S10 Página 1

Presupuesto
Presupuesto 0404003 MEJORAMIENTO DEL SERVICIO DE LA TRANSITABLIDAD VIAL DE LA AV. LOS COLIBRIES DE LA CIUDAD DE TRUJILLO, PROVINCIA DE TRUJILLO - LA LIBERTAD
Cliente MUNICIPALIDAD PROVINCIAL DE TRUJILLO Costo al 28/02/2010
Lugar LA LIBERTAD - TRUJILLO - TRUJILLO

Item Descripción Und. Metrado Precio S/. Mano de Obra Material Equipo Subcontrato Subpartida Parcial S/.
01 OBRAS PROVISIONALES 789.55 1,249.13 1,691.22 10,000.00 13,729.90
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO glb 1.00 11,680.00 1,680.00 10,000.00 11,680.00
01.02 CARTEL DE IDENTIFICACION DE OBRA DE 3.60 x 6.00m u 1.00 1,434.43 374.08 1,049.13 11.22 1,434.43
01.03 DESVIO Y MANTENIMIENTO DE TRAFICO glb 1.00 615.47 415.47 200.00 615.47
02 TRABAJOS PRELIMINARES 25,088.00 1,470.03 1,481.77 28,039.78
02.01 DEMOLICION VEREDAS DE CONCRETO A PULSO, e = 0.10m m2 1,785.70 9.19 15,928.44 482.14 16,410.58
02.02 DEMOLICION DE CARPETA ASFALTICA m2 422.19 5.75 2,355.82 71.77 2,427.59
02.03 DEMOLICION DE SARDINEL EN FORMA DE "L", A PULSO m 958.15 3.06 2,845.71 86.23 2,931.94
02.04 DEMOLICION DE SARDINELES A PULSO m 72.54 2.30 161.76 5.08 166.84
02.05 REMOCION DE ARBOLES u 6.00 45.94 267.60 8.04 275.64
02.06 TRAZO Y REPLANTEO EN PAVIMENTACION m2 6,635.82 0.35 1,526.24 331.79 464.51 2,322.54
02.07 TRAZO Y REPLANTEO EN VEREDAS m2 3,672.76 0.49 991.65 624.37 183.64 1,799.65
02.08 TRAZO Y REPLANTEO EN SARDINELES m 3,573.01 0.46 964.71 500.22 178.65 1,643.58
02.09 TRAZO Y REPLANTEO EN PARCHES m2 170.62 0.36 46.07 13.65 1.71 61.42
03 MOVIMIENTO DE TIERRAS 28,747.62 11.52 119,433.44 148,192.59
03.01 CORTE EN TERRENO NATURAL A NIVEL DE SUB RASANTE C/EQUIPO m3 3,226.85 5.62 3,517.27 14,617.63 18,134.90
03.02 RELLENO MANUAL COMPACTADO CON MATERIAL PROPIO m3 192.07 24.61 2,446.97 11.52 2,268.35 4,726.84
03.03 EXCAVACION DE ZANJAS PARA SARDINELES m 194.78 1.53 290.22 7.79 298.01
03.04 EXCAVACION DE ZANJAS PARA SARDINELES EN FORMA DE "L" m 3,378.13 1.67 5,472.57 168.91 5,641.48
03.05 CORTE DE TERRENO NATURAL PARA VEREDAS, h = 0.10m m2 3,672.76 2.30 8,190.25 257.09 8,447.35
03.06 ELIMINACION DE MATERIAL EXCEDENTE C/ESPONJAMIENTO m3 5,133.92 21.61 8,830.34 102,113.67 110,944.01
04 PAVIMENTACION 7,299.41 99,072.80 63,902.94 143,466.43 313,741.57
04.01 PREPARACION DE LA SUB RASANTE m2 6,635.82 1.98 1,459.88 11,679.04 13,138.92
04.02 SUB BASE GRANULAR, e = 20cm m2 6,635.82 7.02 1,061.73 34,838.06 10,683.67 46,583.46
04.03 BASE GRANULAR, e = 20cm m2 6,635.82 12.37 1,990.75 48,839.64 31,254.71 82,085.09
04.04 BARRIDO Y LIMPIEZA P/LA CARPETA ASFALTICA m2 6,635.82 0.24 132.72 1,459.88 1,592.60
04.05 IMPRIMACION CON MC-30 m2 6,635.82 2.85 995.37 15,395.10 2,521.61 18,912.09
04.06 CARPETA ASFALTICA CON EMULSION, e=2" C/EQUIPO m2 6,635.82 22.82 1,658.96 6,304.03 143,466.43 151,429.41
05 PARCHADO 1,530.89 3,710.99 1,320.38 6,562.28
05.01 PERFILADO DE BORDES DE PAVIMENTO EXISTENTE m 289.41 2.30 645.38 20.26 665.64
05.02 CORTE DE BASE GRANULAR EN PARCHES, e = 7.5cm m2 170.62 1.67 276.40 8.53 284.94
05.03 BARRIDO Y ELIMINACION DE MATERIAL RESULTANTE DEL PARCHE m2 170.62 0.88 17.06 3.41 129.67 150.15
05.04 REPOSICION DE BASE GRANULAR EN PARCHES, e = 7.5cm m2 170.62 5.43 184.27 464.09 278.11 926.47
05.05 IMPRIMACION CON MC-30 EN PARCHES m2 170.62 4.33 175.74 395.84 167.21 738.78
05.06 EMULSION ASFALTICA, e=1.5" EN PARCHES m2 170.62 22.25 232.04 2,847.65 716.60 3,796.30
06 RECAPEO 9,382.03 81,273.06 31,585.57 114,925.03 237,165.69
06.01 BARRIDO Y LIMPIEZA MANUAL PARA RECAPEO m2 7,085.39 0.46 3,117.57 70.85 70.85 3,259.28
06.02 RIEGO CON MC-30 PARA RECAPEO m2 7,085.39 2.85 1,062.81 16,438.10 2,692.45 20,193.36
06.03 CARPETA ASFALTICA CON EMULSION, e=1.50" C/EQUIPO m2 7,085.39 17.42 1,771.35 6,731.12 114,925.03 123,427.49
06.04 SLURRY SEAL, e=10 mm. m2 13,721.21 6.58 3,430.30 64,764.11 22,091.15 90,285.56
07 VEREDAS DE CONCRETO 78,735.49 102,216.40 15,900.13 196,851.99
07.01 PERFILADO, NIVELACION Y COMPACTACION EN SUB-RASANTE P/ VEREDAS m2 3,672.76 2.91 6,794.61 3,893.13 10,687.73
07.02 BASE GRANULAR PARA VEREDAS, e = 0.10m m2 3,672.76 8.59 13,479.03 11,789.56 6,280.42 31,549.01
07.03 VEREDA, e = 4" CONCRETO f'c = 175 kg/cm2, a = 1.50m, una uña m2 3,458.53 40.95 53,607.22 82,658.87 5,360.72 141,626.80
07.04 RAMPAS - INGRESO A COCHERAS: CONCRETO 175 Kg/cm2 m2 214.22 40.02 3,320.41 4,920.63 332.04 8,573.08
07.05 CURADO DE VEREDAS CON CURADOR QUIMICO m2 3,672.76 0.82 367.28 2,644.39 3,011.66
07.06 JUNTAS DE DILATACION EN VEREDAS CADA CUATRO METROS, e=1/2" m 845.61 1.66 1,166.94 202.95 33.82 1,403.71
08 SARDINELES 69,246.79 90,376.17 22,722.13 182,345.09
08.01 PERFILADO DE BORDES DE PAVIMENTO EXISTENTE m 973.54 2.30 2,170.99 68.15 2,239.14
08.02 SARDINEL 0.15 x 0.40 m: CONCRETO f'c=175 kg/cm2 m 194.78 25.61 1,873.78 2,058.82 1,055.71 4,988.32
08.03 SARDINEL EN FORMA DE "L": CONCRETO f'c=175 Kg/cm2, b=0.15 m, B=0.40 m, m 3,378.13 40.83 43,307.63 73,677.02 20,944.41 137,929.05
h=0.25 m, H=0.40 m.
08.04 SARDINEL: ENCOFRADO Y DESENCOFRADO NORMAL m2 56.32 33.52 1,108.94 745.68 33.23 1,887.85
08.05 SARDINEL EN FORMA DE "L": ENCOFRADO Y DESENCOFRADO NORMAL m2 1,013.44 33.52 19,954.63 13,417.95 597.93 33,970.51
08.06 JUNTAS DE DILATACION EN SARDINEL CADA TRES METROS, e=1/2" m 9.60 2.93 17.57 10.08 0.48 28.13
S10 Página 1
Presupuesto
Presupuesto 0404003 MEJORAMIENTO DEL SERVICIO DE LA TRANSITABLIDAD VIAL DE LA AV. LOS COLIBRIES DE LA CIUDAD DE TRUJILLO, PROVINCIA DE TRUJILLO - LA LIBERTAD
Cliente MUNICIPALIDAD PROVINCIAL DE TRUJILLO Costo al 28/02/2010
Lugar LA LIBERTAD - TRUJILLO - TRUJILLO

Item Descripción Und. Metrado Precio S/. Mano de Obra Material Equipo Subcontrato Subpartida Parcial S/.
08.07 JUNTAS DE DILATACION EN SARDINEL ENFORMA DE "L" CADA TRES m 444.40 2.93 813.25 466.62 22.22 1,302.09
METROS, e=1/2"
09 VARIOS 22,045.93 16,504.03 12,075.34 50,625.31
09.01 SEÑALIZACION HORIZONTAL m2 2,037.10 10.39 5,113.12 7,740.98 8,311.37 21,165.47
09.02 SEÑALIZACION VERTICAL u 41.00 531.28 9,677.64 8,534.56 3,570.28 21,782.48
09.03 NIVELACION DE TAPAS DE BUZONES, h.prom = 0.10m u 8.00 170.70 1,217.84 91.28 56.48 1,365.60
09.04 LIMPIEZA EN OBRA m2 13,721.21 0.46 6,037.33 137.21 137.21 6,311.76
COSTO DIRECTO 1,177,254.20
GASTOS GENERALES (10%) 117,725.42
UTILIDAD (5%) 58,862.71
-----------------
SUB TOTAL 1,353,842.33
I.G.V. (19%) 257,230.04
============
PRESUPUESTO TOTAL 1,611,072.37