PROBETAS PARA ENSAYO DE COMPRESIÓN EDAD 7 DIAS

Control de Resistencias f'c= 28 Mpa ( f'c=280kg/cm2) (07 Dias)


Ubicación Fecha Edad Slump
N° Estructura Elemento (Descripcion)
(Prog.) Vaciado Rotura (Dias) (Pulgadas)

271A 16-10-23 23-10-23 7


271 A
271B 16-10-23 23-10-23 7
271 B TK 8
HPGR
MURO DE CONTENCION
271C 16-10-23 23-10-23 7
271 C
7 ''
271D 16-10-23 13-11-23 28
271 D SOBRECIMIENTO
TALLER ELECTRICO MINA
A00/2-4, A/A00
271E 16-10-23 13-11-23 28
271 E
271F 16-10-23 13-11-23 28
271 F
272A 17-10-23 24-10-23 7
272 A
272B 17-10-23 24-10-23 7
272 B
272C 17-10-23 24-10-23 7
272 C BAHIA ALMACENAMIENTO
LOSA DE PISO A-B/5´ 7 ''
AROS Y LLANTAS
272D 17-10-23 14-11-23 28
272 D
272E 17-10-23 14-11-23 28
272 E
272F 17-10-23 14-11-23 28
272 F
273A 18-10-23 25-10-23 7
273 A
273B 18-10-23 25-10-23 7
273 B
273C 18-10-23 25-10-23 7
273 C BAHIA ALMACENAMIENTO
LOSA DE PISO C´-D/1-3 6 3/4''
AROS Y LLANTAS
273D 18-10-23 15-11-23 28
273 D
273E 18-10-23 15-11-23 28
273 E
273F 18-10-23 15-11-23 28
273 F
274A 19-10-23 26-10-23 7
274 A
274B 19-10-23 26-10-23 7
274 B
274C 19-10-23 26-10-23 7
274 C BAHIA ALMACENAMIENTO B-B´/5´
LOSA DE PISO 7 ''
AROS Y LLANTAS
274D 19-10-23 16-11-23 28
274 D
274E 19-10-23 16-11-23 28
274 E
274F 19-10-23 16-11-23 28
274 F
275A 19-10-23 26-10-23 7
275 A
275B 19-10-23 26-10-23 7
275 B
275C 19-10-23 26-10-23 7
275 C
HPGR LOSA DE PISO TANQUE TK-08 7 1/2''
275D 19-10-23 16-11-23 28
275 D
275E 19-10-23 16-11-23 28
275 E
275F 19-10-23 16-11-23 28
275 F
276A 20-10-23 27-10-23 7
276 A
276B 20-10-23 27-10-23 7
276 B LOSA DE PISO 4-6/A00-A0
TALLER ELECTRICO MINAS
276C 20-10-23 27-10-23 7
276 C
6 3/4''
276D TALLER ELECTRICO DE 20-10-23 17-11-23 28
276 D
PALAS Y PERFORADORAS
LOSA DE PISO D-E/1
276E 20-10-23 17-11-23 28
276 E
276F 20-10-23 17-11-23 28
276 F
277A 21-10-23 28-10-23 7
277 A
277B 21-10-23 28-10-23 7
277 B
277C 21-10-23 28-10-23 7
277 C BAHIA ALMACENAMIENTO
LOSA B-C/5-5' 7 ''
AROS Y LLANTAS
277D 21-10-23 18-11-23 28
277 D
277E 21-10-23 18-11-23 28
277 E
277F 21-10-23 18-11-23 28
277 F
278A 21-10-23 28-10-23 7
278 A
278B a) TORRE TRANSFERENCIA 21-10-23 28-10-23 7
278 B a) BASE ESCALERA 6
278C b) SARDINEL b) INICIO TUNEL 21-10-23 28-10-23 7
278 C
HPGR 7 ''
278D c) SARDINEL c) TK-008 21-10-23 18-11-23 28
278 D
d) VEREDA d) SALIDA EDIFICO
278E ZARANDA 21-10-23 18-11-23 28
278 E
278F 21-10-23 18-11-23 28
278 F

Control de Resistencias f'c= 21 Mpa ( f'c=210kg/cm2) (07 Dias)


17A 18-10-23 25-10-23 7
17 A
17B 18-10-23 25-10-23 7
17 B
17C 18-10-23 25-10-23 7
17 C TALLER MECANICA MANHOLE 7 A OFICINA
BANCODUCTO 7 1/4''
LIVIANA TRAMO 2
17D 18-10-23 15-11-23 28
17 D
17E 18-10-23 15-11-23 28
17 E
17F 18-10-23 15-11-23 28
17 F

Control de Resistencias f'c= 1 Mpa ( f'c=10kg/cm2) (07 Dias)


70A 17-10-23 24-10-23 7
70 A
70B 17-10-23 24-10-23 7
70 B
70C 17-10-23 24-10-23 7
70 C RELLENO FLUIDO MURO
HPGR TK-8
DE CONTECCION
70D 17-10-23 14-11-23 28
70 D
70E 17-10-23 14-11-23 28
70 E
70F 17-10-23 14-11-23 28
70 F
71A 21-10-23 28-10-23 7
71 A
71B 21-10-23 28-10-23 7
71 B
71C 21-10-23 28-10-23 7
71 C
HPGR SOLADO MURO M1 FAJA 9J
71D 21-10-23 18-11-23 28
71 D
71E 21-10-23 18-11-23 28
71 E
71F 21-10-23 18-11-23 28
71 F

PROBETAS PARA ENSAYO DE COMPRESIÓN EDAD 28 DIAS


Control de Resistencias f'c= 28 Mpa ( f'c=280kg/cm2) (28 Dias)
Ubicación Fecha Edad Slump
N° Estructura Elemento (Descripcion)
(Prog.) Vaciado Rotura (Dias) (Pulgadas)

241A 26-09-23 03-10-23 7


241 A
241B 26-09-23 03-10-23 7
241 B
241C 26-09-23 03-10-23 7
241 C BAHIA ALMACENAMIENTO
LOSA PISO A'-B/3-5 7 ''
AROS Y LLANTAS
241D 26-09-23 24-10-23 28
241 D
241E 26-09-23 24-10-23 28
241 E
241F 26-09-23 24-10-23 28
241 F
242A 26-09-23 03-10-23 7
242 A
242B BAHIA ALMACENAMIENTO 26-09-23 03-10-23 7
242 B LOSA PISO A'-B/3-5
AROS Y LLANTAS
242C 26-09-23 03-10-23 7
242 C
7 ''
242D BAHIA ALMACENAMIENTO 26-09-23 24-10-23 28
242 D
COMPONENTES PARA
ROMBO A2-11; B-2; B-5; B-11
242E VOLQUETES 26-09-23 24-10-23 28
242 E
242F 26-09-23 24-10-23 28
242 F
243A 27-09-23 04-10-23 7
243 A
243B 27-09-23 04-10-23 7
243 B
243C a) LOSA PISO a) A0-A1/4-6 27-09-23 04-10-23 7
243 C
TALLER ELECTRICO MINAS 6 3/4''
243D b) ZAPATA b) B'-1/A-1 27-09-23 25-10-23 28
243 D
243E 27-09-23 25-10-23 28
243 E
243F 27-09-23 25-10-23 28
243 F
244A 27-09-23 04-10-23 7
244 A
244B 27-09-23 04-10-23 7
244 B
244C 27-09-23 04-10-23 7
244 C INGRESO SALA DE
HPGR LOSA PISO 7 ''
ZARANDA
244D 27-09-23 25-10-23 28
244 D
244E 27-09-23 25-10-23 28
244 E
244F 27-09-23 25-10-23 28
244 F
245A 28-09-23 05-10-23 7
245 A
245B BAHIA ALMACENAMIENTO 28-09-23 05-10-23 7
245 B BANCO DUCTO A'-5
AROS Y LLANTAS
245C 28-09-23 05-10-23 7
245 C
7 ''
245D BAHIA ALMACENAMIENTO 28-09-23 26-10-23 28
245 D
COMPONENTES PARA
BANCO DUCTO A-A3
245E VOLQUETES 28-09-23 26-10-23 28
245 E
245F 28-09-23 26-10-23 28
245 F
246A 29-09-23 06-10-23 7
246 A
246B BAHIA ALMACENAMIENTO 29-09-23 06-10-23 7
246 B LOSA PISO A-B'/3-5
AROS Y LLANTAS
246C 29-09-23 06-10-23 7
246 C
7 ''
246D BAHIA ALMACENAMIENTO 29-09-23 27-10-23 28
246 D
COMPONENTES PARA
ROMBO B-3/B-4
246E VOLQUETES 29-09-23 27-10-23 28
246 E
246F 29-09-23 27-10-23 28
246 F
247A 29-09-23 06-10-23 7
247 A
'A-B'/3-5
247B BAHIA ALMACENAMIENTO 29-09-23 06-10-23 7
247 B AROS Y LLANTAS LOSA PISO
247C 29-09-23 06-10-23 7
247 C
7 ''
247D TALLER OFICINA BASE PARA SOPORTE 29-09-23 27-10-23 28
247 D TRANSPORTES EQUIPO CERCO PERIMETRICO DE
AUXILIAR Y REPARACION TRANSFORMADOR
247E DE COMPRESORES 29-09-23 27-10-23 28
247 E
247F 29-09-23 27-10-23 28
247 F
248A 30-09-23 07-10-23 7
248 A
248B 30-09-23 07-10-23 7
248 B
248C 30-09-23 07-10-23 7
248 C REPOSICION DE LOSA
TALLER ELECTRICO 1'-A/1-B ; 1-C/1-D ; 4-B/4-C 7 ''
EXISTENTE
248D PALAS Y PERFORADORAS 30-09-23 28-10-23 28
248 D
248E 30-09-23 28-10-23 28
248 E
248F 30-09-23 28-10-23 28
248 F
249A 30-09-23 07-10-23 7
249 A
249B TALLER ELECTRICO MINA 30-09-23 07-10-23 7
249 B VIGAS Y PEDESTALES A00-5/A00-8
249C 30-09-23 07-10-23 7
249 C
7 ''
BAHIA ALMACENAMIENTO
249D COMPONENTES PARA 30-09-23 28-10-23 28
249 D
VOLQUETES
ROMBO 9-A/A-11 ; A1-11/A-10
249E 30-09-23 28-10-23 28
249 E
249F 30-09-23 28-10-23 28
249 F

Control de Resistencias f'c= 10 Mpa ( f'c=100kg/cm2) (28 Dias)


48A 27-09-23 04-10-23 7
48 A
48B 27-09-23 04-10-23 7
48 B
3-7/F (NAVE COMPRESORES
48C TALLER OFICINA 27-09-23 04-10-23 7
48 C TRANSPORTE EQUIPO
VEREDAS EXTERIORES 6 ''
AUXILIAR Y REPARACION A-A'/8 (OFICINAS)
48D COMPRESORES 27-09-23 25-10-23 28
48 D
1@6'
48E 27-09-23 25-10-23 28
48 E
48F 27-09-23 25-10-23 28
48 F

Control de Resistencias f'c= 1 Mpa ( f'c=10kg/cm2) (28 Dias)


62A 27-09-23 04-10-23 7
62 A
62B 27-09-23 04-10-23 7
62 B
62C 27-09-23 04-10-23 7
62 C TALLER ELECTRICO DE
RELLENO FLUIDO 3-F/1'-F LADO NORTE
PALAS Y PERFORADORAS
62D 27-09-23 25-10-23 28
62 D
62E 27-09-23 25-10-23 28
62 E
62F 27-09-23 25-10-23 28
62 F
63A 29-09-23 06-10-23 7
63 A
63B 29-09-23 06-10-23 7
63 B
63C 29-09-23 06-10-23 7
63 C MALLA TIERRA Y COSTADO
HPGR RELLENO FLUIDO
DE PEDESTALES
63D 29-09-23 27-10-23 28
63 D
63E 29-09-23 27-10-23 28
63 E
63F 29-09-23 27-10-23 28
63 F

Control de Resistencias de Mortero Sika Grout - 212 (Cubos) (28 Dias)


8A 29-09-23 06-10-23 7
8A
8B 29-09-23 06-10-23 7
8B
PEDESTALES
8C A/4 ; A/5 ; A/7 ; 29-09-23 06-10-23 7
8C TALLER MECANICA
B/4 ; B/5 ; B/7 ;
LIVIANA
8D C/4 ; C/5 ; C/7 ; 29-09-23 27-10-23 28
8D D/7
8E 29-09-23 27-10-23 28
8E
8F 29-09-23 27-10-23 28
8F
9A 30-09-23 07-10-23 7
9A
9B a) PEDESTALES 30-09-23 07-10-23 7
9B
G/8;G/9;G/10;G/11;G/
9C 12;G/13 30-09-23 07-10-23 7
9C TALLER MECANICA
F/13;E/13;E'/13;B1/9;B/13
LIVIANA
9D 30-09-23 28-10-23 28
9D b) BASE DE EQUIPOS
9E (XM-003;XM-004;XM-007) 30-09-23 28-10-23 28
9E
9F 30-09-23 28-10-23 28
9F