Está en la página 1de 2

EMPRESA XYZ

LIDER DEL PROYECTO


4 05/07/2021 Mon, 05/07/2021
INICIO DEL PROYECTO Thu, 01/07/2021 05 06 07 08 09

TAREA RESPONSABLE PROGRESO INICIO FIN L M M J V

FASE 1
Tarea 1.1 Persona x 50% 04/07/2021 07/07/2021
Tarea 1.2 Persona x 100% 06/07/2021 10/07/2021
Tarea 1.3 Persona x 60% 10/07/2021 14/07/2021
Tarea 1.4 Persona x 25% 14/07/2021 18/07/2021
FASE 2
Tarea 2.1 Persona x 75% 13/07/2021 16/07/2021
Tarea 2.2 Persona x 50% 16/07/2021 19/07/2021
Tarea 2.3 Persona x 25% 19/07/2021 23/07/2021
FASE 3
Tarea 3.1 Persona x 50% 21/07/2021 23/07/2021
Tarea 3.2 Persona x 35% 23/07/2021 28/07/2021
Tarea 3.3 Persona x 75% 28/07/2021 31/07/2021
Tarea 3.4 Persona x 45% 31/07/2021 06/08/2021
Tarea 3.5 Persona x 45% 06/08/2021 15/08/2021
7/2021 Mon, 12/07/2021 Mon, 19/07/2021 Mon, 26/07/2021
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01
S D L M M J V S D L M M J V S D L M M J V S D

También podría gustarte