ITEM DESCRIPCION M3
1 SECTOR 1 4345.70
2 SECTOR 2 2921.48
3 SECTOR 3 1653.13
4 SECTOR 4 2538.58
5 SECTOR 5 1000.00
6 SECTOR 6 2862.70
7 SECTOR 7 716.15
8 SECTOR 8 1604.65
9 TALUD etapa I 2872.29
10 TALUD etapa II 185.33
5 CALZADURA 969.91
SUBTOTAL 22702.05
ACOPIO
MA
REPORTE DE MOVIMIENTO DE TIERRAS 16/11/2023
TOTAL TOTAL TOTAL DE CORTE TOTAL POR
ITEM
CONTRACTUAL TERORICO AL 16.11.2023 CORTAR
1 20395.13 m3 22702.5 13619.12 m3 9083.38 m3
TOTAL DE TOTAL POR
2
ELIMINACION ELIMINAR
1.25% 17023.9 11354.225