATIONAL TESTING Upon completion of the electrical installation & at such time as the owner/ engineer may direct, the contractor shall conduct apparatus and system operating tests for approval and acceptance purposes. All apparatus control schemes, interlocking safety & protective devices etc., shall be demonstrated to operate and function in accordance with the requirements of this specification. All malfunctions & improper operations disclosed through these tests, shall be corrected to the satisfaction of the owner/engineer. All necessary corrections to the contractor-supplied equipment shall be at contractor's expense. The contractor shall provide all electrical skill & labour required during the course of this operational testing. 13.07 INSULATION RESISTANCE TEST FOR LIGHTING INSTALLATION
Page 56 of 89
For record purposes test data shall include the measured values of leakage current. The DC high voltage test shall be performed as detailed below : Cable shall be installed in final position with all the straight through joints complete. Termination shall be kept unfinished so that motors switchgear, transformer etc., are not subjected to test voltage. The test voltage and duration shall be as per relevant codes and practice of Bureau of Indian Standards. The result of all the tests conducted at site shall be furnished in a tabulated form given below, to the purchaser for their approval. All tests shall be performed with genuine instruments. The Bidder shall, therefore, submit a list of all such instruments proposed to be used for testing the installation. 13.11 COMPLETION CERTIFICATE FOR TESTING & REQUEST FOR COMMISSIONING
Page 58 of 89
I/We certify that the installation detailed below has been installed by me/us and tested and that to the best of my/our knowledge and belief, it complied with I.E Rules, 1956, as well as Technical Specifications for Electrical Works. All precommissioning checks / tests have been completed and test certificates are enclosed. Approval from Statutory authority has also been obtained and is enclosed. Now we request for regular commissioning clearance. Electrical installation at : ..................... ....................
Particulars of instruments used 1. Insulation tester Make Type Sl. No 2. Earth tester Make Type Sl. No. 3. Any other instrument Make Type Sl. No. ..................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... .....................
II.
Particulars of works A. Equipment details Sl. No. 1. 2. 3. 4. 5. B. Internal electrical installation No. Equipment Description Rating Remarks (Enclose site test certificate)
Page 59 of 89
........tee joints .......straight-through joints D. Earthing a) Description of earth electrode b) No. of earth electrode c) Size of main earthing lead III. Test result a) Insulation resistance i) Insulation resistance of the whole system of conductors to earth ........Meg-ohms. ii) Insulation resistance between the phase conductor and neutral Between phase R & N Between phase Y & N Between phase B & N Meg-ohms Meg-ohms Meg-ohms
iii) Insulation resistance between phase-conductors in case of three phase supply Between phase R & Y Between phase Y & B Between phase B & R b) Polarity test Polarity of all single pole branch switches and cutouts
Hindustan Petroleum Corporation Limited Page 60 of 89
i) Cutout ii) Switch No.1 No.2 c) Earth continuity tests Maximum resistance between any point in the earth continuity conductor including metal conduits and main earthing lead ........................ ohms. d) Earth - Electrode Resistance No.1 ......................... ohms No.2 ......................... ohms No.3 ......................... ohms No.4 ......................... ohms e) Cable testing i) Before laying Date of test ........
Sl. No.
From .......
Length
Insulation resistance in Meg-ohms At the time of issue During laying & before covering
Between
RY ...... RY .... YB ...... YB .... BR ...... BR ...... RN ...... RN ..... YN ...... YN .... BN ...... BN ......
Between
RE ...... RE ...... YE ...... YE ...... BE ...... BE ...... NE ...... NE ...... ------------------------------------------------------ii) Before commissioning a) Whether high voltage test conducted YES/NO
Between
b) If conducted, system of supply................ test voltage at ........... KV .............for ........ minutes, Result of test : Satisfactory/unsatisfactory. c) If not conducted, Voltage of megger used
Hindustan Petroleum Corporation Limited
:
Page 61 of 89
Result of megger testing : Between R & Y Y&B B&R Between R & N Y&N B&N Between R & E Between Y & E Between B & E : : : : : : : : : SIGNATURE OF CONTRACTOR
SIGNATURE OF SUPERVISOR
The system and equipment as above has been checked / verified along with test documents and Statutory Authoritys clearance. The system / equipment may be commissioned
(ENGINEER)
(ENGINEER) HPCL
14.00
14.02
Drawings to be submitted for approval on order Placement a. b. c. d. Design and drawing of Lighting and earthing system GA drawing and data sheet for cables, DBs and other supply items List of vendors for various supply items chosen from the approved makes. Copy of Unpriced PO placed on sub vendors for supply items during execution of
14.03
Drawings / documents to be submitted for information project a)Erection/Installation Manuals b)Manufacturing Drawings c)Factory test reports& & TPI report wherever applicable. d)Technical literatures/ Product data /catalogues.
Page 62 of 89
e)Cable layout drawing/Cable Schedule. 14.04 Drawings Documents to be submitted before final Acceptance. a) As Built Drawings for Entire Plant Electrics. b) Operation and Maintenance Manuals c) Detailed Bill of Quantity for all Equipment. d) As Built Cable routing drawings / Cable Schedules e) Testing and commissioning Reports. f) Statutory Approval Documents. 15.00 PREFFERED MAKES OF EQUIPMENT Makes of the equipment offered shall be generally limited to the Following only. In case, the approved vendor is not able to supply the materials, then alternate vendor may be considered during detailed engineering, subject to meeting the specification. Technical literature and publications of items to be offered by the Bidder shall be forwarded prior to procurement. Makes of all the equipment and accessories must be clearly mentioned against each item. In case rating, type, make and other details of all these items are not Mentioned by the Bidder, their quotation is likely to be treated as incomplete. The purchaser reserves the right, to select an item of any make, based on Standardization needs, in case he has not \indicated make specifically or Has Indicated, more than one make. The Bidder shall ensure that equipment and components are from Indigenous sources to the maximum possible. Imported equipment/components shall be resorted to only in case of Non availability of equipment/ component from Indigenous sources and with prior approval of owner/Consultant. LIST OF PREFERRED MAKES 1. BATTERY CHARGER : CHABBI ELECTRICALS / SABNIFE / AUTOMATIC ELECTRIC / EXIDE NICCO / RPG /UNIVERSAL / TORRENT / INDIAN CABLE CO.,/ CABLE CORPORATION OF INDIA / FORT GLOSTER INDUSTRIES / ASIAN CABLES / POLYCAB/HAVELL PHILIPS / CGL / BAJAJ / CANARA LEGRAND/GE POWER/INDO ASEAN/HAVELS CCI/RAYCHEM/MAHINDRA ENGG. ALSTOM / ABB / GE-MULTILIN / EASUN REY ROLLE / SEG / ENGLISH ELECTRIC AUTOMATIC ELECTRIC / KAPPA / JYOTHI / PRAGATHI / INSTRANS / KALPA AUTOMATIC ELECTRIC / MECO / IMP / RISHAB / UNIVERSAL / SIMCO / BHEL
Page 63 of 89
3. LIGHTING FIXTURES : 4. MCBs : 5. 11 KV TERMINATION KIT &: STRAIGHT THROUGH JOINTS 6. PROTECTIVE RELAYS, : AUXILIARY RELAYS & SEMAPHORES 7. INSTRUMENTTRANSFORMERS : Current Transformers 8. INDICATING/RECORDING Meters :
Hindustan Petroleum Corporation Limited
SOCKETS
MCCB, ACB : G. I. CONDUITS : MS CONDUITS : EXHAUST FANS : CELING FANS : COPPER WIRES : (lighting) PVC CONDUITS AND PVC : CASING N CAPPING DECORATIVE SWITCHES &: SOCKETS DIGITAL METERS : POWER PLUG & SOCKET (INDUSTRIAL TYPE) INDICATING LAMPS SOLID STATE ANNUNCIATOR BATTERIES Street Lighting Poles High Mast SFU ESD
APPLICABLE STANDARDS & CODES All applicable Indian and IEC codes, regulations and standards shall govern the work hereunder. In the event of the requirements of the specification, exceed the requirements of the, corresponding codes, regulations or standards, the specification shall govern. Where there are more than one applicable codes or standards for any item, the most stringent will apply. All parts issued against a standard/code shall be referred to wherever specific Part No is or not given. Equipment covered by this specification shall conform to the latest editions and revisions of all relevant applicable codes, and standards in addition to the ones listed below: Latest revision of all applicable codes, regulations and standards shall govern the design, manufacture, installation, testing & commissioning of individual equipment and total installation even when the requirement of the specification is less stringent than the codes, regulations & standards. In the event of conflict between specification & codes, the most stringent shall govern. In the event of conflict between codes, regulations and standards referred to in the specification, the owner's/consultant's decision is final and binding.
Page 64 of 89
Wherever IS are not available, relevant IEC standards are to be followed: Equipment covered by this specification shall conform to the latest editions and revisions of all relevant applicable codes, and standards in addition to the ones listed below: It may Please, be noted that the above list is not exhaustive. 1 2 3 4 5 6 7 8 BS 4999 (Parts 1,4,31,32,33,60) IEC 34-1 Part 1 IEC 34-2 Part 2 IEC 34-2 Part - 3 IS 0325-1996 IS 0900 1965 : : : : : : General requirement of rotating Electrical machines Rotating Electrical Machines Rating and Performance Methods for determining losses and efficiency of rotating machine from tests Methods for determining losses and efficiency of Rotating machine from tests 3-phase induction motors. Code of practice for induction motors installation and maintenance. Colours for ready mixed paints and enamel Power transformers
9 10 11 12
13
IS 0005-1994 : IS 2026 - 1977 : Parts 1,2 & 4 1977 Part 3 1981 IS 0335-1993 : IS 0374 1979 : IS 0396 Part I to V : Reaffirmed 1992 IS 2121 : Part 1,2 1981 Part 3-1992 Part 4-1991 IS 0731-1971 :
New insulating oils Electric Ceiling type Fans & Regulators Aluminum conductors for over-head transmission purpose. Conductors and earth wire accessories for overhead power lines.
14
IS 1651-1991
: : : : : : : 1983 : : :
15. IS 1652-1991 16. IS 0732 1989, IS 3854-1988/1990 17 IS 1239 Part-1 1190 /Part-2 1992 18 IS 0722 Part 1 to 9 19 IS 1248-1993 IS 2419-1979 Re-affirmed 1991 21. IS 1255 Reaffirmed 1991 22 IS 694 1990 23 20
24 25
Specification for porcelain insulator for overhead power lines with a nominal voltage greater than 1000V. Stationary cells and batteries, lead acid type (with tubular positive plates) Stationary cells and batteries, lead acid type (with plante positive plates) Code of practice Electrical wiring installations Mild Steel tubes, tubulars and other wrought steel fittings. Alternating current Electricity meters Direct acting analogue electrical measuring Instruments and their Accessories Dimensions for panel mounted indicating and recording electrical instruments Code of practice for installation & maintenance of power cables up to 33 kV rating PVC insulated electric cables for working voltages upto and including 1100 Volts PVC Insulated (Heavy duty)electric cables for working voltages upto and including 11000 Volts Thermal evaluation and classification of Electrical Insulation Recommended current ratings of cables.
Page 65 of 89
26 27
: : : 1988 :
Industrial luminaires with metal reflectors General & safety requirement of luminaires Explosion proof light fittings50019 for Group II C areas (German Specification) Plug & socket outlets for rated voltages upto and including 250 Volts and rated currents upto and including 16 Amperes Graphical symbols used in electrical technology Bushing for alternating voltages above 1000V. Degrees of protection provided by enclosures for LV switchgear & control gear. Specification for Flame proof, enclosure of electrical apparatus. Specification for Flame proof, electrical light fittings. Tubular flourescent lamps for general lighting service, requirements & tests Adhesive insulating tapes for electrical Purposes Specification for porcelain post insulators for systems with nominal Voltage greater than 1000V. warning symbols Danger boards, warning symbols
28 29
30. IS 2032 31. IS 2099-1986 32 33 34 35 36 37 IS 2147-1962 Reaffirmed 1990 IS 2148-1981 Re-affirmed 1993 IS 2206 IS 2418-1977 parts 1-4 Reaffirmed 1990-1993 IS 2448-1963 Re-affirmed 1995 IS 2544-1973 Re-affirmed 1991 IS 2551-1982 Re-affirmed 1990 IS 8923-1978 IS 2705 1992 Parts 1 to 4 IS 2721-1979 Re-affirmed 1991 IS 3043-1987 Re-affirmed 1991 IS 3070-Part-1 1985 re-affirmed 1990, Part 3 1993 IS 3156-1992 Parts 1 to 4 IS 3231 IS 3427-1997
: : : : : : : :
38
39 40 41 42
: : : :
Current transformers. Galvanized steel chain link Fencing Code of practice for earthing Lightning arresters for alternating current systems Voltage transformers. Electrical relays for power system protection. Metal enclosed switch gear and control gear for voltage above 1000V but not exceeding 52 kV. Flexible steel conduits for electrical Wiring Gas operated relays Application guide for gas operated relays. Fittings and accessories for Power transformers Code of practice for Interior Illumination
43 44 45
: : :
46 47 48 49 50
IS 3480-1966 Re-affirmed 1990 IS 3637-1966 Re-affirmed 1991 IS 3638-1966 Re-affirmed 1991 IS 3639-1966 Re-affirmed 1991 IS 3646 Part-1 1992 Parts 2 & 3 1966 Re-affirmed 1992
: : : : :
Page 66 of 89
54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73
: : : : : : : : : : : : : : : : : : : : :
74 75
76 77 78 79
: : : :
84
85 86 87
88 89 90
91 92
Reference ambient temperature for electrical equipment. Switches and Switch Isolators for voltage above 1000V
93 94
95
Methods of tests for IC engines Performance Requirements for constant speed compression Ignition engine for general purposes (above 20 kW). Code of practice for selection installation and maintenance of transformers
Part and : Code of practice for design, installation and maintenance of switch gear and control gear. Method of tests of cables
96
97
Page 68 of 89
98 99
: :
Vented type Nickel-Cadmium batteries. Control transformers for switchgear & control gear for voltages not exceeding 1000V High voltage Air circuit breakers Low voltage fuses for voltage not Exceeding 1000VAC or 1500VDC Specification for low voltage switchgear and control gear. Latest Edition Oct2010
100 IS13118-1991 101 IS13703 1993 Parts 1 to 4 Re-affirmed 1998 102 IS13947-1993 Parts 1 to 5 103 OISD Standard
: :
17.00 17.01
QUALITY ASSURANCE, INSPECTION & TESTING GENERAL REQUIREMENT OF QUALITY ASSURANCE All materials, components and equipment covered under the technical specification for this Project shall be procured, manufactured, tested, erected and commissioned as per a comprehensive Quality Assurance Programme. It shall be the primary responsibility of the contractor to draw up and implement such a programme which shall be duly approved by the Owner / Consultant/their authorised Inspection Agency. The detailed Quality Assurance Plan (QAP) for manufacturing and testing of equipment shall be prepared by the contractor and submitted for approval by the Owner/their aurhorised Inspection Agency.
17.02 17.02.01
Inspection and Testing The equipment shall be inspected by the Owner and / or their Inspection Agency at the manufacturers works prior to despatch. The equipment will be inspected as per the tests pre-identified in the approved QAP to ensure conformity of the same with relevant approved drawings, data sheets, technical specification, National/International Standard. The contractor shall finalise the QAP within the stipulated schedule mentioned in the Purchase Order and the QAP shall be submitted in four sets (Blank QAP formats enclosed shall be adopted). In case of any sub-contracting, the QAP shall be prepared by the contractor in consultation with his sub-contractor to avoid any lapse in quality and disputes and misunderstanding. The contractor shall provide full and free access of the Inspection Agency to the manufacturers works to carry out any stage inspection to ensure the quality of the equipment being manufactured. Only on readiness of the equipment and approval of all relevant drawings & QAP, the contractor shall give Inspection Call (Blank format enclosed shall be adopted) to the Owner & the Inspection Agency with a clear notice of 10 days for inspection. The Inspection Call shall be accompanied by the manufacturers internal inspection report, test certificates, purchase order, sub-purchase order, technical specification, approved QAP and approved drawings / data sheets. The Inspection Call without above documents shall be ignored. In case of any approved sub-contracting, only the main contractor shall give the Inspection Call enclosing internal inspection/ test reports of the sub-contractor duly verified by the main contractor. In case the equipment offered for inspection is found not ready, all the cost of the visit of the Inspection Agency shall be borne by the contractor.
Page 69 of 89
17.02.02
17.02.03
17.02.04
17.02.06
17.02.07 17.02.08
17.02.09 - 11 Deleted 17.02.12 The contractor shall provide all required instruments, tools, necessary testing and inspection facilities free of cost to carry out the inspection. These instruments and testing machines shall be calibrated by an agency of National/ International recognition and the calibration shall be valid during inspection period. The inspection Agency shall have the right to demand for re-testing of any material recalibration of the instrument and testing machine & the charges for the above will be borne by the contractor. Performance tests of any particular equipment which cannot be conducted / demonstrated either partially or wholly at the manufacturers works, shall be conducted after erection at site in the presence of Owner and their Inspection Agency. In all the cases, prior approval of the Owner shall be obtained. No equipment shall be dispatched before inspection and issue of Inspection Certificate and dispatch clearance from the Owner / Inspection Agency. In case of waiver category items, the same shall be pre-identified in the QAP itself. For such items, the contractor shall furnish necessary certificate, test reports, etc., as agreed upon and indicated in the QAP. For these items also the contractor shall obtain Inspection Waiver Certificate and dispatch clearance from the Owner Inspection Agency before effecting dispatch of equipment. The issue of Inspection Certificate / Waiver Certificate for any equipment or component thereof does not absolve the contractor from his contractual obligations towards subsequent satisfactory performance of the equipment at site. Should any equipment be found defective, In whole or part thereof after receipt at site or during erection/ commissioning and testing shall be made good by the contractor free of cost. Owner shall be given minimum four weeks advance notice for witnessing the final testing. The minimum testing / inspection requirements for all components/equipment shall conform to the requirements stipulated in applicable codes and standards. Test certificates including test records and performance curves etc. shall be furnished by the Contractor. TESTING Contractor shall provide test certificates for Type and Routine tests carried out on the equipment / boards etc. as specified in the relevant standards and tests as specifically mentioned in this TS.
17.02.13
17.02.14
17.02.15
17.02.16
17.02.17
17.02.18
17.03
Page 70 of 89
INSPECTION FORMAT PAGE:1 OF 1 REVISION - 1 DATE: OWNER CONTRACTORS ORDER NO. & DATE PLACE OF INSPECTION WITH ADDRESS PHONE NO. / FAX NO. NAME & DESIGNATION OF CONTACT PERSON WITH PHONE NO. QAP & DRG NO WITH REVISION
DESCRIPTION
Page 71 of 89
18.00 INFORMATION TO BE SUBMITTED BY SUCCESSFUL BIDDER 18.01 Drawing and information to be submitted within one month from the date of placement of order for approval of the Owner / before manufacture / procurement of equipment and components: Outline & general arrangement drawings incorporating the principal dimensions of all equipment covered under Part-A of price schedule. Control & interlocking scheme with write up Complete coordinated layout drawing indicating types of underground communication such as electrical cable ducts. Earthing layout drgs Lightning protection drgs Illumination layout, bill of materials, single line diagrams of all lighting boards For main equipment. GA drawing of above boards & distribution trafos indicating front view, dimensional details. Cable routing drgs with various section as indicative locations and arrangement of trenches. However the actual works as will be actually executed by contractor as per site conditions and as per owner or site engineers instructions will be indicated in contractor drgs. Cable schedules and interconnections drawings. Earthing layout drgs Lightning protection drgs. Lighting layout drgs. Final drgs showing actual layout and wiring arrangement. Control Scheme drawings of various electrical equipment vendor whose equipment are included in free issue items. 18.02 Interconnection and external connection diagram and cable schedule Installation, operation and maintenance manual for reference. Termination diagrams. Layout drawing for switchgear rooms, cable routing and earthing. Data sheet for HT / LT Cables and other cable and termination kits. List of 2 years maintenance spares, commissioning spares.
Documents to be submitted along with supply of equipment. i) Material test certificates. ii) Reports on shop tests and test certificates and certified test characteristics. ii) The instruction manual shall furnish the following information in practical and comprehensive manner prepared for use by operating and / or maintenance personnel. Instructions for initial installation. Instructions for operation, maintenance and repair. Recommended inspection points and period of inspection.
Page 72 of 89
iv)
v)
vi) vii)
viii)
18.03
LIST OF TENDER DRAWINGS The following drawings are enclosed with this tender. Sl. No. Description 1. 2. 3 4 Electrical Distribution Single line diagram for various Boards to be supplied by OWNER. Layout Plan Cable route/ crossing drawing Lighting poles, Earth electrode, and other misc drawings
Page 73 of 89
PART-II
Page 74 of 89
Sl.No.
DESCRIPTION
01 02 03 04 05 06 07 08 09 10 11 12 13
GENERAL & SCOPE OF WORK GENERAL CONDITIONS MAKES OF EQUIPMENT AND INTERCHANGEABILITY TRAINING DESCRIPTION OF EPABX SYSTEM DESCRIPTION OF PLANT COMMUNICATION SYSTEM AND COMPONENTS VHF COMMUNICATION SYSTEM DRAWINGS AND DOCUMENTS INTERCONNECTION CABLES AND WIRES
Test and Inspection Two years OPERATIONAL spares LIST OF PREFFERED MAKES Location of facilities FOR BIHTA DEPOT
1.0
SCOPE OF WORK:
Page 75 of 89
B) ERECTION & COMMISSIONING: Transportation to the place of erection from store, erection, testing and commissioning of (a) EPABX (b) Plant communication and (c) VHF communication Systems
C) POWER SUPPLY: Supply, Laying/ Erection and Termination of all power supply Cables and Distribution equipment for EPABX, Plant Communication System and VHF Charging units shall be in the scope of work of the tenderer. For supply to all these equipment, a feeder of suitable rating shall be provided by the client at a single location i.e. at the DB of UPS. Beyond this point all activities related to distribution and termination shall be in tenderer scope.
2.00 2.01
GENERAL CONDITIONS: Components/ parts of the equipment/ system shall be suitable for service in an explosion prone area, wherever specified. The digital switch based exchange shall be complete in all respect and any device not included in the specification but essential for proper operation of the system shall be deemed to be within the scope of the tenderer whether specifically mentioned in this specification or not.
2.02
2.03
The exchange(s) shall be TEC approved and confirmation from the exchange manufacturer/ supplier shall be furnished to this respect during procurement. All nameplates, drawings, operating and maintenance instructions etc. shall be in English language. The dimensions, weights shall be in metric units. All equipment, materials and components supplied shall be newly manufactured and without loose or temporary cabling. Wired options used in the system hardware shall be minimum.
2.04
2.05
2.06
All components shall be rated for continuous operation. The circuits also must be designed so as to prevent damage to other modules within the equipment or to other equipment under any conditions of operation or any condition of fault.
Page 76 of 89
2.09
2.10
2.11 2.12
2.13
2.14
2.15
2.16 Tenderer shall clearly indicate deviation, if any, from this specification, in the offer. 2.17 Explosion-proof equipment wherever specified shall be suitable for Zone II, Group II A, B and made up of die cast aluminium. The unit shall have approval of CMRI and CCOE. MAKES OF EQUIPMENT AND INTERCHANGEABILITY: Equipment / components offered shall be from the list of preferred makes as given in this specification. Similar equipment and components shall be of same makes. Equipment of same type and rating shall be interchangeable. TRAINING: During erection and commissioning of the system the Contractor shall involve the working personnel of customer and train them, free of cost, in all type of hardware and software for safe, and efficient operation and maintenance of the equipment and system. The Number of personnel to be trained shall be at least 3 and the duration and structure of the training shall be mutually discussed and finalised. 5.00 DESCRIPTION OF EPABX SYSTEM:
3.00 3.01
Page 77 of 89
SPECIFICATION FOR ELECTRIFICATION AND PLANT COMMUNICATION SYSTEM The description given below is for the main system units/ components and may not cover all. The tenderer shall take responsibility for the completeness of the system and furnish the details of the units not covered here, along with the offer. Main units of the system like Switching unit, MDF, Operator console etc are proposed to be located in the Terminal control room.
5.01 MAIN DISTRIBUTION FRAME (MDF): It shall serve as a common terminating point of the telephone cables network. The MDF shall be compact and modular with systematic wiring and termination, following a numbering scheme facilitating quick and easy maintenance. Spare capacity shall be provided for terminating additional cables keeping in view the future expansion. Both sides of the MDF shall be complete with protection and safety devices e.g. Protection against short circuit and surge shall be provided through Fuses and GD tubes. The number of terminations towards field side shall be minimum double the number of terminations on exchange side. MDF shall be wall/ floor mounting type, constructed of min. 2mm thick CRCA sheet with ample no. of Krone modules for trunk and subscriber cable termination. It shall be suitable for both top and bottom cable entries. Punch-out type holes shall be provided at the top and bottom for entry/ exit of various size cables. 5.02 EXCHANGE EQUIPMENT: The EPABX/ exchange proper shall have following features: i. ii. Fully digital employing stored program control and PCM/ TDM switching technique. 100% Non blocking
iii. ISDN compatible. iv. Configured for minimum 48 extensions expandable to 72 extensions and 6 lines. Trunk
v.
The PSU, CPU, Ringer unit, TDM bus, etc should be integrated within the system and the system should have indication for faulty modules. The EPABX system should have necessary hardware/ software for facilitating routing of the calls to the VHF handsets and also from VHF handset to other telephones associated with the EPABX. Switch shall be ISDN ready and shall be able to accept ISDN BRI.
vi.
vii. System architecture should be built-up with suitable processor to handle traffic of at least 50,000 BHCA. viii. Generation of required tones like dial, busy, NUT etc.
ix. Port cards should have equal access to any free available time slot and should have
equal access time to TDM bus. x. System shall work on 240 V AC power supply with voltage varying between +/- 10%. There should be a provision to connect a set of battery bank to the system for back up. Drawing the required power from the nearby DB of clients UPS shall be in the scope of tenderer. One no. of feeder for the purpose shall be made available at the UPS DB.
xi. Exchange shall support Caller Line Identification for all subscribers and trunks.
Hindustan Petroleum Corporation Limited Page 78 of 89
xii. System shall include a Digital telephone to carry out maintenance, operations and programming functions. The same shall work as an operator console also. xiii. System shall have auto restart capability to automatically reload the system software in case of system power failure and restoration. xiv The system shall provide the minimum facilities as given below # # # # # # # # # # # Abbreviated dialing. Last number redial Call forwarding. Caller line ID. Caller ID for call waiting. COS programming for subscribers through Operator console. Boss-secretary feature. MSN (Multiple subscriber no.) for ISDN lines. DID / DOD Call billing Landing on any subscriber through IVRS
THE OPERATOR CONSOLE SHALL OFFER FOLLOWING MINIMUM FACILITIES: # # # # # # # 5.03 i. Visual display of calling and called stations. Keypad dialling. Busy override. Trunk to Trunk, Trunk to Subscriber and Subscriber-to-Subscriber transfer. Breaking in into busy extension with interruption tone. External line hold. Indication of waiting calls.
EXPLOSION PROOF / PUSH BUTTON TELEPHONE INSTRUMENTS: All telephone instruments shall be desk type, rugged construction suitable for industrial application. These shall be complete with all necessary devices, circuits, and push buttons, ringer bell, flexible coiled cord, plug connector, etc., The telephone instruments should be rugged, elegant & electronic push button type DP / DTMF phones for general use. Explosion proof telephones(in specified locations) shall be suitable for Zone II, Group II A, B and made up of die cast aluminium, wall or column mounted. Handset shall be
Page 79 of 89
ii.
iii.
5.04
TELEPHONE JUNCTION BOX: 10/ 20/ 50 Pair, wall mounting, Junction boxes with Krone connectors shall be provided for cable termination on the incoming side and required no. of cables in the outgoing side. Sizes of junction box shall be got approved before execution.
6.00
DESCRIPTION OF PLANT COMMUNICATION SYSTEM AND COMPONENTS: The plant communication system shall be of Centralised Broadcasting type and shall mainly consist of a) A central rack consisting of Amplifier stack, Zone switching unit, Cable termination and management system b) Speakers of different types for Indoor and Outdoor applications suiting to the place of installation c) Cable termination boxes for speaker cables at Central rack and Speaker locations For making announcements, all speakers shall be distributed in three to four functional zones namely Tank/ Truck Parking areas, Tank truck filling areas/ Gantry and Nonplant office areas. A central announcement unit with a goose neck microphone shall be provided in the main control room , Security Cabin and In-Charge room for making the announcements. This announcement unit shall also include provision for selection of individual zones/ more than one zone / all zones for making the announcement. The selection of zone(s) shall switch the required Amplifier modules and direct the announcement to speakers in the selected zones. A broad description is given below for the main system units/ components and may not cover all. The tenderer shall take responsibility for the completeness of the system and shall include in his offer all the details of the units not covered here.
6.01
CENTRAL AMPLIFIER RACK: The unit shall consist of required no. of Line and Power Amplifier modules and terminal blocks for termination of power, signaling and loud speaker cables. Housing for the unit shall be constructed of Powder Coated Anodised Aluminium of 1.6 mm minimum thickness and suitable to accept 19 inch Rack mounts for accommodating Amplifier modules. The unit shall operate from 240V +/- 10%, 50+/-1Hz, Single phase AC. The rack shall contain a music source like a DVD player of reputed make like Philips/ Sony/ LG/ Samsung. A switch shall be provided in the front to switch on the the music source and channelise the music to all the speakers. The capacity of amplifiers shall be adequate to meet the power requirement of the speakers in individual Terminals and shall have at least 25 percent spare capacity to add speakers in future. The speakers shall be preferably connected in parallel to 70/ 100 V line of Amplifiers.
Page 80 of 89
Min. 200 W rms rated output. Suitable to match the line amplifier used for the central announcement unit 15 Hz to 15 kHz min. Better than 60 Db Power on, Volume, Tone(Bass and Treble) 4 ohm, 8 ohm, 70 V and 100 V.
i.
The unit shall be desktop type consisting of Gooseneck Microphone, Line/ Pre amplifier, Zone selection switches, Power supply and LED Indications
ii. All Terminations shall be through Connectors mounted at rear side. iii. The unit shall be elegent, surface mountable, made of min. 1.6 mm thick powder coated Anodised Aluminium, working on 240 V, Single phase AC. iv The microphone assembly shall comprise of microphone, suitable gooseneck desk stand with press - to talk switch with cable and connectors. The microphone shall be of robust construction, unidirectional type, matching with the amplifier, immune to stray magnetic fields and with noise cancelling characteristics. It shall have a frequency response covering frequency range of amplifier and noise free true reproduction of human speech shall be possible with the microphones. v. Selection switches shall be provided for one each for individual zones. One switch shall be provided to select all zones simultaneously so as to make announcements in all speakers simultaneously. LED indications shall be provided for Power on and all Zone switches.
vi.
6.03
LOUD SPEAKERS: The loud speakers shall be designed to cater to the needs of audibility of announcement in a plant. Depending on the ambient noise and sound output requirement the speakers shall be either cone type or horn type. The Cone type speaker shall cater to enclosed space like control rooms, office rooms etc, while the Horn type speakers caters to open space like Plant buildings/ locations. The horn type speakers shall provide output, which is 6dB above the surrounding industrial noise of approximately 80 dB. Control rooms with false ceiling shall be provided with Ceiling mounted speakers, which shall be flushed with the ceiling. The speakers shall be complete with mounting brackets and accessories. Explosion/ Flameproof Loudspeakers shall be provided in specified locations. The speakers shall be normally connected in parallel configuration to the 70/ 100 V output line of the Amplifiers. Individual speaker shall have volume control. The applicable details of each type are given below: Construction Material for Cone speaker Construction Material for Horn speaker Construction Material for Flame proof speaker, Driver unit housing Finish Mounting Aesthetically designed wooden/ sheet metal cabinet LM-6, min.3 mm thick LM-6, min 3 mm thick MATT. Wall/Column
Page 81 of 89
OTHER FEATURES: A. CONE TYPE SPEAKER: These shall be permanent magnet, cone type speaker with 6 watts power, line matching transformer housed in sturdy wooden/ metallic enclosure suitable for wall mounting and generally shall be used indoor premises like Control rooms, Electrical rooms etc. The speaker shall be provided with volume level adjustment . The cabinet shall have grilled metal faceplate to diffuse high frequencies and prevent damage to the speaker. Housing shall be treated with acoustic under-coats to prevent resonance. Technical parameters for these units shall be as follows: Output power Voice coil impedance Frequency response Volume control Protection-class B. CEILING MOUNT SPEAKER: Power Min Max Frequency Response Type Mounting Impedance SPL at 1 kHz LMT Size Material RMS-6W 1kHz, 8 ohms 200Hz 10000Hz, +/-3dB To be provided IP-54
6W 10 W 100 Hz to 8000 Hz min. Indoor Ceiling 8 Ohms 93 dB Optional 260 mm. Dia (typical) FRP
C.
HORN-TYPE SPEAKER: They shall be of power rating 20 Watts complete with driver units, impedance matching transformers, weather canopies, mounting brackets suitable for wall /column mounting and other accessories, suitable for outdoor use normally in Factory shop floors, Gantries, Pumphouse etc. These shall be designed to have uniform sensitivity, high efficiency and shall provide crisp clear speech reproduction. The mounting bracket shall be with adjustable base, suitable for vertical and horizontal mounting. Firm fixing arrangement with spring/ washers shall be provided. These speakers shall be weatherproof conforming to IP 65-protection class. Explosion proof/ Intrinsically safe units shall also be provided wherever specified. Technical parameters for these speakers shall be as follows: Output power RMS 20W Voice coil impedance 1kHz, 8 ohms Frequency response 200Hz 10000Hz, +/-3dB Protection-class IP-65 LOUD SPEAKER JUNCTION BOX: Connector Screw type
Page 82 of 89
6.04
For hazardous locations Explosion-proof LSJBs shall be provided with min. IP 65 Class of protection.
6.05 POWER SUPPLY: Provision is being made for one no. of feeder of 240 V, 50 Hz. Single ph. AC of suitable rating at a single location i.e. UPS DB. The same shall be used for both Telephone Exchange as well as Plant communication System. Requirement of power for all main and sub units shall be met from this location by use of proper distribution and cabling. For this purpose, all necessary distribution boards, sockets (including explosion proof sockets/ JBs wherever required) hardware, cabling, termination etc. beyond the outgoing terminals of the UPS DB, shall be considered by the tenderer in his scope. VHF COMMUNICATION SYSTEM: For facilitating ease in operation and maintenance a no. of hand-held VHF Sets(Walkie-Talkie) are envisaged in each Terminal. The sets shall be complete with Rechargeable battery set, Battery charger with detachable Power chord, Set cover and other required accessories. Tenderers scope shall include the responsibilities for obtaining the allotment of three frequencies from the statutory allotment authorities in Govt. of India. For this, all necessary liasoning work from the stage of filing application up to allotment shall be in the tenderer scope. Client shall reimburse the statutory payments made by the tenderer on production of documentary evidence.
7.00 7.01
7.02
- Resistance against Shock/Vibration- To confirm MIL std 810 C/D/E and 603. Battery strength indication- Through Tri-colour LED. Power level adjustment- Switchable. Channel sparing- 12.5/25 KHz, switchable/programmable. Signalling- PTT-ID.
Other features- Channel scan, Time-out-Timer, Busy channel lockout. B. TRANSMITTER: Operating temperature
Hindustan Petroleum Corporation Limited
Maximum 600C
Page 83 of 89
C. RECEIVER: Sensitivity Intermodulation Adjacent channel selectivity Spurious rejection Rated audio Audio distortion Hum & Noise Audio response Conducted spurious emission 0.25 micro volt 70 dB 60 dB @ 12.5 KHz / 70 dB @ 25 KHz 70 dB 500 mW < 3%. -45dB @ 12.5 KHz, -50 dB @ 50 KHz. 300-3000 Hz -57 dBm
8.00 A.
DRAWINGS AND DOCUMENTS: The successful tenderer shall submit 6 sets of the following documents / drawings for approval by the purchaser / his consultants, within 4 weeks of placement of order:
- Technical specification of each components, units/ sub-units and cables.
- Configuration diagram of complete system showing different units and sub-units - QAP and inspection procedure for main control panel and other units and system as a whole. - Cable routing B. Following drawings / documents shall be submitted in six sets by the successful tenderer along with the supply of equipment: - Technical specification/ Data sheets for each component - Manufacturers catalogue for the above. - General arrangement / system configuration drawing for different units - Wiring diagram for the system - Cable schedule, routing drawing, cable termination details etc. Instruction manuals for maintenance and operation as well as erection of the equipment supplied.
Page 84 of 89
Page 86 of 89
Power amplifier module Outdoor horn type speaker Driver unit for Horn speaker Explosion proof telephone instrument for outdoor type 10 pair krone module 4" * 4" junction box with RJ socket Battery charger unit for VHF set 12.00 LIST OF PREFERED MAKES: EPABX TELEPHONE INSTRUMENTS TELEPHONE INSTRUMENTS, EXPLOSION PROOF SMF BATTERY PA SYSTEM TELEPHONE CABLES
: : : : : :
NEC/ SIEMENS / AVAYA / CROMPTON GREAVES BEETEL / TATA / SIEMENS/ ITI FLAMEPACK, BALIGA AMARA RAJA / AMCO / EXIDE/ HITACHI BOSCH / BNA / AHUJAS / NEUMANN VINDHYA TELELINK / NICCO / DELTON / RAVICAB/ DOORVANI / RPG TELECOM / FINOLEX USHA BELTRON / VINDHYA TELELINK / DELTON / FINOLEX INCAB / CCI / UNIVERSAL / NICCO / POLYCAB/ FINOLEX CCI / UNIVERSAL / NICCO /POLYCAB INDUSTRIES/ DELTON / RAVICAB
: : :
AVONPLAST /PRECISION/other ISI brands GTS / KHANDELWAL / APPOLO ZENITH / JINDAL / TATA / NICCO MOTOROLA, BEL, KENWOOD
B: GI (CLASS B)
Page 87 of 89
13.00 LOCATION OF FACILITIES & SCOPE OF SUPPLY FOR BIHTA DEPOT: 13.1 Owners Scope Owner shall carryout Internal Telephone wiring along with One JB wherein the internal telephone wires shall be duly terminated in Krone Connector. The telephone outlets shall also be provided in the buildings where internal wiring has been done. The electrical contractor shall carryout cable laying up to the junction box of respective buildings, terminate and duly tag the wirings and fix telephone instruments as per the scheme. The details of buildings are as under a. Administration Building- Gr & 1st Floor b. MCC-1,2,3,4- White & Black Oil c. TXR Bldg d. Marketing Room e. Security Bldg- White Oil & Black Oil f. Weigh Bridge room g. Workers Rest Room Contractors Scope of Supply All materials, equipments, tools and tackles etc complete as per scope including fixing, testing ,commissioning and training except for internal wiring, JBs and telephone outlets in the buildings as indicated above under Owners scope. The No. and type of Telephone Instruments shall be as per the Telephone Schematic Diagram. Additionally 2 Nos telephone points (Weather Proof) for Outdoor use shall be provided one each at Transformer Yard and Wagon Siding without any extra cost. The telephone outlets and instruments for hazardous area shall be IS, Ex-d type for Gr IIA/IIB. Total FLP Telephone Instruments to be fixed are as under 1. TT Gantry (BO+WO)= 2 Nos ( 2 Nos Gantry) 2. White Oil Pump House = 2 Nos ( 2 Nos Pump House) 3. Black Oil Pump House = 3 Nos. (3 Nos Pump House) 4. Lube Ware House = 1 No 5. ETP =1 No. Total = 9 Nos Total Non FLP normal telephone instruments in Building/ Structures a. Admn 1st Floor = 20 Nos b. Admn Gr. Flr =6 Nos c. Security Bldg = 2 Nos d. MCC 1,2,3,4 = 8Nos e. TXR Bldg = 1Nos f. Mktg Rm = 3 Nos g. Maintenance Rm = 1 No h. FWPH =1 No i. Security Bldg+WB Cabin Black Oil =2Nos Total = 44 Nos Note: The Contractor should note that the location of the instruments are indicative and final placement and scheme shall be decided during execution by Site-in-Charge. However, the total no. of telephone instruments shall not exceed the quantity as indicated above. 13.3 The location of Speaker Unit for PA System shall be as under:
Hindustan Petroleum Corporation Limited Page 88 of 89
13.2
a. TAS Control Room (Admn Bldg Gr. Floor) : 1 No. Ceiling Mounted b. In-Charge Room : 1 No.(ceiling Mounted ) c. Corridor Admn Bldg. Gr. & 1st Floor : 2 No.(Indoor) d. Conference room: 1 No. (Indoor) e. Marketing room : 1 No. (Indoor) f. Security Bldg (1st Floor): 1 No. (Indoor) g. Security Bldg (Gr Floor): 1 No. (Outdoor) h. Weigh Bridge Cabin+ BO Security Cabin : 2 Nos (Indoor) i. Effluent Treatment Plant : 1 No. (Explosion Proof) j. Product Pump House: 5 Nos. (Explosion Proof) k. Fire Water Pump House: 1 No. (Outdoor) l. MCC Building : 4 Nos. (Outdoor) 13.3 The location of Announcement Module for PA System shall be as under: Incharge Room- Admn Bldg 1st Floor Control Room- Admn Bldg Gr. Floor Security Bldg- White Oil Gr. Floor Security Building- Black Oil Note: The Contractor should note that the location of the instruments are indicative and final placement and scheme shall be decided during execution by Site-in-Charge. However, the total no. of telephone instruments shall not exceed the quantity as indicated above. The Telephone schematic drawing has been attached with the tender. The Plot plan has also been attached. The Bidder shall estimate the cabling requirement for Telephone System and PA system and quote accordingly. The unit of measurement/ payment is LOT.
Page 89 of 89