Documentos de Académico
Documentos de Profesional
Documentos de Cultura
15,786,011.27 498,287.07 3.15% 3,225,014.41 20.43% 6,800,839.57 43.08% 10,524,140.57 66.67% 5,261,870.62 33.33%
TOTAL 498,287.07 3.15% 3,225,014.41 20.43% 6,800,839.57 43.08% 10,524,140.57 66.67% 5,261,870.62 33.33%
15,786,011.27 498,287.07 3.15% 3,225,014.41 20.43% 6,800,839.57 43.08% 10,524,140.57 66.67% 5,261,870.62 33.33%
TOTAL 498,287.07 3.15% 3,225,014.41 20.43% 6,800,839.57 43.08% 10,524,140.57 66.67% 5,261,870.62 33.33%
04.02.04.01.06 ENCOFRADO Y DESENCOFRADO CARAVISTA EN OBRAS DE ARTE M2 402.00 58.39 23,472.78 - - - - - - - - - - 0.00% 402.00 23,472.78 100.00%
04.02.04.01.07 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 2,688.51 6.55 17,609.74 - - - - - - - - - - 0.00% 2,688.51 17,609.74 100.00%
04.02.04.01.08 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE 1:2+SIKA M2 252.00 62.42 15,729.84 - - - - - - - - - - 0.00% 252.00 15,729.84 100.00%
04.02.04.01.09 JUNTA WATER STOP 6" M 23.10 60.24 1,391.54 - - - - - - - - - - 0.00% 23.10 1,391.54 100.00%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.02.04.01.10 m3 234.00 13.45 3,147.30 - - - - - - - - - - 0.00% 234.00 3,147.30 100.00%
PREPARADO DEL MATERIAL
04.02.04.01.11 CURADO DE CONCRETO CON ADITIVO QUIMICO M2 516.00 3.12 1,609.92 - - - - - - - - - - 0.00% 516.00 1,609.92 100.00%
04.02.04.02 TAPA DE CANAL RECTANGULAR KM 8+420 A 8+480 17,653.58
04.02.04.02.01 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 108.00 55.02 5,942.16 - - - - - - - - - - 0.00% 108.00 5,942.16 100.00%
04.02.04.02.02 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 748.30 6.55 4,901.37 - - - - - - - - - - 0.00% 748.30 4,901.37 100.00%
04.02.04.02.03 CONCRETO F'C=175 KG/CM2 m3 9.60 454.73 4,365.41 - - - - - - - - - - 0.00% 9.60 4,365.41 100.00%
04.02.04.02.04 COLOCACION DE TAPA DE CONCRETO UND 120.00 15.38 1,845.60 - - - - - - - - - - 0.00% 120.00 1,845.60 100.00%
04.02.04.02.05 CURADO DE CONCRETO CON ADITIVO QUIMICO M2 192.00 3.12 599.04 - - - - - - - - - - 0.00% 192.00 599.04 100.00%
04.03 OBRAS DE ARTE EN CANAL DE CONCRETO 1,154,499.12
04.03.01 ALCANTARILLA DE CºAº TIPO I, (3 UND) 64,317.86
04.03.01.01 LIMPIEZA MANUAL DE TERRENO M2 109.50 2.33 255.14 - - 73.00 170.09 - - - - 73.00 170.09 66.67% - - -
04.03.01.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 109.50 6.60 722.70 - - 73.00 481.80 - - - - 73.00 481.80 66.67% - - -
04.03.01.03 EXCAVACIÓN EN MATERIAL SUELTO, MANUAL m3 209.52 52.45 10,989.32 - - 139.64 7,324.33 - - - - 139.64 7,324.33 66.65% - - -
04.03.01.04 RELLENO Y COMPACTADO CON MATERIAL SELECCIONADO M3 9.08 16.29 147.91 - - 6.12 99.69 - - - - 6.12 99.69 67.40% - - -
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.01.05 m3 40.79 13.45 548.63 - - 27.18 365.52 - - - - 27.18 365.52 66.62% - - -
PREPARADO DEL MATERIAL
04.03.01.06 ELIMINACIÓN DE MATERIAL EXCEDENTE D PROMEDIO=30 M. m3 251.42 17.49 4,397.34 - - 167.57 2,930.85 - - - - 167.57 2,930.85 66.65% - - -
04.03.01.07 SOLADO DE COCRETO 1:12, E=4" M2 62.49 44.77 2,797.68 - - 41.61 1,862.97 - - - - 41.61 1,862.97 66.59% - - -
CONCRETO CICLOPEO FC= 140 KG/CM2 + 30%PM CON
04.03.01.08 M3 4.72 356.15 1,681.03 - - 2.59 923.14 - - - - 2.59 923.14 54.92% - - -
MEZCLADORA
FORMATO Nº 03-IF
VALORIZACION FINAL - OBRA PRINCIPAL
(Meta : 148 - 2022)
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (16 FEBRERO AL 31 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 15,786,011.27
EJECUCIÓN AÑO 2022 (META: 148)
METRADO PROGRAMADO DEDUCTIVO DE OBRA
(Exp. Tecnico Saldo de Obra - OBRA PRINCIPAL (R.G.R N°
DEL 16 DE MAYORES OBRAS
ITEM DESCRIPCION R.G.R N° 173-2021-GRA/GG-GRI) DEL 01 DE MAYO AL METRADOS ADICIONALES
TOTAL VALORIZADO
322-2022-GRA/GGR-GRI)
FEBRERO AL 30 DE
20 DE DICIEMBRE
ABRIL
Unid. Metrado P.Unit. P.Parcial METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO % METRADO MONTO %
04.03.01.09 EMBOQUILLADO DE PIEDRA E=0.20M(fc=175km/cm2+60%PM) m2 9.30 65.26 606.92 - - 6.20 404.61 - - - - 6.20 404.61 66.67% - - -
04.03.01.10 CONCRETO F´C=210 KG/CM2 M3 33.44 642.81 21,495.57 - - 21.99 14,136.68 4.42 2,838.65 - - 21.99 14,136.68 65.77% - - -
04.03.01.11 ENCOFRADO Y DESENCOFRADO CARAVISTA EN OBRAS DE ARTE M2 210.54 58.39 12,293.43 - - 140.20 8,186.28 26.68 1,557.85 - - 140.20 8,186.28 66.59% - - -
04.03.01.12 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 1,256.31 6.55 8,228.83 - - 1,217.83 7,976.78 244.46 1,601.23 - - 1,217.83 7,976.78 96.94% - - -
04.03.01.13 SELLADO DE JUNTA DE DILATACIÓN CON MASILLA ELASTICA 2" M 7.20 21.30 153.36 - - - - - - - - - - 0.00% - - -
04.03.02 TOMAS PREDIALES 31 UND, KM 0+000-13+220 67,424.71
04.03.02.01 TOMA PREDIAL TIPO I, 21 UND 25,684.34
04.03.02.01.01 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 15.71 6.60 103.69 - - 15.71 103.69 - - - - 15.71 103.69 100.00% - - -
04.03.02.01.02 EXCAVACIÓN EN MATERIAL SUELTO, MANUAL m3 10.16 52.45 532.89 - - 10.16 532.89 - - - - 10.16 532.89 100.00% - - -
04.03.02.01.03 REFINE Y NIVELACIÓN DE SUB RASANTE m2 7.31 1.04 7.60 - - 7.31 7.60 - - - - 7.31 7.60 100.00% - - -
04.03.02.01.04 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 20.83 55.02 1,146.07 - - 20.83 1,146.07 - - - - 20.83 1,146.07 100.00% - - -
04.03.02.01.05 CONCRETO F´C=210 KG/CM2 M3 5.22 642.81 3,355.47 - - 4.24 2,725.05 - - - - 4.24 2,725.05 81.21% - - -
04.03.02.01.06 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 104.57 6.55 684.93 - - 81.78 535.66 - - - - 81.78 535.66 78.21% - - -
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.02.01.07 m3 13.36 13.45 179.69 - - 13.36 179.69 - - - - 13.36 179.69 100.00% - - -
PREPARADO DEL MATERIAL
04.03.02.01.08 TARRAJEO CON IMPERMEABILIZANTE E=1.5 CM, M 1:5 m2 22.93 34.35 787.65 - - 22.93 787.65 - - - - 22.93 787.65 100.00% - - -
04.03.02.01.09 INSTALACIÓN DE COMPUERTA METÁLICA EN TOMA PARCELARIA und 21.00 899.35 18,886.35 - - 16.00 14,389.60 - - - - 16.00 14,389.60 76.19% - - -
04.03.02.02 TOMA PREDIAL TIPO II, 08 UND 31,270.87
04.03.02.02.01 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 13.50 6.60 89.10 - - - - - - - - - - 0.00% - - -
04.03.02.02.02 EXCAVACIÓN EN MATERIAL SUELTO, MANUAL m3 20.39 52.45 1,069.46 - - - - - - - - - - 0.00% - - -
04.03.02.02.03 REFINE Y NIVELACIÓN DE SUB RASANTE m2 13.50 1.04 14.04 - - - - - - - - - - 0.00% - - -
04.03.02.02.04 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 85.77 55.02 4,719.07 - - - - - - - - - - 0.00% - - -
04.03.02.02.05 CONCRETO F´C=210 KG/CM2 M3 8.76 642.81 5,631.02 - - - - - - - - - - 0.00% - - -
04.03.02.02.06 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 245.68 6.55 1,609.20 - - - - - - - - - - 0.00% - - -
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.02.02.07 m3 124.80 13.45 1,678.56 - - - - - - - - - - 0.00% - - -
PREPARADO DEL MATERIAL
04.03.02.02.08 TARRAJEO CON IMPERMEABILIZANTE E=1.5 CM, M 1:5 m2 41.78 34.35 1,435.14 - - - - - - - - - - 0.00% - - -
SUM. Y COLOC. DE COMP. MET. DE 1.33, 0.25X0.42X 1/8", SEGUN
04.03.02.02.09 UND 16.00 939.08 15,025.28 - - - - - - - - - - 0.00% - - -
DISEÑO
04.03.02.03 TOMA PREDIAL TIPO III, 02 UNID 10,469.50
04.03.02.03.01 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 6.06 6.60 40.00 - - - - - - - - - - 0.00% - - -
04.03.02.03.02 EXCAVACIÓN EN MATERIAL SUELTO, MANUAL m3 8.42 52.45 441.63 - - - - - - - - - - 0.00% - - -
FORMATO Nº 03-IF
VALORIZACION FINAL - OBRA PRINCIPAL
(Meta : 148 - 2022)
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (16 FEBRERO AL 31 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 15,786,011.27
EJECUCIÓN AÑO 2022 (META: 148)
METRADO PROGRAMADO DEDUCTIVO DE OBRA
(Exp. Tecnico Saldo de Obra - OBRA PRINCIPAL (R.G.R N°
DEL 16 DE MAYORES OBRAS
ITEM DESCRIPCION R.G.R N° 173-2021-GRA/GG-GRI) DEL 01 DE MAYO AL METRADOS ADICIONALES
TOTAL VALORIZADO
322-2022-GRA/GGR-GRI)
FEBRERO AL 30 DE
20 DE DICIEMBRE
ABRIL
Unid. Metrado P.Unit. P.Parcial METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO % METRADO MONTO %
04.03.02.03.03 REFINE Y NIVELACIÓN DE SUB RASANTE m2 6.06 1.04 6.30 - - - - - - - - - - 0.00% - - -
04.03.02.03.04 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 26.69 55.02 1,468.48 - - - - - - - - - - 0.00% - - -
04.03.02.03.05 CONCRETO F'C=175 KG/CM2 m3 3.04 454.73 1,382.38 - - - - - - - - - - 0.00% - - -
04.03.02.03.06 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 82.82 6.55 542.47 - - - - - - - - - - 0.00% - - -
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.02.03.07 m3 33.36 13.45 448.69 - - - - - - - - - - 0.00% - - -
PREPARADO DEL MATERIAL
04.03.02.03.08 TARRAJEO CON IMPERMEABILIZANTE E=1.5 CM, M 1:5 m2 14.65 34.35 503.23 - - - - - - - - - - 0.00% - - -
SUM. Y COLOC. DE COMP. MET. DE 1.33, 0.70X0.70X 1/8", SEGUN
04.03.02.03.09 UND 4.00 1,409.08 5,636.32 - - - - - - - - - - 0.00% - - -
DISEÑO
04.03.03 TOMAS DE DESFOGUE 09 UND 69,308.26
04.03.03.01 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 5.40 6.60 35.64 - - 5.40 35.64 - - - - 5.40 35.64 100.00% - - -
04.03.03.02 EXCAVACIÓN EN MATERIAL SUELTO, MANUAL m3 120.39 52.45 6,314.46 - - 75.32 3,950.67 - - - - 75.32 3,950.67 62.57% - - -
04.03.03.03 REFINE Y NIVELACIÓN DE SUB RASANTE m2 92.61 1.04 96.31 - - 54.99 57.19 - - - - 54.99 57.19 59.38% - - -
04.03.03.04 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 542.97 55.02 29,874.21 - - 128.54 7,072.16 - - - - 128.54 7,072.16 23.67% - - -
04.03.03.05 CONCRETO F'C=175 KG/CM2 m3 49.12 454.73 22,336.34 - - 17.11 7,779.41 - - - - 17.11 7,779.41 34.83% - - -
04.03.03.06 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 44.82 6.55 293.57 - - 44.82 293.57 - - - - 44.82 293.57 100.00% - - -
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.03.07 m3 118.75 13.45 1,597.19 - - 45.99 618.51 - - - - 45.99 618.51 38.72% - - -
PREPARADO DEL MATERIAL
04.03.03.08 TARRAJEO CON IMPERMEABILIZANTE E=1.5 CM, M 1:5 m2 19.40 34.35 666.39 - - 19.40 666.39 - - - - 19.40 666.39 100.00% - - -
04.03.03.09 INSTALACIÓN DE COMPUERTA METÁLICA EN TOMA PARCELARIA und 9.00 899.35 8,094.15 - - 4.00 3,597.40 - - - - 4.00 3,597.40 44.44% - - -
04.03.04 CANOA TIPO I, 06 UND (2.20 X 3.95 MT) 69,439.69
04.03.04.01 LIMPIEZA MANUAL DE TERRENO M2 183.78 2.33 428.21 - - - - - - - - - - 0.00% - - -
04.03.04.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 245.40 6.60 1,619.64 - - - - - - - - - - 0.00% - - -
04.03.04.03 EXCAVACION MANUAL EN MATERIAL CONGLOMERADO M3 110.47 55.24 6,102.36 - - - - - - - - - - 0.00% - - -
04.03.04.04 ELIMINACIÓN DE MATERIAL EXCEDENTE D PROMEDIO=30 M. m3 138.09 17.49 2,415.19 - - - - - - - - - - 0.00% - - -
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.04.05 m3 40.02 13.45 538.27 - - - - - - - - - - 0.00% - - -
PREPARADO DEL MATERIAL
CONCRETO CICLOPEO FC= 140 KG/CM2 + 30%PM CON
04.03.04.06 M3 42.24 356.15 15,043.78 - - - - - - - - - - 0.00% - - -
MEZCLADORA
04.03.04.07 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 119.94 55.02 6,599.10 - - - - - - - - - - 0.00% - - -
04.03.04.08 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 1,404.36 6.55 9,198.56 - - - - - - - - - - 0.00% - - -
04.03.04.09 CONCRETO F'C=175 KG/CM2 m3 26.16 454.73 11,895.74 - - - - - - - - - - 0.00% - - -
04.03.04.10 EMBOQUILLADO DE PIEDRA E=0.20M(fc=175km/cm2+60%PM) m2 125.94 65.26 8,218.84 - - - - - - - - - - 0.00% - - -
04.03.04.11 CONCRETO CICLOPEO FC = 175 KG/CM2 + 30% P.M. M3 25.68 232.64 5,974.20 - - - - - - - - - - 0.00% - - -
FORMATO Nº 03-IF
VALORIZACION FINAL - OBRA PRINCIPAL
(Meta : 148 - 2022)
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (16 FEBRERO AL 31 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 15,786,011.27
EJECUCIÓN AÑO 2022 (META: 148)
METRADO PROGRAMADO DEDUCTIVO DE OBRA
(Exp. Tecnico Saldo de Obra - OBRA PRINCIPAL (R.G.R N°
DEL 16 DE MAYORES OBRAS
ITEM DESCRIPCION R.G.R N° 173-2021-GRA/GG-GRI) DEL 01 DE MAYO AL METRADOS ADICIONALES
TOTAL VALORIZADO
322-2022-GRA/GGR-GRI)
FEBRERO AL 30 DE
20 DE DICIEMBRE
ABRIL
Unid. Metrado P.Unit. P.Parcial METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO % METRADO MONTO %
04.03.04.12 SELLADO DE JUNTA DE DILATACIÓN CON MASILLA ELASTICA 2" M 66.00 21.30 1,405.80 - - - - - - - - - - 0.00% - - -
04.03.05 CANOA TIPO II 04 UND (2.70 X 4.45 MT) 89,823.16
04.03.05.01 LIMPIEZA MANUAL DE TERRENO M2 135.92 2.33 316.69 35.15 81.90 71.56 166.72 - - - - 106.71 248.62 78.51% - - -
04.03.05.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 190.88 6.60 1,259.81 35.15 231.99 71.56 472.26 - - - - 106.71 704.25 55.90% - - -
04.03.05.03 EXCAVACION MANUAL EN MATERIAL CONGLOMERADO M3 147.02 55.24 8,121.38 8.00 441.92 51.56 2,847.98 - - - - 59.56 3,289.90 40.51% - - -
04.03.05.04 ELIMINACIÓN DE MATERIAL EXCEDENTE D PROMEDIO=30 M. m3 183.78 17.49 3,214.31 22.06 385.84 52.39 916.21 - - - - 74.45 1,302.05 40.51% - - -
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.05.05 m3 53.81 13.45 723.74
0.85 11.43 5.31 71.42 - - - - 6.16 82.85 11.45% - - -
PREPARADO DEL MATERIAL
CONCRETO CICLOPEO FC= 140 KG/CM2 + 30%PM CON
04.03.05.06 M3 48.25 356.15 17,184.24
2.55 908.18 23.34 8,310.76 - - - - 25.89 9,218.94 53.65% - - -
MEZCLADORA
04.03.05.07 ENCOFRADO Y DESENCOFRADO CARAVISTA EN OBRAS DE ARTE M2 199.77 58.39 11,664.57 - - 113.02 6,599.24 - - - - 113.02 6,599.24 56.58% - - -
04.03.05.08 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 1,213.62 6.55 7,949.21 124.79 817.37 461.25 3,021.16 - - - - 586.04 3,838.53 48.29% - - -
04.03.05.09 CONCRETO F´C=210 KG/CM2 M3 38.01 642.81 24,433.21 - - 12.01 7,720.02 - - - - 12.01 7,720.02 31.60% - - -
04.03.05.10 EMBOQUILLADO DE PIEDRA E=0.20M(fc=175km/cm2+60%PM) m2 102.22 65.26 6,670.88 - - 31.42 2,050.47 - - - - 31.42 2,050.47 30.74% - - -
04.03.05.11 CONCRETO CICLOPEO FC = 175 KG/CM2 + 30% P.M. M3 30.12 232.64 7,007.12 - - 9.08 2,113.21 - - - - 9.08 2,113.21 30.16% - - -
04.03.05.12 SELLADO DE JUNTA DE DILATACIÓN CON MASILLA ELASTICA 2" M 60.00 21.30 1,278.00 - - - - - - - - - - 0.00% - - -
04.03.06 PASARELA VEHICULAR 02 UND (KM 3+000) 49,483.47
04.03.06.01 LIMPIEZA MANUAL DE TERRENO M2 50.00 2.33 116.50 25.00 58.25 25.00 58.25 - - - - 50.00 116.50 100.00% - - -
04.03.06.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 50.00 6.60 330.00 25.00 165.00 25.00 165.00 - - - - 50.00 330.00 100.00% - - -
04.03.06.03 EXCAVACION MANUAL EN MATERIAL CONGLOMERADO M3 129.60 55.24 7,159.10 25.31 1,398.26 25.04 1,383.21 - - - - 50.35 2,781.47 38.85% - - -
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.06.04 m3 160.00 13.45 2,152.00
11.85 159.39 9.90 133.16 - - - - 21.75 292.54 13.59% - - -
PREPARADO DEL MATERIAL
04.03.06.05 ELIMINACIÓN DE MATERIAL EXCEDENTE D PROMEDIO=30 M. m3 162.00 17.49 2,833.38 16.15 282.54 18.17 317.76 - - - - 34.32 600.30 21.19% - - -
CONCRETO CICLOPEO FC= 140 KG/CM2 + 30%PM CON
04.03.06.06 M3 34.60 356.15 12,322.79
13.46 4,794.56 15.14 5,392.11 - - - - 28.60 10,186.67 82.67% - - -
MEZCLADORA
04.03.06.07 ENCOFRADO Y DESENCOFRADO CARAVISTA EN OBRAS DE ARTE M2 60.00 58.39 3,503.40 30.57 1,784.98 29.43 1,718.42 - - - - 60.00 3,503.40 100.00% - - -
04.03.06.08 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 1,114.64 6.55 7,300.89 521.35 3,414.84 519.95 3,405.64 - - - - 1,041.30 6,820.49 93.42% - - -
04.03.06.09 CONCRETO F´C=210 KG/CM2 M3 12.50 642.81 8,035.13 4.10 2,635.92 4.05 2,603.38 - - - - 8.15 5,239.30 65.20% - - -
04.03.06.10 BARANDA METALICAL DE F°G° DE 2" M 40.80 129.93 5,301.14 - - - - - - - - - - 0.00% - - -
04.03.06.11 PINTURA EPOXICA EN BARANDAS M 10.00 40.89 408.90 - - - - - - - - - - 0.00% - - -
04.03.06.12 JUNTA DE CONSTRUCCIÓN DE TECNOPOR E=1" M 8.00 2.53 20.24 - - - - - - - - - - 0.00% - - -
04.03.07 PASARELA PEATONAL 20 UND 301,137.03
04.03.07.01 LIMPIEZA MANUAL DE TERRENO M2 240.30 2.33 559.90 18.49 43.09 24.03 55.99 - - - - 42.52 99.08 17.70% - - -
FORMATO Nº 03-IF
VALORIZACION FINAL - OBRA PRINCIPAL
(Meta : 148 - 2022)
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (16 FEBRERO AL 31 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 15,786,011.27
EJECUCIÓN AÑO 2022 (META: 148)
METRADO PROGRAMADO DEDUCTIVO DE OBRA
(Exp. Tecnico Saldo de Obra - OBRA PRINCIPAL (R.G.R N°
DEL 16 DE MAYORES OBRAS
ITEM DESCRIPCION R.G.R N° 173-2021-GRA/GG-GRI) DEL 01 DE MAYO AL METRADOS ADICIONALES
TOTAL VALORIZADO
322-2022-GRA/GGR-GRI)
FEBRERO AL 30 DE
20 DE DICIEMBRE
ABRIL
Unid. Metrado P.Unit. P.Parcial METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO % METRADO MONTO %
04.03.07.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 240.30 6.60 1,585.98 18.49 122.06 24.03 158.60 - - - - 42.52 280.65 17.70% - - -
04.03.07.03 EXCAVACION MANUAL EN MATERIAL CONGLOMERADO M3 432.54 55.24 23,893.51 24.79 1,369.62 4.54 250.57 - - - - 29.33 1,620.19 6.78% - - -
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.07.04 m3 384.48 13.45 5,171.26 - - - - - - - - - - 0.00% - - -
PREPARADO DEL MATERIAL
04.03.07.05 ELIMINACIÓN DE MATERIAL EXCEDENTE D PROMEDIO=30 M. m3 768.96 17.49 13,449.11 33.82 591.55 2.84 49.58 - - - - 36.66 641.14 4.77% - - -
CONCRETO CICLOPEO FC= 140 KG/CM2 + 30%PM CON
04.03.07.06 M3 307.94 356.15 109,672.83
9.28 3,304.36 5.18 1,846.28 - - - - 14.46 5,150.64 4.70% - - -
MEZCLADORA
04.03.07.07 ENCOFRADO Y DESENCOFRADO CARAVISTA EN OBRAS DE ARTE M2 433.35 58.39 25,303.31 26.38 1,540.15 31.54 1,841.39 - - - - 57.91 3,381.54 13.36% - - -
04.03.07.08 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 2,742.58 6.55 17,963.90 424.20 2,778.51 197.40 1,292.97 - - - - 621.60 4,071.48 22.66% - - -
04.03.07.09 CONCRETO F´C=210 KG/CM2 M3 60.00 642.81 38,568.60 5.70 3,664.01 3.68 2,365.54 - - - - 9.38 6,029.55 15.63% - - -
04.03.07.10 BARANDA METALICAL DE F°G° DE 2" M 476.00 129.93 61,846.68 - - - - - - - - - - 0.00% - - -
04.03.07.11 PINTURA EPOXICA EN BARANDAS M 71.40 40.89 2,919.55 - - - - - - - - - - 0.00% - - -
04.03.07.12 JUNTA DE CONSTRUCCIÓN DE TECNOPOR E=1" M 80.00 2.53 202.40 - - - - - - - - - - 0.00% - - -
04.03.08 BADEN DE CONCRETO SIMPLE 17 UND 126,578.91
04.03.08.01 BADEN DE CONCRETO SIMPLE 126,578.91
04.03.08.01.01 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 447.70 6.60 2,954.82 - - 285.26 1,882.72 - - - - 285.26 1,882.72 63.72% - - -
04.03.08.01.02 EXCAVACIÓN EN MATERIAL SUELTO, MANUAL m3 237.77 52.45 12,471.04 - - 132.31 6,939.66 - - - - 132.31 6,939.66 55.65% - - -
04.03.08.01.03 COMPACTADO DE LA SUBRASANTE m2 447.70 1.96 877.49 - - 289.94 568.27 - - - - 289.94 568.27 64.76% - - -
04.03.08.01.04 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 117.65 55.02 6,473.10 - - 96.71 5,320.98 - - - - 96.71 5,320.98 82.20% - - -
04.03.08.01.05 CONCRETO F'C=175 KG/CM2 m3 89.54 454.73 40,716.52 - - 57.05 25,943.26 - - - - 57.05 25,943.26 63.72% - - -
CONCRETO CICLOPEO FC= 140 KG/CM2 + 30%PM CON
04.03.08.01.06 M3 166.35 356.15 59,245.55 - - 65.86 23,456.04 - - - - 65.86 23,456.04 39.59% - - -
MEZCLADORA
04.03.08.01.07 SELLADO DE JUNTA DE DILATACIÓN CON MASILLA ELASTICA 2" M 180.30 21.30 3,840.39 - - - - - - - - - - 0.00% - - -
04.03.09 MURO DE CONTENCION TIPO VOLADO 08 UND 292,637.22
04.03.09.01 LIMPIEZA MANUAL DE TERRENO M2 217.53 2.33 506.84 - - 30.00 69.90 - - - - 30.00 69.90 13.79% - - -
04.03.09.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 217.53 6.60 1,435.70 - - 30.00 198.00 - - - - 30.00 198.00 13.79% - - -
04.03.09.03 EXCAVACION MANUAL EN MATERIAL CONGLOMERADO M3 530.34 55.24 29,295.98 - - 105.76 5,842.18 - - - - 105.76 5,842.18 19.94% - - -
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.09.04 m3 300.30 13.45 4,039.04 - - - - - - - - - - 0.00% - - -
PREPARADO DEL MATERIAL
04.03.09.05 SOLADO DE COCRETO 1:12, E=4" M2 155.93 44.77 6,980.99 - - 3.00 134.31 - - - - 3.00 134.31 1.92% - - -
CONCRETO CICLOPEO FC= 140 KG/CM2 + 30%PM CON
04.03.09.06 M3 50.05 356.15 17,825.31 - - 3.60 1,282.14 - - - - 3.60 1,282.14 7.19% - - -
MEZCLADORA
04.03.09.07 ENCOFRADO Y DESENCOFRADO CARAVISTA EN OBRAS DE ARTE M2 277.49 58.39 16,202.64 - - 78.36 4,575.44 - - - - 78.36 4,575.44 28.24% - - -
04.03.09.08 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 11,599.04 6.55 75,973.71 - - 837.79 5,487.50 - - - - 837.79 5,487.50 7.22% - - -
FORMATO Nº 03-IF
VALORIZACION FINAL - OBRA PRINCIPAL
(Meta : 148 - 2022)
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (16 FEBRERO AL 31 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 15,786,011.27
EJECUCIÓN AÑO 2022 (META: 148)
METRADO PROGRAMADO DEDUCTIVO DE OBRA
(Exp. Tecnico Saldo de Obra - OBRA PRINCIPAL (R.G.R N°
DEL 16 DE MAYORES OBRAS
ITEM DESCRIPCION R.G.R N° 173-2021-GRA/GG-GRI) DEL 01 DE MAYO AL METRADOS ADICIONALES
TOTAL VALORIZADO
322-2022-GRA/GGR-GRI)
FEBRERO AL 30 DE
20 DE DICIEMBRE
ABRIL
Unid. Metrado P.Unit. P.Parcial METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO % METRADO MONTO %
04.03.09.09 CONCRETO F´C=210 KG/CM2 M3 216.76 642.81 139,335.50 - - 16.56 10,644.93 - - - - 16.56 10,644.93 7.64% - - -
04.03.09.10 FILTRO DE GRAVA ZARANDEADA Ø 1/2"-3/4" M3 4.62 61.54 284.31 - - - - - - - - - - 0.00% - - -
04.03.09.11 TUBERÍA PERFORADA PVC SAP C-5 Ø 4" M 56.55 13.39 757.20 - - - - - - - - - - 0.00% - - -
04.03.10 MURO DE CONTENCION TIPO GRAVEDAD 24,348.81
04.03.10.01 LIMPIEZA MANUAL DE TERRENO M2 28.80 2.33 67.10 - - - - - - - - - - 0.00% - - -
04.03.10.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 28.80 6.60 190.08 - - - - - - - - - - 0.00% - - -
04.03.10.03 EXCAVACION MANUAL EN MATERIAL CONGLOMERADO M3 43.32 55.24 2,393.00 - - - - - - - - - - 0.00% - - -
04.03.10.04 ELIMINACIÓN DE MATERIAL EXCEDENTE D PROMEDIO=30 M. m3 51.98 17.49 909.13 - - - - - - - - - - 0.00% - - -
04.03.10.05 PERFILADO Y COMPACTADO DE FONDO M2 36.00 5.64 203.04 - - - - - - - - - - 0.00% - - -
04.03.10.06 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 101.28 55.02 5,572.43 - - - - - - - - - - 0.00% - - -
04.03.10.07 CONCRETO CICLOPEO FC = 175 KG/CM2 + 30% P.M. M3 62.04 232.64 14,432.99 - - - - - - - - - - 0.00% - - -
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.10.08 m3 43.20 13.45 581.04 - - - - - - - - - - 0.00% - - -
PREPARADO DEL MATERIAL
05 PLAN DE MANEJO AMBIENTAL 750,924.68
05.01 PROGRAMA DE SUPERVISION Y VIGILANCIA 35,087.50
05.01.01 SUPERVISION Y VIGILANCIA MES 10.00 3,508.75 35,087.50 - - 7.00 24,561.25 - - - - 7.00 24,561.25 70.00% - - -
05.02 PROGRAMA DE SEÑALIZACION 7,148.64
05.02.01 COLOCACION DE SEÑALES INFORMATIVAS AMBIENTALES UND 16.00 446.79 7,148.64 - - 14.00 6,255.06 - - - - 14.00 6,255.06 87.50% - - -
05.03 PROGRAMA DE RECUPERACION MORFOLOGICA 59,827.94
05.03.01 RECUPERACION MORFOLOGICA DE TERRENOS DE CULTIVO M2 31,488.39 1.90 59,827.94 - - 240.00 456.00 - - - - 240.00 456.00 0.76% - - -
CONTROL DE CARCAVAS CON REFORESTACION EN ZONAS
05.04 538,417.62
CRITICAS
05.04.01 TRAZO Y REPLANTEO DURANTE EL PROCESO DE LA OBRA M2 23,005.61 2.32 53,373.02 - - - - - - - - - - 0.00% - - -
05.04.02 COLOCACION DE MADERA ROLLIZO EUCALIPTO DE 3"X2.10 MT UND 3,193.00 12.21 38,986.53 - - - - - - - - - - 0.00% - - -
COLOCACION DE SACOS CON MAT. DE RELLENO EN FORMA DE
05.04.03 UND 28,741.00 8.03 230,790.23 - - - - - - - - - - 0.00% - - -
MURO
05.04.04 COLOCACION DE MADERA CORRIENTE P2 46,703.40 1.99 92,939.77 - - - - - - - - - - 0.00% - - -
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
05.04.05 m3 6,901.68 13.45 92,827.60 - - - - - - - - - - 0.00% - - -
PREPARADO DEL MATERIAL
05.04.06 HOYACION PARA PLANTACION EN MACIZO 0.40X0.40X0.40M UND 2,953.00 3.69 10,896.57 - - - - - - - - - - 0.00% - - -
05.04.07 PLANTACION EN MACIZO UND 2,953.00 6.30 18,603.90 - - - - - - - - - - 0.00% - - -
05.05 PROGRAMA DE ABANDONO DE OBRA 104,332.58
05.05.01 RESTAURACION DE AREA DE CAMPAMENTO M2 500.00 2.94 1,470.00 - - - - - - - - - - 0.00% - - -
FORMATO Nº 03-IF
VALORIZACION FINAL - OBRA PRINCIPAL
(Meta : 148 - 2022)
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (16 FEBRERO AL 31 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 15,786,011.27
EJECUCIÓN AÑO 2022 (META: 148)
METRADO PROGRAMADO DEDUCTIVO DE OBRA
(Exp. Tecnico Saldo de Obra - OBRA PRINCIPAL (R.G.R N°
DEL 16 DE MAYORES OBRAS
ITEM DESCRIPCION R.G.R N° 173-2021-GRA/GG-GRI) DEL 01 DE MAYO AL METRADOS ADICIONALES
TOTAL VALORIZADO
322-2022-GRA/GGR-GRI)
FEBRERO AL 30 DE
20 DE DICIEMBRE
ABRIL
Unid. Metrado P.Unit. P.Parcial METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO % METRADO MONTO %
05.05.02 MANEJO DE DESECHOS (EXCAVACION DE TRINCHERAS) M3 80.00 80.20 6,416.00 - - 40.00 3,208.00 - - - - 40.00 3,208.00 50.00% - - -
05.05.03 ACONDICIONAMIENTO DE MATERIAL EXCEDENTE (DME) M3 88,483.10 1.09 96,446.58 - - 41,762.54 45,521.17 - - - - 41,762.54 45,521.17 47.20% - - -
05.06 PLAN DE CONTINGENCIAS 6,110.40
05.06.01 PLAN DE CONTINGENCIAS E IMPREVISTOS GBL 1.00 6,110.40 6,110.40 - - 1.00 6,110.40 - - - - 1.00 6,110.40 100.00% - - -
06 CAPACITACIÓN EN OPERACIÓN Y MANTENIMIENTO 5,050.00
06.01 FORTALECIMIENTO ORGANIZACIONAL DE LA JUNTA DE USUARIOS GBL 1.00 2,050.00 2,050.00 - - - - - - - - - - 0.00% - - -
06.02 CAPACITACION COMUNAL A LA JUNTA USUSARIA UND 2.00 1,500.00 3,000.00 - - - - - - - - - - 0.00% - - -
07 CONTROL DE CALIDAD 8,887.37
07.01 DISEÑO DE MEZCLA gbl 1.00 590.00 590.00 - - - - - - - - - - 0.00% - - -
07.02 ENSAYO A LA ROTURA DE LAS PROBETAS DE CONCRETO UND 95.00 47.20 4,484.00 - - 75.00 3,540.00 - - - - 75.00 3,540.00 78.95% - - -
ENSAYO DENSIDAD DE CAMPO
07.03 UND 33.00 48.89 1,613.37 - - - - - - - - - - 0.00% - - -
07.04 ENSAYO PRÓCTOR (COMPACTACIÒN DEL SUELO) UND 22.00 100.00 2,200.00 - - - - - - - - - - 0.00% - - -
08 FLETE DE MATERIALES 1,127,006.79
08.01 FLETE TERRESTRE gbl 1.00 ### 288,674.56 0.09 25,980.71 0.23 66,395.15 - - - - 0.32 92,375.86 32.00% - - -
08.02 FLETE RURAL gbl 1.00 ### 838,332.23 0.08 67,066.58 0.31 259,882.99 - - - - 0.39 326,949.57 39.00% - - -
1 COSTO DIRECTO (CD) 14,265,262.69 414,834.97 2,481,561.01 5,997.72 0.00 2,896,395.98 6,165,206.32
2 PORCENTAJE DE AVANCE (%) 2.91% 17.40% 0.00 0.00 20.30% 43.22%
3 GASTOS GENERALES (7.76 %CD) 1,106,984.38 32,191.19 192,569.13 465.42 0.00 224,760.33 478,420.01
4 SUB TOTAL (1) + (3) 15,372,247.07 447,026.16 2,674,130.15 6,463.15 0.00 3,121,156.31 6,643,626.33
5 GASTOS DE SUPERVISION (2.55 % C. D.) 363,764.20 10,578.29 63,279.81 152.94 0.00 73,858.10 157,212.76
6 EXPEDIENTE TÉCNICO 30,000.00 30,000.00 0.00 0.00 0.00 30,000.00 0.00
7 LIQUIDACIÓN DE OBRA 20,000.00 0.00 0.00 0.00 0.00 0.00 0.00
COSTO TOTAL VALORIZADO (4+5+6+7) 15,786,011.27 487,604.45 2,737,409.95 6,616.09 0.00 3,225,014.41 6,800,839.10
FORMATO Nº 03A-IF
VALORIZACION FINAL DE OBRA CON RESPECTO AL EXPEDIENTE TECNICO MATRIZ
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (16 FEBRERO AL 31 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 15,786,011.27
METRADO PROGRAMADO EJECUCIÓN-
EJECUCIÓN AÑO 2022 (META: 148)
(Exp. Tecnico Saldo de Obra - AÑO 2021 TOTAL VALORIZADO SALDO DE OBRA
ITEM DESCRIPCION R.G.R N° 173-2021-GRA/GG-GRI) OBRA PRINCIPAL OBRA PRINCIPAL DEDUCTIVO APROB.
Unid. Metrado P.Unit. P.Parcial METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO % METRADO MONTO %
01 TRABAJOS PRELIMINARES 63,726.29
01.01 CARTEL DE OBRA 3.60 X 2.40 M CON GIGANTOGRAFIA und 1.00 771.40 771.40 1.00 771.40 - - - - 1.00 771.40 100.00% - - 0.00%
01.02 CAMPAMENTO DE TRIPLAY CON TECHO DE CALAMINA DE 7.20X4.80M m2 276.48 101.11 27,954.89 40.00 4,044.40 172.00 17,390.92 - - 212.00 21,435.32 76.68% 64.48 6,519.57 23.32%
01.03 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPOS gbl 1.00 35,000.00 35,000.00 0.18 6,300.00 0.52 18,200.00 - - 0.70 24,500.00 70.00% 0.30 10,500.00 30.00%
02 SEGURIDAD Y SALUD 191,268.06
02.01 EQUIPOS DE PROTECCION INDIVIDUAL 71,590.36
02.01.01 ELAB., IMPLEM.Y ADM. DEL PLAN DE SEGURIDAD Y SALUD DEL TRABAJO GBL 1.00 1,694.88 1,694.88 0.28 474.57 0.72 1,220.31 - - 1.00 1,694.88 100.00% - - 0.00%
02.01.02 TALLER DE CAPACITACION DE SEGURIDAD EN OBRA Tal 10.00 362.56 3,625.60 1.93 699.74 7.07 2,563.30 - - 9.00 3,263.04 90.00% 1.00 362.56 10.00%
02.01.03 EQUIPOS DE PROTECCIÓN PERSONAL gbl 1.00 62,460.00 62,460.00 0.28 17,488.80 0.51 31,854.60 - - 0.79 49,343.40 79.00% 0.21 13,116.60 21.00%
02.01.04 BOTIQUIN DE PRIMEROS AUXILIOS gbl 1.00 380.00 380.00 0.19 72.20 0.81 307.80 - - 1.00 380.00 100.00% - - 0.00%
02.01.05 SEÑALIZACION TEMPORAL DE SEGURIDAD GBL 1.00 1,735.00 1,735.00 0.28 485.80 0.42 728.70 - - 0.70 1,214.50 70.00% 0.30 520.50 30.00%
02.01.06 CAPACITACION EN SEGURIDAD Y SALUD GBL 1.00 1,694.88 1,694.88 0.36 610.16 0.44 745.75 - - 0.80 1,355.91 80.00% 0.20 338.97 20.00%
02.02 PLAN DE VIGILANCIA, PREVENCION Y CONTROL DE COVID 19 119,677.70
02.02.01 LIMPIEZA Y DESINFECCION DE CAMPAMENTO M2 2,000.00 3.47 6,940.00 250.00 867.50 1,200.00 4,164.00 - - 1,450.00 5,031.50 72.50% 550.00 1,908.50 27.50%
02.02.02 SENSIBILIZACION DE LA PREVENCION DEL CONTAGIO COVI-19 EN OBRA UND 12.00 1,888.00 22,656.00 4.00 7,552.00 6.00 11,328.00 - - 10.00 18,880.00 83.33% 2.00 3,776.00 16.67%
02.02.03 PROTECCION PERSONAL EN LA OBRA UND 25,000.00 2.52 63,000.00 3,000.00 7,560.00 11,812.00 29,766.24 - - 14,812.00 37,326.24 59.25% 10,188.00 25,673.76 40.75%
02.02.04 EVALUACION DE DESCARTE UND 300.00 5.75 1,725.00 15.00 86.25 157.00 902.75 - - 172.00 989.00 57.33% 128.00 736.00 42.67%
02.02.05 EVALUACION MEDICA GRUPOS ETAREOS UND 100.00 22.68 2,268.00 0.00 0.00 97.00 2,199.96 - - 97.00 2,199.96 97.00% 3.00 68.04 3.00%
02.02.06 CERTIFICACION DE SINTOMATOLOGIA COVID-19 UND 100.00 85.24 8,524.00 0.00 0.00 97.00 8,268.28 - - 97.00 8,268.28 97.00% 3.00 255.72 3.00%
02.02.07 PANELES INFORMATIVOS COVID-19 UND 12.00 84.00 1,008.00 1.00 84.00 9.00 756.00 - - 10.00 840.00 83.33% 2.00 168.00 16.67%
02.02.08 ZONA DE CONTROL PREVIO DE INGRESO UND 2,500.00 0.44 1,100.00 600.00 264.00 558.00 245.52 - - 1,158.00 509.52 46.32% 1,342.00 590.48 53.68%
02.02.09 ZONA DE CONTROL DE VESTUARIOS, TRABAJO UND 360.00 4.67 1,681.20 60.00 280.20 180.00 840.60 - - 240.00 1,120.80 66.67% 120.00 560.40 33.33%
02.02.10 TRASLADO DE PERSONAL HASTA EL FRENTE DE TRABAJO UND 150.00 3.05 457.50 50.00 152.50 87.00 265.35 - - 137.00 417.85 91.33% 13.00 39.65 8.67%
02.02.11 ZONA DE LAVADO DE MANO UND 25,000.00 0.13 3,250.00 85.00 11.05 14,097.00 1,832.61 - - 14,182.00 1,843.66 56.73% 10,818.00 1,406.34 43.27%
02.02.12 CONTENEDOR DE DESECHOS UND 8.00 5.00 40.00 4.00 20.00 3.00 15.00 - - 7.00 35.00 87.50% 1.00 5.00 12.50%
ZONA DE CONTROL, LIMPIEZA Y DESINFECCION DE MAQUINARIA PESADA Y
02.02.13 UND 200.00 35.14 7,028.00 10.00 351.40 76.00 2,670.64 - - 86.00 3,022.04 43.00% 114.00 4,005.96 57.00%
VEHICULOS
03 REHABILITACION DE LAS ESTRUCTURAS EXISTENTES 3,331,722.16
03.01 REHABILITACION DE BOCATOMA TIPO BARRAJE 629,329.66
03.01.01 DESCOLMATACION DEL VASO NATURAL 97,120.91
DESCOLMATACION Y ACOMODO DE MATERIAL AGUAS ARRIBA DE LA
03.01.01.01 M3 12,372.09 7.85 97,120.91 3,088.00 24,240.80 5,160.00 40,506.00 - - 8,248.00 64,746.80 66.67% 4,124.09 32,374.11 33.33%
BOCATOMA C/MAQ
FORMATO Nº 03A-IF
VALORIZACION FINAL DE OBRA CON RESPECTO AL EXPEDIENTE TECNICO MATRIZ
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (16 FEBRERO AL 31 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 15,786,011.27
METRADO PROGRAMADO EJECUCIÓN-
EJECUCIÓN AÑO 2022 (META: 148)
(Exp. Tecnico Saldo de Obra - AÑO 2021 TOTAL VALORIZADO SALDO DE OBRA
ITEM DESCRIPCION R.G.R N° 173-2021-GRA/GG-GRI) OBRA PRINCIPAL OBRA PRINCIPAL DEDUCTIVO APROB.
Unid. Metrado P.Unit. P.Parcial METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO % METRADO MONTO %
MURO DE CONTENCION TIPO VOLADO L=15 MT km 0+000 (ALERO
03.01.02 89,099.37
IZQUIERDO DE LA BOCATOMA)
03.01.02.01 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 53.25 6.60 351.45 - - - - - - - - 0.00% 53.25 351.45 100.00%
03.01.02.02 EXCAVACIÓN EN MATERIAL SUELTO, MANUAL m3 391.35 52.45 20,526.31 - - - - - - - - 0.00% 391.35 20,526.31 100.00%
03.01.02.03 ELIMINACIÓN DE MATERIAL EXCEDENTE D PROMEDIO=30 M. m3 469.62 17.49 8,213.65 - - - - - - - - 0.00% 469.62 8,213.65 100.00%
03.01.02.04 PERFILADO Y COMPACTADO DE FONDO M2 53.25 5.64 300.33 - - - - - - - - 0.00% 53.25 300.33 100.00%
03.01.02.05 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 169.26 55.02 9,312.69 - - - - - - - - 0.00% 169.26 9,312.69 100.00%
03.01.02.06 CONCRETO F´C=210 KG/CM2 M3 57.68 642.81 37,077.28 - - - - - - - - 0.00% 57.68 37,077.28 100.00%
03.01.02.07 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 1,834.97 6.55 12,019.05 - - - - 1,834.97 12,019.05 1,834.97 12,019.05 100.00% 0.00 0.00 0.00%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
03.01.02.08 m3 88.20 13.45 1,186.29 - - - - - - - - 0.00% 88.20 1,186.29 100.00%
PREPARADO DEL MATERIAL
03.01.02.09 CURADO DE CONCRETO CON ADITIVO QUIMICO M2 36.00 3.12 112.32 - - - - - - - - 0.00% 36.00 112.32 100.00%
MURO DE CONTENCION TIPO VOLADO L=35 ML KM 0+000 (ALERO DERECHO
03.01.03 241,706.70
BOCATOMA)
03.01.03.01 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 163.30 6.60 1,077.78 - - 142.00 937.20 21.30 140.58 163.30 1,077.78 100.00% - - 0.00%
03.01.03.02 EXCAVACIÓN EN MATERIAL SUELTO, MANUAL m3 696.90 52.45 36,552.41 - - 696.90 36,552.41 - - 696.90 36,552.41 100.00% - 0.00 - 0.01 0.00%
03.01.03.03 ELIMINACIÓN DE MATERIAL EXCEDENTE D PROMEDIO=30 M. m3 836.28 17.49 14,626.54 - - 836.28 14,626.54 - - 836.28 14,626.54 100.00% - 0.00 - 0.00 0.00%
03.01.03.04 PERFILADO Y COMPACTADO DE FONDO M2 53.25 5.64 300.33 - - 53.25 300.33 - - 53.25 300.33 100.00% - - 0.00%
03.01.03.05 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 510.26 55.02 28,074.51 - - 444.26 24,443.19 66.00 3,631.32 510.26 28,074.51 100.00% - 0.00 - 0.00 0.00%
03.01.03.06 CONCRETO F´C=210 KG/CM2 M3 176.87 642.81 113,693.80 - - 153.80 98,864.17 23.07 14,829.63 176.87 113,693.80 100.00% 0.00 0.00 0.00%
03.01.03.07 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 5,468.68 6.55 35,819.85 - - - - 5,468.68 35,819.85 5,468.68 35,819.85 100.00% - - 0.00%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
03.01.03.08 m3 833.98 13.45 11,217.03 - - 833.98 11,217.03 - - 833.98 11,217.03 100.00% 0.00 0.00 0.00%
PREPARADO DEL MATERIAL
03.01.03.09 CURADO DE CONCRETO CON ADITIVO QUIMICO M2 110.40 3.12 344.45 - - 110.40 344.45 - - 110.40 344.45 100.00% - 0.00 - 0.00 0.00%
MURO DE CONTENCION TIPO GRAV. L=35 ML(RIO ABAJO DE LA BOCAT.,
03.01.04 62,165.28
MARGEN DER.)
03.01.04.01 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 84.00 6.60 554.40 60.00 396.00 24.00 158.40 - - 84.00 554.40 100.00% - - 0.00%
03.01.04.02 EXCAVACIÓN EN MATERIAL SUELTO, MANUAL m3 306.25 52.45 16,062.81 175.01 9,179.14 131.24 6,883.67 - - 306.25 16,062.81 100.00% 0.00 0.00 0.00%
03.01.04.03 ELIMINACIÓN DE MATERIAL EXCEDENTE D PROMEDIO=30 M. m3 367.50 17.49 6,427.58 210.01 3,673.05 157.49 2,754.53 - - 367.50 6,427.58 100.00% - 0.00 - 0.01 0.00%
03.01.04.04 PERFILADO Y COMPACTADO DE FONDO M2 84.00 5.64 473.76 48.00 270.72 36.00 203.04 - - 84.00 473.76 100.00% - - 0.00%
03.01.04.05 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 214.63 55.02 11,808.94 63.04 3,468.24 151.59 8,340.70 - - 214.63 11,808.94 100.00% 0.00 0.00 0.00%
03.01.04.06 CONCRETO CICLOPEO FC = 175 KG/CM2 + 30% P.M. M3 103.25 232.64 24,020.08 33.41 7,772.50 69.84 16,247.58 - - 103.25 24,020.08 100.00% - - 0.00%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
03.01.04.07 m3 203.00 13.45 2,730.35 20.00 269.00 183.00 2,461.35 - - 203.00 2,730.35 100.00% - - 0.00%
PREPARADO DEL MATERIAL
FORMATO Nº 03A-IF
VALORIZACION FINAL DE OBRA CON RESPECTO AL EXPEDIENTE TECNICO MATRIZ
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (16 FEBRERO AL 31 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 15,786,011.27
METRADO PROGRAMADO EJECUCIÓN-
EJECUCIÓN AÑO 2022 (META: 148)
(Exp. Tecnico Saldo de Obra - AÑO 2021 TOTAL VALORIZADO SALDO DE OBRA
ITEM DESCRIPCION R.G.R N° 173-2021-GRA/GG-GRI) OBRA PRINCIPAL OBRA PRINCIPAL DEDUCTIVO APROB.
Unid. Metrado P.Unit. P.Parcial METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO % METRADO MONTO %
03.01.04.08 CURADO DE CONCRETO CON ADITIVO QUIMICO M2 28.00 3.12 87.36 8.00 24.96 20.00 62.40 - - 28.00 87.36 100.00% - - 0.00%
03.01.05 COMPUERTA METALICA 8,645.34 - - - - - - - - 0.00% - - 0.00%
03.01.05.01 DESMONTAJE DE COMPUERTA METALICA UND 2.00 2,593.59 5,187.18 2.00 5,187.18 - - - - 2.00 5,187.18 100.00% - - 0.00%
03.01.05.02 SUMINISTRO Y COLOCACION DE COMPUERTA METALICA DE 1.10X0.60X1/8" UND 2.00 1,729.08 3,458.16 2.00 3,458.16 - - - - 2.00 3,458.16 100.00% - - 0.00%
03.01.06 REHABILITACION DE LINEA DE TRANSICION DE SALIDA DE LA BOCATOMA 130,174.76
03.01.06.01 DEMOLICIÓN DE CANAL DE CONCRETO DETERIORADO m 18.56 389.95 7,237.47 - - 18.56 7,237.47 - - 18.56 7,237.47 100.00% 0.00 0.00 0.00%
03.01.06.02 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 21.58 55.02 1,187.33 - - 21.58 1,187.33 - - 21.58 1,187.33 100.00% 0.00 0.00 0.00%
03.01.06.03 CONCRETO F´C=210 KG/CM2 M3 120.14 642.81 77,227.19 - - 120.14 77,227.19 - - 120.14 77,227.19 100.00% 0.00 0.00 0.00%
03.01.06.04 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 6,797.37 6.55 44,522.77 - - 5,849.02 38,311.07 - - 5,849.02 38,311.07 86.05% 948.35 6,211.71 13.95%
03.01.07 ENCAUSAMIENTO DE RIO PACCHA 417.30 - - - - - - - - 0.00% - - 0.00%
03.01.07.01 PERFORACION Y DISPARO EN ROCA FIJA M3 30.00 13.91 417.30 30.00 417.30 - - - - 30.00 417.30 100.00% - - 0.00%
03.02 REHABILITACION CANAL RECTANGULAR 139,396.56
03.02.01 DEMOLICIÓN DE CANAL DE CONCRETO DETERIORADO m3 46.71 389.95 18,214.56 46.71 18,214.56 - - - - 46.71 18,214.56 100.00% 0.00 0.00 0.00%
03.02.02 ELIMINACIÓN DE MATERIAL EXCEDENTE D PROMEDIO=30 M. m3 56.05 17.49 980.31 56.05 980.31 - - - - 56.05 980.31 100.00% 0.00 0.00 0.00%
03.02.03 PERFILADO Y COMPACTADO DE FONDO M2 155.70 5.64 878.15 155.70 878.12 - - - - 155.70 878.12 100.00% 0.00 0.03 0.00%
03.02.04 CONCRETO F'C=175 KG/CM2 m3 108.98 454.73 49,556.48 107.60 48,928.95 1.38 627.53 - - 108.98 49,556.48 100.00% - 0.00 - 0.00 0.00%
03.02.05 ENCOFRADO Y DESENCOFRADO DE MUROS EN CANALES m2 817.43 15.27 12,482.16 807.03 12,323.35 10.40 158.81 - - 817.43 12,482.16 100.00% - 0.00 - 0.00 0.00%
03.02.06 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 4,328.01 6.55 28,348.47 4,179.35 27,374.75 148.66 973.72 - - 4,328.01 28,348.47 100.00% - 0.00 - 0.00 0.00%
03.02.07 TARRAJEO CON IMPERMEABILIZANTE E=1.5 CM, M 1:5 m2 389.25 34.35 13,370.74 384.30 13,200.71 4.95 170.03 - - 389.25 13,370.74 100.00% - 0.00 - 0.00 0.00%
03.02.08 SELLADO DE JUNTA DE DILATACIÓN CON MASILLA ELASTICA 2" M 247.80 21.30 5,278.14 168.00 3,578.40 79.80 1,699.74 - - 247.80 5,278.14 100.00% - - 0.00%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
03.02.09 m3 506.03 13.45 6,806.10 499.59 6,719.49 6.44 86.61 - - 506.03 6,806.10 100.00% 0.00 0.00 0.00%
PREPARADO DEL MATERIAL
03.02.10 CURADO DE CONCRETO CON ADITIVO QUIMICO M2 1,115.85 3.12 3,481.45 1,104.84 3,447.10 11.01 34.35 - - 1,115.85 3,481.45 100.00% 0.00 0.00 0.00%
03.03 REHABILITACION DE ALCANTARILLA 196.80
03.03.01 DESCOLMATACION Y ACOMODO DE MAT. DE ARRASTRE, MANUAL M3 10.00 19.68 196.80 5.00 98.40 - - - - 5.00 98.40 50.00% 5.00 98.40 50.00%
03.04 REHABILITACION DE DESARENADOR 9,659.75
03.04.01 MOVIMIENTO DE TIERRAS 593.16
03.04.01.01 DESCOLMATACION Y ACOMODO DE MAT. DE ARRASTRE, MANUAL M3 30.14 19.68 593.16 30.14 593.16 - - - - 30.14 593.16 100.00% - 0.00 - 0.00 0.00%
03.04.02 CANAL DE LIMPIA 4,743.92
03.04.02.01 EXCAVACION MANUAL EN MATERIAL CONGLOMERADO M3 10.80 55.24 596.59 5.00 276.42 2.16 119.10 3.64 201.07 10.80 596.59 100.00% 0.00 0.00 0.00%
03.04.02.02 CONCRETO F´C=175 KG/CM2 M3 6.03 457.58 2,759.21 - - 3.07 1,404.11 2.96 1,355.10 6.03 2,759.21 100.00% - 0.00 - 0.00 0.00%
03.04.02.03 ENCOFRADO Y DESENCOFRADO DE MUROS EN CANALES m2 45.90 15.27 700.89 - - 28.08 428.78 17.82 272.11 45.90 700.89 100.00% - - 0.00%
FORMATO Nº 03A-IF
VALORIZACION FINAL DE OBRA CON RESPECTO AL EXPEDIENTE TECNICO MATRIZ
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (16 FEBRERO AL 31 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 15,786,011.27
METRADO PROGRAMADO EJECUCIÓN-
EJECUCIÓN AÑO 2022 (META: 148)
(Exp. Tecnico Saldo de Obra - AÑO 2021 TOTAL VALORIZADO SALDO DE OBRA
ITEM DESCRIPCION R.G.R N° 173-2021-GRA/GG-GRI) OBRA PRINCIPAL OBRA PRINCIPAL DEDUCTIVO APROB.
Unid. Metrado P.Unit. P.Parcial METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO % METRADO MONTO %
03.04.02.04 SELLADO DE JUNTA DE DILATACIÓN CON MASILLA ELASTICA 2" M 18.08 21.30 385.10 - - - - 6.78 144.41 6.78 144.41 37.50% 11.30 240.69 62.50%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
03.04.02.05 m3 16.20 13.45 217.89 - - 9.72 130.73 6.48 87.16 16.20 217.89 100.00% - - 0.00%
PREPARADO DEL MATERIAL
03.04.02.06 CURADO DE CONCRETO CON ADITIVO QUIMICO M2 27.00 3.12 84.24 - - 16.20 50.54 10.80 33.70 27.00 84.24 100.00% - - 0.00%
03.04.03 COMPUERTA METALICA 4,322.67
03.04.03.01 DESMONTAJE DE COMPUERTA METALICA UND 1.00 2,593.59 2,593.59 1.00 2,593.59 - - - - 1.00 2,593.59 100.00% - - 0.00%
03.04.03.02 SUMINISTRO Y COLOCACION DE COMPUERTA METALICA DE 1.10X0.60X1/8" UND 1.00 1,729.08 1,729.08 1.00 1,729.08 - - - - 1.00 1,729.08 100.00% - - 0.00%
03.05 REHABILITACION DE LA RAPIDA EXISTENTE (L=140.90M) 160,954.70
03.05.01 DEMOLICIÓN DE CANAL DE CONCRETO DETERIORADO m 50.89 389.95 19,844.56 - - 50.89 19,844.56 - - 50.89 19,844.56 100.00% - 0.00 - 0.00 0.00%
03.05.02 ELIMINACIÓN DE MATERIAL EXCEDENTE D PROMEDIO=30 M. m3 61.07 17.49 1,068.11 - - 61.07 1,068.11 - - 61.07 1,068.11 100.00% 0.00 0.00 0.00%
03.05.03 PERFILADO Y COMPACTADO DE FONDO M2 183.17 5.64 1,033.08 - - - - 183.17 1,033.08 183.17 1,033.08 100.00% - 0.00 - 0.00 0.00%
03.05.04 CONCRETO F´C=210 KG/CM2 M3 90.68 642.81 58,290.01 - - - - 90.68 58,290.01 90.68 58,290.01 100.00% 0.00 0.00 0.00%
03.05.05 ENCOFRADO Y DESENCOFRADO DE MUROS EN CANALES m2 733.95 15.27 11,207.42 - - - - 733.95 11,207.42 733.95 11,207.42 100.00% - 0.00 - 0.00 0.00%
03.05.06 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 3,425.22 6.55 22,435.19 - - - - 3,425.22 22,435.19 3,425.22 22,435.19 100.00% 0.00 0.00 0.00%
03.05.07 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE 1:2+SIKA M2 521.33 62.42 32,541.42 - - - - 521.33 32,541.42 521.33 32,541.42 100.00% - 0.00 - 0.00 0.00%
03.05.08 SELLADO DE JUNTA DE DILATACIÓN CON MASILLA ELASTICA 2" M 240.50 21.30 5,122.65 - - - - 240.50 5,122.65 240.50 5,122.65 100.00% - - 0.00%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
03.05.09 m3 457.93 13.45 6,159.16 - - - - 457.93 6,159.16 457.93 6,159.16 100.00% - 0.00 - 0.00 0.00%
PREPARADO DEL MATERIAL
03.05.10 CURADO DE CONCRETO CON ADITIVO QUIMICO M2 1,042.66 3.12 3,253.10 - - - - 1,042.66 3,253.10 1,042.66 3,253.10 100.00% - 0.00 - 0.00 0.00%
03.06 REHABILITACION CANAL TRAPEZOIDAL KM 0+000-6+094 85,800.98
03.06.01 DEMOLICIÓN DE CANAL DE CONCRETO DETERIORADO m 78.44 389.95 30,587.68 6.91 2,695.33 71.53 27,892.35 - - 78.44 30,587.68 100.00% - 0.00 - 0.00 0.00%
03.06.02 TRAZO Y REPLANTEO DURANTE EL PROCESO DE LA OBRA M2 196.10 2.32 454.95 37.20 86.30 158.90 368.65 - - 196.10 454.95 100.00% 0.00 0.00 0.00%
03.06.03 CONCRETO F'C=175 KG/CM2 m3 76.48 454.73 34,777.75 21.33 9,698.48 55.15 25,079.27 - - 76.48 34,777.75 100.00% 0.00 0.00 0.00%
03.06.04 ENCOFRADO Y DESENCOFRADO DE MUROS EN CANALES m2 28.65 15.27 437.49 6.50 99.26 22.15 338.23 - - 28.65 437.49 100.00% - 0.00 - 0.00 0.00%
03.06.05 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE 1:2+SIKA M2 29.24 62.42 1,825.16 6.20 387.00 23.04 1,438.16 - - 29.24 1,825.16 100.00% 0.00 0.00 0.00%
03.06.06 SELLADO DE JUNTA DE DILATACIÓN CON MASILLA ELASTICA 2" M 341.10 21.30 7,265.43 42.25 899.93 298.85 6,365.50 - - 341.10 7,265.43 100.00% - - 0.00%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
03.06.07 m3 431.42 13.45 5,802.60 109.12 1,467.66 322.30 4,334.94 - - 431.42 5,802.60 100.00% - 0.00 - 0.00 0.00%
PREPARADO DEL MATERIAL
03.06.08 CURADO DE CONCRETO CON ADITIVO QUIMICO M2 1,490.36 3.12 4,649.92 161.20 502.94 1,329.16 4,146.98 - - 1,490.36 4,649.92 100.00% 0.00 0.00 0.00%
03.07 TAPA DE CANAL TRAPEZOIDAL L=77 ML 31,985.65
03.07.01 ENCOFRADO Y DESENCOFRADO DE MUROS EN CANALES m2 207.90 15.27 3,174.63 162.00 2,473.74 - - - - 162.00 2,473.74 77.92% 45.90 700.89 22.08%
03.07.02 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 2,037.66 6.55 13,346.67 1,611.47 10,555.10 - - - - 1,611.47 10,555.10 79.08% 426.19 2,791.57 20.92%
03.07.03 CONCRETO F'C=175 KG/CM2 m3 25.27 454.73 11,491.03 20.70 9,412.91 - - - - 20.70 9,412.91 81.92% 4.57 2,078.12 18.08%
FORMATO Nº 03A-IF
VALORIZACION FINAL DE OBRA CON RESPECTO AL EXPEDIENTE TECNICO MATRIZ
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (16 FEBRERO AL 31 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 15,786,011.27
METRADO PROGRAMADO EJECUCIÓN-
EJECUCIÓN AÑO 2022 (META: 148)
(Exp. Tecnico Saldo de Obra - AÑO 2021 TOTAL VALORIZADO SALDO DE OBRA
ITEM DESCRIPCION R.G.R N° 173-2021-GRA/GG-GRI) OBRA PRINCIPAL OBRA PRINCIPAL DEDUCTIVO APROB.
Unid. Metrado P.Unit. P.Parcial METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO % METRADO MONTO %
03.07.04 COLOCACION DE TAPA DE CONCRETO UND 154.00 15.38 2,368.52 120.00 1,845.60 - - - - 120.00 1,845.60 77.92% 34.00 522.92 22.08%
03.07.05 CURADO DE CONCRETO CON ADITIVO QUIMICO M2 514.36 3.12 1,604.80 414.00 1,291.68 - - - - 414.00 1,291.68 80.49% 100.36 313.12 19.51%
03.08 TAPA DE CANAL RECTANGULAR L=293 ML 65,239.75
03.08.01 ENCOFRADO Y DESENCOFRADO DE MUROS EN CANALES m2 527.40 15.27 8,053.40 - - - - 527.40 8,053.40 527.40 8,053.40 100.00% - 0.00 - 0.00 0.00%
03.08.02 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 3,653.53 6.55 23,930.62 - - - - 3,653.53 23,930.62 3,653.53 23,930.62 100.00% 0.00 0.00 0.00%
03.08.03 CONCRETO F'C=175 KG/CM2 m3 46.88 454.73 21,317.74 - - - - 46.88 21,317.74 46.88 21,317.74 100.00% 0.00 0.00 0.00%
03.08.04 COLOCACION DE TAPA DE CONCRETO UND 586.00 15.38 9,012.68 - - - - 586.00 9,012.68 586.00 9,012.68 100.00% - - 0.00%
03.08.05 CURADO DE CONCRETO CON ADITIVO QUIMICO M2 937.60 3.12 2,925.31 - - - - 937.60 2,925.31 937.60 2,925.31 100.00% 0.00 0.00 0.00%
03.09 RESANE DE CANAL TRAPEZOIDAL EXISTENTE KM 0+000-6+094 1,284,285.32
03.09.01 LIMPIEZA DE MUROS, LOSA DE FONDO M2 16,859.20 6.69 112,788.05 - - 13,670.10 91,452.94 - - 13,670.10 91,452.94 81.08% 3,189.10 21,335.11 18.92%
03.09.02 PICADO DE MUROS, LOSA DE FONDO PARA RESANE M2 16,859.20 19.67 331,620.46 - - 984.64 19,367.96 3,594.20 70,697.91 4,578.84 90,065.87 27.16% 12,280.36 241,554.59 72.84%
03.09.03 RESANE DE MUROS, LOSA DE FONDO M2 16,859.20 37.07 624,970.54 - - 984.64 36,500.77 3,594.20 133,236.99 4,578.84 169,737.77 27.16% 12,280.36 455,232.78 72.84%
03.09.04 RESANE DE JUNTA DE DILATACIÓN EN CANAL M 7,223.74 29.75 214,906.27 - - 996.63 29,649.74 - - 996.63 29,649.74 13.80% 6,227.11 185,256.52 86.20%
03.10 REHABILITACION DE DISIPADOR 1,088.16
03.10.01 DESCOLMATACION Y ACOMODO DE MAT. DE ARRASTRE, MANUAL M3 12.00 19.68 236.16 - - 12.00 236.16 - - 12.00 236.16 100.00% - - 0.00%
03.10.02 SELLADO DE JUNTA DE DILATACIÓN CON MASILLA ELASTICA 2" M 40.00 21.30 852.00 - - - - - - - - 0.00% 40.00 852.00 100.00%
03.11 REHABILITACION DE CANOAS 08 UND 19,977.13
DESCOLMATACION Y ACOMODO DE MATERIAL AGUAS ARRIBA DE LA
03.11.01 M3 134.40 7.85 1,055.04 84.00 659.40 - - - - 84.00 659.40 62.50% 50.40 395.64 37.50%
BOCATOMA C/MAQ
03.11.02 EMBOQUILLADO DE PIEDRA E=0.20M(fc=175km/cm2+60%PM) m2 114.00 65.26 7,439.64 - - - - - - - - 0.00% 114.00 7,439.64 100.00%
03.11.03 ENCOFRADO Y DESENCOFRADO DE MUROS EN CANALES m2 269.28 15.27 4,111.91 - - - - - - - - 0.00% 269.28 4,111.91 100.00%
03.11.04 CONCRETO F'C=175 KG/CM2+ PEGAMENTO EPOXICO m3 13.26 549.73 7,289.42 - - - - - - - - 0.00% 13.26 7,289.42 100.00%
03.11.05 CURADO DE CONCRETO CON ADITIVO QUIMICO M2 26.00 3.12 81.12 - - - - - - - - 0.00% 26.00 81.12 100.00%
03.12 REHABILITACION DE MURO DE CONTENCION TIPO CANAL 99,071.81
03.12.01 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 120.00 6.60 792.00 - - - - 120.00 792.00 120.00 792.00 100.00% - - 0.00%
03.12.02 EXCAVACIÓN EN MATERIAL SUELTO, MANUAL m3 174.95 52.45 9,176.13 - - - - 174.95 9,176.13 174.95 9,176.13 100.00% - - 0.00%
03.12.03 ELIMINACIÓN DE MATERIAL EXCEDENTE D PROMEDIO=30 M. m3 209.94 17.49 3,671.85 - - - - 209.94 3,671.85 209.94 3,671.85 100.00% - - 0.00%
03.12.04 PERFILADO Y COMPACTADO DE FONDO M2 120.00 5.64 676.80 - - - - 120.00 676.80 120.00 676.80 100.00% - - 0.00%
03.12.05 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 337.20 55.02 18,552.74 - - - - 337.20 18,552.74 337.20 18,552.74 100.00% - - 0.00%
03.12.06 CONCRETO CICLOPEO FC= 140 KG/CM2 + 30%PM CON MEZCLADORA M3 62.40 356.15 22,223.76 - - - - 62.40 22,223.76 62.40 22,223.76 100.00% - - 0.00%
03.12.07 CONCRETO F´C=210 KG/CM2 M3 11.90 642.81 7,649.44 - - - - 11.90 7,649.44 11.90 7,649.44 100.00% - - 0.00%
03.12.08 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 3,915.25 6.55 25,644.89 - - - - 3,915.25 25,644.89 3,915.25 25,644.89 100.00% - - 0.00%
FORMATO Nº 03A-IF
VALORIZACION FINAL DE OBRA CON RESPECTO AL EXPEDIENTE TECNICO MATRIZ
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (16 FEBRERO AL 31 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 15,786,011.27
METRADO PROGRAMADO EJECUCIÓN-
EJECUCIÓN AÑO 2022 (META: 148)
(Exp. Tecnico Saldo de Obra - AÑO 2021 TOTAL VALORIZADO SALDO DE OBRA
ITEM DESCRIPCION R.G.R N° 173-2021-GRA/GG-GRI) OBRA PRINCIPAL OBRA PRINCIPAL DEDUCTIVO APROB.
Unid. Metrado P.Unit. P.Parcial METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO % METRADO MONTO %
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
03.12.09 m3 83.55 13.45 1,123.75 - - - - 83.55 1,123.75 83.55 1,123.75 100.00% - - 0.00%
PREPARADO DEL MATERIAL
03.12.10 TUBERÍA PERFORADA PVC SAP C-5 Ø 4" M 36.00 13.39 482.04 - - - - 36.00 482.04 36.00 482.04 100.00% - - 0.00%
03.12.11 JUNTA WATER STOP 6" M 48.75 60.24 2,936.70 - - - - 48.75 2,936.70 48.75 2,936.70 100.00% - - 0.00%
03.12.12 DEMOLICIÓN DE CANAL DE CONCRETO DETERIORADO m 15.75 389.95 6,141.71 - - - - 15.75 6,141.71 15.75 6,141.71 100.00% - - 0.00%
03.13 REHABILITACION DE PASE PEATONAL 565.20
DESCOLMATACION Y ACOMODO DE MATERIAL AGUAS ARRIBA DE LA
03.13.01 M3 72.00 7.85 565.20 48.00 376.80 - - - - 48.00 376.80 66.67% 24.00 188.40 33.33%
BOCATOMA C/MAQ
03.14 REHABILITACION DE ACCESO EXISTENTE CANTERA Y CANAL 776,559.93
03.14.01 REHABILITACION PARA ACCESO DE CANTERA 15,101.21
03.14.01.01 TRAZO, NIVELES Y REPLANTEO EN KM KM 0.28 1,161.69 325.27 0.28 325.27 - - - - 0.28 325.27 100.00% 0.00 0.00 0.00%
03.14.01.02 PERFILADO Y COMPACTADO DE PLATAFORMA m2 1,120.00 1.22 1,366.40 600.00 732.00 - - - - 600.00 732.00 53.57% 520.00 634.40 46.43%
03.14.01.03 ESCARIFICADO, PERFILADO Y COMPACTADO SUBRASANTE m2 1,120.00 1.46 1,635.20 600.00 876.00 - - - - 600.00 876.00 53.57% 520.00 759.20 46.43%
03.14.01.04 MATERIAL DE LASTRADO (MAT. ZARANDEO E=0.15 M M3 201.60 46.46 9,366.34 - - - - - - - - 0.00% 201.60 9,366.34 100.00%
03.14.01.05 EXTENDIDO, REGADO Y COMPACTADO E=15 CM M2 1,120.00 2.15 2,408.00 - - - - - - - - 0.00% 1,120.00 2,408.00 100.00%
03.14.02 CONFORMACION DE PLATAFORMA DE SERVICIO KM 0+000 - 16+225 761,458.72
03.14.02.01 PERFILADO Y COMPACTADO DE PLATAFORMA m2 64,900.00 1.22 79,178.00 14,800.00 18,056.00 18,800.00 22,936.00 - - 33,600.00 40,992.00 51.77% 31,300.00 38,186.00 48.23%
03.14.02.02 MATERIAL DE LASTRADO (MAT. ZARANDEO E=0.15 M M3 11,682.00 46.46 542,745.72 1,051.20 48,838.75 2,980.80 138,487.97 - - 4,032.00 187,326.72 34.51% 7,650.00 355,419.00 65.49%
03.14.02.03 EXTENDIDO, REGADO Y COMPACTADO E=15 CM M2 64,900.00 2.15 139,535.00 5,840.00 12,556.00 16,560.00 35,604.00 - - 22,400.00 48,160.00 34.51% 42,500.00 91,375.00 65.49%
03.15 REJILLAS INGRESO DE CANAL CERRADO 540.63
03.15.01 SUM. Y COLOCACION DE REJILLA DE PROTECCION S/DISEÑO UND 3.00 180.21 540.63 - - - - - - - - 0.00% 3.00 540.63 100.00%
03.16 LECHO FILTRANTE 27,070.13
03.16.01 FILTRO CON GRAVA Ø 2"-4" M3 4.50 52.98 238.41 - - - - - - - - 0.00% 4.50 238.41 100.00%
03.16.02 FILTRO CON PIEDRA Ø 4"-6" M3 74.00 112.82 8,348.68 - - - - - - - - 0.00% 74.00 8,348.68 100.00%
03.16.03 TUBERÍA PERFORADA PVC SAP C-5 Ø 2" M 520.00 9.19 4,778.80 - - - - - - - - 0.00% 520.00 4,778.80 100.00%
03.16.04 FILTRO CON PIEDRA Ø 4"-8" M3 132.00 103.82 13,704.24 - - - - - - - - 0.00% 132.00 13,704.24 100.00%
04 SISTEMA DE CONDUCCION CON CANAL ABIERTO KM 6+094 A 16+225 8,786,677.34
04.01 EXPLANACION PLATAFORMA CANAL 1,201,394.55
04.01.01 DESBROCE Y LIMPIEZA m 10,131.00 1.38 13,980.78 - - 4,114.40 5,677.87 - - 4,114.40 5,677.87 40.61% 6,016.60 8,302.91 59.39%
04.01.02 ELIMINACION DE RAICES Y TRONCOS m 10,131.00 2.44 24,719.64 - - 4,114.40 10,039.14 - - 4,114.40 10,039.14 40.61% 6,016.60 14,680.50 59.39%
04.01.03 TRAZO, NIVELES Y REPLANTEO EN KM KM 10.13 1,161.69 11,767.92 - - 4.11 4,779.66 - - 4.11 4,779.66 40.62% 6.02 6,988.26 59.38%
04.01.04 CORTE EN MATERIAL SUELTO C/MAQ M3 6,473.74 2.91 18,838.58 - - 6,473.74 18,838.58 - - 6,473.74 18,838.58 100.00% 0.00 0.00 0.00%
04.01.05 PERFORACION Y DISPARO EN ROCA FIJA M3 8,509.54 13.91 118,367.70 - - 8,509.54 118,367.70 - - 8,509.54 118,367.70 100.00% 0.00 0.00 0.00%
FORMATO Nº 03A-IF
VALORIZACION FINAL DE OBRA CON RESPECTO AL EXPEDIENTE TECNICO MATRIZ
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (16 FEBRERO AL 31 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 15,786,011.27
METRADO PROGRAMADO EJECUCIÓN-
EJECUCIÓN AÑO 2022 (META: 148)
(Exp. Tecnico Saldo de Obra - AÑO 2021 TOTAL VALORIZADO SALDO DE OBRA
ITEM DESCRIPCION R.G.R N° 173-2021-GRA/GG-GRI) OBRA PRINCIPAL OBRA PRINCIPAL DEDUCTIVO APROB.
Unid. Metrado P.Unit. P.Parcial METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO % METRADO MONTO %
04.01.06 EXCAVACION Y DESQUINCHE EN ROCA FIJA M3 8,509.54 12.09 102,880.34 - - 8,509.54 102,880.34 - - 8,509.54 102,880.34 100.00% - 0.00 - 0.00 0.00%
04.01.07 PERFORACION Y DISPARO EN ROCA SUELTA M3 27,562.08 9.78 269,557.14 - - 27,562.08 269,557.14 - - 27,562.08 269,557.14 100.00% 0.00 0.00 0.00%
04.01.08 EXCAVACION Y DESQUINCHE EN ROCA SUELTA M3 27,562.08 6.21 171,160.52 - - 27,562.08 171,160.52 - - 27,562.08 171,160.52 100.00% - 0.00 - 0.00 0.00%
04.01.09 CONFORMACION DE TERRAPLEN CON MATERIAL PROPIO M3 34,035.81 9.00 306,322.29 - - 1,313.48 11,821.32 32,722.33 294,500.97 34,035.81 306,322.29 100.00% - - 0.00%
04.01.10 ELIMINACION DE EXCEDENTE D=> 2KM M3 21,272.68 7.70 163,799.64 - - 21,272.68 163,799.64 - - 21,272.68 163,799.64 100.00% - 0.00 - 0.00 0.00%
04.02 CANAL DE CONCRETO 6,430,783.67
04.02.01 MOVIMIENTO DE TIERRAS 3,454,892.09
04.02.01.01 TRAZO, NIVELACIÓN Y REPLANTEO EJE DE CANAL m 10,496.13 3.74 39,255.53 200.00 748.00 3,245.94 12,139.82 - - 3,445.94 12,887.82 32.83% 7,050.19 26,367.71 67.17%
04.02.01.02 CORTE EN MATERIAL SUELTO C/MAQ M3 29,042.89 2.91 84,514.81 220.00 640.20 1,272.12 3,701.88 22,262.60 64,784.17 23,754.72 69,126.24 81.79% 5,288.17 15,388.57 18.21%
04.02.01.03 PERFORACION Y DISPARO EN ROCA FIJA M3 25,979.77 13.91 361,378.60 80.00 1,112.80 464.75 6,464.61 24,143.82 335,840.54 24,688.57 343,417.94 95.03% 1,291.20 17,960.66 4.97%
04.02.01.04 EXCAVACION Y DESQUINCHE EN ROCA FIJA M3 25,979.77 12.09 314,095.42 - - 464.75 5,618.77 24,143.82 291,898.78 24,608.57 297,517.55 94.72% 1,371.20 16,577.87 5.28%
04.02.01.05 PERFORACION Y DISPARO EN ROCA SUELTA M3 79,736.46 9.78 779,822.58 - - 2,902.11 28,382.66 71,828.80 702,485.66 74,730.91 730,868.33 93.72% 5,005.55 48,954.25 6.28%
04.02.01.06 EXCAVACION Y DESQUINCHE EN ROCA SUELTA M3 79,736.46 6.21 495,163.42 - - 2,902.11 18,022.12 71,828.80 446,056.85 74,730.91 464,078.97 93.72% 5,005.55 31,084.45 6.28%
04.02.01.07 REFINE Y NIVELACIÓN DE SUB RASANTE m2 43,101.22 1.04 44,825.27 - - 11,540.48 12,002.10 - - 11,540.48 12,002.10 26.78% 31,560.74 32,823.17 73.22%
04.02.01.08 COMPACTADO DE LA SUBRASANTE m2 43,101.22 1.96 84,478.39 - - 11,317.32 22,181.95 - - 11,317.32 22,181.95 26.26% 31,783.90 62,296.44 73.74%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.02.01.09 m3 459.77 13.45 6,183.91 - - 459.77 6,183.91 - - 459.77 6,183.91 100.00% - 0.00 - 0.00 0.00%
PREPARADO DEL MATERIAL
04.02.01.10 ELIMINACION DE EXCEDENTE D=> 2KM M3 ### 7.70 1,245,174.16 - - 5,361.25 41,281.59 142,447.95 1,096,849.22 147,809.20 1,138,130.80 91.40% 13,901.73 107,043.36 8.60%
04.02.02 CONCRETO SIMPLE 2,308,635.55
04.02.02.01 ENCOFRADO Y DESENCOFRADO DE MUROS EN CANALES m2 1,108.35 15.27 16,924.50 - - 151.91 2,319.66 956.44 14,604.84 1,108.35 16,924.50 100.00% 0.00 0.00 0.00%
04.02.02.02 CONCRETO F'C=175 KG/CM2 m3 4,174.45 454.73 1,898,247.65 - - 156.61 71,215.27 4,017.84 1,827,032.38 4,174.45 1,898,247.65 100.00% - 0.00 - 0.00 0.00%
04.02.02.03 SELLADO DE JUNTA DE DILATACIÓN CON MASILLA ELASTICA 2" M 18,472.46 21.30 393,463.40 - - 697.36 14,853.77 17,775.10 378,609.63 18,472.46 393,463.40 100.00% - 0.00 - 0.00 0.00%
04.02.03 TAPA DE CANAL TRAPEZOIDAL L=1,012 ML 531,535.22
04.02.03.01 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 2,732.40 55.02 150,336.65 - - - - - - - - 0.00% 2,732.40 150,336.65 100.00%
04.02.03.02 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 26,759.46 6.55 175,274.46 - - - - - - - - 0.00% 26,759.46 175,274.46 100.00%
04.02.03.03 CONCRETO F'C=175 KG/CM2 m3 338.01 454.73 153,703.29 - - - - - - - - 0.00% 338.01 153,703.29 100.00%
04.02.03.04 COLOCACION DE TAPA DE CONCRETO UND 2,024.00 15.38 31,129.12 - - - - - - - - 0.00% 2,024.00 31,129.12 100.00%
04.02.03.05 CURADO DE CONCRETO CON ADITIVO QUIMICO M2 6,760.16 3.12 21,091.70 - - - - - - - - 0.00% 6,760.16 21,091.70 100.00%
04.02.04 PUENTE CANAL KM 8+420 A 8+480 135,720.81
04.02.04.01 CONCRETO ARMADO 118,067.23
04.02.04.01 EXCAVACIÓN EN MATERIAL SUELTO, MANUAL m3 94.96 52.45 4,980.65 - - - - 94.96 4,980.65 94.96 4,980.65 100.00% 0.00 0.00 0.00%
04.02.04.01 REFINE Y NIVELACIÓN DE SUB RASANTE m2 30.94 1.04 32.18 - - - - 30.94 32.18 30.94 32.18 100.00% - 0.00 - 0.00 -0.01%
04.02.04.01 COMPACTADO DE LA SUBRASANTE m2 30.94 1.96 60.64 - - - - 30.94 60.64 30.94 60.64 100.00% 0.00 0.00 0.00%
FORMATO Nº 03A-IF
VALORIZACION FINAL DE OBRA CON RESPECTO AL EXPEDIENTE TECNICO MATRIZ
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (16 FEBRERO AL 31 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 15,786,011.27
METRADO PROGRAMADO EJECUCIÓN-
EJECUCIÓN AÑO 2022 (META: 148)
(Exp. Tecnico Saldo de Obra - AÑO 2021 TOTAL VALORIZADO SALDO DE OBRA
ITEM DESCRIPCION R.G.R N° 173-2021-GRA/GG-GRI) OBRA PRINCIPAL OBRA PRINCIPAL DEDUCTIVO APROB.
Unid. Metrado P.Unit. P.Parcial METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO % METRADO MONTO %
04.02.04.01 CONCRETO CICLOPEO FC = 175 KG/CM2 + 30% P.M. M3 95.44 232.64 22,203.16 - - - - 95.44 22,203.16 95.44 22,203.16 100.00% 0.00 0.00 0.00%
04.02.04.01 CONCRETO F'C=175 KG/CM2 m3 61.20 454.73 27,829.48 - - - - 61.20 27,829.48 61.20 27,829.48 100.00% - 0.00 - 0.00 0.00%
04.02.04.01 ENCOFRADO Y DESENCOFRADO CARAVISTA EN OBRAS DE ARTE M2 402.00 58.39 23,472.78 - - - - 402.00 23,472.78 402.00 23,472.78 100.00% - - 0.00%
04.02.04.01 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 2,688.51 6.55 17,609.74 - - - - 2,688.51 17,609.74 2,688.51 17,609.74 100.00% 0.00 0.00 0.00%
04.02.04.01 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE 1:2+SIKA M2 252.00 62.42 15,729.84 - - - - 252.00 15,729.84 252.00 15,729.84 100.00% - - 0.00%
04.02.04.01 JUNTA WATER STOP 6" M 23.10 60.24 1,391.54 - - - - 23.10 1,391.54 23.10 1,391.54 100.00% 0.00 0.00 0.00%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.02.04.01 m3 234.00 13.45 3,147.30 - - - - 234.00 3,147.30 234.00 3,147.30 100.00% - - 0.00%
PREPARADO DEL MATERIAL
04.02.04.01 CURADO DE CONCRETO CON ADITIVO QUIMICO M2 516.00 3.12 1,609.92 - - - - 516.00 1,609.92 516.00 1,609.92 100.00% - - 0.00%
04.02.04.02 TAPA DE CANAL RECTANGULAR KM 8+420 A 8+480 17,653.58
04.02.04.02 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 108.00 55.02 5,942.16 - - - - 108.00 5,942.16 108.00 5,942.16 100.00% - - 0.00%
04.02.04.02 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 748.30 6.55 4,901.37 - - - - 748.30 4,901.37 748.30 4,901.37 100.00% - 0.00 - 0.01 0.00%
04.02.04.02 CONCRETO F'C=175 KG/CM2 m3 9.60 454.73 4,365.41 - - - - 9.60 4,365.41 9.60 4,365.41 100.00% - 0.00 - 0.00 0.00%
04.02.04.02 COLOCACION DE TAPA DE CONCRETO UND 120.00 15.38 1,845.60 - - - - 120.00 1,845.60 120.00 1,845.60 100.00% - - 0.00%
04.02.04.02 CURADO DE CONCRETO CON ADITIVO QUIMICO M2 192.00 3.12 599.04 - - - - 192.00 599.04 192.00 599.04 100.00% - - 0.00%
04.03 OBRAS DE ARTE EN CANAL DE CONCRETO 1,154,499.12
04.03.01 ALCANTARILLA DE CºAº TIPO I, (3 UND) 64,317.86
04.03.01.01 LIMPIEZA MANUAL DE TERRENO M2 109.50 2.33 255.14 - - 73.00 170.09 - - 73.00 170.09 66.67% 36.50 85.04 33.33%
04.03.01.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 109.50 6.60 722.70 - - 73.00 481.80 - - 73.00 481.80 66.67% 36.50 240.90 33.33%
04.03.01.03 EXCAVACIÓN EN MATERIAL SUELTO, MANUAL m3 209.52 52.45 10,989.32 - - 139.64 7,324.33 - - 139.64 7,324.33 66.65% 69.88 3,665.00 33.35%
04.03.01.04 RELLENO Y COMPACTADO CON MATERIAL SELECCIONADO M3 9.08 16.29 147.91 - - 6.12 99.69 - - 6.12 99.69 67.40% 2.96 48.22 32.60%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.01.05 m3 40.79 13.45 548.63 - - 27.18 365.52 - - 27.18 365.52 66.62% 13.61 183.11 33.38%
PREPARADO DEL MATERIAL
04.03.01.06 ELIMINACIÓN DE MATERIAL EXCEDENTE D PROMEDIO=30 M. m3 251.42 17.49 4,397.34 - - 167.57 2,930.85 - - 167.57 2,930.85 66.65% 83.85 1,466.49 33.35%
04.03.01.07 SOLADO DE COCRETO 1:12, E=4" M2 62.49 44.77 2,797.68 - - 41.61 1,862.97 - - 41.61 1,862.97 66.59% 20.88 934.71 33.41%
04.03.01.08 CONCRETO CICLOPEO FC= 140 KG/CM2 + 30%PM CON MEZCLADORA M3 4.72 356.15 1,681.03 - - 2.59 923.14 - - 2.59 923.14 54.92% 2.13 757.89 45.08%
04.03.01.09 EMBOQUILLADO DE PIEDRA E=0.20M(fc=175km/cm2+60%PM) m2 9.30 65.26 606.92 - - 6.20 404.61 - - 6.20 404.61 66.67% 3.10 202.31 33.33%
04.03.01.10 CONCRETO F´C=210 KG/CM2 M3 33.44 642.81 21,495.57 - - 21.99 14,136.68 - - 21.99 14,136.68 65.77% 11.45 7,358.89 34.23%
04.03.01.11 ENCOFRADO Y DESENCOFRADO CARAVISTA EN OBRAS DE ARTE M2 210.54 58.39 12,293.43 - - 140.20 8,186.28 - - 140.20 8,186.28 66.59% 70.34 4,107.15 33.41%
04.03.01.12 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 1,256.31 6.55 8,228.83 - - 1,217.83 7,976.78 - - 1,217.83 7,976.78 96.94% 38.48 252.05 3.06%
04.03.01.13 SELLADO DE JUNTA DE DILATACIÓN CON MASILLA ELASTICA 2" M 7.20 21.30 153.36 - - - - - - - - 0.00% 7.20 153.36 100.00%
04.03.02 TOMAS PREDIALES 31 UND, KM 0+000-13+220 67,424.71
04.03.02.01 TOMA PREDIAL TIPO I, 21 UND 25,684.34
FORMATO Nº 03A-IF
VALORIZACION FINAL DE OBRA CON RESPECTO AL EXPEDIENTE TECNICO MATRIZ
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (16 FEBRERO AL 31 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 15,786,011.27
METRADO PROGRAMADO EJECUCIÓN-
EJECUCIÓN AÑO 2022 (META: 148)
(Exp. Tecnico Saldo de Obra - AÑO 2021 TOTAL VALORIZADO SALDO DE OBRA
ITEM DESCRIPCION R.G.R N° 173-2021-GRA/GG-GRI) OBRA PRINCIPAL OBRA PRINCIPAL DEDUCTIVO APROB.
Unid. Metrado P.Unit. P.Parcial METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO % METRADO MONTO %
04.03.02.01 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 15.71 6.60 103.69 - - 15.71 103.69 - - 15.71 103.69 100.00% - 0.00 - 0.00 0.00%
04.03.02.01 EXCAVACIÓN EN MATERIAL SUELTO, MANUAL m3 10.16 52.45 532.89 - - 10.16 532.89 - - 10.16 532.89 100.00% 0.00 0.00 0.00%
04.03.02.01 REFINE Y NIVELACIÓN DE SUB RASANTE m2 7.31 1.04 7.60 - - 7.31 7.60 - - 7.31 7.60 100.00% 0.00 0.00 0.03%
04.03.02.01 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 20.83 55.02 1,146.07 - - 20.83 1,146.07 - - 20.83 1,146.07 100.00% - 0.00 - 0.00 0.00%
04.03.02.01 CONCRETO F´C=210 KG/CM2 M3 5.22 642.81 3,355.47 - - 4.24 2,725.05 - - 4.24 2,725.05 81.21% 0.98 630.42 18.79%
04.03.02.01 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 104.57 6.55 684.93 - - 81.78 535.66 - - 81.78 535.66 78.21% 22.79 149.27 21.79%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.02.01 m3 13.36 13.45 179.69 - - 13.36 179.69 - - 13.36 179.69 100.00% 0.00 0.00 0.00%
PREPARADO DEL MATERIAL
04.03.02.01 TARRAJEO CON IMPERMEABILIZANTE E=1.5 CM, M 1:5 m2 22.93 34.35 787.65 - - 22.93 787.65 - - 22.93 787.65 100.00% - 0.00 - 0.00 0.00%
04.03.02.01 INSTALACIÓN DE COMPUERTA METÁLICA EN TOMA PARCELARIA und 21.00 899.35 18,886.35 - - 16.00 14,389.60 - - 16.00 14,389.60 76.19% 5.00 4,496.75 23.81%
04.03.02.02 TOMA PREDIAL TIPO II, 08 UND 31,270.87
04.03.02.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 13.50 6.60 89.10 - - - - - - - - 0.00% 13.50 89.10 100.00%
04.03.02.02 EXCAVACIÓN EN MATERIAL SUELTO, MANUAL m3 20.39 52.45 1,069.46 - - - - - - - - 0.00% 20.39 1,069.46 100.00%
04.03.02.02 REFINE Y NIVELACIÓN DE SUB RASANTE m2 13.50 1.04 14.04 - - - - - - - - 0.00% 13.50 14.04 100.00%
04.03.02.02 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 85.77 55.02 4,719.07 - - - - - - - - 0.00% 85.77 4,719.07 100.00%
04.03.02.02 CONCRETO F´C=210 KG/CM2 M3 8.76 642.81 5,631.02 - - - - - - - - 0.00% 8.76 5,631.02 100.00%
04.03.02.02 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 245.68 6.55 1,609.20 - - - - - - - - 0.00% 245.68 1,609.20 100.00%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.02.02 m3 124.80 13.45 1,678.56 - - - - - - - - 0.00% 124.80 1,678.56 100.00%
PREPARADO DEL MATERIAL
04.03.02.02 TARRAJEO CON IMPERMEABILIZANTE E=1.5 CM, M 1:5 m2 41.78 34.35 1,435.14 - - - - - - - - 0.00% 41.78 1,435.14 100.00%
04.03.02.02 SUM. Y COLOC. DE COMP. MET. DE 1.33, 0.25X0.42X 1/8", SEGUN DISEÑO UND 16.00 939.08 15,025.28 - - - - - - - - 0.00% 16.00 15,025.28 100.00%
04.03.02.03 TOMA PREDIAL TIPO III, 02 UNID 10,469.50
04.03.02.03 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 6.06 6.60 40.00 - - - - - - - - 0.00% 6.06 40.00 99.99%
04.03.02.03 EXCAVACIÓN EN MATERIAL SUELTO, MANUAL m3 8.42 52.45 441.63 - - - - - - - - 0.00% 8.42 441.63 100.00%
04.03.02.03 REFINE Y NIVELACIÓN DE SUB RASANTE m2 6.06 1.04 6.30 - - - - - - - - 0.00% 6.06 6.30 100.04%
04.03.02.03 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 26.69 55.02 1,468.48 - - - - - - - - 0.00% 26.69 1,468.48 100.00%
04.03.02.03 CONCRETO F'C=175 KG/CM2 m3 3.04 454.73 1,382.38 - - - - - - - - 0.00% 3.04 1,382.38 100.00%
04.03.02.03 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 82.82 6.55 542.47 - - - - - - - - 0.00% 82.82 542.47 100.00%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.02.03 m3 33.36 13.45 448.69 - - - - - - - - 0.00% 33.36 448.69 100.00%
PREPARADO DEL MATERIAL
04.03.02.03 TARRAJEO CON IMPERMEABILIZANTE E=1.5 CM, M 1:5 m2 14.65 34.35 503.23 - - - - - - - - 0.00% 14.65 503.23 100.00%
04.03.02.03 SUM. Y COLOC. DE COMP. MET. DE 1.33, 0.70X0.70X 1/8", SEGUN DISEÑO UND 4.00 1,409.08 5,636.32 - - - - - - - - 0.00% 4.00 5,636.32 100.00%
04.03.03 TOMAS DE DESFOGUE 09 UND 69,308.26
FORMATO Nº 03A-IF
VALORIZACION FINAL DE OBRA CON RESPECTO AL EXPEDIENTE TECNICO MATRIZ
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (16 FEBRERO AL 31 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 15,786,011.27
METRADO PROGRAMADO EJECUCIÓN-
EJECUCIÓN AÑO 2022 (META: 148)
(Exp. Tecnico Saldo de Obra - AÑO 2021 TOTAL VALORIZADO SALDO DE OBRA
ITEM DESCRIPCION R.G.R N° 173-2021-GRA/GG-GRI) OBRA PRINCIPAL OBRA PRINCIPAL DEDUCTIVO APROB.
Unid. Metrado P.Unit. P.Parcial METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO % METRADO MONTO %
04.03.03.01 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 5.40 6.60 35.64 - - 5.40 35.64 - - 5.40 35.64 100.00% - - 0.00%
04.03.03.02 EXCAVACIÓN EN MATERIAL SUELTO, MANUAL m3 120.39 52.45 6,314.46 - - 75.32 3,950.67 - - 75.32 3,950.67 62.57% 45.07 2,363.78 37.43%
04.03.03.03 REFINE Y NIVELACIÓN DE SUB RASANTE m2 92.61 1.04 96.31 - - 54.99 57.19 - - 54.99 57.19 59.38% 37.62 39.12 40.62%
04.03.03.04 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 542.97 55.02 29,874.21 - - 128.54 7,072.16 - - 128.54 7,072.16 23.67% 414.43 22,802.05 76.33%
04.03.03.05 CONCRETO F'C=175 KG/CM2 m3 49.12 454.73 22,336.34 - - 17.11 7,779.41 - - 17.11 7,779.41 34.83% 32.01 14,556.92 65.17%
04.03.03.06 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 44.82 6.55 293.57 - - 44.82 293.57 - - 44.82 293.57 100.00% 0.00 0.00 0.00%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.03.07 m3 118.75 13.45 1,597.19 - - 45.99 618.51 - - 45.99 618.51 38.72% 72.76 978.68 61.28%
PREPARADO DEL MATERIAL
04.03.03.08 TARRAJEO CON IMPERMEABILIZANTE E=1.5 CM, M 1:5 m2 19.40 34.35 666.39 - - 19.40 666.39 - - 19.40 666.39 100.00% - - 0.00%
04.03.03.09 INSTALACIÓN DE COMPUERTA METÁLICA EN TOMA PARCELARIA und 9.00 899.35 8,094.15 - - 4.00 3,597.40 - - 4.00 3,597.40 44.44% 5.00 4,496.75 55.56%
04.03.04 CANOA TIPO I, 06 UND (2.20 X 3.95 MT) 69,439.69
04.03.04.01 LIMPIEZA MANUAL DE TERRENO M2 183.78 2.33 428.21 30.63 71.37 - - - - 30.63 71.37 16.67% 153.15 356.84 83.33%
04.03.04.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 245.40 6.60 1,619.64 40.90 269.94 - - - - 40.90 269.94 16.67% 204.50 1,349.70 83.33%
04.03.04.03 EXCAVACION MANUAL EN MATERIAL CONGLOMERADO M3 110.47 55.24 6,102.36 14.48 799.76 - - - - 14.48 799.76 13.11% 95.99 5,302.60 86.89%
04.03.04.04 ELIMINACIÓN DE MATERIAL EXCEDENTE D PROMEDIO=30 M. m3 138.09 17.49 2,415.19 18.10 316.57 - - - - 18.10 316.57 13.11% 119.99 2,098.62 86.89%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.04.05 m3 40.02 13.45 538.27 6.67 89.71 - - - - 6.67 89.71 16.67% 33.35 448.56 83.33%
PREPARADO DEL MATERIAL
04.03.04.06 CONCRETO CICLOPEO FC= 140 KG/CM2 + 30%PM CON MEZCLADORA M3 42.24 356.15 15,043.78 7.04 2,507.30 - - - - 7.04 2,507.30 16.67% 35.20 12,536.48 83.33%
04.03.04.07 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 119.94 55.02 6,599.10 19.99 1,099.85 - - - - 19.99 1,099.85 16.67% 99.95 5,499.25 83.33%
04.03.04.08 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 1,404.36 6.55 9,198.56 234.06 1,533.09 - - - - 234.06 1,533.09 16.67% 1,170.30 7,665.47 83.33%
04.03.04.09 CONCRETO F'C=175 KG/CM2 m3 26.16 454.73 11,895.74 4.36 1,982.62 - - - - 4.36 1,982.62 16.67% 21.80 9,913.12 83.33%
04.03.04.10 EMBOQUILLADO DE PIEDRA E=0.20M(fc=175km/cm2+60%PM) m2 125.94 65.26 8,218.84 20.99 1,369.81 - - - - 20.99 1,369.81 16.67% 104.95 6,849.03 83.33%
04.03.04.11 CONCRETO CICLOPEO FC = 175 KG/CM2 + 30% P.M. M3 25.68 232.64 5,974.20 4.28 995.70 - - - - 4.28 995.70 16.67% 21.40 4,978.50 83.33%
04.03.04.12 SELLADO DE JUNTA DE DILATACIÓN CON MASILLA ELASTICA 2" M 66.00 21.30 1,405.80 - - - - - - - - 0.00% 66.00 1,405.80 100.00%
04.03.05 CANOA TIPO II 04 UND (2.70 X 4.45 MT) 89,823.16
04.03.05.01 LIMPIEZA MANUAL DE TERRENO M2 135.92 2.33 316.69 - - 106.71 248.62 - - 106.71 248.62 78.51% 29.21 68.07 21.49%
04.03.05.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 190.88 6.60 1,259.81 - - 106.71 704.25 - - 106.71 704.25 55.90% 84.17 555.55 44.10%
04.03.05.03 EXCAVACION MANUAL EN MATERIAL CONGLOMERADO M3 147.02 55.24 8,121.38 - - 59.56 3,289.90 - - 59.56 3,289.90 40.51% 87.46 4,831.49 59.49%
04.03.05.04 ELIMINACIÓN DE MATERIAL EXCEDENTE D PROMEDIO=30 M. m3 183.78 17.49 3,214.31 - - 74.45 1,302.05 - - 74.45 1,302.05 40.51% 109.33 1,912.26 59.49%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.05.05 m3 53.81 13.45 723.74 - - 6.16 82.85 - - 6.16 82.85 11.45% 47.65 640.89 88.55%
PREPARADO DEL MATERIAL
04.03.05.06 CONCRETO CICLOPEO FC= 140 KG/CM2 + 30%PM CON MEZCLADORA M3 48.25 356.15 17,184.24 - - 25.89 9,218.94 - - 25.89 9,218.94 53.65% 22.37 7,965.29 46.35%
04.03.05.07 ENCOFRADO Y DESENCOFRADO CARAVISTA EN OBRAS DE ARTE M2 199.77 58.39 11,664.57 - - 113.02 6,599.24 - - 113.02 6,599.24 56.58% 86.75 5,065.33 43.42%
FORMATO Nº 03A-IF
VALORIZACION FINAL DE OBRA CON RESPECTO AL EXPEDIENTE TECNICO MATRIZ
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (16 FEBRERO AL 31 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 15,786,011.27
METRADO PROGRAMADO EJECUCIÓN-
EJECUCIÓN AÑO 2022 (META: 148)
(Exp. Tecnico Saldo de Obra - AÑO 2021 TOTAL VALORIZADO SALDO DE OBRA
ITEM DESCRIPCION R.G.R N° 173-2021-GRA/GG-GRI) OBRA PRINCIPAL OBRA PRINCIPAL DEDUCTIVO APROB.
Unid. Metrado P.Unit. P.Parcial METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO % METRADO MONTO %
04.03.05.08 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 1,213.62 6.55 7,949.21 - - 586.04 3,838.53 - - 586.04 3,838.53 48.29% 627.58 4,110.68 51.71%
04.03.05.09 CONCRETO F´C=210 KG/CM2 M3 38.01 642.81 24,433.21 - - 12.01 7,720.02 - - 12.01 7,720.02 31.60% 26.00 16,713.19 68.40%
04.03.05.10 EMBOQUILLADO DE PIEDRA E=0.20M(fc=175km/cm2+60%PM) m2 102.22 65.26 6,670.88 - - 31.42 2,050.47 - - 31.42 2,050.47 30.74% 70.80 4,620.41 69.26%
04.03.05.11 CONCRETO CICLOPEO FC = 175 KG/CM2 + 30% P.M. M3 30.12 232.64 7,007.12 - - 9.08 2,113.21 - - 9.08 2,113.21 30.16% 21.04 4,893.91 69.84%
04.03.05.12 SELLADO DE JUNTA DE DILATACIÓN CON MASILLA ELASTICA 2" M 60.00 21.30 1,278.00 - - - - - - - - 0.00% 60.00 1,278.00 100.00%
04.03.06 PASARELA VEHICULAR 02 UND (KM 3+000) 49,483.47
04.03.06.01 LIMPIEZA MANUAL DE TERRENO M2 50.00 2.33 116.50 - - 50.00 116.50 - - 50.00 116.50 100.00% - - 0.00%
04.03.06.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 50.00 6.60 330.00 - - 50.00 330.00 - - 50.00 330.00 100.00% - - 0.00%
04.03.06.03 EXCAVACION MANUAL EN MATERIAL CONGLOMERADO M3 129.60 55.24 7,159.10 - - 50.35 2,781.47 - - 50.35 2,781.47 38.85% 79.25 4,377.63 61.15%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.06.04 m3 160.00 13.45 2,152.00 - - 21.75 292.54 - - 21.75 292.54 13.59% 138.25 1,859.46 86.41%
PREPARADO DEL MATERIAL
04.03.06.05 ELIMINACIÓN DE MATERIAL EXCEDENTE D PROMEDIO=30 M. m3 162.00 17.49 2,833.38 - - 34.32 600.30 - - 34.32 600.30 21.19% 127.68 2,233.08 78.81%
04.03.06.06 CONCRETO CICLOPEO FC= 140 KG/CM2 + 30%PM CON MEZCLADORA M3 34.60 356.15 12,322.79 - - 28.60 10,186.67 - - 28.60 10,186.67 82.67% 6.00 2,136.12 17.33%
04.03.06.07 ENCOFRADO Y DESENCOFRADO CARAVISTA EN OBRAS DE ARTE M2 60.00 58.39 3,503.40 - - 60.00 3,503.40 - - 60.00 3,503.40 100.00% - - 0.00%
04.03.06.08 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 1,114.64 6.55 7,300.89 - - 1,041.30 6,820.49 - - 1,041.30 6,820.49 93.42% 73.34 480.41 6.58%
04.03.06.09 CONCRETO F´C=210 KG/CM2 M3 12.50 642.81 8,035.13 - - 8.15 5,239.30 - - 8.15 5,239.30 65.20% 4.35 2,795.82 34.79%
04.03.06.10 BARANDA METALICAL DE F°G° DE 2" M 40.80 129.93 5,301.14 - - - - - - - - 0.00% 40.80 5,301.14 100.00%
04.03.06.11 PINTURA EPOXICA EN BARANDAS M 10.00 40.89 408.90 - - - - - - - - 0.00% 10.00 408.90 100.00%
04.03.06.12 JUNTA DE CONSTRUCCIÓN DE TECNOPOR E=1" M 8.00 2.53 20.24 - - - - - - - - 0.00% 8.00 20.24 100.00%
04.03.07 PASARELA PEATONAL 20 UND 301,137.03
04.03.07.01 LIMPIEZA MANUAL DE TERRENO M2 240.30 2.33 559.90 29.57 68.89 42.52 99.08 - - 72.09 167.97 30.00% 168.21 391.93 70.00%
04.03.07.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 240.30 6.60 1,585.98 29.57 195.13 42.52 280.65 - - 72.09 475.78 30.00% 168.21 1,110.20 70.00%
04.03.07.03 EXCAVACION MANUAL EN MATERIAL CONGLOMERADO M3 432.54 55.24 23,893.51 20.70 1,143.22 29.33 1,620.19 - - 50.03 2,763.41 11.57% 382.51 21,130.10 88.43%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.07.04 m3 384.48 13.45 5,171.26 11.83 159.06 - - - - 11.83 159.06 3.08% 372.65 5,012.20 96.92%
PREPARADO DEL MATERIAL
04.03.07.05 ELIMINACIÓN DE MATERIAL EXCEDENTE D PROMEDIO=30 M. m3 768.96 17.49 13,449.11 14.78 258.55 36.66 641.14 - - 51.44 899.69 6.69% 717.52 12,549.42 93.31%
04.03.07.06 CONCRETO CICLOPEO FC= 140 KG/CM2 + 30%PM CON MEZCLADORA M3 307.94 356.15 109,672.83 14.20 5,057.33 14.46 5,150.64 - - 28.66 10,207.97 9.31% 279.28 99,464.86 90.69%
04.03.07.07 ENCOFRADO Y DESENCOFRADO CARAVISTA EN OBRAS DE ARTE M2 433.35 58.39 25,303.31 13.80 805.61 57.91 3,381.54 - - 71.71 4,187.15 16.55% 361.64 21,116.16 83.45%
04.03.07.08 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 2,742.58 6.55 17,963.90 137.00 897.35 621.60 4,071.48 - - 758.60 4,968.83 27.66% 1,983.98 12,995.07 72.34%
04.03.07.09 CONCRETO F´C=210 KG/CM2 M3 60.00 642.81 38,568.60 1.97 1,266.34 9.38 6,029.55 - - 11.35 7,295.89 18.92% 48.65 31,272.71 81.08%
04.03.07.10 BARANDA METALICAL DE F°G° DE 2" M 476.00 129.93 61,846.68 - - - - - - - - 0.00% 476.00 61,846.68 100.00%
04.03.07.11 PINTURA EPOXICA EN BARANDAS M 71.40 40.89 2,919.55 - - - - - - - - 0.00% 71.40 2,919.55 100.00%
04.03.07.12 JUNTA DE CONSTRUCCIÓN DE TECNOPOR E=1" M 80.00 2.53 202.40 8.00 20.24 - - - - 8.00 20.24 10.00% 72.00 182.16 90.00%
FORMATO Nº 03A-IF
VALORIZACION FINAL DE OBRA CON RESPECTO AL EXPEDIENTE TECNICO MATRIZ
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (16 FEBRERO AL 31 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 15,786,011.27
METRADO PROGRAMADO EJECUCIÓN-
EJECUCIÓN AÑO 2022 (META: 148)
(Exp. Tecnico Saldo de Obra - AÑO 2021 TOTAL VALORIZADO SALDO DE OBRA
ITEM DESCRIPCION R.G.R N° 173-2021-GRA/GG-GRI) OBRA PRINCIPAL OBRA PRINCIPAL DEDUCTIVO APROB.
Unid. Metrado P.Unit. P.Parcial METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO % METRADO MONTO %
04.03.08 BADEN DE CONCRETO SIMPLE 17 UND 126,578.91
04.03.08.01 BADEN DE CONCRETO SIMPLE 126,578.91
04.03.08.01 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 447.70 6.60 2,954.82 - - 285.26 1,882.72 - - 285.26 1,882.72 63.72% 162.44 1,072.10 36.28%
04.03.08.01 EXCAVACIÓN EN MATERIAL SUELTO, MANUAL m3 237.77 52.45 12,471.04 - - 132.31 6,939.66 - - 132.31 6,939.66 55.65% 105.46 5,531.38 44.35%
04.03.08.01 COMPACTADO DE LA SUBRASANTE m2 447.70 1.96 877.49 - - 289.94 568.27 - - 289.94 568.27 64.76% 157.77 309.22 35.24%
04.03.08.01 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 117.65 55.02 6,473.10 - - 96.71 5,320.98 - - 96.71 5,320.98 82.20% 20.94 1,152.12 17.80%
04.03.08.01 CONCRETO F'C=175 KG/CM2 m3 89.54 454.73 40,716.52 - - 57.05 25,943.26 - - 57.05 25,943.26 63.72% 32.49 14,773.27 36.28%
04.03.08.01 CONCRETO CICLOPEO FC= 140 KG/CM2 + 30%PM CON MEZCLADORA M3 166.35 356.15 59,245.55 - - 65.86 23,456.04 - - 65.86 23,456.04 39.59% 100.49 35,789.51 60.41%
04.03.08.01 SELLADO DE JUNTA DE DILATACIÓN CON MASILLA ELASTICA 2" M 180.30 21.30 3,840.39 - - - - - - - - 0.00% 180.30 3,840.39 100.00%
04.03.09 MURO DE CONTENCION TIPO VOLADO 08 UND 292,637.22
04.03.09.01 LIMPIEZA MANUAL DE TERRENO M2 217.53 2.33 506.84 - - 30.00 69.90 - - 30.00 69.90 13.79% 187.53 436.94 86.21%
04.03.09.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 217.53 6.60 1,435.70 - - 30.00 198.00 - - 30.00 198.00 13.79% 187.53 1,237.70 86.21%
04.03.09.03 EXCAVACION MANUAL EN MATERIAL CONGLOMERADO M3 530.34 55.24 29,295.98 - - 105.76 5,842.18 - - 105.76 5,842.18 19.94% 424.58 23,453.80 80.06%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.09.04 m3 300.30 13.45 4,039.04 - - - - - - - - 0.00% 300.30 4,039.04 100.00%
PREPARADO DEL MATERIAL
04.03.09.05 SOLADO DE COCRETO 1:12, E=4" M2 155.93 44.77 6,980.99 - - 3.00 134.31 - - 3.00 134.31 1.92% 152.93 6,846.68 98.08%
04.03.09.06 CONCRETO CICLOPEO FC= 140 KG/CM2 + 30%PM CON MEZCLADORA M3 50.05 356.15 17,825.31 - - 3.60 1,282.14 - - 3.60 1,282.14 7.19% 46.45 16,543.17 92.81%
04.03.09.07 ENCOFRADO Y DESENCOFRADO CARAVISTA EN OBRAS DE ARTE M2 277.49 58.39 16,202.64 - - 78.36 4,575.44 - - 78.36 4,575.44 28.24% 199.13 11,627.20 71.76%
04.03.09.08 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 11,599.04 6.55 75,973.71 - - 837.79 5,487.50 - - 837.79 5,487.50 7.22% 10,761.25 70,486.21 92.78%
04.03.09.09 CONCRETO F´C=210 KG/CM2 M3 216.76 642.81 139,335.50 - - 16.56 10,644.93 - - 16.56 10,644.93 7.64% 200.20 128,690.56 92.36%
04.03.09.10 FILTRO DE GRAVA ZARANDEADA Ø 1/2"-3/4" M3 4.62 61.54 284.31 - - - - - - - - 0.00% 4.62 284.31 100.00%
04.03.09.11 TUBERÍA PERFORADA PVC SAP C-5 Ø 4" M 56.55 13.39 757.20 - - - - - - - - 0.00% 56.55 757.20 100.00%
04.03.10 MURO DE CONTENCION TIPO GRAVEDAD 24,348.81
04.03.10.01 LIMPIEZA MANUAL DE TERRENO M2 28.80 2.33 67.10 28.80 67.10 - - - - 28.80 67.10 100.00% 0.00 0.00 0.01%
04.03.10.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE m2 28.80 6.60 190.08 28.80 190.08 - - - - 28.80 190.08 100.00% - - 0.00%
04.03.10.03 EXCAVACION MANUAL EN MATERIAL CONGLOMERADO M3 43.32 55.24 2,393.00 43.32 2,393.00 - - - - 43.32 2,393.00 100.00% - 0.00 - 0.00 0.00%
04.03.10.04 ELIMINACIÓN DE MATERIAL EXCEDENTE D PROMEDIO=30 M. m3 51.98 17.49 909.13 51.98 909.13 - - - - 51.98 909.13 100.00% 0.00 0.00 0.00%
04.03.10.05 PERFILADO Y COMPACTADO DE FONDO M2 36.00 5.64 203.04 36.00 203.04 - - - - 36.00 203.04 100.00% - - 0.00%
04.03.10.06 ENCOFRADO Y DESENCOFRADO EN OBRAS DE ARTE m2 101.28 55.02 5,572.43 101.28 5,572.43 - - - - 101.28 5,572.43 100.00% - 0.00 - 0.00 0.00%
04.03.10.07 CONCRETO CICLOPEO FC = 175 KG/CM2 + 30% P.M. M3 62.04 232.64 14,432.99 62.04 14,432.99 - - - - 62.04 14,432.99 100.00% - 0.00 - 0.00 0.00%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
04.03.10.08 m3 43.20 13.45 581.04 43.20 581.04 - - - - 43.20 581.04 100.00% - - 0.00%
PREPARADO DEL MATERIAL
05 PLAN DE MANEJO AMBIENTAL 750,924.68
FORMATO Nº 03A-IF
VALORIZACION FINAL DE OBRA CON RESPECTO AL EXPEDIENTE TECNICO MATRIZ
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (16 FEBRERO AL 31 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 15,786,011.27
METRADO PROGRAMADO EJECUCIÓN-
EJECUCIÓN AÑO 2022 (META: 148)
(Exp. Tecnico Saldo de Obra - AÑO 2021 TOTAL VALORIZADO SALDO DE OBRA
ITEM DESCRIPCION R.G.R N° 173-2021-GRA/GG-GRI) OBRA PRINCIPAL OBRA PRINCIPAL DEDUCTIVO APROB.
Unid. Metrado P.Unit. P.Parcial METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO % METRADO MONTO %
05.01 PROGRAMA DE SUPERVISION Y VIGILANCIA 35,087.50
05.01.01 SUPERVISION Y VIGILANCIA MES 10.00 3,508.75 35,087.50 - - 7.00 24,561.25 - - 7.00 24,561.25 70.00% 3.00 10,526.25 30.00%
05.02 PROGRAMA DE SEÑALIZACION 7,148.64
05.02.01 COLOCACION DE SEÑALES INFORMATIVAS AMBIENTALES UND 16.00 446.79 7,148.64 - - 14.00 6,255.06 - - 14.00 6,255.06 87.50% 2.00 893.58 12.50%
05.03 PROGRAMA DE RECUPERACION MORFOLOGICA 59,827.94
05.03.01 RECUPERACION MORFOLOGICA DE TERRENOS DE CULTIVO M2 31,488.39 1.90 59,827.94 - - 240.00 456.00 - - 240.00 456.00 0.76% 31,248.39 59,371.94 99.24%
05.04 CONTROL DE CARCAVAS CON REFORESTACION EN ZONAS CRITICAS 538,417.62
05.04.01 TRAZO Y REPLANTEO DURANTE EL PROCESO DE LA OBRA M2 23,005.61 2.32 53,373.02 - - - - - - - - 0.00% 23,005.61 53,373.02 100.00%
05.04.02 COLOCACION DE MADERA ROLLIZO EUCALIPTO DE 3"X2.10 MT UND 3,193.00 12.21 38,986.53 - - - - - - - - 0.00% 3,193.00 38,986.53 100.00%
05.04.03 COLOCACION DE SACOS CON MAT. DE RELLENO EN FORMA DE MURO UND 28,741.00 8.03 230,790.23 - - - - - - - - 0.00% 28,741.00 230,790.23 100.00%
05.04.04 COLOCACION DE MADERA CORRIENTE P2 46,703.40 1.99 92,939.77 - - - - - - - - 0.00% 46,703.40 92,939.77 100.00%
RELLENO Y COMPACTADO CON MATERIAL PROPIO, INCLUYE EL
05.04.05 m3 6,901.68 13.45 92,827.60 - - - - - - - - 0.00% 6,901.68 92,827.60 100.00%
PREPARADO DEL MATERIAL
05.04.06 HOYACION PARA PLANTACION EN MACIZO 0.40X0.40X0.40M UND 2,953.00 3.69 10,896.57 - - - - - - - - 0.00% 2,953.00 10,896.57 100.00%
05.04.07 PLANTACION EN MACIZO UND 2,953.00 6.30 18,603.90 - - - - - - - - 0.00% 2,953.00 18,603.90 100.00%
05.05 PROGRAMA DE ABANDONO DE OBRA 104,332.58
05.05.01 RESTAURACION DE AREA DE CAMPAMENTO M2 500.00 2.94 1,470.00 - - - - - - - - 0.00% 500.00 1,470.00 100.00%
05.05.02 MANEJO DE DESECHOS (EXCAVACION DE TRINCHERAS) M3 80.00 80.20 6,416.00 - - 40.00 3,208.00 - - 40.00 3,208.00 50.00% 40.00 3,208.00 50.00%
05.05.03 ACONDICIONAMIENTO DE MATERIAL EXCEDENTE (DME) M3 88,483.10 1.09 96,446.58 8,686.07 9,467.82 41,762.54 45,521.17 - - 50,448.61 54,988.99 57.01% 38,034.49 41,457.59 42.99%
05.06 PLAN DE CONTINGENCIAS 6,110.40
05.06.01 PLAN DE CONTINGENCIAS E IMPREVISTOS GBL 1.00 6,110.40 6,110.40 - - 1.00 6,110.40 - - 1.00 6,110.40 100.00% - - 0.00%
06 CAPACITACIÓN EN OPERACIÓN Y MANTENIMIENTO 5,050.00
06.01 FORTALECIMIENTO ORGANIZACIONAL DE LA JUNTA DE USUARIOS GBL 1.00 2,050.00 2,050.00 - - - - - - - - 0.00% 1.00 2,050.00 100.00%
06.02 CAPACITACION COMUNAL A LA JUNTA USUSARIA UND 2.00 1,500.00 3,000.00 - - - - - - - - 0.00% 2.00 3,000.00 100.00%
07 CONTROL DE CALIDAD 8,887.37
07.01 DISEÑO DE MEZCLA gbl 1.00 590.00 590.00 1.00 590.00 - - - - 1.00 590.00 100.00% - - 0.00%
07.02 ENSAYO A LA ROTURA DE LAS PROBETAS DE CONCRETO UND 95.00 47.20 4,484.00 20.00 944.00 75.00 3,540.00 - - 95.00 4,484.00 100.00% - - 0.00%
ENSAYO DENSIDAD DE CAMPO
07.03 UND 33.00 48.89 1,613.37 - - - - - - - - 0.00% 33.00 1,613.37 100.00%
07.04 ENSAYO PRÓCTOR (COMPACTACIÒN DEL SUELO) UND 22.00 100.00 2,200.00 - - - - - - - - 0.00% 22.00 2,200.00 100.00%
08 FLETE DE MATERIALES 1,127,006.79
08.01 FLETE TERRESTRE gbl 1.00 288,674.56 288,674.56 0.08 21,650.60 0.32 92,375.86 - - 0.40 114,026.46 39.50% 0.60 174,648.10 60.50%
08.02 FLETE RURAL gbl 1.00 838,332.23 838,332.23 - - 0.39 326,949.57 - - 0.39 326,949.57 39.00% 0.61 511,382.66 61.00%
FORMATO Nº 03A-IF
VALORIZACION FINAL DE OBRA CON RESPECTO AL EXPEDIENTE TECNICO MATRIZ
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (16 FEBRERO AL 31 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 15,786,011.27
METRADO PROGRAMADO EJECUCIÓN-
EJECUCIÓN AÑO 2022 (META: 148)
(Exp. Tecnico Saldo de Obra - AÑO 2021 TOTAL VALORIZADO SALDO DE OBRA
ITEM DESCRIPCION R.G.R N° 173-2021-GRA/GG-GRI) OBRA PRINCIPAL OBRA PRINCIPAL DEDUCTIVO APROB.
Unid. Metrado P.Unit. P.Parcial METRADO MONTO METRADO MONTO METRADO MONTO METRADO MONTO % METRADO MONTO %
1 COSTO DIRECTO (CD) 14,265,262.69 451,715.23 2,896,395.98 6,165,206.32 9,513,317.54 4,751,945.09
3 GASTOS GENERALES (7.76 %CD) 1,106,984.38 35,053.10 224,760.33 478,420.01 738,233.44 368,750.94
4 SUB TOTAL (1) + (3) 15,372,247.07 486,768.33 3,121,156.31 6,643,626.33 10,251,550.97 5,120,696.02
5 GASTOS DE SUPERVISION (2.55 % C. D.) 363,764.20 11,518.74 73,858.10 157,212.76 242,589.60 121,174.60
6 EXPEDIENTE TÉCNICO 30,000.00 0.00 30,000.00 0.00 30,000.00 0.00
7 LIQUIDACIÓN DE OBRA 20,000.00 0.00 0.00 0.00 0.00 20,000.00
COSTO TOTAL VALORIZADO (4+5+6+7) 15,786,011.27 498,287.07 3,225,014.41 6,800,839.10 10,524,140.57 5,261,870.62
PORCENTAJE TOTAL DE AVANCE FISICO VALORIZADO 3.16% 20.43% 43.08% 66.67% 33.33%
PORCENTAJE DE AVANCE FISICO ACUMULADO EJECUTADO 3.16% 23.59% 66.67% 66.67% 33.33%
FORMATO Nº 01-LT
METRADOS REALMENTE EJ ECUTADOS - MAYOR METRADO
(Meta : 148 - 2022)
PLIEGO : 444 GOBIERNO REGIONAL DE AYACUCHO
UNIDAD EJECUTORA : 001 SEDE CENTRAL-GOBIERNO REGIONAL DE AYACUCHO
OFICINA EJECUTORA : UEI DEL GOBIERNO REGIONAL AYACUCHO
FUNCIÓN : 10 AGROPECUARIA
DIVISIÓN FUNCIONAL : 025 RIEGO
GRUPO FUNCIONAL : 0050 INFRAESTRUCTURA DE RIEGO
OBRA/META : "CONSTRUCCION CANAL DE IRRIGACION CCOCHAQ - HUAYLLAY- DISTRITO DE VINCHOS - HUAMANGA - AYACUCHO"/ 148-2022
CUI : 2110614
MODALIDAD EJECUCION : ADMINISTRACIÓN DIRECTA
PERIODO DE EJECUCIÓN : AÑO FISCAL 2022 (01 SETIEMBRE AL 20 DE DICIEMBRE)
MONTO VALOR REFERENCIAL : S/. 3,403,632.00
TOTAL COSTO DIRECTO 14,619,336.76 451,715.23 3.09% 5,230,743.55 35.78% 5,682,458.78 38.87% 8,936,877.91 61.13%
GASTOS GENERALES (7.76% CD) 1,134,460.53 35,053.10 405,905.70 440,958.80 693,501.73
PRESUPUESTO DE EJECUCION DE OBRA 15,753,797.29 486,768.33 5,636,649.25 6,123,417.59 9,630,379.64
GASTOS DE SUPERVISION (2.55%) 372,793.09 11,518.74 133,383.96 144,902.70 227,890.39
EXPEDIENTE TECNICO 30,000.00 - 30,000.00 30,000.00 -
LIQUIDACION DE OBRA 20,000.00 - - - 20,000.00
TOTAL PRESUPUESTO 16,176,590.38 498,287.07 5,800,033.21 6,298,320.28 9,878,270.03
PORCENTAJE DE AVANCE (%) 100% 3.08% 35.85% 38.93% 61.07%