PLANILLA DE METRADO

Obra: “MEJORAMIENTO DEL CAMINO VECINAL EMP. CU-119 (INKA CONCORINA): EMP. CU 138 (CAPACMARCA) DEL DISTRITO DE CAPACMARCA , DE LA
PROVINCIA DE CHUMBIVILCAS, DEL DEPARTAMENTO DE CUSCO”

Partida: HOJA DE METRADOS - MUROS

MEDIDAS SUB
PARTIDA DESCRIPCIÓN UNID. CANT. VECES FACTOR PARCIAL TOTAL
LARGO ANCHO ALTO ÁREA TOTAL

600.00 OBRAS COMPLEMENTARIAS

102.B TRAZO NIVEL Y REPLANTEO M2 423.10

MURO H=5.00 M 423.10 423.10


PROGRESIVA: 5+389 - 5+439 50.00 5.15 257.50
PROGRESIVA: 20+772 - 20+781 9.00 5.15 46.35
PROGRESIVA: 25+820 - 25+835 15.00 5.15 77.25
MURO H=1.65M
PROGRESIVA: 5+439 - 5+459 20.00 1.20 24.00
PROGRESIVA: 10+497 - 10+512 15.00 1.20 18.00

501.C EXCAVACIÓN PARA ESTRUCTURAS EN MATERIAL CO M3 1498.34

MURO H=5M 1498.34 1498.34


PROGRESIVA: 5+389 - 5+439 50.00 19.51 975.50
PROGRESIVA: 20+772 - 20+781 9.00 19.51 175.59
PROGRESIVA: 25+820 - 25+835 15.00 19.51 292.65
MURO H=1.65M
PROGRESIVA: 5+439 - 5+459 20.00 1.56 31.20
PROGRESIVA: 10+497 - 10+512 15.00 1.56 23.40

502.A RELLENO PARA ESTRUCTURAS M3 1468.11 1468.11

MURO H=5M Volumen descuento


PROGRESIVA: 5+389 - 5+439 50.00 15.46 1.25 966.25
PROGRESIVA: 20+772 - 20+781 9.00 15.46 1.25 173.93
PROGRESIVA: 25+820 - 25+835 15.00 15.46 1.25 289.88
MURO H=1.65M
PROGRESIVA: 5+439 - 5+459 20.00 0.87 1.25 21.75
PROGRESIVA: 10+497 - 10+512 15.00 0.87 1.25 16.31

700.A TRANSPORTE DE MATERIAL EXCEDENTE PARA DISTANC M3 30.23


VER HOJA DE CALCULO DE TRANSPORTE DE ELIMINACION DE MATERIAL
MURO H=5M Volumen de cvolumen de relleno 30.23
PROGRESIVA: 5+389 - 5+439 975.50 966.25 9.25
PROGRESIVA: 20+772 - 20+781 175.59 173.93 1.66
PROGRESIVA: 25+820 - 25+835 292.65 289.88 2.78
MURO H=1.65M
PROGRESIVA: 5+439 - 5+459 31.20 21.75 9.45
PROGRESIVA: 10+497 - 10+512 23.40 16.31 7.09

610.A NIVELADO Y COMPACTADO C/EQUIPO LIVIANO 423.10


MURO H=5M 423.10 423.10
PROGRESIVA: 5+389 - 5+439 50.00 5.15 257.50
PROGRESIVA: 20+772 - 20+781 9.00 5.15 46.35
PROGRESIVA: 25+820 - 25+835 15.00 5.15 77.25
MURO H=1.65M
PROGRESIVA: 5+439 - 5+459 20.00 1.20 24.00
PROGRESIVA: 10+497 - 10+512 15.00 1.20 18.00

503.I ENCOFRADO Y DESENCOFRADO M2 743.58

MURO H=5M 743.58 743.58


PROGRESIVA: 05+389-05+439 2.00 50.00 4.35 435.00
TAPA LATERAL @ 3M 2 4.39 8.78
PANTALLA PUNTA
PROGRESIVA: 20+772 - 20+781 2.00 9.00 4.35 78.30
PROGRESIVA: 25+820 - 25+835 2.00 15.00 4.35 130.50
MURO H=1.65M
PROGRESIVA: 5+439 - 5+459 2.00 20.00 1.30 52.00
PROGRESIVA: 10+497 - 10+512 2.00 15.00 1.30 39.00

503.D CONCRETO CLASE D (F'C=210 KG/CM2) M3 325.60

MURO H=5M 325.60 325.60


PROGRESIVA: 05+389-05+439 50.00 4.40 220.00
PROGRESIVA: 20+772 - 20+781 9.00 4.40 39.60
PROGRESIVA: 25+820 - 25+835 15.00 4.40 66.00

504.A ACERO DE REFUERZO FY=4200 KM/CM2 KG 34327.04

PROGRESIVA: 5+439 - 5+459 34327.04 34327.04


MURO H=5M - 25+820 a 25+835

503.H CONCRETO CLASE H (F'C=100 KG/CM2) M 38.11


38.11 38.11
MURO H=5M
PROGRESIVA: 05+389-05+439 50.00 5.15 0.10 25.75
PROGRESIVA: 20+772 - 20+781 9.00 5.15 0.10 4.64
PROGRESIVA: 25+820 - 25+835 15.00 5.15 0.10 7.73

503.D.1 CONCRETO CLASE D (F'c = 210 KG/CM2+30%PM) M3 31.85

MURO H=1.65M 31.85 31.85


PROGRESIVA: 5+439 - 5+459 20.00 0.91 18.20
PROGRESIVA: 10+497 - 10+512 15.00 0.91 13.65

609 VARIOS
609.A JUNTA DE DILATACIÓN PARA PUENTES UND 65.12
65.12 65.12
PROGRESIVA: 05+389-05+439 9.00 4.36 39.24
MURO H=5M - 25+820 a 25+835 4.00 6.47 25.88
METRADO DE ACEROS EN MURO

OBRA MEJORAMIENTO DEL CAMINO VECINAL EMP. CU-119 (INKA CONCORINA): EMP. CU-138 DISTRITO DE CCA
REGIÓN CUSCO

504.A ACERO DE REFUERZO FY=4,200 KG/CM2

ELEMENTO UBICACIÓN ESPECÍFICA FIERRO ø CANT. VECES LONG. PARC.


PROGRESIVA 05+389-05+439
MURO H=5M CIMENTACIÓN MALLA INFERIOR A1 1 1 250 5.30 1,325.00

MURO H=5M CIMENTACIÓN MALLA A2 1/2 1 42 49.86 2,094.12

MURO H=5M CIMENTACIÓN MALLA SUPERIOR A3 5/8 1 250 5.20 1,300.00

MURO H=5M PANTALLA ANTERIOR B1 5/8 1 500 5.40 2,700.00

MURO H=5M PANTALLA POSTERIOR B2 1/2 1 143 5.40 772.20

MURO H=5M PANTALLA LONGITUDINAL B3 1/2 1 26 49.86 1,296.36

PROGRESIVA: 20+772 - 20+781


MURO H=5M CIMENTACIÓN MALLA INFERIOR A1 1 1 250 5.30 1,325.00

MURO H=5M CIMENTACIÓN MALLA A2 1/2 1 42 8.86 372.12

MURO H=5M CIMENTACIÓN MALLA SUPERIOR A3 5/8 1 250 5.20 1,300.00

MURO H=5M PANTALLA ANTERIOR B1 5/8 1 500 5.40 2,700.00

MURO H=5M PANTALLA POSTERIOR B2 1/2 1 143 5.40 772.20

MURO H=5M PANTALLA LONGITUDINAL B3 1/2 1 26 8.86 230.36

PROGRESIVA: 25+820 - 25+835


MURO H=5M CIMENTACIÓN MALLA INFERIOR A1 1 1 250 5.30 1,325.00

MURO H=5M CIMENTACIÓN MALLA A2 1/2 1 42 14.86 624.12

MURO H=5M CIMENTACIÓN MALLA SUPERIOR A3 5/8 1 250 5.20 1,300.00

MURO H=5M PANTALLA ANTERIOR B1 5/8 1 500 5.40 2,700.00

MURO H=5M PANTALLA POSTERIOR B2 1/2 1 143 5.40 772.20

MURO H=5M PANTALLA LONGITUDINAL B3 1/2 1 26 14.86 386.36

TOTAL
MURO

EMP. CU-138 DISTRITO DE CCAPACMARCA DE PROVINCIA DE CHUMBIVILCAS DE


IÓN CUSCO

34,327.04 KG

1/4 3/8 1/2 5/8 3/4 1


0.25 0.559 0.993 1.552 2.235 3.973

5,264.23

2,079.46

2,017.60

4,190.40

766.79

1,287.29

5,264.23

369.52

2,017.60

4,190.40

766.79

228.75

5,264.23

619.75

2,017.60

4,190.40

766.79

383.66
- - 6,118.35 12,416.00 - 15,792.69
34,327.04