Está en la página 1de 58

BBU3900 V300

Installation Guide

Issue: 16 Date: 2010-07-30

HUAWEI TECHNOLOGIES Co., Ltd.

Contents
Installation Tools 2 Installation Scenarios 3 BBU Hardware 5 Installation Procedure 6 Installing the BBU in the APM30 7 Installing the BBU in the APM30H(Ver.A) 13 Installing the BBU in the 19-Inch Rack 15 Installing the BBU in the TMC 17 Installing the BBU in the PS4890 Cabinet 20 Installing the BBU in the RRU3004 Rack 23 Installing the IMB03 on the H-Shaped Stand 27 Installing the RRU on the H-Shaped Stand 28 Installing the BBU on the Wall 29 Installing the BBU in the APM30H(Ver.B) 33 Installing the BBU in the TMC11H(Ver.B) 37 Installing the BBU in the APM30H(Ver.B, +24V) 39 Installing the BBU in the OMB 41 BBU Hardware Installation Checklist 47 Powering On the BBU 47 Appendix 48 Obtaining the ESN 48 Change History 56

Copyright Huawei Technologies Co., Ltd. 2010. All rights reserved.

Installation Tools

Measuring tape

Phillips screwdriver (M3-M6)

Flat-head screwdriver (M3-M6)

Adjustable wrench

Socket wrench

Hammer drill

ESD wrist strap

Vacuum cleaner

Wire stripper

Torque wrench

Marking pen

Level

Rubber Mallet

RJ-45 crimping tool

Multimeter

Power cable crimping tool

Cable cutter

ESD gloves

Installation Scenarios
The GTMU in this document is based on the first type of GTMU.

In the APM30/APM30H(Ver.A)

In the PS4890

In the APM30H(Ver.B)

In the 19-inch rack

In the TMC

In the RRU3004 rack

Installation Scenarios

In the TMC11H(Ver.B)

In the APM30H (Ver.B, +24V)

On the wall

In the OMB

BBU Hardware
1. Exterior of the BBU
mm

442

86 mm (2U)
310 m

2. Configuration Principles of the BBU Boards

Board GTMU UPEU

Mandatory/ Optional Mandatory Mandatory

Full Configuration 1 2

Installation Slot S5 and S6 S18 or S19

Remarks Can be installed only in S5 and S6. A single UPEU is preferentially configured in the S19 slot. Can be installed only in the S16 slot. Preferentially installed in the slot4. A single UELP is preferentially configured in the S4 slot. A single UELP is preferentially configured in the S4 slot. Preferentially installed in the S1 slot. Preferentially installed in the S18 slot.

FAN UTRP UELP

Mandatory Optional Optional

1 1 2

S16 S0 or S4 S0 or S4

UFLP

Optional

S0 or S4

USCU UEIU

Optional Optional

1 1

S0 or S1 S18

The UELP and UFLP need to be optionally configured in the BBU or SLPU on site according to the field requirements. UTRP is supported in V300R012 and later versions.

Installation Procedure

When the equipment is unpacked, it must be powered on in 24 hours. The maximum duration of the power-off state of the equipment is 24 hours during maintenance.

Installing the BBU in the APM30 a Installing the BBU Case


1. Install the mounting ears at both sides of the BBU reversely.

PDU

BBU M6 bolt

2. Slide the BBU case into the cabinet.

Installing the BBU Cables

Cable connections of the BBU


External power supply External monitoring device External alarm device E1/T1 surge protection transfer cable E1/T1cable CPRI signal cable Alarm cable
Monitoring signal cable

FE/GE surge protection transfer cable

FE/GE cable

Power cable

Installing the BBU in the APM30 b Installing the BBU Cables


1. Install BBU power cable.
Connect the OT terminal of the power cable to the LOAD3 terminal of the PDU, and then fix the 3V3 connector of the power cable to the PWR port on the BBU.

LOAD3 NEG(-) RNT(+)

PWR

2. Install the CPRI optical cable.

The OT terminals of the power cable is to be made on site.

Connect the fiber tails labeled 2A and 2B to one of the CPRI0 to CPRI5 ports on the GTMU, and connect the fiber tails labeled 1A and 1B to the CPRI_W port on the RRU.

Optical module Puller

a. Insert the optical module into the CPRI0, CPRI1, CPRI2 CPRI3, CPRI4 or CPRI5 port, and then turn outwards the puller on the optical module. b. Insert one end of the CPRI optical cable into the optical module, and then lead the CPRI optical cable out of the cabinet along the right side of the cabinet. c. Wrap the fiber tail with the winding pipe.

Winding pipe

The single-mode optical module is labeled "SM" and multi-mode optical module is labeled "MM".

The TX port on the BBU is connected to the RX port on the RRU. The RX port on the BBU is connected to the TX port on the RRU.

Installing the BBU in the APM30 b Installing the BBU Cables


3. Install the E1/T1 surge protection transfer cable. Fix the DB25 connector of the E1/T1 surge protection transfer cable to the INSIDE port on the UELP and the DB26 connector to the E1/T1 port on the GTMU. 4. Install the E1/T1 cable. 4.1. Cabling the E1/T1 cable. 4.2. Fix the DB26 connector of the E1/T1 cable to the OUTSIDE port on the UELP. 4.3. Strip the jacket off the E1/T1 cable near the grounding point at the lower right corner of the cabinet to expose the shielding layer
Shielding layer of the E1/T1 cable (25 mm)

4.4. Thread the E1/T1 cable through the grounding clip. Then, tighten the screw on the grounding clip to make the shielding layer of the E1/T1 cable in full contact with the grounding clip. Finally, connect the PGND cable on the grounding clip to the ground bolt of the APM30.

Shielding layer of the E1/T1 cable

E1/T1cable

E1/T1 surge protection transfer cable

Grounding clip

Before soldering the connectors to the E1/T1 cable, ensure that both ends of the E1 cable are disconnected from any devices. In addition, all the connectors should be soldered to the cable.

Installing the BBU in the APM30 b Installing the BBU Cables


5. Install the FE/GE surge protection transfer cable (FE/GE transmission mode).
Connect one end of the FE/GE surge protection transfer cable to the FE0 port near the INSIDE label on the UFLP and the other end to the FE0 port on the GTMU.

6. Install the FE/GE cable (FE/GE transmission mode).


6.1. Connect one end of the FE/GE cable to the FE0 port near the OUTSIDE label on the UFLP. Then, lead the other end out of the cabinet along the right side of the cabinet. (25 mm)

FE/GE surge protection transfer cable

FE/GE cable

6.2. Thread the FE/GE cable through the grounding clip. Then, tighten the screw on the grounding clip to make the shielding layer of the FE/GE cable in full contact with the grounding clip. Finally, connect the PGND cable on the grounding clip to the ground bolt of the APM30.

Shielding layer of the FE/GE cable

7. Install the monitoring signal cable between the APMI and the BBU.
7.1. Fix the RJ45 connector at one end of the cable to the MON1 port on the UPEU. 7.2. Cut off the RJ45 connector at the other end of the cable on site, and then connect the four exposed wires to the RX+, RX-, TX+, and TX- ports on the APMI.

10

Installing the BBU in the APM30 b


Installing the BBU Cables
8. Install the EMUA monitoring signal cable. (The EMUA is configured if there are external dry contacts or analog detection is required.) Cut off the RJ45 connector of the EMUA monitoring signal cable, and then connect the four exposed wires to the RX+, RX-, TX+, and TX- ports on the APMI. Fix the DB9 connector to the corresponding port on the EMUA.

EMUA monitoring signal cable


Pin on the RJ45 Connector X1.1 X1.2 X1.4 X1.5 Pin of the DB9 Male Connector X2.3 X2.7 X2.2 X2.6 Wire Color Wire Type Port on the APMI TX+ TXRX+ RX-

White Orange Blue White

Twisted pair Twisted pair Twisted pair Twisted pair

11

Installing the BBU in the APM30 b


Installing the BBU Cables
9. Install the alarm cable.

Connect one end of the alarm cable to the EXT-ALM port on the UPEU and the other end to the corresponding alarm device.

12

Installing the BBU in the APM30H(Ver.A) a BBU Cable Connections


The procedure for installing the BBU case in the APM30H is the same as that in the APM30. For details, see pages 7 to 12. The following figure shows the cable connections of the BBU. For details on how to install the monitoring signal cable between the HEUA and the BBU in the APM30H, see page 14.

No.

Cable

Installation Position One end is connected to... The other end is connected to... PWR port on the BBU INSIDE port on the UELP External transmission device MON1 port on the BBU

BBU power cable E1/T1 surge protection transfer cable E1/T1 cable Monitoring signal cable CPRI optical cable

LOAD3 terminal of the PDU E1/T1 port on the GTMU OUTSIDE port on the UELP COM IN port on the HEUA

CPRI port on the GTMU

CPRI port on the RRU

13

Installing the BBU in the APM30H(Ver.A) b


Installing the Monitoring Signal Cable Between the HEUA and the BBU

HEUA

COM IN MON1 UPEU on the BBU

14

Installing the BBU in the 19-Inch Rack a Space Requirements

When the BBU3900 is installed in the 19-inch cabinet, no space is required on the left and right of the BBU3900.

Installing the BBU Case

c Installing the DCDU-03B

15

Installing the BBU in the 19-Inch Rack d Installing the BBU Cables

No.

Cable

Installation Position
One end is connected to... The other end is connected to...
CPRI port on the RRU External power equipment LOAD6 on the DCDU-03B

CPRI optical cable External power cable BBU power cable

CPRI port on the GTMU BEG(-) and RTN(+) on the DCDU-03B PWR1 on the UPEU

16

Installing the BBU in the TMC a


Installing the DCDU-03B
Slide the DCDU-03B into the TMC. Then, tighten the four M6 screws.

Installing the BBU Case


Slide the BBU into the TMC. Then, tighten the four M6 screws.

17

Installing the BBU in the TMC c


Installing the BBU Cables

DCDU-03B input power cable

For details on how to install the TMC alarm cable, see page 19. The DCDU-03B input power cable is connected to the external DC power supply system. For cable connections of the BBU, see page 7.

18

Installing the BBU in the TMC c


Installing the BBU Cables
Door status sensor

Procedure for installing the TMC alarm cable:

APMI panel

a. Fix the RJ45 connector at one end of the alarm cable to the EXT_ALM1 port on the BBU. b. Connect the two bare terminals X1.4 (blue) and X1.5 (white) to the alarm wiring terminals of the door status sensor. c. Connect the two bare terminals X1.1 (white) and X1.2 (orange) to the OUT1+ and OUT1alarm wiring terminals on the APMI. d. Connect the two bare terminals X1.3 (white) and X1.6 (green) to the alarm wiring terminals of the DCDU.

The white and green bare wire terminals are not distinguished from different wiring terminals.

19

Installing the BBU in the PS4890 Cabinet a


Installing the DCDU-03B
2. Install the DCDU-03B input power cable. Connect one end of the power cable in blue to the DC output terminal LOAD2(-) on the power subrack and the other end to the DC input terminal NEG(-) on the DCDU-03B . Connect one end of the power cable in black to the DC output terminal RTN(+) on the power subrack and the other end to the DC input terminal RTN(+) on the DCDU-03B. 1. Slide the DCDU-03B into the PS4890 cabinet. Then, tighten the four M6 screws.

DC input terminal on the DCDU-03B

DC output terminal on the power subrack

Installing the BBU Case

Slide the BBU case into the PS4890 cabinet. Then, tighten the four M6 screws.

20

Installing the BBU in the PS4890 Cabinet c Installing the BBU Cables
Cable connections of the BBU

Connect the BBU power cable to the DC output terminal LOAD6 of the DCDU-03B.

CPRI optical cable Monitoring signal cable between the PMU and the BBU

BBU power cable BBU alarm cable

E1/T1 cable

In addition to the BBU cables installed in the APM30, a monitoring signal cable between the PMU and the BBU needs to be installed when the BBU is installed in the PS4890 cabinet. The monitoring signal cable between the APMI and the BBU is not required. For details on how to install the monitoring signal cable between the PMU and the BBU, see page 22.

21

Installing the BBU in the PS4890 Cabinet c Installing the BBU Cables
Install the monitoring signal cable between the PMU and the BBU.

Connect one end of the cable to the MON port on the BBU and the other end to the RS232/RS422 port on the PMU.

RS232/RS422 port

Monitoring signal cable between the PMU and the BBU

22

Installing the BBU in the RRU3004 Rack a


Marking Anchor Points (Unit: mm)

Drilling Holes and Installing the Expansion Bolt Assembly

Bolt M10x60 Spring washer 12 Flat washer 12

Expansion tube

c a Installing the H-shaped Stand


1. Secure the stand. 2. Adjust the level of the stand. 3. Install the beam.

Pre-tightening

Tightening

The beam on the other side is installed in the same way.

23

Installing the BBU in the RRU3004 Rack d a Removing the Washers e


Fitting the Tabs on One Side of the RRU3004 Rack into the Anchor Slots on the Stand

f a

Fixing the Lower Part of the RRU3004 Rack

Installing the Adapting Pieces

Tighten the screws

h Installing the BBU Case

Installing the DCDU-03B (48 V Input Power)


Case 2

Installing the EPS30-4815AF (AC Input Power)

24

Installing the BBU in the RRU3004 Rack j


Installing the BBU Cables
48 V input power

DCDU

Cable
CPRI optical cable

One End Is Connected to...


The end with the optical cable labels 2A and 2B is connected to CPRI ports 0 to 5 of the GTMU of the BBU.

The Other End Is Connected to...


The end with the optical cable labels 1A and 1B is connected to the CPRI_W port of the cabling cavity of the RRU. Ground bar of the stand LOAD6 port of the DCDU GEHUB or HUBBTS

Ground cable for the subrack Power cable for the BBU E1/T1 cable Power cable for the DCDU

Ground terminal of the RRU3004 rack PWR port of the BBU E1/T1 port of the BBU

RTN (+) and NEG (-) terminals at the DC input end of External power supply system the DCDU

External PGND cable Equipotential cable for the subrack Ground cable for the DCDU

Ground bar of the stand Ground terminal of the RRU3004 rack Ground terminal of the RRU3004 rack

External ground busbar Ground terminal of the RRU3004 rack Ground terminal of the DCDU

25

Installing the BBU in the RRU3004 Rack j


Installing the BBU Cables
220 V input power

4815

Only two countersunk screws are required.


Cable CPRI optical cable One End Is Connected to...

The mounting ears need to be installed in an inverse manner during the installation of the 4815.

The Other End Is Connected to...

The end with the optical cable labels 2A and The end with the optical cable labels 1A and 2B is connected to CPRI ports 0 to 5 of the GTMU of the BBU. 1B is connected to the CPRI_W port of the cabling cavity of the RRU. Ground bar of the stand External ground busbar Ground terminal of the RRU3004 rack LOAD1 port of the 4815 RS232/RS485 port of the 4815, close to the 232 side GEHUB or HUBBTS Ground terminal of the RRU3004 rack Power supply equipment of the customer

PGND cable for the RRU3004 rack External PGND cable Equipotential cable for the rack Power cable for the BBU 4815 - BBU monitoring signal cable E1/T1 cable PGND cable for the 4815 Input power cable for the 4815

Ground terminal of the RRU3004 rack Ground bar of the stand Ground terminal of the RRU3004 rack PWR port of the BBU MON1 port of the BBU E1/T1 port of the BBU Bolts for the mounting ears of the 4815 AC INPUT port of the 4815

26

Installing the IMB03 on the H-Shaped Stand a


Installing the Mounting Ears for the IMB03
Insulation pad Fitting to the mounting hole M6x16

b Installing the Bolts


Upper mounting hole for the IMB03

Beam Lower mounting hole for the IMB03

3 Nm

c Installing the IMB03 a

d Securing the IMB03


M10x30

30 Nm

20 mm to 30 mm

For details about how to install the BBU and DCDU, see page 24.

27

Installing the RRU on the H-Shaped Stand a Preparing the Installation


Auxiliary Bracket Main bracket

b Installing the Main Bracket

Dual-nut bolt

Main bracket

Brackets for installing the RRU

Only the main bracket is used for installing the RRU on the H-shaped stand, and the dual-nut bolt and auxiliary bracket are not used.

c Installing the RRU a

When the expansion bolt assemblies are used to secure the H-shaped stand, only the bolt and spring washer are used, and the expansion tube and plastic tube are removed.

d Securing the RRU

For details about cable connections, see pages 25 and 26.

28

Installing the BBU on the Wall a Space Requirements


A single BBU BBU+DCDU-03B
DCDU-03B BBU

0mm 10

The DCDU should be installed close to the BBU, but the distance between BBU and DCDU must be greater than 100 mm.

a b

Installing the Mounting Ears for Wall Installation

Mounting ears on the BBU case

Mounting ears for wall installation


Use screws to join the mounting ears for wall installation and the mounting ears on the BBU case.

29

Installing the BBU on the Wall c a


Determining the Anchor Points on the Wall Place the BBU against the wall, and then use the marking pen to mark the anchor points.

Wall

BBU

a d

Installing the Expansion Bolts

Fixing the BBU Case on the Wall

Bolt M660 Nut Spring washer 6 Flat washer 6 Expansion tube

Flat washer

Spring washer

30

Installing the BBU on the Wall f


Installing the DCDU-03B Case
1. Installing the mounting ears for the DCDU-03B. 2. Place the mounting ears for wall installation against the wall, and then use the marker to mark the holes of the mounting ears for wall installation.

Wall
M6x12

2 Nm

3. Install the expansion bolt.

4. Install the DCDU-03 on the wall.

Bolt M660 Nut Spring washer 6 Flat washer 6 Expansion tube

31

Installing the BBU on the Wall g


Installing the BBU Cables

External ground bar

External power equipment

External transmission equipment

External ground bar

External monitoring equipment

SN

Cable

Installation Position One End Connected to... The Other End Connected to...
Power supply socket on the RRU

RRU power cable

LOAD0 to LOAD5 on the DCDU-03

CPRI optical cable E1/T1 cable Monitoring signal cable BBU power cable DCDU power cable PGND cable

CPRI port on the BBU E1/T1 port on the GTMU MON/ALM port on the BBU

CPRI port on the RRU GEHUB or HUBBTS External monitoring equipment

PWR port on the BBU DC input port on the DCDU-03 Ground bolt on the equipment

LOAD6 on the DCDU-03 External power equipment External ground bar

32

Installing the BBU in the APM30H(Ver.B) a Installing the BBU Case


1. Installing the BBU Case Slide the BBU into the 2 U space close to the EPS along the guide rails, and then tighten the four M6 screws on the BBU panel.
M6x16

2. Installing the SLPU Case Slide the SLPU box into the 1U space above the EPS in the cabinet, and then fasten the two M6 screws on the panel.

EPS 01

2 Nm

BBU SLPU

M6 screws

b BBU Cable Connections

Monitoring signal cable Alarm cable BBU power cable E1/T1 cable

FE/GE cable FE/GE surge protection transfer cable E1/T1 surge protection transfer cable CPRI optical cable 33

Installing the BBU in the APM30H(Ver.B) c Installing the BBU Cables


1. Install power cable. Link the easy power receptacle (pressfit type) connector at one end to the LOAD1 terminal of the EPS01, and then link the 3V3 connector at the other end to the -48V port on the BBU. LOAD1

2. Install the CPRI optical cable. The connectors labeled 2A and 2B are connected to the optical module on the port labeled CPRI0 to CPRI5 on the GTMU of the BBU, the connectors labeled 1A and 1B are connected to the optical module on the port labeled CPRI_W on the RRU.
2.1. Turn the puller on the optical module outwards, and then insert the optical module to the port CPRI 0 to CPRI5. 2.2. Remove the dustproof caps from the optical connectors. Insert the optical connector at one end of the CPRI optical cable into the optical module. Lead the CPRI optical cable out of the cabinet along the left side of the cabinet. 2.3. Wrap the winding pipe at the fiber tails.

Optical module Puller

Winding pipe

Connect the fiber tails labeled 1A and 1B to the CPRI_W port on the RRU. Connect the fiber tails labeled 2A and 2B to one of the CPRI0 to CPRI5 ports on the GTMU.

34

Installing the BBU in the APM30H(Ver.B) c


Installing the BBU Cables
Fix the DB25 connector of the E1/T1 surge protection transfer cable to the INSIDE port on the UELP and the DB26 connector to the E1/T1 port on the GTMU.

3. Install the E1/T1 surge protection transfer cable.

4. Install the E1/T1 cable.


4.1. Cabling the E1/T1 cable. 4.2. Fix the DB26 connector of the E1/T1 cable to the OUTSIDE port on the UELP.

Before soldering the connectors to the E1/T1 cable, ensure that both ends of the E1 cable are disconnected from any devices. In addition, all the connectors should be soldered to the cable.

E1/T1 cable E1/T1 surge protection transfer cable

5. Install the FE/GE surge protection transfer cable (FE/GE transmission mode).

Connect one end of the FE/GE surge protection transfer cable to the FE0 port near the INSIDE label on the UFLP and the other end to the FE0 port on the GTMU.

6. Install the FE/GE cable (FE/GE transmission mode).


6.1. Connect one end of the FE/GE cable to the FE0 port near the OUTSIDE label on the UFLP. Then, lead the other end out of the cabinet along the right side of the cabinet.

FE/GE surge protection transfer cable

FE/GE cable

35

Installing the BBU in the APM30H(Ver.B) c Installing the BBU Cables


7. Install the monitoring signal cable between the CMUA and the BBU.

COM_IN

MON1

36

Installing the BBU in the TMC11H(Ver.B) a Installing the BBU


Slide the BBU into the TMC11H along guide rails, and then tighten the four M6 screws on the BBU panel.
M6x16 M6x16

Slide the SLPU into the TMC11H along the guide rails, and then tighten the two M6 screws on the SLPU panel.

DCDU
2 Nm 2 Nm

SLPU BBU

b Installing the BBU Cable


Install the BBU power cable.

LOAD6

37

Installing the BBU in the TMC11H(Ver.B) b Installing the BBU Cable


The procedure for installing BBU cables (except the power cable) in the TMC11H cabinet is the same as that in the APM30H(Ver.B). For details, see the description on pages 33 to 36. For details on the BBU cable connections, see BBU Cable Connections on pages 33.

Cable
CPRI optical cable

Connector Type
DLC

Connects to
The connectors labeled 2A and 2B are connected to the optical module on the port labeled CPRI0 to CPRI5 on the GTMU. The connectors labeled 1A and 1B are connected to the optical module on the port labeled CPRI_W on the RRU. OUTSIDE port on the UELP Port on the transmission device

DLC

E1/T1 cable

DB26 connector The connector needs to be made on site according to the field requirements.

E1/T1 surge protection transfer cable

DB26 connector DB25 connector

E1/T1 port on the GTMU INSIDE port on the UELP FE0 port at the OUTSIDE side on the UFLP Port on the transmission device FE0 port at the INSIDE side on the UFLP FE0 port on the GTMU MON1 port on the BBU COM_IN port on the CMUA -48V port on the UPEU LOAD6 port on the DCDU-03B

FE/GE cable

RJ45 connector RJ45 connector

FE/GE surge protection transfer cable Monitoring signal cable between the CMUA and the BBU BBU power cable

RJ45 connector RJ45 connector RJ45 connector RJ45 connector 3V3 connector OT terminal

38

Installing the BBU in the APM30H(Ver.B, +24V) a Installing the BBU


Slide the BBU to the APM30H (+24V) along guide rails, and then tighten the four M6 screws on the BBU panel.
M6x16 M6x16

Slide the SLPU to the APM30H (+24V) along guide rails, and then tighten the two M6 screws on the SLPU panel.

EPS48100D

2 Nm

2 Nm

BBU

b Installing BBU Cables


Installing the monitoring signal cable for the PSU and the in-position signal cable for the PSU PRESENT ALM

EXT-ALM1

EXT-ALM0

39

Installing the BBU in the APM30H(Ver.B, +24V) b Installing BBU Cables


The procedure for installing BBU cables (except the power cable) in the APM30H(+24 V) cabinet is the same as that in the APM30H(Ver.B). For details, see the description on pages 33 to 36. For details on the BBU cable connections, see BBU Cable Connections on pages 33.

Cable
CPRI optical cable

Connector Type
DLC

Connects to
The connectors labeled 2A and 2B are connected to the optical module on the port labeled CPRI0 to CPRI2 on the GTMU. The connectors labeled 1A and 1B are connected to the optical module on the port labeled CPRI_W on the RRU. E1/T1 port on the GTMU Port on the transmission device

DLC

E1/T1 cable

DB26 Connector The connector needs to be made on site according to the field requirements.

E1/T1 Surge Protection Transfer Cable FE/GE cable

DB26 connector DB25 connector RJ45 connector RJ45 connector

E1/T1 port on the GTMU INSIDE port on the UELP FE0 port on the GTMU Port on the transmission device FE0 port at the INSIDE side on the UFLP FE0 port on the GTMU MON1 port on the BBU COM_IN port on the CMUA EXT-ALM0 port on the UPEU ALM port on the EPS48100D EXT-ALM1 port on the UPEU PRESENT port on the EPS48100D -48V port on the UPEU LOAD6 port on the DCDU-03B

FE/GE Surge Protection Transfer Cable Monitoring signal cable between the CMUA and the BBU Monitoring signal cable for the PSU In-position signal cable for the PSU BBU power cable

RJ45 connector RJ45 connector RJ45 connector RJ45 connector RJ-45 RJ-45 RJ-45 Cord end terminal 3V3 OT

40

Installing the BBU in the OMB a Installing the Brackets on the Metal Pole and Mounting Plate
1. Install the brackets on the metal pole.
Use a level to adjust the level of the brackets to ensure that the front and back brackets are on the same plane.
M10x110
Flat washer Spring washer Bolt

255-306 kgfcm

2. Install the mounting plate.


M10x40

255-306 kgfcm

Flat Spring Bolt washer washer

Mounting plate

41

Installing the BBU in the OMB b Installing the OMB


Slide the BBU case into the OMB gently. Then, tighten the four M6 screws.

Ensure that the fan is on the bottom when installing the BBU.

c Installing the BBU Cables


The procedures for installing the PGND cable, E1/T1 cable or FE/GE cable, and optical cable in the DC OMB and in the AC OMB are the same: PGND cable E1/T1 cable or FE/GE cable Optical cable The following description takes the installation in the DC OMB as an example.

1. Install the PGND cable for OMB.

Ground bar

42

Installing the BBU in the OMB c Installing the BBU Cables


2. Install the input power cable for the DC OMB.

RNT (+) NEG(-)

3. Install the input power cable for the AC OMB.

PE

43

Installing the BBU in the OMB c Installing the BBU Cables


4. Install the BBU power cable for the DC OMB.
LOAD6

5. Install the BBU power cable for the AC OMB.


DC INPUT

PWR

LOAD1

44

Installing the BBU in the OMB c Installing the BBU Cables


6. Install the E1/T1 cable (E1/T1 transmission mode).
E1/T1

OUTSIDE

INSIDE

PGND

Shielding layer (25 mm)

Shielding layer

45

Installing the BBU in the OMB c Installing the BBU Cables


7. Install the FE/GE cable (FE/GE transmission mode). c

a c b

8. Install the CPRI optical cable.


Connect the longer end of the optical cable to CPRI0, CPRI1, CPRI2, CPRI3,CPRI4 or CPRI5 on the GTMU. Then, connect the other end to the RRU.

1. Insert the optical module into the CPRI0, CPRI1, CPRI2, CPRI3, CPRI4 or CPRI5 port. 2. Turn outwards the puller on the optical module.

Optical module

Puller

3. Remove the dustproof caps from the optical connectors. 4. Insert the optical connector at one end of the CPRI optical cable into the optical module. Lead the CPRI optical cable out of the cabinet along the left side of the cabinet.

46

BBU Hardware Installation Checklist


SN
1

Item
All self-made PGND cables are copper-based with the proper wire diameters. No breaking device such as switch and fuse is allowed for the electric connection of the grounding system. No short circuit is allowed. Each terminal on the ground bar can be connected with only one wiring terminal of the PGND cable. The redundant part of the power cable or PGND cable is stripped off rather than coiled. The terminals at both ends of the power cable or PGND cable are securely soldered or crimped. The bare wires and the terminal handles at the wiring terminals are coated with heat-shrinkable tubes. The flat washer and the spring washer are well mounted on all OT terminals. All cables are connected securely and reliably. Pay special attention to the cable connections at the bottom of the cabinet. The cables are neatly and tightly bound. The cable ties are evenly spaced and face the same direction. The power cable, PGND cable, feeder, optical cable and the E1/T1/FE/GE signal cable are bound separately with a spacing of larger than 3 cm. The cable layout facilitates maintenance and future capacity expansion, and the bending radius of the cables meet the requirements. All the labels at both ends of the cables are legible. The extra length of each indoor cable tie is cut, and the cut surface is smooth without sharp edges. An extra length of 3 mm to 5 mm is reserved for each outdoor cable tie. The idle connectors of the cables are properly protected.

2 3 4 5 6

7 8

10 11

12

Powering On the BBU

47

Obtaining the ESN


Record the Electronic Serial Number (ESN) shown on the label attached to the mounting ear of the BBU, and report the ESN to the engineer for the commissioning of the base station.

ESN

Appendix a Setting the DIP Switches


Remove the GTMU and UELP from the BBU.

Wear an ESD wrist strap during the operations on the boards to prevent damage to the boards.

The UELP is optional. Please check the settings of the DIP switches according to the field conditions.

48

Appendix a Setting the DIP Switches


Set the DIP switches of the BBU. Settings of the DIP switches on the UELP
75-ohm E1 Mode

Other Modes

Settings of the DIP switches on the GTMU


T1 Mode

75-ohm E1 Mode

120-ohm E1 Mode

All the DIP bits of S2 on the GTMU are set to OFF by default in all modes. When four 75-ohm E1/T1 links are faulty, all the DIP bits of S2 should be set to ON so that the faults are rectified.

49

Appendix a Setting the DIP Switches


Settings of S4 and S5 on the GTMU
DIP Switch Setting of DIP Bit 1 S4 ON OFF 2 ON OFF 3 ON OFF 4 ON OFF The E1 link can be bypassed. The E1 link cannot be bypassed. Not available Description

Miscellaneous

DIP Switch

Setting of DIP Bit 1 ON OFF 2 ON ON 3 ON ON 4 ON OFF

Description

S5

The E1 link can be bypassed. The E1 link of the Level 1 cascaded BTS can be bypassed.

ON

OFF

ON

OFF

The E1 link of the Level 2 cascaded BTS can be bypassed.

OFF

OFF

ON

OFF

The E1 link of the Level 3 cascaded BTS can be bypassed.

Reinstall the GTMU and the UELP.

50

Appendix a Setting the DIP Switches


No. 1 to 5 Function Defining the communication address of the PMU Operation (1) Switches 1 to 5 correspond to bits 0 to 4. ON:1; OFF: 0 For example: to set the address of PMU to 3, set switches 3 to 5 as OFF. (2) Default setting before delivery: 1 (BIT0), ON 2 (BIT1), ON 3 (BIT2), OFF 4 (BIT3), OFF 5 (BIT4), OFF 6 Selecting baud rate for communicating with the BTS Set as ON, indicating that the baud rate is 9600. (If it is set as OFF, the baud rate is 19200.) 7 and 8 Reserved and not defined Set as OFF

Set the DIP switches of the PMU.

51

Appendix b Pin Assignment for the BBU Signal Cables


75-ohm E1 cable
Pin of the DB26 Male Connector X1.1 X1.2 X1.3 X1.4 X1.5 X1.6 X1.7 X1.8 X1.19 X1.20 X1.21 X1.22 X1.23 X1.24 X1.25 X1.26 Wire Type Tip Ring Tip Ring Tip Ring Tip Ring Tip Ring Tip Ring Tip Ring Tip Ring 8 6 4 2 7 5 3 Coaxial Series No. 1 Label RX1+ RX1RX2+ RX2RX3+ RX3RX4+ RX4TX1+ TX1TX2+ TX2TX3+ TX3TX4+ TX4-

52

Appendix b Pin Assignment for the BBU Signal Cables


120-ohm E1 cable
Pin of the DB26 Male Connector X1.1 X1.2 X1.3 X1.4 X1.5 X1.6 X1.7 X1.8 X1.19 X1.20 X1.21 X1.22 X1.23 X1.24 X1.25 X1.26 Wire Color Blue Twisted pair White Orange White Green Twisted pair White Brown Twisted pair White Grey Twisted pair White Blue Twisted pair Red Orange Twisted pair Red Green Twisted pair Red TX4TX3TX4+ TX2TX3+ TX1TX2+ RX4TX1+ RX3RX4+ Twisted pair RX1RX2+ RX2RX3+ Wire Type Label RX1+

53

Appendix b Pin Assignment for the BBU Signal Cables


Monitoring signal cable between the APMI and the BBU
Pin of the RJ45 Connector Wire Color Pins of X2, X3, X4, and X5 X2 X3 X4 X5 Wire Type Port on the APMI

X1.1 X1.2 X1.4 X1.5

White Orange Blue White

Twisted pair Twisted pair Twisted pair Twisted pair

TX+ TXRX+ RX-

EMUA monitoring signal cable


Pin on the RJ45 Connector X1.1 X1.2 X1.4 X1.5 Pin of the DB9 Male Connector X2.3 X2.7 X2.2 X2.6 Wire Color Wire Type Port on the APMI TX+ TXRX+ RX-

White Orange Blue White

Twisted pair Twisted pair Twisted pair Twisted pair

54

Appendix b Pin Assignment for the BBU Signal Cables


BBU alarm cable
Pin of the RJ45 Connector X1.1 X1.2 X1.3 X1.6 X1.5 X1.4 X1.7 X1.8 Pin of the RJ45 Connector X2.1 X2.2 X2.3 X2.6 X2.5 X2.4 X2.7 X2.8 Wire Color Wire Type

White/orange Orange White/green Green White/blue Blue White/brown Brown

Twisted pair

Twisted pair

Twisted pair

Twisted pair

55

Change History
This describes the changes in the BBU3900 Installation Guide. 16 (2010-07-30) This is the sixteenth commercial release. Compared with issue 15 (2010-06-30) of V300R008&R009, this issue excludes the safety information. 15 (2010-06-30) This is the fifteenth commercial release. Compared with issue 14 (2010-04-10) of V300R008&R009, this issue incorporates the description about installing the IMB03 on the H-Shaped stand. 14 (2010-04-10) This is the fourteen commercial release. Compared with issue 13 (2010-03-15) of V300R008&R009, the UTRP is added. 13 (2010-03-15) This is the thirteenth commercial release. Compared with issue 12 (2010-01-30) of V300R008&R009, the procedure for obtaining the ESN is added. 12 (2010-01-30) This is the twelfth commercial release. Compared with issue 11 (2009-12-30) of V300R008&R009, the configuration principles of the UFLP is modified. 11 (2009-12-30) This is the eleventh commercial release. Compared with issue 10 (2009-11-10) of V300R008&R009, the installation scenarios of OMB are added. 10 (2009-11-10) This is the tenth commercial release. Compared with issue 09 (2009-07-15) of V300R008&R009, the installation scenarios of APM30H(Ver.B), TMC11H(Ver.B) and APM30H(Ver.B, +24V) are added. 09 (2009-07-15) This is the ninth commercial release. Compared with issue 08 (2009-04-20) of V300R008, no contents are added or deleted. 56

HUAWEI TECHNOLOGIES CO., LTD.


Huawei Industrial Base Bantian Longgang Shenzhen 518129 Peoples Republic of China www.huawei.com