No Descriptions Unit Vol Bobot
vol Progress Bobot
A. PEKERJAAN STRUKTUR BAJA
1 Column H.Beam 250x250x9x14 mm - 72.41 kg/m (K1) Kg 4344.60 11.05% 4127.37 95.00% 10.49%
2 Column WF 350x175x7x11 mm - 49,58 kg/m (K2) Kg 778.46 1.98% 739.537 95.00% 1.88%
3 Column WF 250x125x6x9 mm - 29,58 kg/m (K3) Kg 159.73 0.41% 151.7435 95.00% 0.39%
4 Rafter WF 350x175x7x11 mm - 49,58 kg/m (W3) Kg 3768.33 9.58% 3579.9135 95.00% 9.10%
5 Rafter WF 150x75x5x7 mm - 14,0 kg/m (W4) Kg 306.60 0.78% 291.27 95.00% 0.74%
6 Beam WF 250x125x6x9 mm - 29,58 kg/m (W1) Kg 4414.82 11.22% 4194.079 95.00% 10.66%
7 Kanopi WF 250x125x6x9 mm - 29,58 kg/m (W1) Kg 369.75 0.94% 351.2625 95.00% 0.89%
8 Kanopi WF 200x100x5,5x8 mm - 21,33 kg/m (W2) Kg 319.99 0.81% 303.9905 95.00% 0.77%
9 Gording CNP -150x65x20x3,2 mm - 5,5 kg/m Kg 2305.88 5.86% 2190.586 95.00% 5.57%
10 Voute WF 350,WF 250, WF 200, WF 150 Kg 2167.35 5.51% 2058.9825 95.00% 5.23%
11 Kolom UNP 150 Kg 224.40 0.57% 89.76 40.00% 0.23%
12 Trek Stang dia. 12 Kg 524.30 1.33% 498.085 95.00% 1.27%
13 Ikatan Angin dia. 16 mm Kg 379.20 0.96% 360.24 95.00% 0.92%
14 Base Plat, Plat Sambung, Stiffener dll. Kg 2216.26 5.63% 2105.447 95.00% 5.35%
15 Tumbuckle Pcs 32.00 0.18% 26 81.25% 0.15%
16 Baut HTB M12 Pcs 1332.00 1.19% 1198.8 90.00% 1.07%
17 Baut HTB M16 Pcs 536.00 0.72% 482.4 90.00% 0.65%
18 Anchor Bolt D32 mm L = 1000 mm Pcs 80.00 1.31% 80 100.00% 1.31%
19 Anchor Bolt D22 mm L = 1000 mm Pcs 8.00 0.10% 8 100.00% 0.10%
20 Semen grouting bawah plat kolom ex. Combextra/Sika GP t=25 mm M3 0.11 0.03% 0 0.00% 0.00%
21 Pengecetan dengan Zinchromate Kg 25409.00 2.69% 20327.2 80.00% 2.15%
A. Lapis dengan zinchromate ex. ICI 0.00% 0 0.00% 0.00%
B. Lapis dengan finish cat ex. FTALIT - setara 0.00% 0 0.00% 0.00%
B. PEKERJAAN ATAP
1 Penutup atap, zinc-aluminium gelombang type spandek tct=0,45 mm NA ex. KEPUH setara M² 640.00 320 50.00% 3.86%
7.72%

2 Roof Insulation Bubble Almunium Foil M² 640.00 8.48% 256 40.00% 3.39%
3 Roof Mesh 1,8 x 30 spasi 50x50 ddiameter 1.63 M² 24.70 0.09% 9.88 40.00% 0.04%
4 Penutup atap skylight ex Fiberlux setara M² 96.00 1.18% 38.4 40.00% 0.47%
5 Talang Zincalume ( termasuk bak talang ) tct = 0,40 mm + penggantung plat strip 50x5 M1 69.00 34.5 50.00% 0.41%
0.82%

6 Roof Drain PVC dia.4" Pcs 8.00 0.04% 0 0.00% 0.00%


7 Steel Flashing tct = 0.35 mm NA 0.00% 0 0.00% 0.00%
- Nok M1 27.00 0.14% 10.8 40.00% 0.06%
- Pertemuan Talang dengan atap M1 69.00 0.85% 27.6 40.00% 0.34%
- Pertemuan atap dengan cladding M1 32.00 0.39% 12.8 40.00% 0.16%
C. PEKERJAAN WALLCLADING
1 CNP 150x65x20x2.3 - 5,5kg/m Kg 3127.30 8.15% 1250.92 40.00% 3.26%
302.4 40.00% 3.71%
2 Corrugated Zincalume Tct.0,35 mm NA type Spandek untuk Penutup Cladding M2 756.00 9.29%
GRAND TOTAL 100.00% TOTAL 74.61%