TABLA AGUAS RESIDUALES ClaudineMonteroPuello 100573550

total
Derivacio I La Du Dp Fr Lv Ld unidad s=1% Q (pulg) Tabla XVI
n Columna Total U. Q (pulg) T. XVII Tramo U.D S=2% Q (pulg) T. XIX Colector

1 4 1 2 2 9 4.000 1 36 4 1-2' 36 4 120


3 4 1 2 2 9 4.000 3 36 4 2-3' 36 4
trampagrasa 4 3 3 2.000 4 12 2 3-4' 72 4
5 3 3 6 4.000 5 24 4 4-5' 84 4
6 4 1 2 2 3 3 15 4.000 6 60 4 5-6' 108 4
trampagrasa 8A 3 3 2.000 8A 12 2 6-7' 168 6 720
trampagrasa 8B 3 3 2.000 8B 12 2 7-8' 168 6
Caseta seg. 9 4 1 5 2.000 Caseta 9 5 2 8-14' 192 6
11 4 1 2 2 9 4.000 11 36 4 9' 5 4
13 4 1 2 2 9 4.000 13 36 4 9-10' 5 4
15 3 3 6 4.000 15 24 4 10-11' 41 4
16 4 1 2 2 9 4.000 16 36 4 11-12' 41 4
18 4 1 2 2 9 4.000 18 36 4 12-13' 77 4
19 3 3 6 4.000 19 24 4 13-14' 77 4
trampagrasa 20 3 3 2.000 20 12 2 14' 269 6
21 4 1 2 2 9 4.000 21 36 4 14-15' 293 6
22A 4 1 2 2 9 4 22A 36 4 15-16' 329 6
22B 4 1 2 2 9 4 22B 36 4 16-17' 329 6
23 4 1 2 2 9 4 23 36 4 17-18' 365 6
trampagrasa 24 3 3 2 24 12 2 18-19' 389 6
25 3 3 6 4 25 24 4 19-20' 401 6
26 3 3 6 4 26 24 4 20-21' 437 6
trampagrasa 27 3 3 2 27 12 2 21-22' 509 6
28 4 1 2 2 9 4 28 36 4 22-23' 545 6
30 4 1 2 2 9 4 30 36 4 23-24' 557 6
176 689 24-25' 581 6
25-26' 605 6
26-27' 617 6
27-28' 653 6
28-29' 653 6
29-30' 689 6
30-31' 689
9331
Septico
Dotacion 350 Lit/hab/dia
Poblacion 6 personas por apartamento
Poblacion total 6 hab
Relacion L=2a L= 2.90m
T. de retencion 12h 1ra 2da Filtro
Altura M. 1.5m
Qmd= 350L/hab/dia * 6 * 24 = 50,400 L/dia
QL= 1L/hab/dia * 6 * 24 = 144l t/dia
Qt= 50,544 Lt/dia
V=Q*T= 50,544 Lt/dia * 0.5dia = 25.272m3
A= 25.272m3/1.5m= 16.848m2 2.90m

1ra y 2da= 0.75*2.9=2.175m


Filtro=0.25*2.9m=0.725m 1.45m 0.725m 0.725m
1ra= 2/3 * 2.175m=1.45m
2da= 1/3 * 2.175m=0.725m
1.5m

2.90m
Trampa de grasa

Produccion= 24hab*0.5=12kg/dia ENTRADA 5,152.94m3 SALIDA


Produccion=12kg/dia*365dia=4,380kg
V= (4,380Kg/0.85)=5,152.94m3

AGUAS PLUVIALES EN TECHO BAJANTES PLUVIALES Intensidad 100mm/hora DRENAJE PLUVIAL PARQUEO S=2%
BLOQUE A BLOQUE A PULG S=2%
A (m2) Q (m3/s) N D RH A(m2) S Qc(m3/s)
A1 43.75m2 BP1 70mm 3 D/4
A2 46.39m2 BP2 70mm 3 A1 121 0.00479 0.01 8" 0.0508 0.0324 0.02 0.0628
A3 44.47m2 BP3 70mm 3 A2 76.16 0.0013 0.01 8" 0.0508 0.0324 0.02 0.0628
A4 52.64m2 BP4 70mm 3 A3 83.82 0.0032 0.01 8" 0.0508 0.0324 0.02 0.0628
A5 11.04m2 BP5 35mm 3 A4 65.07 0.00258 0.01 8" 0.0508 0.0324 0.02 0.0628
A5 79.05 0.00313 0.01 8" 0.0508 0.0324 0.02 0.0628
BLOQUE B BLOQUE B PULG A6 43.19 0.00171 0.01 8" 0.0508 0.0324 0.02 0.0628
A7 34.16 0.00135 0.01 8" 0.0508 0.0324 0.02 0.0628
A1 43.09m2 BP1 70mm 3 A8 47.97 0.0019 0.01 8" 0.0508 0.0324 0.02 0.0628
A2 30.41m2 BP2 50mm 3 A9 52.39 0.00207 0.01 8" 0.0508 0.0324 0.02 0.0628
A3 49.20m2 BP3 70mm 3 0.2032m
A4 44.48m2 BP4 70mm 3
A5 11.06m2 BP5 35mm 3

BLOQUE C BLOQUE C PULG

A1 40.85m2 BP1 50mm 3


A2 38.37m2 BP2 50mm 3
A3 44.39m2 BP3 70mm 3
A4 44.46m2 BP4 70mm 3
A5 11.04m2 BP5 35mm 3