ID Task Task Name Duration Start Finish 24 Jul '23 31 Jul '23 07 Aug '23 14 Aug '23 21 Aug

sh 24 Jul '23 31 Jul '23 07 Aug '23 14 Aug '23 21 Aug '23
Mode S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
1 MANTENIMIENTO DEL PARQUE SAN MIGUEL 22 days Mon 24/07/23 Wed 23/08/23
2 INICIO 0 days Mon 24/07/23 Mon 24/07/23 24/07
3 OBRAS E INSTALACIONES PROVISIONALES 1 day Mon 24/07/23 Mon 24/07/23
4 LIMPIEZA DEL TERRENO MANUAL 1 day Mon 24/07/23 Mon 24/07/23
5 CARPINTERIA METALICA 4 days Tue 25/07/23 Mon 31/07/23
6 ESPALDAR METALICO DE BANCAS T FG 2.5'' 2 days Tue 25/07/23 Wed 26/07/23
7 MANTENIMIENTO Y MONTAJE DE TECHO DE 2 days Thu 27/07/23 Mon
ESTRADO 31/07/23
8 PINTURAS 17 days Tue 01/08/23 Wed 23/08/23
9 PINTURA ESMALTE JARDINERAS 5 days Tue 01/08/23 Mon 07/08/23
10 PINTURA ESMALTE PILETAS 3 days Tue 08/08/23 Thu 10/08/23
11 PINTURA ESMALTE ESTRADO 3 days Fri 11/08/23 Tue 15/08/23
12 PINTURA PISO ADOQUINADO 4 days Wed 16/08/23 Mon 21/08/23
13 PINTURA ESMALTE BARANDA METALICA 1 day Thu 03/08/23 Thu 03/08/23
14 PINTURA TECHO DE ESTRADO 2 days Tue 22/08/23 Wed 23/08/23
15 PINTURA ESMALTE CARPINTERIA FAROLES 1 day Fri 04/08/23 Fri 04/08/23
16 INSTALACIONES ELECTRICAS 2 days Tue 01/08/23 Wed 02/08/23
17 SUMINISTRO E INST. DE FAROLA LED TIPO ISLA 2 days Tue 01/08/23 Wed
ORNAMENTAL 02/08/23
18 FIN 0 days Wed 23/08/23 Wed 23/08/23 23/08

Task Project Summary Manual Task Start-only Deadline

Project: Project1 Split Inactive Task Duration-only Finish-only Progress


Date: Wed 05/07/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone