US FARATHANE APODACA EMISION: 03/11/2023

AMEF/VDA Update Planning

Qty. of Tools % of
CUSTOMER Engineer Status
- Actives- Completion
No.
P. Obregon 4
1 A Raymond Tinnerman 2 0%
R. Cantu 0
B.Sanchez 2
2 Antolín Derramadero 2 0%
R. Cantu 0
B. Sanchez 5
3 Antolín Hermosillo 5 0%
R. Cantu 0
B. Sanchez 1
4 Antolín Arteaga 1 0%
R. Cantu 0
B. Sanchez 3
5 Antolin Saltillo 3 0%
R. Cantu 0
P. Obregon 6
6 ADIENT Saltillo 6 67%
J. Estrada 4
P. Obregon 15
8 HFI Monclova 15 0%
R. Cantu 0
P. Obregon 1
9 IACNA Monterrey 1 0%
R. Cantu 0
P. Obregon 6
10 Mexauria Puebla 6 100%
J. Estrada 6
P. Obregon 13
11 Plastic Omnium Ramos 13 0%
R. Cantu 0
P. Obregon 10
12 MAHLE Mexico 10 0%
R. Cantu 0
P. Obregon 1
14 MITSUBA 1 0%
R. Cantu 0
P. Obregon 1
15 PMW 1 0%
R. Cantu 0
22
19 GM B.Sanchez 22 100%
22
B. Sanchez 2
19 Tristone 2 100%
J. Acuña 2
2
19 HSAM Sanchez 2 100%
2
P. Obregon 7
20 LEAR Silao 7 100%
J. Estrada 7
P. Obregon 13
21 LEAR Ramos 13 100%
J. Acuña 13
B. Sanchez
21
22 FEHRER J. Acuña 21 0%
R. Cantu 0
B Sanchez 8
23 HBPO 8 38%
J. Estrada 3
P. Obregon 26
24 Stellantis 26 100%
J. Acuña 26
B. Sanchez 22
25 LEAR HERMOSILLO 22 64%
J. Acuña 14
B Sanchez 7
26 ADIENT LERMA 7 100%
J. Estrada 7
B Sanchez 4
27 FORD Cuatitlan 4 100%
J. Estrada 4
B Sanchez 3
28 FORD Hermosillo 3 100%
J. Estrada 3
P. Obregon 3
28 NYX 3 100%
J. Acuña 3
P. Obregon 1
29 LEAR Saltillo 1 100%
J. Acuña 1
Beatriz S. 1
29 Hutchinson 1 100%
J. Acuña 1

210
No. Moldes Completados
Total 208 57% 118
118
Avance vs programado: 104% Debe : 113
Es: 118