CLAVE CONCEPTO UNIDAD CANTIDAD PU IMPORTE

1 VARILLA CORRUGADA 3/8 TMO 107.00 180.00 19,260.00


2 ALAMBRE RECOCIDO KG 30.00 33.50 1,005.00
3 CLAVO DE 4-2 1/2 KG 10.00 43.00 430.00
4 MADERA 1X8X12 PZA 20.00 288.00 5,760.00
5 VARILLA CORRUGADA 1/2 TMO 35.00 298.00 10,430.00
6 CEMENTO 50KG SACO 119.00 338.00 40,222.00
7 ARENA M3 19.00 500.00 9,500.00
8 GRAVA M3 17.00 500.00 8,500.00
9 BLOCK 15X20X40 PZA 2,200.00 17.00 37,400.00
10 MORTERO 50KG SACO 35.00 268.00 9,380.00
11 PTR 2 1/2 X 2 1/2 CAL 14 TMO 9.00 991.45 8,923.05
12 SOLDADURA 6011 KG 3.00 109.00 327.00
13 BISAGRA DE BARRIL PZA 4.00 35.00 140.00
14 PASADOR PZA 1.00 230.00 230.00
15 MALLA CICLONICA 20M X 2M ROLLO 1.00 2,675.00 2,675.00
16 ALAMBRE DE PUAS 360M ROLLO 1.00 1,260.00 1,260.00
17 CONCERTINA DE 8M ROLLO 11.00 669.00 7,359.00
18 DISCO DE CORTE CONCRETO 7 PZA 6.00 236.00 1,416.00
19 DISCO DE CORTE MADERA 7 PZA 2.00 719.00 1,438.00
20 DISCO DE CORTE ACERO 14 PZA 3.00 75.00 225.00
21 DISCO DE CORTE ACERO 4 PZA 6.00 25.00 150.00
22 DISCO DE DESBASTE 4 PZA 2.00 30.00 60.00
23 TUINO 1 PZA 40.00 30.00 1,200.00
24 CLAVO DE 1 KG 0.50 69.00 34.50
25 BROCHA DE 6 PZA 4.00 128.00 512.00
26 CURACRETO CUBETA 1.00 1,118.00 1,118.00
27 BROCA CONCRETO 1/4X8 PZA 6.00 158.00 948.00
169,902.55

MANO DE OBRA
1 ZAPATA 80X80X15 PZA 26.00
2 DADO 20X20X1 PZA 26.00
3 CONTRATRABE 20X30 ML 87.60
4 MURO DE BLOCK DE 15 M2 169.00
5 CASTILLO 15X20 ML 54.60
6 DALA 15X20 ML 73.20
7 CERCO DE ALAMBRE DE PUAS Y ML 87.60
CONCERTINA
8 CERCO DE MALLA CICLONICXA 2M ML 12.50
9 PUERTA DE 2X2M MALLA CICLONICA PZA 1.00
10 LIMPIEZA LOTE 1.00