DATOS DE OBRA

RENOVACION DE PUENTE EN EL CAMINO VECINAL SECTOR CHICMABAMBA EN LA LOCALIDAD


OBRA
URANMARCA, DISTRITO DE URANMARCA, PROVINCIA CHINCHEROS, DEPARTAMENTO APURIMAC
DISTRITO URANMARCA CONTRATO CONTRATISTA Nº 001-2023-MDU/GM
PROVINCIA CHINCHEROS CONTRATO SUPERVISOR Nº 037-2023-MDU-GM
DEPARTAMENTO APURIMAC FECHA DE INICIO DE OBRA : 11/09/2023
LOCALIDAD URANMARCA FECHA DE TERMINO OBRA: 10/11/2023
PERIODO DE VALORIZACION: 11/09/23 a 30/09/23 FECHA VALOR REFERENCIAL S/. 492,007.47
PLAZO DE EJECUCION. 60 dias calendarios
CONTRATISTA CONSORCIO YANCE ADELANTO DIRECTO 15% (CON IGV) S/. 0.00
SUPERVISOR GRUPO ALF S.A.C ADELANTO DIRECTO 15% (SIN IGV) S/. 0.00
MONTO COTRATADO (CON IGV) S/. 442,806.73
MONTO COTRATADO (CON IGV) S/. 442,807.73
FACTOR DE RELACION (0.90)
COSTO DIRECTO (SIN IGV) S/. 359,212.25
FIEL CUMPLIMIENTO (10%) S/. 44,280.67
ING. RESIDENTE Ing. Percy Obed Azpur Gomez.
ING. SUPERVISOR Ing. Jose Carlos Riveros Zorrilla
ADJUDICACION CONTRATISTA Adjudicacion Simplificada N° 02-2023-MDU/CS
ADJUDICACION SUPERVISOR
B C D E F G H I J K L M N O P Q R S
1 VALORIZACION DE OBRA Nº 02
RENOVACION DE PUENTE EN EL CAMINO VECINAL SECTOR CHICMABAMBA EN LA LOCALIDAD URANMARCA, DISTRITO DE URANMARCA, PROVINCIA
OBRA
2 CHINCHEROS, DEPARTAMENTO APURIMAC
3 PERIODO DE VALORIZACION: RENOVACION DE PUENTE EN EL CAMINO VECINAL SECTOR CHICMABAMBA EN LA LOCALIDAD URANMARCA, DISTRITO DE URANMARCA, PROVINCIA CHINCHEROS, DEPARTAMENTO APURIMAC
4 CONTRATISTA CONSORCIO YANCE DISTRITO URANMARCA FECHA DE INICIO DE OBRA : 11/09/2023
5 SUPERVISOR GRUPO ALF S.A.C PROVINCIA CHINCHEROS FECHA DE TERMINO OBRA: 10/11/2023
6 MONTO COTRATADO (CON IGV) 442,806.73 INC. IGV DEPARTAMENTO APURIMAC
7 PLAZO DE EJECUCION. 60 dias calendarios LOCALIDAD URANMARCA
8 FECHA DE INICIO DE OBRA : 11/09/2023
9
10 AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO
Item Descripción Und. Metrado Precio S/. Parcial S/.
11 % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO
12 01 OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD 12,862.1600 10,150.38 2,229.22 12,379.60 482.56
13 01.01 OBRAS PROVISIONALES 3,617.3900 2,055.3700 1,362.03 3,417.40 199.99
14 01.01.01 ALQUILER DE ALMACÉN Y OFICINA EN OBRA mes 2.00 400.00 800.0000 25.00% 0.50 200.0000 50.00% 1.00 400.00 75.00% 1.5000 600.0000 25.00% 0.50 200.000
15 01.01.02 CARTEL DE OBRA DE 3.60X2.40M glb 1.00 893.34 893.3400 100.00% 1.00 893.3400 0.00% 0.00 100.00% 1.0000 893.3400 0.00% 0.00 0.000
16 01.01.03 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA glb 1.00 1924.05 1,924.0500 50.00% 0.50 962.0300 50.00% 0.50 962.03 100.00% 1.0000 1,924.0600 0.00% 0.00 -0.010
17 01.02 SEGURIDAD Y SALUD OCUPACIONAL 5,624.6200 5,320.5000 152.06 5,472.56 152.06
18 01.02.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SST glb 1.00 400.00 400.0000 100.00% 1.00 400.0000 0.00% 0.00 100.00% 1.0000 400.0000 0.00% 0.00 0.000
19 01.02.02 EQUIPOS DE PROTECCION INDIVIDUAL und 1.00 2177.65 2,177.6500 100.00% 1.00 2,177.6500 0.00% 0.00 100.00% 1.0000 2,177.6500 0.00% 0.00 0.000
20 01.02.03 EQUIPOS DE PROTECCION COLECTIVA und 1.00 1159.22 1,159.2200 100.00% 1.00 1,159.2200 0.00% 0.00 100.00% 1.0000 1,159.2200 0.00% 0.00 0.000
21 01.02.04 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 1279.50 1,279.5000 100.00% 1.00 1,279.5000 0.00% 0.00 100.00% 1.0000 1,279.5000 0.00% 0.00 0.000
22 01.02.05 CAPACITACION EN SALUD EN EL TRABAJO glb 1.00 608.25 608.2500 50.00% 0.50 304.1300 25.00% 0.25 152.06 75.00% 0.7500 456.1900 25.00% 0.25 152.060
23 01.03 IMPLEMENTACION DE PROTOCOLOS SANITARIOS 1,301.5500 455.91 715.13 1,171.04 130.51
24 01.03.01 LIMPIEZA Y DESINFECCION mes 2.00 389.74 779.4800 25.00% 0.50 194.8700 75.00% 1.50 584.61 100.00% 2.0000 779.4800 0.00% 0.00 0.000
25 01.03.02 LAVADO Y DESINFECCION DE MANOS glb 1.00 522.07 522.0700 50.00% 0.50 261.0400 25.00% 0.25 130.52 75.00% 0.7500 391.5600 25.00% 0.25 130.510
26 01.04 DEMOLICION DE CONCRETO 2,318.6000 2,318.60 0.00 2,318.60 0.00
27 01.04.01 DEMOLICION DE VEREDAS DE 0.10 M. m3 2.63 86.88 228.4900 100.00% 2.63 228.4900 0.00% 0.00 100.00% 2.6300 228.4900 0.00% 0.00 0.000
28 01.04.02 DEMOLICIÓN DE PAVIMENTO DE CONCRETO E=0.20M m3 15.24 86.88 1,324.0500 100.00% 15.24 1,324.0500 0.00% 0.00 100.00% 15.2400 1,324.0500 0.00% 0.00 0.000
29 01.04.03 DEMOLICION DE CONCRETO CICLOPEO m3 5.45 120.33 655.8000 100.00% 5.45 655.8000 0.00% 0.00 100.00% 5.4500 655.8000 0.00% 0.00 0.000
30 01.04.04 TRANSPORTE DE MATERIAL EXCEDENTE D<=1KM (DEMOLICION) m3 23.31 4.73 110.2600 100.00% 23.31 110.2600 0.00% 0.00 100.00% 23.3100 110.2600 0.00% 0.00 0.000
31 02 SUB ESTRUCTURA 146,645.9100 90,433.78 56,212.15 146,645.93 -0.02
32 02.01 OBRAS PRELIMINARES 1,369.2200 1,369.22 0.00 1,369.22 0.00
33 02.01.01 LIMPIEZA DE TERRENO Y CAUCE m2 201.00 4.03 810.0300 100.00% 201.00 810.0300 0.00% 0.00 100.00% 201.0000 810.0300 0.00% 0.00 0.000
34 02.01.02 TRAZO Y REPLANTEO CON EQUIPO m2 213.43 2.62 559.1900 100.00% 213.43 559.1900 0.00% 0.00 100.00% 213.4300 559.1900 0.00% 0.00 0.000
35 02.02 MOVIMIENTO DE TIERRAS 23,067.9900 21,603.53 1,464.46 23,067.99 0.00
36 02.02.01 EXCAVACION P/ESTRUCTURAS EN MATERIAL COMUN BAJO AGUA m3 138.82 8.63 1,198.0200 100.00% 138.82 1,198.0200 0.00% 0.00 100.00% 138.8200 1,198.0200 0.00% 0.00 0.000
37 02.02.02 EXCAVACION P/ESTRUCTURAS EN MATERIAL COMUN EN SECO m3 78.34 12.87 1,008.2400 100.00% 78.34 1,008.2400 0.00% 0.00 100.00% 78.3400 1,008.2400 0.00% 0.00 0.000
38 02.02.03 NIVELACION Y APISONADO PARA SOLADO m2 78.34 5.12 401.1000 100.00% 78.34 401.1000 0.00% 0.00 100.00% 78.3400 401.1000 0.00% 0.00 0.000
39 02.02.04 RELLENO CON MATERIAL DE PRESTAMO SELECCIONADO m3 151.18 103.05 15,579.1000 100.00% 151.18 15,579.1000 0.00% 0.00 100.00% 151.1800 15,579.1000 0.00% 0.00 0.000
40 02.02.05 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 217.15 8.22 1,784.9700 70.00% 152.01 1,249.4800 30.00% 65.15 535.49 100.00% 217.1500 1,784.9700 0.00% 0.00 0.000
41 02.02.06 ACOMODO DE MATERIAL EXCEDENTE EN DME m3 217.15 14.26 3,096.5600 70.00% 152.01 2,167.5900 30.00% 65.15 928.97 100.00% 217.1500 3,096.5600 0.00% 0.00 0.000
42 02.03 OBRAS DE CONCRETO SIMPLE 1,641.5200 1,149.07 492.46 1,641.53 -0.01
43 02.03.01 SOLADO CONCRETO FC=100 KG/CM2 E=0.10M m3 7.87 208.58 1,641.5200 70.00% 5.51 1,149.0700 30.00% 2.36 492.46 100.00% 7.8700 1,641.5300 0.00% 0.00 -0.010
44 02.04 OBRAS DE CONCRETO ARMADO 120,567.1800 66,311.96 54,255.23 120,567.19 -0.01
45 02.04.01 ZAPATAS 34,476.6000 18,962.14 15,514.47 34,476.61 -0.01
46 02.04.01.01 CONCRETO F'C=240 kg/cm2 EN ZAPATAS BAJO AGUA m3 55.12 520.08 28,666.8100 55.00% 30.32 15,766.7500 45.00% 24.80 12,900.06 100.00% 55.1200 28,666.8100 0.00% 0.00 0.000
47 02.04.01.02 ENCOFRADO Y DESENCOFRADO EN ZAPATAS BAJO AGUA m2 71.12 81.69 5,809.7900 55.00% 39.12 3,195.3900 45.00% 32.00 2,614.41 100.00% 71.1200 5,809.8000 0.00% 0.00 -0.010
48 02.04.02 ESTRIBOS 86,090.5800 47,349.82 38,740.76 86,090.58 0.00
49 02.04.02.01 CONCRETO F'C=240 KG/CM2 PARA ESTRIBOS BAJO AGUA m3 84.21 520.08 43,795.9400 55.00% 46.32 24,087.7700 45.00% 37.89 19,708.17 100.00% 84.2100 43,795.9400 0.00% 0.00 0.000
50 02.04.02.02 CONCRETO F'C=240 KG/CM2 PARA ESTRIBOS EN SECO m3 41.26 434.64 17,933.2500 55.00% 22.69 9,863.2900 45.00% 18.57 8,069.96 100.00% 41.2600 17,933.2500 0.00% 0.00 0.000
51 02.04.02.03 ENCOFRADO Y DESENCOFRADO EN ESTRIBOS BAJO AGUA m2 102.88 81.69 8,404.2700 55.00% 56.58 4,622.3500 45.00% 46.30 3,781.92 100.00% 102.8800 8,404.2700 0.00% 0.00 0.000
52 02.04.02.04 ENCOFRADO Y DESENCOFRADO EN ESTRIBOS EN SECO m2 127.52 77.44 9,875.1500 55.00% 70.14 5,431.3300 45.00% 57.38 4,443.82 100.00% 127.5200 9,875.1500 0.00% 0.00 0.000
53 02.04.02.05 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 680.31 8.94 6,081.9700 55.00% 374.17 3,345.0800 45.00% 306.14 2,736.89 100.00% 680.3100 6,081.9700 0.00% 0.00 0.000
54 03 SUPERESTRUCTURA 158,176.9952 115.28 34,637.50 34,752.78 123,424.22
55 03.01 OBRAS PRELIMINARES 144.1000 115.28 0.00 115.28 28.82
56 03.01.01 TRAZO Y REPLANTEO CON EQUIPO m2 55.00 2.62 144.1000 80.00% 44.00 115.2800 0.00% 0.00 80.00% 44.0000 115.2800 20.00% 11.00 28.820
57 03.02 VIGAS PRINCIPALES 65,185.0200 0.00 27,798.54 27,798.54 37,386.48
58 03.02.01 CONCRETO F'C=280 KG/CM2 PARA LOSA DE PUENTE m3 12.15 475.81 5,781.0900 0.00% 0.00 0.0000 0.00% 0.00 0.00% 0.0000 0.0000 100.00% 12.15 5,781.090
59 03.02.02 ENCOFRADO Y DESENCOFRADO EN LOSA DE PUENTE m2 48.60 507.32 24,655.7500 0.00% 0.00 0.0000 0.00% 0.00 0.00% 0.0000 0.0000 100.00% 48.60 24,655.750
60 03.02.03 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 3835.34 9.06 34,748.1800 0.00% 0.00 0.0000 75.00% 3068.27 27,798.54 80.00% 3,068.2720 27,798.5400 20.00% 767.07 6,949.640
61 03.03 VIGAS DIAFRAGMA 12,543.9752 0.00 2,036.11 2,036.11 10,507.87
62 03.03.01 CONCRETO F'C=280 KG/CM2 PARA LOSA DE PUENTE m3 2.59 475.81 1,232.3500 0.00% 0.00 0.0000 0.00% 0.00 0.00% 0.0000 0.0000 100.00% 2.59 1,232.350
63 03.03.02 ENCOFRADO Y DESENCOFRADO EN LOSA DE PUENTE m2 17.28 507.32 8,766.4900 0.00% 0.00 0.0000 0.00% 0.00 0.00% 0.0000 0.0000 100.00% 17.28 8,766.490
64 03.03.03 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 280.92 9.06 2,545.1352 0.00% 0.00 0.0000 75.00% 224.74 2,036.11 80.00% 224.7360 2,036.1100 20.00% 56.18 509.025
65 03.04 LOSA DE PUENTE 43,672.6600 0.0000 4,802.85 4,802.85 38,869.81
66 03.04.01 CONCRETO F'C=280 KG/CM2 PARA LOSA DE PUENTE m3 17.37 475.81 8,264.8200 0.00% 0.00 0.0000 0.00% 0.00 0.00% 0.0000 0.0000 100.00% 17.37 8,264.820
67 03.04.02 ENCOFRADO Y DESENCOFRADO EN LOSA DE PUENTE m2 57.96 507.32 29,404.2700 0.00% 0.00 0.0000 0.00% 0.00 0.00% 0.0000 0.0000 100.00% 57.96 29,404.270
68 03.04.03 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 671.54 8.94 6,003.5700 0.00 0.0000 75.00% 537.23 4,802.85 80.00% 537.2320 4,802.8500 1,200.720
B C D E F G H I J K L M N O P Q R S
1 VALORIZACION DE OBRA Nº 02
RENOVACION DE PUENTE EN EL CAMINO VECINAL SECTOR CHICMABAMBA EN LA LOCALIDAD URANMARCA, DISTRITO DE URANMARCA, PROVINCIA
OBRA
2 CHINCHEROS, DEPARTAMENTO APURIMAC
3 PERIODO DE VALORIZACION: RENOVACION DE PUENTE EN EL CAMINO VECINAL SECTOR CHICMABAMBA EN LA LOCALIDAD URANMARCA, DISTRITO DE URANMARCA, PROVINCIA CHINCHEROS, DEPARTAMENTO APURIMAC
4 CONTRATISTA CONSORCIO YANCE DISTRITO URANMARCA FECHA DE INICIO DE OBRA : 11/09/2023
5 SUPERVISOR GRUPO ALF S.A.C PROVINCIA CHINCHEROS FECHA DE TERMINO OBRA: 10/11/2023
6 MONTO COTRATADO (CON IGV) 442,806.73 INC. IGV DEPARTAMENTO APURIMAC
7 PLAZO DE EJECUCION. 60 dias calendarios LOCALIDAD URANMARCA
8 FECHA DE INICIO DE OBRA : 11/09/2023
9
10 AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO
Item Descripción Und. Metrado Precio S/. Parcial S/.
11 % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO
12
69 03.05 LOSA DE APROXIMACIÓN 5,883.9200 0.00 0.00 0.00 5,883.92
70 03.05.01 CONCRETO F'C=240 kg/cm2 PARA LOSA DE APROXIMACION m3 11.46 434.64 4,980.9700 0.00% 0.00 0.0000 0.00% 0.00 0.00% 0.0000 0.0000 100.00% 11.46 4,980.970
71 03.05.02 ENCOFRADO Y DESENCOFRADO EN LOSA DE APROXIMACION m2 11.66 77.44 902.9500 0.00% 0.00 0.0000 0.00% 0.00 0.00% 0.0000 0.0000 100.00% 11.66 902.950
72 03.06 VEREDAS DE CONCRETO 1,442.2300 0.00 0.00 0.00 1,442.23
73 03.06.01 CONCRETO F'C=210 kg/cm2 EN VEREDAS m3 2.70 414.82 1,120.0100 0.00% 0.00 0.0000 0.00% 0.00 0.00% 0.0000 0.0000 100.00% 2.70 1,120.010
74 03.06.02 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 5.40 59.67 322.2200 0.00% 0.00 0.0000 0.00% 0.00 0.00% 0.0000 0.0000 100.00% 5.40 322.220
75 03.07 OTROS 29,305.0900 0.00 0.00 0.00 29,305.09
76 03.07.01 JUNTAS DE DILATACION METALICA m 16.00 607.24 9,715.8400 0.00% 0.00 0.0000 0.00% 0.00 0.00% 0.0000 0.0000 100.00% 16.00 9,715.840
77 03.07.02 APOYOS DE NEOPRENO und 6.00 1360.05 8,160.3000 0.00% 0.00 0.0000 0.00% 0.00 0.00% 0.0000 0.0000 100.00% 6.00 8,160.300
78 03.07.03 TUBO DE DRENAJE, D=3", L=0.70M und 6.00 18.82 112.9200 0.00% 0.00 0.0000 0.00% 0.00 0.00% 0.0000 0.0000 100.00% 6.00 112.920
79 03.07.04 BARANDA METALICAL DE F°G° ( SEGUN DISEÑO) m 20.30 557.44 11,316.0300 0.00% 0.00 0.0000 0.00% 0.00 0.00% 0.0000 0.0000 100.00% 20.30 11,316.030
80 04 OBRAS DE PROTECCION 24,385.9100 786.08 17,813.56 18,599.64 5,786.27
81 04.01 OBRAS PRELIMINARES 2,067.9100 620.37 1,240.77 1,861.14 206.77
82 04.01.01 LIMPIEZA DE TERRENO MANUAL m2 457.50 3.21 1,468.5800 30.00% 137.25 440.5700 60.00% 274.50 881.15 90.00% 411.7500 1,321.7200 10.00% 45.75 146.860
83 04.01.02 TRAZO Y REPLANTEO CON EQUIPO m2 228.75 2.62 599.3300 30.00% 68.63 179.8000 60.00% 137.26 359.62 90.00% 205.8850 539.4200 10.00% 22.87 59.910
84 04.02 MOVIMIENTO DE TIERRAS 662.8500 165.71 331.43 497.14 165.71
85 04.02.01 EXCAVACION PARA CIMENTACION DE GAVIONES m3 22.50 29.46 662.8500 25.00% 5.63 165.7100 50.00% 11.25 331.43 75.00% 16.8750 497.1400 25.00% 5.63 165.710
86 04.03 MURO DE GAVIONES 21,655.1500 0.00 16,241.36 16,241.36 5,413.79
87 04.03.01 GAVIONES TIPO CAJON - SUMINISTRO E INSTALACIÓN m3 55.00 393.73 21,655.1500 0.00% 0.00 0.0000 75.00% 41.25 16,241.36 75.00% 41.2500 16,241.3600 25.00% 13.75 5,413.790
88 05 SEÑALIZACION 5,246.4000 2,449.71 0.00 2,449.71 2,796.69
89 05.01 SEÑALIZACIONES PREVENTIVAS E INFORMATICAS und 2.00 2449.71 4,899.4200 50.00% 1.00 2,449.7100 0.00% 0.00 50.00% 1.0000 2,449.7100 50.00% 1.00 2,449.710
90 05.02 PINTADO DE VEREDAS AMBAS CARAS (LINEA CONTINUA) m 24.78 10.76 266.6300 0.00% 0.00 0.0000 0.00% 0.00 0.00% 0.0000 0.0000 100.00% 24.78 266.630
91 05.03 TACHAS REFLEXTIVAS und 5.00 16.07 80.3500 0.00% 0.00 0.0000 0.00% 0.00 0.00% 0.0000 0.0000 100.00% 5.00 80.350
92 06 MITIGACION DE IMPACTO AMBIENTAL 5,030.8700 1,818.06 727.13 2,545.19 2,485.68
93 06.01 TRABAJOS PRE OPERACIÓN 1,393.5600 1,393.56 0.00 1,393.56 0.00
94 06.01.01 ACONDICIONAMIENTO DE AREA PARA BOTADERO glb 1.00 1393.56 1,393.5600 100.00% 1.00 1,393.5600 0.00% 0.00 100.00% 1.0000 1,393.5600 0.00% 0.00 0.000
95 06.02 TRABAJOS EN LA OPERACIÓN 848.9900 424.50 0.00 424.50 424.49
96 06.02.01 MANEJO DE RESIDUOS SÓLIDOS Y LÍQUIDOS glb 1.00 848.99 848.9900 50.00% 0.50 424.5000 0.00% 0.00 50.00% 0.5000 424.5000 50.00% 0.50 424.490
97 06.03 TRABAJOS EN EL CIERRE DE LA OPERACIÓN 2,788.3200 0.00 727.13 727.13 2,061.19
98 06.03.01 REACONDICIONAMIENTO DE AREA DE BOTADERO m2 525.00 2.77 1,454.2500 0.00% 0.00 0.0000 50.00% 262.50 727.13 50.00% 262.5000 727.1300 50.00% 262.50 727.120
99 06.03.02 REVEGETACIÓN DE AREAS AFECTADAS ha 1.00 1334.07 1,334.0700 0.00% 0.00 0.0000 0.00% 0.00 0.00% 0.0000 0.0000 100.00% 1.00 1,334.070
100 07 FLETE 6,864.0000 5,491.20 0.00 5,491.20 1,372.80
101 07.01 FLETE TERRESTRE glb 1.00 6864.00 6,864.0000 80.00% 0.80 5,491.2000 0.00% 0.00 80.00% 0.8000 5,491.2000 20.00% 0.20 1,372.800
102
103 COSTO DIRECTO 359,212.250 111,244.4900 111,619.5600 222,864.0500 136,348.2001
104 Gastos Generales (11.0749%) 39,782.62 12,320.28 12,361.82 24,682.11 15,100.5113
105 Utilidad (5%) 17,960.61 5,562.22 5,580.98 11,143.20 6,817.4100
106 ============= ============= ============= ============= =============
107 416,955.48 129,127.00 129,562.36 258,689.36 158,266.1214
Sub total (Factor de relacion (0.90)) 375,259.94 116,214.30 116,606.13 232,820.43 142,439.51
108
109 IGV (18%) 67,546.79 20,918.57 20,989.10 41,907.68 25,639.11
110 ============= ============= ============= ============= =============

111 PRESUPUESTO TOTAL 442,806.73 30.97% 137,132.87 31.07% 137,595.23 62.04% 274,728.11 37.96% 168,078.62
112
RESUMEN DE VALORIZACION
RENOVACION DE PUENTE EN EL CAMINO VECINAL SECTOR CHICMABAMBA EN LA LOCALIDAD
OBRA
URANMARCA, DISTRITO DE URANMARCA, PROVINCIA CHINCHEROS, DEPARTAMENTO APURIMAC
PERIODO DE VALORIZACION: DEL 01 AL 31 DE OCTUBRE AÑO 2020
CONTRATISTA CONSORCIO YANCE DISTRITO URANMARCA
SUPERVISOR GRUPO ALF S.A.C PROVINCIA CHINCHEROS
MONTO COTRATADO (CON IGV) 442,806.73
MONTO CONTRACTUAL DE LA OBRA (CON IGV) 442,806.73 DEPARTAMENTO APURIMAC
MONTO CONTRACTUAL DE LA OBRA SIN IGV) 375,259.94
VALORIZACION ACTUAL (CON IGV) 137,595.23
VALORIZACION ACTUAL (SIN IGV) 116,606.13
PLAZO DE EJECUCION. 60 dias calendarios LOCALIDAD URANMARCA

VALORIZACION
MONTO % AVANCE SALDO POR
DESCRIPCION
CONTRATO ACUMULADO VALORIZAR
ANTERIOR ACTUAL ACUMULADO
(S/IGV)

A: VALORIZACION CONTRACTUAL
CONTRATO PRINCIPAL 375,259.94 116,214.30 116,606.13 232,820.43 62.04% 142,439.51
TOTAL (A) 375,259.94 116,214.30 116,606.13 232,820.43 142,439.51

AVANCE FISICO DE OBRA 30.97% 31.07% 62.04% 37.96%

B: REAJUSTES
SALDO DE VALORIZACION ANTERIOR 0.00 0.00 0.00
CONTRATO PRINCIPAL 0.00 0.00 0.00
TOTAL (B) 0.00 0.00 0.00
VALORIZACION BRUTA (VB=A+B) 116,214.30 116,606.13 232,820.43 142,439.51

C: AMORTIZACIONES
AMORTIZACION DEL ADELANTO DIRECTO 0.00 0.00 0.00 0.00 0.00
AMORTIZACION DEL ADELANTO DE MATERIALES 0.00 0.00 0.00 0.00 0.00
TOTAL (C) 0.00 0.00 0.00 0.00 0.00

VALORIZACION NETA (VN=VB-C) 116,214.30 116,606.13 232,820.43 142,439.51

D: RETENCIONES
FONDO DE GARANTIA (5%*VB) 0.00 0.00 0.00
GASTOS DE LICITACION 0.00 0.00 0.00
MULTA POR ATRASO DE OBRA 0.00 0.00 0.00
TOTAL (D) 0.00 0.00 0.00

E: DESCUENTO A LOS GASTOS GENERALES


POR PERMANENCIA DEL PERSONAL PROFESIONAL EN OBRA 0.00 0.00 0.00
TOTAL (E) 0.00 0.00 0.00

F: MONTO A PAGAR AL CONTRATISTA


EN EFECTIVO (VN-D) 116,214.30 116,606.13 232,820.43 142,439.51
EN I.G.V. (18%*VN) 20,918.57 20,989.10 41,907.68 25,639.11
TOTAL (E) 137,132.87 137,595.23 274,728.11 168,078.62

TOTAL COMPROMISO A SOLICITAR 137,132.87 137,595.23 274,728.11 168,078.62


RESUMEN GENERAL DE VALORIZACIONES

RENOVACION DE PUENTE EN EL CAMINO VECINAL SECTOR CHICMABAMBA EN LA LOCALIDAD URANMARCA, DISTRITO DE


OBRA
URANMARCA, PROVINCIA CHINCHEROS, DEPARTAMENTO APURIMAC

PERIODO DE VALORIZACION: DEL 01 AL 31 DE OCTUBRE DE 2023


CONTRATISTA CONSORCIO YANCE DISTRITO URANMARCA
SUPERVISOR GRUPO ALF S.A.C PROVINCIA CHINCHEROS
MONTO COTRATADO (CON IGV) 442806.73 DEPARTAMENTO APURIMAC
PLAZO DE EJECUCION. 60 dias calendarios LOCALIDAD URANMARCA
COSTO DIRECTO (SIN IGV) 359,212.25 S/. - 0.00
AMORTIZACION DEL ADELANTO DEDUCCION DEDUCCION
VALORIZ. MONTO VALORIZACION
PERIODO DE VALORIZACION EN EFECTIVO DEL DEL IGV NETO A PAGAR
Nº BRUTO MATERIALES NETA
(con IGV) ADELANTO ADELANTO
Valor. 01 Del 01 al 30 de SETIEMBRE 2023 1.00 116,214.30 0.00 0.00 0.00 0.00 116,214.30 20,918.57 137,132.87
Valor. 02 Del 01 al 31 de OCTUBRE 2023 1.00 116,606.13 116,606.13 20,989.10 137,595.23
CALCULO DEL COEFICIENTE DE REAJUSTE "K"
RENOVACION DE PUENTE EN EL CAMINO VECINAL SECTOR CHICMABAMBA EN LA LOCALIDAD URANMARCA, DISTRITO DE
OBRA
URANMARCA, PROVINCIA CHINCHEROS, DEPARTAMENTO APURIMAC
PERIODO DE VALORIZACION: DEL 01 AL 31 DE OCTUBRE DEL 2023
FECHA VALOR REFERENCIAL DISTRITO URANMARC
A
LOCALIDAD URANMARC
FECHA DE INICIO DE OBRA : 11/09/2023
A
PLAZO DE
MONTO COTRATADO (CON IGV) 442,806.73 EJECUCION. 60 dias calendarios
COSTO DIRECTO (SIN IGV) 359,212.25
Io (Indice a la fecha del presupuesto)
K = 0.239*(Mr / Mo) + 0.268*(Cr / Co) + 0.101*(Ar / Ao) + 0.145*(Ar / AMo) + 0.069*(Mr / Mo)+ 0.178*(Ir/Io)
Io SET-2023 OCT-2023
I.U DESCRIPCION SIMBOLO COEF. %
Fecha Base Ir Ir/Io K Ir Ir/Io K Ir/Io K
47 MANO DE OBRA INC. LEYES SOCIALES. 0.224 93.920% 702.10 738.61 1.052 0.236
M
37 HERRAMIENTO MANUAL 0.015 6.080% 403.11 384.85 0.955 0.014
0.239 0.250
21 CEMENTO PORTAND TIPO I 0.187 69.598% 527.800 578.010 1.095 0.205

30 DÓLAR (GENERAL PONDERADO) 0.017 6.278% 688.550 658.930 0.957 0.016

43 MADERA NACIONALPARA ENCOFRADO Y CARPINTERIA C 0.023 8.499% 1,170.070 1,168.600 0.999 0.023

13 ASFALTO 0.003 1.099% 3,403.580 3,095.610 0.910 0.003

29 DÓLAR 0.039 14.5268% 688.550 658.930 0.957 0.037

0.268 100.0000% 0.283


5 AGREGADO GRUESO 0.061 60.1622% 468.110 474.130 1.013 0.062
4 AGREGADO FINO A 0.036 35.1202% 1,191.670 1,229.250 1.032 0.037
54 HORMIGON 0.005 4.7176% 545.180 568.520 1.043 0.005
0.101 100.0000% 3.08721 0.103
3 ACERO DE CONSTRUCCION CORRUGADO 0.087 59.6804% 913.200 826.740 0.905 0.078
2 ACERO DE CONSTRUCCION LISO 0.043 29.6646% 823.860 799.440 0.970 0.042
56 PLANCHA DE ACERO LAC A 0.000 0.0138% 1,147.670 1,066.390 0.929 0.000
72 TUBERIA DE PVC PARA AGUA 0.000 0.1584% 718.300 594.100 0.827 0.000
65 TUBERIA DE ACERO NEGRO Y/O GALVANIZADO 0.015 10.4828% 333.940 297.630 0.891 0.014
0.145 1.0000 4.5232 0.134
49 MAQUINARIA Y EQUIPO IMPORTADO 0.034 51.152% 436.490 422.940 0.969 0.034
48 MAQUINARIA Y EQUIPO NACIONAL M 0.018 27.110% 414.120 400.810 0.968 0.018
32 FLETE YTERRESTRE 0.016 21.739% 533.810 547.750 1.026 0.015
0.069 100.000% 2.96293 0.067
39 INDICE GENERAL DE PRECIOS LA CONSUMIDOR 0.171 96.476% 535.120 560.080 1.047 0.179
55 PINTURA TEMPLE 0.000 0.197% 772.140 844.000 1.093 0.000
I
54 PINTURA LATEX 0.002 1.013% 545.180 568.520 1.043 0.002
34 GASOLINA 0.004 2.314% 799.580 712.300 0.891 0.004
0.178 100.000% 4.07336 0.185

COEFICIENTE DE REAJUSTE: K= 1.000 1.023


REINTEGRO POR REAJUSTE
(CONTROL DE VALORIZACIONES Y REAJUSTES)
CONTRATO PRINCIPAL
OBRA RENOVACION DE PUENTE EN EL CAMINO VECINAL SECTOR CHICMABAMBA EN LA LOCALIDAD URANMARCA, DISTRITO DE
URANMARCA, PROVINCIA CHINCHEROS, DEPARTAMENTO APURIMAC
PERIODO DE VALORIZACION: DEL 01 AL 31 DE OCTUBRE DE 2023
CONTRATISTA CONSORCIO YANCE DISTRITO URANMARCA
SUPERVISOR GRUPO ALF S.A.C PROVINCIA CHINCHEROS
FECHA VALOR REFERENCIAL DEPARTAMENTO APURIMAC
MONTO COTRATADO (CON IGV) S/. 442,806.73 LOCALIDAD URANMARCA
ADELANTO DIRECTO 15% (CON IGV) S/. -
ADELANTO DIRECTO 15% (SIN IGV) S/. -
K = 1.0233
VALORIZACION REINTEGRO REINTEGRO DEDUCCION REINTEGRO
No. MES K-1 BRUTO NETO
PROGRAM. EJECUTADO PROGRAM. EJECUTADO AUTORIZADO EFECTIVO MATER. AUTORIZADO
FORMULA 01.-
1.00 Set-23 23,216.79 0.00 0.0233 541.99 0.00 0.00 0.00 0.00 0.00

TOTAL 23,216.79 0.00 541.99 0.00 0.00 0.00 0.00 0.00


EN VALORIZ. ANTERIOR 0.00
REINTEGRO ACTUAL 0.00
AMORTIZACION DEL ADELANTO DIRECTO
VALORIZACION DE OBRA Nº 02
RENOVACION DE PUENTE EN EL CAMINO VECINAL SECTOR CHICMABAMBA EN LA LOCALIDAD URANMARCA, DISTRITO
OBRA
DE URANMARCA, PROVINCIA CHINCHEROS, DEPARTAMENTO APURIMAC
PERIODO DE VALORIZACION:

CONTRATISTA CONSORCIO YANCE

SUPERVISOR GRUPO ALF S.A.C

MONTO COTRATADO (CON IGV) S/. 442,806.73

MONTO CONTRACTUAL DE LA OBRA (SIN IGV) S/. 375,259.94

ADELANTO DIRECTO 15% (CON IGV) S/. 0.00

NO CORRESPONDE
ADELANTO DIRECTO 15% (SIN IGV) S/. 0.00

VALORIZACION Nº 01 (SIN IGV) (V) S/. 129,562.36


Valorizacion V (sin Adelanto Directo (sin IGV)
AM =
IGV) X Monto Contratado (sin IGV)
VALORIZACION AMORTIZACION SALDO POR
ADELANTO
MONTO DEL ADELANTO AMORTIZAR
No. MES V DIRECTO (A) AM=V*A/C S=A-AM
1.00 Set-23 129,562.36 0.00 0.00 0.00
TOTAL 129,562.36 0.00

AMORTIZACION ACUMULADA ANTERIOR 0.00


AMORTIZACION PRESENTE VALORIZACION 0.00 sin IGV
AMORTIZACION ACUMULADA 0.00
SALDO POR AMORTIZAR S/. -
CURVA "S" DE OBRA PROGRAMADO Y EJECUTADO

OBRA "RENOVACION DE PUENTE; EN EL(LA) CAMINO VECINAL SECTOR CHICMABAMBA EN LA LOCALIDAD URANMARCA, DISTRITO DE URANMARCA,
PROVINCIA CHINCHEROS, DEPARTAMENTO APURIMAC"

MONTO TOTAL : 442,806.73 NUEVOS SOLES PLAZO DE EJECUCION : 60 DIAS CALENDARIOS (02 MESES)

CURVA DE AVANCE DE OBRA


PROGRAMADO
120%
AVANCE MESUAL ACUMULADO EN PORCENTAJE (%)

100.00%
100%

77.43%
80%

60% 62.04%

40% 30.97%

20%
6.19%
0.00%
0% 0.00%
MES 01 MES 02 MES 03
PROG.ACUM 0.00% 6.19% 77.43% 100.00%
EJECUTADO. 0.00% 30.97% 62.04%
VALORIZACIONES MENSUALES

MONTOS VALORIZADOS PROGRAMADOS MONTOS VALORIZADOS EJECUTADOS


MONTOS TOTAL (SIN/ IGV) PORCENTAJES MONTOS TOTAL (SIN/ IGV) PORCENTAJES
MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES PARCIAL ACUMUL. PARCIAL ACUMUL.
S/. S/. % % S/. S/. % %
0.00% 0.00% 0.00%
MES 01 23,216.79 23,216.79 6.19% 6.19% MES 01 116,214.30 116,214.30 30.97% 30.97%
MES 02 267,329.39 290,546.20 71.24% 77.43% MES 02 116,606.13 232,820.43 31.07% 62.04%
MES 03 84,713.76 375,259.96 22.57% 100.00% MES 03 0.00
TOTAL 375,259.94 100.00% TOTAL 232,820.43 62.04%