Está en la página 1de 55

C & V INVERSIONES INMOBILIARIAS

Cl. Narciso de la Colina N° 421, Of. 1401, Miraflores


www.cyvperu.com

HOJA DE PRESUPUESTO RESUMEN

OBRA: CONSTRUCCION DEL CONDOMINIO PORTOFINO


PROPIET. : PROPIA
LUGAR: Av. Santa Cruz 1550, Miraflores
FECHA: 20 de Enero del 2022
MONEDA: Nuevos Soles
VENTA VENTA CORREGIDO META REV 00
ITEM DESCRIPCIÓN COSTO DIRECTO COSTO DIRECTO COSTO DIRECTO DIFERENCIA INGRESO

1.00 DEMOLICION S/. 61,108.28 S/. 61,108.28 S/. 82,708.81 -21,600.53 EN S10
2.00 OBRAS PROVISIONALES & TRABAJOS PRELIMINARES S/. 2,256,582.94 S/. 2,256,582.94 S/. 1,882,639.33 373,943.61 EN S10
3.00 ESTRUCTURAS S/. 11,724,494.33 S/. 13,286,994.11 S/. 13,172,206.84 -1,447,712.51 EN S10
4.00 ARQUITECTURA S/. 12,655,060.90 S/. 12,655,060.90 S/. 14,377,168.34 -1,722,107.44 EN EXCEL
5.00 INSTALACIONES SANITARIAS S/. 1,323,821.31 S/. 1,323,821.31 S/. 1,331,208.48 -7,387.17 EN S10
6.00 INSTALACIONES ELECTRICAS S/. 2,332,475.86 S/. 2,332,475.86 S/. 2,093,336.69 239,139.17 EN S10
7.00 INSTALACIONES DE GAS S/. 162,000.00 S/. 162,000.00 S/. 162,000.00 0.00 EN S10
8.00 EQUIPAMIENTO S/. 3,423,911.22 S/. 3,423,911.22 S/. 2,731,704.16 692,207.06 EN S10
OBRAS COMPLEMENTARIAS S/. 360,000.00 S/. 360,000.00 S/. 360,000.00 0.00 PPTO VENTA

TOTAL COSTO DIRECTO S/. 34,299,454.84 S/. 35,861,954.62 S/. 36,192,972.65

GASTOS GENERALES 6.09% S/. 2,089,718.84 S/. 2,089,718.84 S/. 1,883,613.73

SUB TOTAL S/. 36,389,173.68 S/. 37,951,673.46 S/. 38,076,586.38

IGV 18.00% S/. 6,550,051.26 S/. 6,831,301.22 S/. 6,853,785.55

TOTAL S/. 42,939,224.94 S/. 44,782,974.68 S/. 44,930,371.93

DIFERENCIA S/. 147,397.25


DIFERENCIA S/. 1,991,146.99
C & V INVERSIONES INMOBILIARIAS
Cl. Narciso de la Colina N° 421, Of. 1401, Miraflores
www.cyvperu.com

PRESUPUESTO

CONDOMINIO PORTOFINO
20 DE ENERO DEL 2022
Costo HH por categoria

Indemnizacio Fiest. Fiest.


Jornal semanal vacaciones Asig. Esc
n Patrias Navidad

s/sem s/sem s/sem s/dia s/dia s/dia


Capataz
Operario 710.76 66.87 44.58 14.15 19.81 6.19
Oficial 562.36 52.61 35.07 11.13 15.59 4.87
Peon 510.00 47.25 31.50 10.00 14.00 4.38

Costo promedio semanal HH


% peso Costo/hr Incidencia TIEMPO
ESTRUCTURA Operario 60% 22.98 13.79
Oficial 10% 18.15 1.81
Peon 30% 16.40 4.92
Total Base 20.53 5.00

ACABADOS % peso Costo/hr Incidencia


Operario 80% 22.98 18.39
Oficial 5% 18.15 0.91
Peon 15% 16.40 2.46
Total Base 21.76 10.00

MURO ANCLADO % peso Costo/hr Incidencia


Operario 85% 22.98 19.54
Oficial 5% 18.15 0.91
Peon 10% 16.40 1.64
Total Base 22.08 4.00
ia
10% adicional por
INCREMENTO
Sub total Costo/hr
SALARIAL 2022-
2023

s/sem s/Hr s/Hr


30.34 pu empresa pu categoria s/igv
1,103.26 22.98 25.28 S/. 973.38 S/. 20.28 S/. 17.19
871.17 18.15 19.96 S/. 768.96 S/. 16.02 S/. 13.58
787.41 16.40 18.04 S/. 695.57 S/. 14.49 S/. 12.28

l HH

PROMEDIO S/. 21.50


C & V INVERSIONES INMOBILIARIAS
Cl. Narciso de la Colina N° 421, Of. 1401, Miraflores
www.cyvperu.com
HOJA DE PRESUPUESTO DETALLADO
OBRA: CONSTRUCCION DEL CONDOMINIO PORTOFINO
ESPECIALIDAD: DEMOLICION TOTAL
PROPIET. : PROPIA
LUGAR: Av. Santa Cruz 1550, Miraflores
FECHA: 20 de Enero del 2022
MONEDA: Nuevos Soles

ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL


01 OBRAS PROVISIONALES 14,714.89

01.01 PROTECCIONES COLECTIVAS Glb 1.00 12,349.45 12,349.45

01.01 TRABAJOS PRELIMINARES - SC Glb 1.00 2,365.44 2,365.44


0.00
03 DEMOLICION 0.00 64,150.00
DEMOLICION DE ESTRUCTURAS
03.01 EXISTENTES Glb 1.00 64,150.00 64,150.00

0.00

COSTO DIRECTO S/. 78,864.89


CONSIDERACIONES

240.00 02 operarios x 8H (4h instalacion + 4h desintalacion) x 15 vecinos FIN DE OBRA OFICIAL

96.00 02 operarios x 48h/sem FIN DE OBRA OFICIAL

Se considera cotizacion del SC GARCIA, incluyendo adicionales facturados a excepcion del adicional CAMA
BAJA, a causa de paralizacion no prevista en el ppto venta
REAL VENTA META BRECHA V BRECHA M
DEMOLICION UND METRADO P.U. TOTAL PPTO DEMOLICION
Demolicion y eliminacion de casa existente, pared perimetricas, area 1451 m2 glb 1.0 S/. 49,870.00 S/ 49,870.00 S/ 52,270.00 S/ 64,150.00 -S/ 12,854.24 -S/ 974.24 ya ejecutado, avance al 85%
colocacion de malla rashell con parantes de eucalipto - protec. A terceros glb 1.0 3,800.00 S/ 3,800.00 S/ 8,838.28 S/ 8,838.28 S/ 5,038.28 S/ 5,038.28 no valorizado ejecutado con personal de casa, SI considerado en ppto meta
EXCAVACION PPTO EXC MASIVA
EXCAVACION MASIVA C/EQUIPO INC. ELIMINACION m3 19,485.00 24.30 S/ 473,485.50 S/ 512,633.42 S/ 559,597.90 S/ 21,067.92 S/ 68,032.40 ahorro de 68k
EXCAVACION LOCALIZADA Y ELIMINACION ZAPATAS CIMIENTOS DE MURO ANCLADOglb 640.85 27.40 S/ 17,559.29 S/ 60,201.90 S/ 27,305.88 S/ 42,642.61 S/ 9,746.59 ahorro de 9k
CONTROL DE POLVOS CON CISTERNA PARA DEMOLICION(ayudante,motobomba)6 glb 6.00 430.00 S/ 2,580.00 no se valorizara,no considerado en ppto meta
demolicion de zapata existente colindante alos vecinos area 1451 m2 m2 194.00 70.00 S/ 13,580.00 S/ 13,580.00 S/ - no ahorro, no perdida

movilzacion, desmovilizacion de equipo, izaje m3 1.00 4,500.00 S/ 4,500.00

HORAS MÁQUINA
HORAS MÁQUINA HM 487.00 200.00 S/ 97,400.00
SUB-TOTAL S/ 662,774.79
IGV S/ 119,299.46
TOTAL S/ 782,074.25

ADICIONAL 01 - DEMOLICION
SC CERTIFICACION S/ 9,800.00 no considerado en el CC contractual
SC CAMBIO DE RUTA ELIMINACION S/ 4,480.00 no considerado en el CC contractual
SC CAMA BAJA S/ 974.24 Perdida, no considerado en el ppto meta

PPTO CONCRETO ARMADO


INCREMENTO TARIFA DEL MERCADO
TIPO RECURSO PROVEDOR
Factor seguridad
$/TON acero TRADI 4.35 1.03 4.48
FC 280 P57 concreto UNICON 260.00 1.03 267.80
FC 350 P67 concreto UNICON 286.00 1.03 294.58
FC 100 P57 concreto UNICON 218.00 1.03 224.54
FC 210 P57 concreto UNICON 245.00 1.03 252.35
FC 210 P67 concreto UNICON 248.00 1.03 255.44
FC 280 P67 concreto UNICON 263.00 1.03 270.89
FC 350 P57 concreto UNICON 283.00 1.03 291.49
bolsa cemento TI CEMEX 19.49 1.10 21.44
C & V INVERSIONES INMOBILIARIAS
Cl. Narciso de la Colina N° 421, Of. 1401, Miraflores
www.cyvperu.com
HOJA DE PRESUPUESTO DETALLADO
OBRA: CONSTRUCCION DEL CONDOMINIO PORTOFINO
ESPECIALIDAD: OBRAS PROVISIONALES & TRABAJOS PRELIMINARES
PROPIET. : PROPIA
LUGAR: Av. Santa Cruz 1550, Miraflores
FECHA: 20 de Enero del 2022
MONEDA: Nuevos Soles

ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL


01 OBRAS PROVISIONALES 199,334.57
01.01 OFICINAS DE OBRAS Glb 1.00 10,690.26 10,690.26
01.02 ALMACEN DE OBRA Glb 1.00 14,023.18 14,023.18
01.03 COMEDOR PERSONAL OBRERO Glb 1.00 16,200.45 16,200.45
01.04 SERVICIOS HIGIENICOS PORTATILES DE OBRA - con Mes 3.00 1,908.41 5,725.23
01.05 gancho Mes 10.00 350.00 3,500.00
01.06 BAÑO PERSONAL OBRERO Glb 1.00 10,461.21 10,461.21
01.07 VESTUARIO PERSONAL OBRERO Glb 1.00 6,974.14 6,974.14
01.08 CERCO PROVISIONAL Glb 1.00 35,720.00 35,720.00
01.09 ESCALERA
PLATAFORMAMETALICA PROVISIONAL
DE SOPORTE - ESCUADRAS, CANALES & Glb 1.00 28,577.86 28,577.86
01.10 PANELERIA DE MADERA Glb 1.00 43,872.00 43,872.00
01.11 CARTEL DE OBRA Und 1.00 1,800.00 1,800.00
01.12 ALMACEN DE ASCENSOR Glb 1.00 19,790.24 19,790.24
DESMONTAJE DE CASETA DE VENTAS 1.00 2,000.00 2,000.00
0.00
02 TRABAJOS PRELIMINARES 0.00 351,180.02
02.01 INSTALACION PROVISIONAL DE AGUA glb 1.00 16,113.60 16,113.60
02.02 TANQUE DE AGUA PROVISIONAL glb 1.00 2,093.90 2,093.90
02.03 AGUA PARA LA CONSTRUCCION mes 16.00 750.00 12,000.00
02.04 DESAGÜE PROVISIONAL PARA LA CONSTRUCCION glb 1.00 4,525.68 4,525.68
02.05 RED PROVISIONAL ENERGIA ELECTRICA glb 1.00 46,103.10 46,103.10
02.06 ENERGIA ELECTRICA PARA LA CONSTRUCCION mes 16.00 1,800.00 28,800.00
INSTALACION TELEFONICA Y COMUNICACION
02.07 PROVISIONAL glb 1.00 2,400.00 2,400.00
02.08 TELEFONO E INTERNET PARA LA OBRA mes 16.00 600.00 9,600.00
02.09 POZO A TIERRA und 1.00 1,820.00 1,820.00
02.10 GUARDIANIA DE OBRA mes 16.00 13,825.00 221,200.00
02.11 RADIOS PARA COMUNICACION DURANTE LA OBRA und 6.00 487.29 2,923.74
02.12 CAMARAS DE VIGILANCIA PROVISIONAL glb 1.00 3,600.00 3,600.00
0.00
03 TRAZO, NIVELES Y REPLANTEO 0.00 237,548.82
TRAZO DURANTE LA EJECUCION DE LA OBRA -
03.01 ESTRUCTURAS mes 16.00 10,934.31 174,948.96
TRAZO DURANTE LA EJECUCION DE LA OBRA -
03.02 ACABADOS mes 6.00 10,433.31 62,599.86
0.00

04 MOVILIZACION DE EQUIPO & HERRAMIENTAS 79,880.00


04.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 79,880.00 79,880.00
0.00
05 TRANSPORTE VERTICAL y HORIZONTAL 0.00 734,496.53
ACARREO VERTICAL DE MATERIALES CON TORRE
05.01
GRUA
ACARREO VERTICAL DE MATERIALES CON TORRE
05.01.01 GRUA (INC. MOVILIZACION, INSTALACION, OPERADOR Y mes 10.00 45,084.40 450,844.00
MANTENIMIENTO)

05.01.02 ALQUILER DE GRUPO ELECTROGENO mes 10.00 3,936.00 39,360.00


05.01.03 COMBUSTIBLE PARA EL G.E. mes 10.00 9,300.00 93,000.00
05.01.03 ZAPATA PARA TORRE GRUA
05.01.03.01 CONCRETO PREMEZCLADO F'C=280 KG/CM2 T.I M3 70.72 355.85 25,167.11
05.01.03.02 ACERO fy=4200 kg/cm2 GRADO 60 Kg 5,639.61 5.72 32,263.08
05.02 ACARREO HORIZONTAL
05.02.01 mes 11.00 8,532.94 93,862.34
ACARRERO HORIZONTAL CON PERSONAL Y ESTOCAS
0.00
06 LIMPIEZA PERMANENTE DE OBRA 0.00 142,617.60
06.01 LIMPIEZA PERMANENTE DE OBRA mes 16.00 8,433.60 134,937.60
06.02 ELIMINACION VERTICAL - CHUTE Glb 1.00 7,680.00 7,680.00
0.00
07 SEGURIDAD Y SALUD 0.00 537,794.02
07.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION
DE PLAN DE SEGURIDAD mes 16.00 8,654.00 138,464.00
07.02 EQUIPOS DE PROTECCION INDIVIDUAL glb 1.00 182,416.78 182,416.78
07.03 EQUIPOS DE PROTECCION COLECTIVA glb 1.00 163,548.70 163,548.70
07.04 SEÑALIZACION TEMPORAL DE OBRA glb 1.00 8,284.50 8,284.50
CAPACITACIONES ESTANDARES DE SALUD Y
07.05
SEGURIDAD
RECURSOS PARA RESPUESTA ANTE EMERGENCIA EN glb 1.00 6,464.04 6,464.04
07.06 SEGURIDAD Y SALUD DURANTE EL TRABAJO glb 1.00 6,616.00 6,616.00
07.07 EXAMENES MEDICOS PARA PERSONAL OBRERO glb 1.00 32,000.00 32,000.00
0.00

COSTO DIRECTO S/. 2,282,851.56


CONSIDERACIONES

136.00

4.00
34.00

80.00
32.00

48.00
363.72

S/. 2,400.00

2.00

6.00

207.84

207.84

S/. 304.00
S/. 76.00

0.1429
0.1667

S/. 22,671.00

415.68

S/. 26,403.67

207.84

S/. 9,600.00

70.72
371.18

1,454.88

727.44
34.00

415.68

1,870.56
1,870.56

S/. 17.00
PRESUPUESTO DE SEGURIDAD, SALUD OCUPACIONAL Y MEDIO AMBIENTE

2022 2023
JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE
HISTOGRAMA DE TRABAJADORES (STAFF GG Y POR CASA)
mes 01 mes 02 mes 03 mes 04 mes 05 mes 06 mes 07 mes 08 mes 09 mes 10 mes 11 mes 12 mes 13 mes 14 mes 15
Personal Staff 6 6 6 7 7 8 8 9 9 9 10 10 10 7 3
RESIDENTE DE OBRA GASTOS GENERALES C&V 1 1 1 1 1 1 1 1 1 1 1 1 1 1 14
INGENIERO DE CAMPO GASTOS GENERALES C&V 1 1 1 1 1 1 1 1 8
ARQUITECTO DE CAMPO GASTOS GENERALES C&V 1 1 1 1 1 1 1 1 8
MAESTRO DE OBRA GASTOS GENERALES C&V 1 1 1 1 1 1 1 1 1 1 1 1 1 13
ARQUITECTO DE CALIDAD GASTOS GENERALES C&V 1 1 1 1 1 1 1 1 1 1 1 11
TECNICO DE CALIDAD GASTOS GENERALES C&V 1 1 1 1 4
JEFE SSOMA GASTOS GENERALES C&V 1 1 1 1 1 1 1 1 1 1 1 1 1 13
INGENIERO DE OT GASTOS GENERALES C&V 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 15
ADMINISTRADOR DE OBRA GASTOS GENERALES C&V 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 15
ALMACENERO GASTOS GENERALES C&V 1 1 1 1 1 1 1 1 1 1 1 1 1 1 14

TRAB. PRELIMINARES
MUROS ANCLADOS CIMENTACIONES CISTERNA LOSA CONTRATERRENO
ESTRUCTURA
SC TORRE GRUA SC ELEVADOR
ACABADOS HUMEDOS
ACABADOS SECOS
OBRAS EXTERIORES

Personal Obrero - casa 2 2 2 2 4 6 6 6 6 6 19 31 29 29 9

RIGER SEGURIDAD C&V 2 2 2 2 2 2 2 2 16


SEÑALERO SEGURIDAD C&V 2 2 2 2 2 2 2 2 2 2 2 2 2 2 28
PDR SEGURIDAD C&V 1 1 1 1 1 1 1 1 1 9
MONITOR SEGURIDAD NO CONSIDERADO 1 1 1 1 1 1 1 1 1 9
DESINFECCION COVID SEGURIDAD hh señalero

OBRAS PROVISIONALES OBRAS PROVISIONALES SC


MANTENIMIENTO OBRAS PROVISIONALES SC
VECINOS OBRAS PROVISIONALES SC
ACARREO DE MATERIALES OBRAS PROVISIONALES SC
LLAVERO OBRAS PROVISIONALES C&V 1 1 1 1 1
LIMPIEZA GRUESA OBRAS PROVISIONALES SC
LIMPIEZA FINA OBRAS PROVISIONALES SC

CONCRETEROS CONCRETO SC
ENCOFRADORES ENCOFRADO SC

LADRILLO SILICO CALCAREO ACABADOS HUMEDOS SC


LIMPIEZA CIELORASO, MUROSACABADOS HUMEDOS SC
SOLAQUEO MUROS KINGBLOCACABADOS HUMEDOS SC
SOLAQUEO Y FORJADO DE ESCACABADOS HUMEDOS SC
SOLAQUEO DE DUCTO DE ASC ACABADOS HUMEDOS SC
LIMPIEZA FACHADA EXTERIOR ACABADOS HUMEDOS SC
ENCHAPE DE PISOS ACABADOS HUMEDOS SC
TODISTAS ACABADOS HUMEDOS C&V 12 24 24 24 8
SANITARIOS IISS SC
ELECTRICOS IIEE SC

8 8 8 9 11 14 14 15 15 15 29 41 39 36 12

2) EQUIPOS DE PROTECCION INDIVIDUAL - CANTIDAD


Descripción Tiempo de Vida mes 01 mes 02 mes 03 mes 04 mes 05 mes 06 mes 07 mes 08 mes 09 mes 10 mes 11 mes 12 mes 13 mes 14 mes 15 Total
Util /Mensual
Lentes de Policarbonato lu 2.00 16.00 4.00 16.00 4.00 22.00 12.00 28.00 12.00 30.00 12.00 58.00 82.00 78.00 72.00 24.00 470.00### 1,645.00
I) Protector Visual
Sobrelentes 1.00 6.00 6.00 7.00 8.00 9.00 10.00 10.00 3.00 59.00### 1,180.00
Guantes Multiflex 2.00 4.00 4.00 4.00 4.00 8.00 12.00 12.00 12.00 12.00 12.00 38.00 62.00 58.00 58.00 18.00 318.00### 1,590.00
Guantes de Jebe 2.00 4.00 4.00 4.00 4.00 8.00 12.00 12.00 12.00 12.00 12.00 38.00 62.00 58.00 58.00 18.00 318.00### 2,544.00
II) Protección para manos Guantes de Nitrolo 2.00 4.00 4.00 4.00 4.00 8.00 12.00 12.00 12.00 12.00 12.00 38.00 62.00 58.00 58.00 18.00 318.00### 1,590.00
Guantes dielectrico 1.00 2.00 2.00### 350.00
Guantes de Cuero 2.00 4.00 4.00 4.00 4.00 8.00 12.00 12.00 12.00 12.00 12.00 38.00 62.00 58.00 58.00 18.00 318.00### 5,088.00
Orejera para adaptar el ca 1.00 6.00 6.00 7.00 8.00 9.00 10.00 10.00 3.00 59.00### 1,475.00
III) Proteccion Auditiva
Tapon de oido 4.00 8.00 8.00 8.00 8.00 16.00 24.00 24.00 24.00 24.00 24.00 76.00 124.00 116.00 116.00 36.00 636.00### 1,590.00
Respirador de 2 filtros 1.00 2.00 6.00 6.00 6.00 19.00 31.00 29.00 29.00 9.00 137.00### 9,179.00
IV) Protección Respiratoria
Filtro retencion de particul 2.00 4.00 12.00 12.00 12.00 38.00 62.00 58.00 58.00 18.00 274.00### 12,330.00
Casco tipo Jockey 1.00 2.00 2.00 4.00 6.00 6.00 19.00 29.00 9.00 77.00### 1,655.50
V) Protección Cabeza Casco tipo Jockey c/ratche 1.00 6.00 6.00 8.00 10.00 30.00### 1,158.00
Barbiquejo con mentonera 4.00 2.00 - 2.00 - 4.00 - 6.00 - 6.00 - 19.00 - 29.00 - 9.00 77.00### 115.50
Camisa STAFF 3.00 18.00 18.00 36.00### 1,350.00
Polo 2.00 4.00 4.00 4.00 4.00 8.00 12.00 12.00 12.00 12.00 12.00 38.00 62.00 58.00 58.00 18.00 318.00### 3,816.00
Chaleco verde STAFF 1.00 6.00 6.00 12.00### 384.00
Chaleco anaranjado 1.00 2.00 2.00 4.00 6.00 6.00 19.00 29.00 9.00 77.00### 1,386.00
VI) Ropa protectora
Pantalon 1.00 2.00 2.00 2.00 2.00 4.00 6.00 6.00 6.00 6.00 6.00 19.00 31.00 29.00 29.00 9.00 159.00### 2,973.30
Cortaviento 2.00 4.00 4.00 4.00 4.00 8.00 12.00 12.00 12.00 12.00 12.00 38.00 62.00 58.00 58.00 18.00 318.00### 1,113.00
Traje Tyvex 1.00 2.00 2.00 4.00 8.00### 100.00
Mandil para Soldador 1.00 1.00 1.00 2.00### 42.00
Botas de Jebe con punta d 1.00 2.00 2.00 4.00 6.00 6.00 19.00 29.00 9.00 77.00### 2,464.00
Botines cuero con punta d 1.00 6.00 2.00 8.00### 960.00
VII) Protección Pies Botines cuero con punta d 1.00 2.00 2.00 2.00 2.00 4.00 6.00 6.00 6.00 6.00 6.00 19.00 31.00 29.00 29.00 9.00 159.00### 7,950.00
Botines Dielectricos 1.00 1.00 1.00 - - - - - - - - 2.00### 120.00
Escarpines para Soldador 1.00 1.00 1.00 - - - - - - - - 2.00### 30.00
VIII) Proteccion contra caidas Arnes de cuerpo entero 1.00 8.00 - - 11.00 14.00 15.00 48.00### 8,880.00

2) EQUIPOS DE PROTECCION INDIVIDUAL - COSTO


Descripción Precio x Und mes 01 mes 02 mes 03 mes 04 mes 05 mes 06 mes 07 mes 08 mes 09 mes 10 mes 11 mes 12 mes 13 mes 14 mes 15 Total
Lentes de Policarbonato lu S/. 3.50 S/ 56.00 S/ 14.00 S/ 56.00 S/ 14.00 S/ 77.00 S/ 42.00 S/ 98.00 S/ 42.00 S/ 105.00 S/ 42.00 S/ 203.00 S/ 287.00 S/ 273.00 S/ 252.00 S/ 84.00 S/. 1,645.00### 0.00
I) Protector Visual
Sobrelentes S/. 20.00 S/ 120.00 S/ - S/ 120.00 S/ - S/ 140.00 S/ - S/ 160.00 S/ - S/ 180.00 S/ - S/ 200.00 S/ - S/ 200.00 S/ - S/ 60.00 S/. 1,180.00### 0.00
Guantes Multiflex S/. 5.00 S/ 20.00 S/ 20.00 S/ 20.00 S/ 20.00 S/ 40.00 S/ 60.00 S/ 60.00 S/ 60.00 S/ 60.00 S/ 60.00 S/ 190.00 S/ 310.00 S/ 290.00 S/ 290.00 S/ 90.00 S/. 1,590.00### 0.00
Guantes de Jebe S/. 8.00 S/ 32.00 S/ 32.00 S/ 32.00 S/ 32.00 S/ 64.00 S/ 96.00 S/ 96.00 S/ 96.00 S/ 96.00 S/ 96.00 S/ 304.00 S/ 496.00 S/ 464.00 S/ 464.00 S/ 144.00 S/. 2,544.00### 0.00
II) Protección para manos Guantes de Nitrolo S/. 3.50 S/ 14.00 S/ 14.00 S/ 14.00 S/ 14.00 S/ 28.00 S/ 42.00 S/ 42.00 S/ 42.00 S/ 42.00 S/ 42.00 S/ 133.00 S/ 217.00 S/ 203.00 S/ 203.00 S/ 63.00 S/. 1,113.00### 0.00
Guantes dielectrico S/. 175.00 S/ 350.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 350.00### 0.00
Guantes de Cuero S/. 16.00 S/ 64.00 S/ 64.00 S/ 64.00 S/ 64.00 S/ 128.00 S/ 192.00 S/ 192.00 S/ 192.00 S/ 192.00 S/ 192.00 S/ 608.00 S/ 992.00 S/ 928.00 S/ 928.00 S/ 288.00 S/. 5,088.00### 0.00
Orejera para adaptar el ca S/. 25.00 S/ 150.00 S/ - S/ 150.00 S/ - S/ 175.00 S/ - S/ 200.00 S/ - S/ 225.00 S/ - S/ 250.00 S/ - S/ 250.00 S/ - S/ 75.00 S/. 1,475.00### 0.00
III) Proteccion Auditiva
Tapon de oido S/. 2.50 S/ 20.00 S/ 20.00 S/ 20.00 S/ 20.00 S/ 40.00 S/ 60.00 S/ 60.00 S/ 60.00 S/ 60.00 S/ 60.00 S/ 190.00 S/ 310.00 S/ 290.00 S/ 290.00 S/ 90.00 S/. 1,590.00### 0.00
Respirador de 2 filtros S/. 67.00 S/ 134.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ 402.00 S/ 402.00 S/ 402.00 S/ 1,273.00 S/ 2,077.00 S/ 1,943.00 S/ 1,943.00 S/ 603.00 S/. 9,179.00### 0.00
IV) Protección Respiratoria
Filtro retencion de particul S/. 45.00 S/ 180.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ 540.00 S/ 540.00 S/ 540.00 S/ 1,710.00 S/ 2,790.00 S/ 2,610.00 S/ 2,610.00 S/ 810.00 S/. 12,330.00### 0.00
Casco tipo Jockey S/. 21.50 S/ 43.00 S/ - S/ 43.00 S/ - S/ 86.00 S/ - S/ 129.00 S/ - S/ 129.00 S/ - S/ 408.50 S/ - S/ 623.50 S/ - S/ 193.50 S/. 1,655.50### 0.00
V) Protección Cabeza Casco tipo Jockey c/ratche S/. 38.60 S/ 231.60 S/ - S/ 231.60 S/ - S/ - S/ - S/ 308.80 S/ - S/ - S/ - S/ 386.00 S/ - S/ - S/ - S/ - S/. 1,158.00### 0.00
Barbiquejo con mentonera S/. 1.50 S/ 3.00 S/ - S/ 3.00 S/ - S/ 6.00 S/ - S/ 9.00 S/ - S/ 9.00 S/ - S/ 28.50 S/ - S/ 43.50 S/ - S/ 13.50 S/. 115.50### 0.00
Camisa STAFF S/. 37.50 S/ 675.00 S/ - S/ 675.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 1,350.00### 0.00
Polo S/. 12.00 S/ 48.00 S/ 48.00 S/ 48.00 S/ 48.00 S/ 96.00 S/ 144.00 S/ 144.00 S/ 144.00 S/ 144.00 S/ 144.00 S/ 456.00 S/ 744.00 S/ 696.00 S/ 696.00 S/ 216.00 S/. 3,816.00### 0.00
Chaleco verde STAFF S/. 32.00 S/ 192.00 S/ - S/ 192.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 384.00### 0.00
Chaleco anaranjado S/. 18.00 S/ 36.00 S/ - S/ 36.00 S/ - S/ 72.00 S/ - S/ 108.00 S/ - S/ 108.00 S/ - S/ 342.00 S/ - S/ 522.00 S/ - S/ 162.00 S/. 1,386.00### 0.00
VI) Ropa protectora
Pantalon S/. 18.70 S/ 37.40 S/ 37.40 S/ 37.40 S/ 37.40 S/ 74.80 S/ 112.20 S/ 112.20 S/ 112.20 S/ 112.20 S/ 112.20 S/ 355.30 S/ 579.70 S/ 542.30 S/ 542.30 S/ 168.30 S/. 2,973.30### 0.00
Cortaviento S/. 3.50 S/ 14.00 S/ 14.00 S/ 14.00 S/ 14.00 S/ 28.00 S/ 42.00 S/ 42.00 S/ 42.00 S/ 42.00 S/ 42.00 S/ 133.00 S/ 217.00 S/ 203.00 S/ 203.00 S/ 63.00 S/. 1,113.00### 0.00
Traje Tyvex S/. 12.50 S/ 25.00 S/ - S/ 25.00 S/ - S/ 50.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 100.00### 0.00
Mandil para Soldador S/. 21.00 S/ 21.00 S/ - S/ - S/ - S/ 21.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 42.00### 0.00
Botas de Jebe con punta d S/. 32.00 S/ 64.00 S/ - S/ 64.00 S/ - S/ 128.00 S/ - S/ 192.00 S/ - S/ 192.00 S/ - S/ 608.00 S/ - S/ 928.00 S/ - S/ 288.00 S/. 2,464.00### 0.00
Botines cuero con punta d S/. 120.00 S/ 720.00 S/ - S/ - S/ - S/ - S/ 240.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 960.00### 0.00
VII) Protección Pies Botines cuero con punta d S/. 50.00 S/ 100.00 S/ 100.00 S/ 100.00 S/ 100.00 S/ 200.00 S/ 300.00 S/ 300.00 S/ 300.00 S/ 300.00 S/ 300.00 S/ 950.00 S/ 1,550.00 S/ 1,450.00 S/ 1,450.00 S/ 450.00 S/. 7,950.00### 0.00
Botines Dielectricos S/. 60.00 S/ 60.00 S/ - S/ - S/ - S/ 60.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 120.00### 0.00
Escarpines para Soldador S/. 15.00 S/ 15.00 S/ - S/ - S/ - S/ 15.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 30.00### 0.00
VIII) Proteccion contra caidas Arnes de cuerpo entero S/. 185.00 S/ 1,480.00 S/ - S/ - S/ - S/ 2,035.00 S/ - S/ 2,590.00 S/ - S/ 2,775.00 S/ - S/ - S/ - S/ - S/ - S/ - S/. 8,880.00### 0.00

S/. 4,905.00 S/. 363.40 S/. 1,945.00 S/. 363.40 S/. 3,563.80 S/. 1,330.20 S/. 4,843.00 S/. 2,032.20 S/. 5,713.20 S/. 2,032.20 S/. 8,728.30 S/. 10,569.70 S/. 12,459.30 S/. 9,871.30 S/. 3,861.30 S/. 72,581.30

3) EQUIPO PROTECCION COLECTIVA - CANTIDAD


Descripción mes 01 mes 02 mes 03 mes 04 mes 05 mes 06 mes 07 mes 08 mes 09 mes 10 mes 11 mes 12 mes 13 mes 14 mes 15
MALLA RASCHEL 80% Grs VERDE/NEGRO 1.00 1.00 - 1.00 - 1.00 - 1.00 - 1.00 - - 6.00
MADERA CACHIMBO 2" X 2" X 12 PIES 100.00 100.00 - 100.00 200.00 200.00 - - - - - - 700.00
SOGA DE NAYLON 5/8" 2.00 2.00 - 2.00 2.00 2.00 2.00 - - - - - 12.00
CAPUCHONES SEGURIDAD 3/4", 1" NARANJA 500.00 500.00 - 500.00 - 500.00 - - - - - - 2000.00
CAPUCHONES SEGURIDAD 3/8", 1/2", 5/8" NAR 500.00 500.00 - 500.00 - 500.00 - - - - - - 2000.00
SC MALLA ANTICAIDA 1.00 1.00
SC FABRICACION MARQUESINA DE PROTECCION DE CAIDAS 11.00 11.00

3) EQUIPOS PROTECCION COLECTIVA - COSTOS


Descripción Precio x Und mes 01 mes 02 mes 03 mes 04 mes 05 mes 06 mes 07 mes 08 mes 09 mes 10 mes 11 mes 12 mes 13 mes 14 mes 15 Total
MALLA RASCHEL 80% Grs S/. 700.00 S/ 700.00 S/ 700.00 S/ - S/ 700.00 S/ - S/ 700.00 S/ - S/ 700.00 S/ - S/ 700.00 S/ - S/ - S/ - S/ - S/ - S/. 4,200.00 ###
MADERA CACHIMBO 2" X 2" S/. 18.80 S/ 1,880.00 S/ 1,880.00 S/ - S/ 1,880.00 S/ 3,760.00 S/ 3,760.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 13,160.00 ###
SOGA DE NAYLON 5/8" S/. 160.00 S/ 320.00 S/ 320.00 S/ - S/ 320.00 S/ 320.00 S/ 320.00 S/ 320.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 1,920.00 ###
CAPUCHONES SEGURIDAD 3 S/. 0.31 S/ 155.00 S/ 155.00 S/ - S/ 155.00 S/ - S/ 155.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 620.00 ###
CAPUCHONES SEGURIDAD 3 S/. 0.29 S/ 145.00 S/ 145.00 S/ - S/ 145.00 S/ - S/ 145.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 580.00 ###
SC MALLA ANTICAIDA S/. 51,659.53 S/ - S/ - S/ - S/ - S/ 51,659.53 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 51,659.53 ###
SC FABRICACION MARQUES S/. 130.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 1,430.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 1,430.00 ###

S/. 3,200.00 S/. 3,200.00 S/. 0.00 S/. 3,200.00 S/. 55,739.53 S/. 5,080.00 S/. 320.00 S/. 2,130.00 S/. 0.00 S/. 700.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 73,569.53

4) SEÑALIZACION TEMPORAL DE OBRA - CANTIDAD


Descripción mes 01 mes 02 mes 03 mes 04 mes 05 mes 06 mes 07 mes 08 mes 09 mes 10 mes 11 mes 12 mes 13 mes 14 mes 15
LETRERO ACRILICO SALIDA 60X40cm 20.00 20.00 - - - 10.00 - - - 10.00 - - - 60.00 67.58
CINTA SEÑALIZADORA COLOR ROJO B.T. 10.00 10.00 - 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 - - 60.00 169.5
CONO DE SEÑALIZACION NARANJA DE 28" DE 20.00 20.00 - - - - - - - - - - - 40.00 24
BARRA RETRACTIL DE 1.30m A 2.30m 20.00 20.00 - - - - - - - - - - - 40.00 16
Señalizacion Interna de Obra 80.00 80.00 - 50.00 - 50.00 - 50.00 - - - - - 310.00 9.0329
Triplay de 4MM (Planchas) 10.00 10.00 - 10.00 - 10.00 - 10.00 - - - - - 50.00 133.5
Listones de 2"X2"X3.0M 50.00 50.00 - 50.00 50.00 - 50.00 - - - - - 250.00 25.8
GALONES DE PINTURA COLOR NARANJA (FAST) 2.00 2.00 - 2.00 2.00 2.00 - - - 10.00 46

4) SEÑALIZACION TEMPORAL DE OBRA - COSTO


Descripción Precio x Und mes 01 mes 02 mes 03 mes 04 mes 05 mes 06 mes 07 mes 08 mes 09 mes 10 mes 11 mes 12 mes 13 mes 14 mes 15 Total
LETRERO ACRILICO SALID S/. 67.58 S/ 1,351.60 S/ 1,351.60 S/ - S/ - S/ - S/ 675.80 S/ - S/ - S/ - S/ 675.80 S/ - S/ - S/ - S/ - S/ - S/. 4,054.80 ###
CINTA SEÑALIZADORA COL S/. 169.50 S/ 1,695.00 S/ 1,695.00 S/ - S/ 847.50 S/ 847.50 S/ 847.50 S/ 847.50 S/ 847.50 S/ 847.50 S/ 847.50 S/ 847.50 S/ - S/ - S/ - S/ - S/. 10,170.00 ###
CONO DE SEÑALIZACION N S/. 24.00 S/ 480.00 S/ 480.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 960.00 ###
BARRA RETRACTIL DE 1.30 S/. 16.00 S/ 320.00 S/ 320.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 640.00 ###
Señalizacion Interna de O S/. 9.03 S/ 722.63 S/ 722.63 S/ - S/ 451.65 S/ - S/ 451.65 S/ - S/ 451.65 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 2,800.20 ###
Triplay de 4MM (Planchas) S/. 133.50 S/ 1,335.00 S/ 1,335.00 S/ - S/ 1,335.00 S/ - S/ 1,335.00 S/ - S/ 1,335.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 6,675.00 ###
Listones de 2"X2"X3.0M S/. 25.80 S/ 1,290.00 S/ 1,290.00 S/ - S/ 1,290.00 S/ - S/ 1,290.00 S/ - S/ 1,290.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 6,450.00 ###
GALONES DE PINTURA COL S/. 46.00 S/ 92.00 S/ 92.00 S/ - S/ 92.00 S/ - S/ 92.00 S/ - S/ 92.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 460.00 ###

S/. 7,286.23 S/. 7,286.23 S/. 0.00 S/. 4,016.15 S/. 847.50 S/. 4,691.95 S/. 847.50 S/. 4,016.15 S/. 847.50 S/. 1,523.30 S/. 847.50 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 32,210.00

5) CAPACITACIONES ESTANDARES DE SALUD Y SEGURIDAD


Costo por
Especialista mes 01 mes 02 mes 03 mes 04 mes 05 mes 06 mes 07 mes 08 mes 09 mes 10 mes 11 mes 12 mes 13 mes 14 mes 15
CAPACITACIONES ESPECIFICAS S/. 350 1 1 1 1
Total S/. 0 S/. 0 S/. 0 S/. 0 S/. 350 S/. 0 S/. 350 S/. 350 S/. 350 S/. 0 S/. 0 S/. 0 S/. 0 S/. 0 S/. 0 S/. 1,400.00

S/. - S/. - S/. - S/. - S/. 350 S/. - S/. 350 S/. 350 S/. 350 S/. - S/. - S/. - S/. - S/. - S/. - S/. 1,400.00

6) RECURSOS PARA RESPUESTA ANTE EMERGENCIA EN SEGURIDAD Y SALUD DURANTE EL TRABAJO - CANTIDAD
Descripción mes 01 mes 02 mes 03 mes 04 mes 05 mes 06 mes 07 mes 08 mes 09 mes 10 mes 11 mes 12 mes 13 mes 14 mes 15
RECARGA DE EXTINTORES x 12Kg. - - - 2.00 - - 2.00 - - 2.00 - - 6.00
EXTINTOR DE POLVO QUIMICO SECO (PQS) DE 1 5.00 5.00 - 3.00 3.00 - - - - 16.00
CAMILLA RIGIDA 1.00 1.00 - - - - - - - - - - 2.00
BOTIQUIN MADERA BLANCO 30x40 1.00 1.00 - - - - - - - - - - 2.00
MANTA 1.00 1.00 - - - - - - - - - - 2.00
CAMILLA METALICA TIPO CANASTA DE RESCATE 1.00 1.00 - - - - - - - - - - 2.00
COLLARINES DE CABEZA 1.00 1.00 - - - - - - - - - - 2.00
CONTENEDO PARA BASURA 5.00 5.00 - - - - - - - - - - 10.00
RECARGA DE MEDICINAS PARA BOTIQUIN - - - - - 1.00 - - - - - 1.00
FUMIGACION - - - - - - - - - - - 1.00 - 1.00
6) RECURSOS PARA RESPUESTA ANTE EMERGENCIA EN SEGURIDAD Y SALUD DURANTE EL TRABAJO - COSTOS
Descripción Precio x Und mes 01 mes 02 mes 03 mes 04 mes 05 mes 06 mes 07 mes 08 mes 09 mes 10 mes 11 mes 12 mes 13 mes 14 mes 15 Total
RECARGA DE EXTINTORES x S/. 33.90 S/ - S/ - S/ - S/ 67.80 S/ - S/ - S/ 67.80 S/ - S/ - S/ 67.80 S/ - S/ - S/ - S/ - S/ - S/. 203.40 ###
EXTINTOR DE POLVO QUIMI S/. 425.00 S/ 2,125.00 S/ 2,125.00 S/ - S/ 1,275.00 S/ - S/ 1,275.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 6,800.00 ###
CAMILLA RIGIDA S/. 186.44 S/ 186.44 S/ 186.44 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 372.88 ###
BOTIQUIN MADERA BLANC S/. 570.00 S/ 570.00 S/ 570.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 1,140.00 ###
MANTA S/. 35.00 S/ 35.00 S/ 35.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 70.00 ###
CAMILLA METALICA TIPO S/. 250.00 S/ 250.00 S/ 250.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 500.00 ###
COLLARINES DE CABEZA S/. 53.45 S/ 53.45 S/ 53.45 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 106.90 ###
CONTENEDO PARA BASUR S/. 150.00 S/ 750.00 S/ 750.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 1,500.00 ###
RECARGA DE MEDICINAS S/. 100.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ 100.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 100.00 ###
FUMIGACION S/. 1,000.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 1,000.00 S/ - S/ - S/ - S/. 1,000.00 ###

S/. 3,969.89 S/. 3,969.89 S/. 0.00 S/. 1,342.80 S/. 0.00 S/. 1,275.00 S/. 167.80 S/. 0.00 S/. 0.00 S/. 67.80 S/. 0.00 S/. 1,000.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 11,793.18

7) EXAMENES MEDICOS PARA PERSONAL OBRERO


Descripción Costo mes 01 mes 02 mes 03 mes 04 mes 05 mes 06 mes 07 mes 08 mes 09 mes 10 mes 11 mes 12 mes 13 mes 14 mes 15 Total
1. Examen Pre Ocupacional
Personal Staff S/. 85.00 S/. 510.00 S/. 510.00 S/. - S/. 85.00 S/. - S/. 85.00 S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. 1,190.00
Personal Obrero - casa S/. 85.00 S/. 170.00 S/. 170.00 S/. - S/. - S/. 170.00 S/. 170.00 S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. 680.00
I) Examenes Médicos
2. Examen Post Ocupacional S/. 0.00
Personal Staff S/. 0.00 S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. 0.00
Personal Obrero - casa S/. 0.00 S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. 0.00

S/. 680.00 S/. 680.00 S/. 0.00 S/. 85.00 S/. 170.00 S/. 255.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,870.00

6 6 6 7 7 8 8 9 9 9 10 10 10 7 3
6 6 0 1 0 1 S/ 208,424.01
2 2 0 0 2 2 0 0 0 0 13 12 -2 0 -20
2 2 0 0 2 2 0 0 0 0 0 0
C & V INVERSIONES INMOBILIARIAS
Cl. Narciso de la Colina N° 421, Of. 1401, Miraflores
www.cyvperu.com
HOJA DE PRESUPUESTO DETALLADO
OBRA: CONSTRUCCION DEL CONDOMINIO PORTOFINO
ESPECIALIDAD: OBRAS PROVISIONALES & TRABAJOS PRELIMINARES
PROPIET. : PROPIA
LUGAR: Av. Santa Cruz 1550, Miraflores
FECHA: 20 de Enero del 2022
MONEDA: Nuevos Soles

ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL


01 MOVIMIENTO DE TIERRAS - 1,234,777.25
01.01 EXCAVACION A MAQUINA glb 23,028.7200 22.26 512,634.04
01.02 EXCAVACION CIMIENTOS Y ZAPATAS m3 1,031.9490 58.34 60,201.84
01.03 PERFILADO Y COMPACTADO SUPERFICIE DE ZAPATA m2 1,206.5790 7.81 9,418.99
01.04 BASE GRANULAR E=0.20 m (Afirmado) m2 1,139.3500 19.60 22,331.26
01.05 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 544.6200 36.86 16,798.79
01.06 RELLENO CON MATERIAL PROPIO m3 1,134.6200 18.43 16,451.49
01.07 PARTIDA DE CONTINGENCIA m3 26,530.7038 22.50 596,940.84

02 OBRAS DE CONCRETO SIMPLE - 96,855.51


02.01 SOLADO - 33,976.51
02.01.01 CONCRETO 1:12 PARA SOLADOS E=0.10 M m2 917.25 40.02 33,976.51
02.02 FALSA ZAPATA - 982.96
02.02.01 CONCRETO CALZADURAS MEZCLA 1:12 + 30% P.G. m3 57.08 180.25 678.49
02.02.02 ENCOFRADO Y DESENCOFRADO DE FALSA ZAPATA m2 103.77 44.49 304.47
02.03 LOSA DE ESTACIONAMIENTO - 59,808.19
02.03.01 CONCRETO PREMEZCLADO PARA LOSA DE ESTACIONAMIENTO m3 226.92 364.07 44,011.27
02.03.02 ENCOFRADO Y DESENCOFRADO EN LOSA DE PISO m2 455.61 26.22 1,441.05
02.03.03 JUNTA DE AISLAMIENTO CON ESTRUCTURA PERIMETRICA (J-3) ml 186.89 9.27 1,464.79
02.03.04 JUNTA ALREDEDOR DE COLUMNAS (J-1) ml 106.61 10.16 1,107.77
02.03.05 JUNTA DE CONTRACCION (J-2) ml 1,165.30 7.07 8,236.42
02.03.06 JUNTA DE DILATACIÓN ml 349.00 10.16 3,546.89
02.04 LOSA DE TERRAZAS - 2,087.85
02.04.01 CONCRETO PREMEZCLADO PARA LOSA DE TERRAZAS m3 55.20 58.26 1,929.87
02.04.02 ENCOFRADO Y DESENCOFRADO EN LOSA DE TERRAZAS m2 16.83 26.22 157.98

03 OBRAS DE CONCRETO ARMADO - 10,322,072.29


03.01 ZAPATAS, CIMIENTOS ARMADOS INTERIORES Y PERIMETRALES - 610,662.12
03.01.01 CONCRETO PREMEZCLADO f'c=210 kg/cm2 PARA ZAPATAS m3 699.30 364.07 226,328.63
03.01.02 ENCOFRADO DE ZAPATA m2 692.51 52.07 31,362.83
03.01.04 ACERO DE REFUERZO fy=4200 kg/cm2 GRADO 60 kg 61,699.53 5.72 352,970.66
-
C & V INVERSIONES INMOBILIARIAS
Cl. Narciso de la Colina N° 421, Of. 1401, Miraflores
www.cyvperu.com
HOJA DE PRESUPUESTO DETALLADO
OBRA: CONSTRUCCION DEL CONDOMINIO PORTOFINO
ESPECIALIDAD: OBRAS PROVISIONALES & TRABAJOS PRELIMINARES
PROPIET. : PROPIA
LUGAR: Av. Santa Cruz 1550, Miraflores
FECHA: 20 de Enero del 2022
MONEDA: Nuevos Soles

ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL


03.02 VIGA DE CIMENTACION - 24,432.43
03.02.01 CONCRETO PREMEZCLADO f'c=210 kg/cm2 PARA VIGAS DE CIMENTACION m3 11.51 333.41 3,836.28
03.02.02 ENCOFRADO Y DESENCOFRADO PARA VIGAS DE CIMENTACION m2 51.14 52.07 2,662.59
03.02.03 ACERO DE REFUERZO fy=4200 kg/cm2 GRADO 60 kg 3,051.52 5.72 17,457.12
03.02.04 TECKNOPOR EN VIGA DE CIMENTACION ml 28.41 16.77 476.44
-
03.03 MUROS PANTALLA / ANCLADOS - 1,319,523.91
03.03.01 ANCLAJES POSTENSADOS TEMPORALES
03.03.01.01 ANCLAJES POSTENSADOS TEMPORALES glb 1.00 267,106.69 267,106.69
03.03.02 MUROS DE CONTENCION
03.03.02.01 CONCRETO PREMEZCLADO f'c=350 kg/cm2 EN MUROS DE CONTENCION m3 715.35 335.90 138,153.31
03.03.02.02 ENCOFRADO Y DESENCOFRADO DE MURO ANCLADO m2 2,090.95 48.84 57,390.93
03.03.02.03 ACERO DE REFUERZO fy=4200 kg/cm2 GRADO 60 kg 183,807.94 5.72 376,212.66
03.03.03 ACTIVIDADES LIGADAS A LOS MUROS ANCLADOS
03.03.03.01 EXCAVACION PUNTUAL DE BANQUETAS PARA MURO PANTALLA HM 487.00 200.00 97,400.00
03.03.03.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINA m3 1,506.75 22.50 33,901.88
03.03.03.03. PERFILADO DE BANQUETAS Y ACARREO DE MATERIAL m2 2,557.62 2.53 6,470.79
03.03.03.04 EXCAVACION LOCALIZADA (PARA TRASLAPE DE ACERO VERTICAL Y PILOTES DE m3 12.00 8.38 100.57
MADERA)
03.03.03.05 RELLENO CON MATERIAL PROPIO EN TRASLAPES m3 4,305.00 8.38 36,080.00
03.03.03.06 m2 2,173.98 1.16 2,528.34
PAÑETEO DEL TERRENO CONTACTO CON CONCRETO DE MURO PANTALLA C:A 1:5
03.03.03.07 NIVELACION DE TERRENO PARA BASE DE SOLADO DE MUROS m2 209.97 11.06 2,321.88
03.03.03.08 SOLADO DE CONCRETO H= 5 CM. PROVISIONAL m2 209.97 40.02 8,402.88
03.03.03.09 Und 8.00 276.48 2,211.84
DADOS DE CONCRETO f´c=80 KG/CM2 PARA APUNTALAMIENTO MURO PANTALLA
DADOS EN MUROS DE CONTENCION-CONCRETO PREMEZCLADO F'C=350 KG/CM2 T.I
03.03.03.10 m3 24.30 8,162.33
PARA TENSADO 335.90
CAJUELAS PARA INGRESOS DE VIGAS PRINCIPALES, VIGUETAS Y VENTANAS DE
03.03.03.11 m 600.00 23.70 14,220.00
VACIADO CON TECNOPOR
03.03.03.12 TUBERIA PVC 150MM (6") PARA PASES DE ANCLAJES EN ENCOFRADOS m 162.00 43.75 7,087.50
03.03.03.13 MAYOR VOLUMEN DE CONCRETO PREMEZCLADO F'C=350 KG/CM2 T.I m3 49.36 335.90 16,579.94
03.03.03.14 MAYOR KILAJE ACERO fy=4200 kg/cm2 GRADO 60 PARA EMPALMES DE PAÑOS MURO kg 779.41 5.72 4,458.85
PANTALLA
03.03.03.15 PICADO DE SOLADO PARA ENCUENTRO DE ANILLOS DE MUROS PANTALLA m3 209.97 4.29 901.19
03.03.03.16 ENCOFRADO LATERAL DE PAÑOS DE MUROS PANTALLA (TAPAS) m2 4,422.36 51.05 225,747.33
03.03.03.17 DEMOLICION DE CACHIMBAS ml 450.00 31.30 14,085.00
-
03.04 COLUMNAS - 1,376,657.36
03.04.01 CONCRETO PREMEZCLADO f´c=350 kg/cm2 EN COLUMNAS m3 23.31 395.36 9,215.71
03.04.02 CONCRETO PREMEZCLADO f'c=280 kg/cm2 EN COLUMNAS m3 490.27 369.11 152,041.88
CONCRETO PREMEZCLADO F'C=280 KG/CM2 PARA COLUMNAS (RELACION a/c = 0.45
03.04.03 MAXIMO CON ADITIVO PLASTIFICANTE) m3 17.25 386.96 6,675.43
03.04.04 ENCOFRADO Y DESENCOFRADO DE COLUMNAS m2 2,804.27 56.04 157,142.11
03.04.05 ENCOFRADO Y DESENCOFRADO PARA COLUMNAS A DOBLE ALTURA m2 779.41 68.04 53,028.49
03.04.06 ACERO DE REFUERZO fy=4200 kg/cm2 GRADO 60 kg 174,547.92 5.72 998,553.74
-
03.05 PLACAS - 575,121.87
03.05.01 CONCRETO PREMEZCLADO f'c=350 kg/cm2 EN PLACAS m3 314.67 382.10 120,234.33
03.05.02 CONCRETO PREMEZCLADO f'c=280 kg/cm2 EN PLACAS m3 623.43 355.85 221,846.40
03.05.03 ENCOFRADO Y DESENCOFRADO DE PLACAS m3 4,839.92 39.91 193,161.10
03.05.04 ENCOFRADO Y DESCENCOFRADO PARA PLACAS DE CONCRETO (1 CARA
CONTRATERRENO) m2 816.58 48.84 39,880.04
03.05.05 ENCOFRADO Y DESENCOFRADO PARA PLACAS A DOBLE ALTURA m2 334.96 47.91
03.05.06 ACERO DE REFUERZO fy=4200 kg/cm2 GRADO 60 kg 270,320.94 5.72
-
03.06 VIGAS - 2,318,166.31
03.06.01 CONCRETO PREMEZCLADO f'c=210 kg/cm2 EN VIGAS m3 1,011.90 336.78 340,786.80
03.06.02 ENCOFRADO Y DESENCOFRADO DE VIGAS m2 6,657.65 107.84 717,960.83
03.06.03 ACERO DE REFUERZO fy=4200 kg/cm2 GRADO 60 kg 220,147.30 5.72 1,259,418.68
-
03.07 LOSAS MACIZAS - 2,648,100.58
03.07.01 CONCRETO PREMEZCLADO f'c=210 kg/cm2 EN LOSAS MACIZAS m3 1,721.00 286.75 493,490.91
03.07.02 ACABADO DE LOSAS m2 8,605.01 8.07 69,442.43
03.07.03 ENCOFRADO Y DESENCOFRADO LOSAS MACIZAS m2 8,605.01 43.62 375,350.54
03.07.04 ACERO DE REFUERZO fy=4200 kg/cm2 GRADO 60 kg 213,358.09 5.72 1,220,578.94
03.07.05 PRELOSAS LOSA MACIZA m2 8,553.50 55.51 474,806.50
03.07.06 PUENTE DE ADHERENCIA ml 585.05 0.97 565.58
03.07.07 EPÓXICO EN UNIÓN ENTRE LOSAS DE TECHO DE SÓTANOS Y MUROS PANTALLA ml 585.05 12.23 7,155.16
RETIRO DE TECNOPOR Y ESCARIFICADO EN UNIÓN ENTRE LOSAS Y MUROS
03.07.08
PANTALLA ml 585.05 7.02 4,107.05
03.07.09
TECNOPOR PARA LOSAS ENTRE LOSAS DE TECHO DE SÓTANOS Y MUROS PANTALLA ml 585.05 4.45 2,603.47
-
03.08 LOSAS ALIGERADAS - 1,199,822.52
03.08.01 CONCRETO PREMEZCLADO f'c=210 kg/cm2 PARA LOSAS ALIGERADAS m3 504.56 286.75 144,681.05
03.08.02 ACABADO DE LOSAS m2 5,922.08 8.07 47,791.19
03.08.03 ENCOFRADO Y DESENCOFRADO DE LOSAS ALIGERADAS m2 5,922.08 43.62 258,321.13
03.08.04 ACERO DE REFUERZO fy=4200 kg/cm2 GRADO 60 kg 53,872.24 5.72 308,192.30
03.08.05 PRELOSAS ALIGERADAS 20CM m2 328.88 69.45 22,840.12
03.08.06 PRELOSAS ALIGERADAS 25M m2 5,469.93 76.42 417,996.73
-
03.09 ESCALERAS - 63,519.92
03.09.01 CONCRETO PREMEZCLADO f'c=210 kg/cm2 EN ESCALERAS m3 40.68 393.78 16,017.35
03.09.02 ENCOFRADO Y DESENCOFRADO DE ESCALERAS m2 268.02 46.02 12,335.05
03.09.03 ACERO DE REFUERZO fy=4200 kg/cm2 GRADO 60 kg 6,147.31 5.72 35,167.52
-
03.10 CISTERNA - 178,154.09
03.10.01 CONCRETO PREMEZCLADO f'c=280 kg/cm2 PARA CISTERNA m3 179.64 359.20 64,526.27
03.10.02 ENCOFRADO Y DESENCOFRADO DE CISTERNA m2 778.76 59.63 46,434.00
03.10.03 ACERO DE REFUERZO fy=4200 kg/cm2 GRADO 60 kg 11,243.56 5.72 64,322.13
03.10.04 WATER STOP DE 6" ml 122.46 23.45 2,871.69
-
03.11 MUROS DE CONTENCION - 7,911.18
03.11.01 CONCRETO PREMEZCLADO f'c=350 kg/cm2 EN PLACAS m3 6.21 382.10 2,374.74
03.11.02 ENCOFRADO Y DESENCOFRADO DE PLACAS m2 65.00 48.84 3,174.26
C & V INVERSIONES INMOBILIARIAS
Cl. Narciso de la Colina N° 421, Of. 1401, Miraflores
www.cyvperu.com
HOJA DE PRESUPUESTO DETALLADO
OBRA: CONSTRUCCION DEL CONDOMINIO PORTOFINO
ESPECIALIDAD: OBRAS PROVISIONALES & TRABAJOS PRELIMINARES
PROPIET. : PROPIA
LUGAR: Av. Santa Cruz 1550, Miraflores
FECHA: 20 de Enero del 2022
MONEDA: Nuevos Soles

ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL


03.11.03 ACERO DE REFUERZO fy=4200 kg/cm2 GRADO 60 kg 412.91 5.72 2,362.18
-
04 VARIOS - 70,789.28
04.01 CURADO DE SUPERFICIES DE CONCRETO m2 34,252.28 0.91 31,169.57
04.02 ENSAYOS DE PROBETA CONCRETO und 272.00 67.00 18,224.00
04.03 JUNTA SISMICA e= 4" m2 1,011.21 12.82 12,963.71
04.04 CEMENTO PARA BOMBEO DE CONCRETO m3 544.00 15.50 8,432.00
-

COSTO DIRECTO S/. 11,724,494.33


1,234,750.29 26.96

96,857.29 -1.78

11,883,760.03 -1,561,687.74
610,613.96 48.16
24,431.54 0.89

1,319,479.20 44.71

19.43 6,524.83
55.50 2,710.51
685.02 3,918.86
0.00
0.00
7.50 168.75
55.50 140.42

0.00
7.50 62.86

55.50 64.55
0.00
0.00

0.00

0.00

15.00 355.50
1.50 65.63
0.00

0.00
0.00
7.77 396.63
15.00 469.50

1,376,527.45 129.91

2,137,409.67 -1,562,287.80

2,212.00 12,654.41

2,317,991.22 175.09

2,647,935.96 164.62

1,199,796.88 25.64

63,515.86 4.06

178,149.00 5.09

7,909.29 1.89
70,789.28 0.00

S/. 13,286,156.89 -S/. 1,561,662.56


23,028.72 22.2606 0.880215
1,031.95 58.3379
1,206.58 7.8064
1,139.35 19.6000
544.62 30.8450
1,134.62 14.4996
26,530.70 22.5000
- #DIV/0!
- #DIV/0!
- #DIV/0!
917.25 37.0417
- #DIV/0!
57.08 11.8867
103.77 2.9341
- #DIV/0!
226.92 193.9506
455.61 3.1629
186.89 7.8377
106.61 10.3909
1,165.30 7.0681
349.00 10.1630
- #DIV/0!
55.20 34.9614
16.83 9.3868 S/. 18.85
- #DIV/0!
- #DIV/0!
- #DIV/0!
699.30 323.6503
692.51 45.2886
61,699.53 5.7208
- #DIV/0!
- #DIV/0!
11.51 333.2997
51.14 52.0647
3,051.52 5.7208
28.41 16.7702
- #DIV/0!
- #DIV/0!
- #DIV/0!
1.00 267,106.6900
- #DIV/0!
715.35 193.1269
2,090.95 27.4473
183,807.94 2.0468
- #DIV/0!
487.00 200.0000
1,506.75 22.5000
2,557.62 2.5300
12.00 8.3808

4,305.00 8.3810
2,173.98 1.1630

209.97 11.0582
209.97 40.0194
8.00 276.4800

24.30 335.8984

600.00 23.7000

162.00 43.7500
49.36 335.8983
779.41 5.7208

209.97 4.2920
4,422.36 51.0468
450.00 31.3000
- #DIV/0!
- #DIV/0! S/. 0.0605
23.31 395.3544
490.27 310.1187
17.25 386.9814

2,804.27 56.0367
779.41 68.0367
174,547.92 5.7208
- #DIV/0!
- #DIV/0!
314.67 382.0966
623.43 355.8481
4,839.92 39.9100
816.58 48.8379 S/. 25.11

334.96 -
S/. 27,532.43 270,320.94 -
S/. 30,285.68 - #DIV/0!
- #DIV/0!
1,011.90 336.7791
6,657.65 107.8400
220,147.30 5.7208
- #DIV/0!
- #DIV/0!
1,721.00 286.7466
8,605.01 8.0700
8,605.01 43.6200
213,358.09 5.7208
S/. 8,553.50 8,553.50 55.5102
585.05 0.9667
585.05 12.2300
585.05 7.0200

585.05 4.4500

- #DIV/0!
- #DIV/0!
504.56 286.7470
5,922.08 8.0700
5,922.08 43.6200
53,872.24 5.7208
S/. 328.88 328.88 69.4482
S/. 5,469.93 5,469.93 76.4172
- #DIV/0!
- #DIV/0!
40.68 393.7402
268.02 46.0229
6,147.31 5.7208
- #DIV/0!
- #DIV/0!
179.64 359.1977
778.76 59.6256
11,243.56 5.7208
122.46 23.4500
- #DIV/0!
- #DIV/0!
6.21 382.4058
65.00 48.8348
412.91 5.7208
- #DIV/0!
- #DIV/0!
34,252.28 0.9100
272.00 67.0000
1,011.21 12.8200
544.00 15.5000
#DIV/0!
ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL

01 MUROS Y TABIQUES - King Block - 1,688,089.02


SOTANO Y TORRE
KING BLOCK 9 - Normal M2 Luis L 7,605.09 89.00 676,853.36
KING BLOCK 9 - RF 120 min M2 Luis L 87.59 92.00 8,057.87
KING BLOCK 14 - Normal M2 Luis L 1,803.46 98.00 176,739.20
KING BLOCK 14 - RF 120 min M2 Luis L 6,270.49 103.00 645,860.27
KING BLOCK 17 - RF 120 min M2 Luis L 3.93 183.00 718.92
KING BLOCK 19 - Normal M2 Luis L 15.28 178.00 2,719.40
KING BLOCK 19 - RF 120 min M2 Luis L 76.07 183.00 13,921.22
KING BLOCK 22 - RF 120 min M2 Luis L 3.88 186.00 720.75
KING BLOCK 24 - Normal M2 Luis L 20.61 186.00 3,833.93
KING BLOCK 25 - Normal M2 Luis L 17.51 187.00 3,274.09
KING BLOCK 25 - RF 120 min M2 Luis L 34.51 187.00 6,452.95
KING BLOCK 30 - Normal M2 Luis L 19.76 190.00 3,755.11
KING BLOCK 30 - RF 120 min M2 Luis L 23.57 206.00 4,855.63
CAJA PARA VALVULAS DE GAS UND Luis L 251.00 50.00 12,550.00
CAJA PARA EXTRACTORES DE BAÑOS UND Luis L 457.00 50.00 22,850.00
NUEVO CAJA PARA EXTRACTORES ALMACENES SOTANOS UND Luis L 91.00 50.00 4,550.00
PASES DE EXTRACCION UND Luis L 182.00 50.00 9,100.00
PASES DE INYECCION UND Luis L 182.00 50.00 9,100.00
CAJA PARA PASES DE MANGUERA UND Luis L 26.00 50.00 1,300.00
LADRILLO REFLACTARIO EN ZONA PARRILLAS M2 Luis L 1.93 150.00 289.50
SARDINEL DE MONTANTES ML Luis L 139.86 75.00 10,489.50
EXTERIORES Y AREAS SOCIALES
KING BLOCK 19 - Normal M2 Luis L 235.26 178.00 41,876.28
MUROS BANCO DE MEDIDORES M2 Luis L 100.79 280.00 28,221.06

02 MUROS Y TABIQUES - Drywall - 28,793.10


02.01 SOTANOS Y TORRE -
CERRAMIENTO DE ASCENSOR - DRYWALL RF 120MIN, 02 PLANCHAS + LANA VIDRIO M2 Luis L 96.41 180.00 17,353.80
FALSO CIELORASO - DRYWALL STD, 01 CARA (EN LOBBY) (CR-04) M2 Miguel P 72.14 90.00 6,492.60
FALSO CIELORASO - DRYWALL STD, 01 CARA (EN COWORKING) (CR-04) M2 Miguel P 16.40 70.00 1,148.00
FALSO CIELORASO - DRYWALL STD, 01 CARA (EN GYM) (CR-04) M2 Miguel P 20.20 70.00 1,414.00
FALSA VIGA - DRYWALL RH, 01 CARA (EN SSHH) M2 Miguel P 17.33 90.00 1,559.70
NUEVO PASE DE MANGUERAS - DRYWALL RF, 01 CARA (EN ESCALERAS) UND Miguel P 15.00 55.00 825.00
-
03 REVOQUES Y ENLUCIDOS - 1,090,367.39
03.01 SOTANOS -
IMPERMEABILIZACION MUROS Y PISOS PARA CISTERNAS M2 Miguel P 659.59 75.00 49,469.25
TARRAJEO CON IMPERMEABILIZANTE P/MURO POZOS SUMIDEROS M2 Luis L 43.00 39.50 1,698.50
SOLAQUEO DE MUROS M2 Luis L 1,903.31 25.00 47,582.63
NUEVO SOLAQUEO DE MUROS DOBLE ALTURA M2 Luis L 246.00 30.00 7,380.00
SOLAQUEO DE PLACAS Y COLUMNAS M2 Luis L 1,111.19 25.00 27,779.75
NUEVO SOLAQUEO DE PLACAS Y COLUMNAS (DOBLE ALTURA) M2 Luis L 392.11 30.00 11,763.30
SOLAQUEO DE VIGAS M2 Luis L 1,609.35 24.00 38,624.40
NUEVO SOLAQUEO DE VIGAS (DOBLE ALTURA) M2 Luis L 249.37 30.00 7,481.10
VESTIDURA DE DERRAMES ML Luis L 450.24 13.00 5,853.12
03.02 TORRE - Departamentos y Areas Comunes -
NUEVO SOLAQUEO DE PLACAS Y COLUMNAS M2 Luis L 8,122.67 25.00 203,066.85
NUEVO SOLAQUEO DE VIGAS M2 Luis L 2,882.83 35.00 100,899.12
NUEVO SOLAQUEO DE DUCTO DE ASCENSOR M2 Luis L 362.21 40.00 14,488.32
NUEVO SOLAQUEO DE DUCTOS DE INSTALACIONES M2 Luis L 702.97 14.00 9,841.59
NUEVO VESTIDURA DE DERRAMES M2 Luis L 8,141.91 13.00 105,844.83
TARRAJEO EN FONDO DE VIGAS M2 Luis L 1,954.33 35.00 68,401.55
03.03 EXTERIORES Y AREAS SOCIALES -
TARRAJEO DE AREAS EXTERIORES - Terrazas e Ingreso Principal M2 Luis L 1,513.98 39.00 59,045.22
BRUÑAS EXTERIORES M2 Luis L 3,914.00 9.00 35,226.00
VESTIDURA DE DERRAMES ML Luis L 917.35 13.00 11,925.54
IMPERMEABILIZACION MUROS Y PISOS PARA JARDINERAS M2 Miguel P 940.94 65.00 61,161.10
IMPERMEABILIZACION DE PISCINA M2 Miguel P 71.68 65.00 4,659.20
03.04 FACHADAS -
TARRAJEO DE FACHADAS PRINCIPALES M2 Miguel P 1,513.98 39.00 59,045.22
SOLAQUEO DE MUROS CIEGOS M2 Luis L 2,083.21 21.00 43,747.33
VESTIDURA DE DERRAMES ML Miguel P 875.65 13.00 11,383.47
ANDAMIO PARA TRABAJOS EN FACHADA GLB Miguel P 1.00 104,000.00 104,000.00
-
04 CIELO RASO - 85,721.14
04.01 SOTANOS -
NUEVO LIMPIEZA DE CIELO RASO M2 Luis L 5,394.53 3.00 16,183.59
IMPERMEABILIZACION DE CIELO RASO EN CISTERNAS M2 Luis L 205.91 75.00 15,443.25
04.02 TORRE - Departamentos y Areas Comunes -
MODIFICADO SELLADO DE JUNTAS DE PRELOSAS M2 Luis L 9,708.56 5.00 48,542.80
TARRAJEO DE FONDO DE ESCALERA M2 Luis L 222.06 25.00 5,551.50
-
05 PISOS - 1,755,927.19
05.01 SOTANOS -
05.01.01 CEMENTO -
ACABADO BARRIDO EN ESTACIONAMIENTOS M2 Luis L - -
ACABADO BARRIDO EN LOSA DE TECHO DE CISTERNA M2 Luis L - -
ACABADO BARRIDO BRUÑADO EN RAMPAS DE ACCESO M2 Luis L - -
PISOS DE CEMENTO PULIDO M2 Luis L 876.79 33.00 28,934.07
NUEVO CEMENTO PULIDO OSCURO CON CEMENTO ANDINO Y CON SELLADOR DRYLOCK M2 Luis L 110.16 37.00 4,075.92
05.01.02 ESCALERA -
TARRAJEO DE FONDO DE ESCALERA M2 Luis L 282.77 25.00 7,069.15
REVESTIMIENTO DE DESCANSOS EN VESTIBULOS M2 Luis L 172.43 45.00 7,759.13
FORJADO DE PASOS Y CONTRAPASO ACABADO PULIDO ESCALERAS EMERGENCIA ML Luis L 559.20 32.00 17,894.40
SOLAQUEO DE LATERALES DE ESCALERAS ML Luis L 97.50 35.00 3,412.50
CANTONERA BRUÑADO ML Luis L 1,398.00 25.00 34,950.00
05.01.03 CERAMICOS Y PORCELANATOS -
PISO DE CERAMICA 0.45 X 0.45 cm - CELIMA CEMENTO PLUS GRIS M2 Luis L 54.96 65.98 3,626.53
05.02 TORRE - Departamentos y Areas Comunes -
05.02.01 CEMENTO -
NIVELACION DE PISOS (ACABADO FROTACHADO DIRECTO AL VACIADO PARA RECIBIR Luis L 10,740.31 28.00 300,728.68
PISO) M2
FORJADO DE CANAL PARA NIVELAR MAMPARAS ML Luis L 1,004.03 31.00 31,124.93
05.02.02 ESCALERA -
REVESTIMIENTO DE DESCANSOS EN VESTIBULOS M2 Luis L 114.95 45.00 5,172.75
FORJADO DE PASOS Y CONTRAPASO ACABADO PULIDO ESCALERAS EMERGENCIA ML Luis L 260.00 32.00 8,320.00
SOLAQUEO DE LATERALES DE ESCALERAS ML Luis L 39.00 35.00 1,365.00
CANTONERA BRUÑADO ML Luis L 210.00 25.00 5,250.00
05.02.03 CERAMICOS Y PORCELANATOS -
PISO PORCELANATO GRAIMAN OAKLAND GREY M2 Luis L 9,405.89 121.44 1,142,244.71
PISO PORCELANATO GRAIMAN CIPRES WHITE M2 Luis L 282.45 121.44 34,300.53
05.03 EXTERIORES Y AREAS SOCIALES -
05.03.01 CEMENTO -
NIVELACION DE PISOS (ACABADO FROTACHADO DIRECTO AL VACIADO PARA RECIBIR Luis L 591.93 28.00 16,574.04
PISO) M2
05.03.02 CERAMICOS Y PORCELANATOS -
ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL

01 MUROS Y TABIQUES - King Block - 1,688,089.02


PISO PORCELANATO ESMALTADO FILO BIANCO MATE M2 Luis L 52.39 120.41 6,308.28
PISO PORCELANATO ESMALTADO TRAVERTINO NAVONA M2 Luis L 252.69 209.51 52,941.87
PISO PORCELANATO GRAIMAN CIPRES WHITE M2 Luis L 13.52 121.44 1,641.86
PISO PIEDRA GRANÍTICA TALAMOYE FORMATO 20*20 CM - INGRESO M2 Luis L 135.29 190.00 25,705.10
PISO PORCELANATO GRAIMAN OAKLAND GREY M2 Luis L 57.37 121.44 6,966.97
05.03.03 VINILICOS -
PISO VINILICO TIPO LVT MARCA TARKETT - GYM M2 Luis L 19.83 195.00 3,866.85
05.03.04 PISCINA -
PEPELMA x DEFINIR M2 Luis L 35.83 158.91 5,693.92
-
06 ZOCALOS & CONTRAZOCALOS - 1,483,662.51
06.01 SOTANOS -
06.01.01 CEMENTO -
CONTRAZOCALO DE CEMENTO PULIDO H = 0.10 cm ML Luis L 5,677.11 25.50 144,766.31
06.01.02 CERAMICOS Y PORCELANATOS -
ZÓCALO DE CERÁMICO CELIMA CEMENTO PLUS GRIS 45x45CM M2 Luis L 84.80 65.98 5,595.38
ZÓCALO DE PORCELANATO BLANCO 45X45 M2 Luis L 15.63 88.00 1,375.64
06.02 TORRE - Departamentos y Areas Comunes -
06.02.01 CERAMICOS Y PORCELANATOS -
ZÓCALO DE PORCELANATP BLANCO 45X45 M2 Luis L 296.43 88.00 26,084.61
CERÁMICO EQUIPE METRO WHITE BRILLANTE, NO RECTIFICADO, BISCELADO 7.5x15 M2 Luis L 361.68 185.48 67,084.01
CERÁMICO ITAGRES KASSOS BIANCO MATE, RECTIFICADO 30.5X60.5 M2 Luis L 1,733.76 139.86 242,492.14
Luis L 698.02 88.00 61,422.87
GRES PORCELÁNICO DALTILE PURE ORIGAMI MATE RECTIFICADO, ALTO RELIEVE 45x90 M2
BAÑO: CERÁMICO KLIPEN NEVADO BLANCO, MATE COLOR BLANCO M2 Luis L 3,620.20 72.29 261,718.69
06.02.02 PIEDRA -
ZÓCALO DE PIEDRA PIZARRA H=ALTURA DE JARDINERA (5) M2 Luis L 22.38 190.00 4,252.85
06.02.03 MADERA -
CONTRAZÓCALO DE MADERA TEÑIDO SIMILAR AL PROCELANATO GRAIMAN OAKLAND Luis L 18,998.72 25.13 477,425.36
GREY ML
06.03 EXTERIORES Y AREAS SOCIALES -
06.03.01 CERAMICOS Y PORCELANATOS -
CONTRAZOCALO IDEM PISO PORCELANATO GRAIMAN CIPRES WHITE ML Luis L 485.02 25.13 12,188.23
ESTUCADO DE CEMENTO M2 Luis L 23.51 115.00 2,703.67
06.03.02 PIEDRA -
ZÓCALO DE PIEDRA PIZARRA H=ALTURA DE JARDINERA (5) M2 Luis L 51.23 190.00 9,734.03

Luis L 143.82 675.00 97,078.50


GRANITO NEGRO ARACRUZ - Hall Ascensores M2
06.03.03 MADERA -
CONTRAZÓCALO DE MADERA TEÑIDO SIMILAR AL PORCELANATO ESMALTADO
Luis L 308.40 33.55 10,346.63
TRAVERTINO NAVONA ML
CONTRAZÓCALO DE MADERA TEÑIDO SIMILAR AL PORCELANATO GRAIMAN CIPRES
Luis L 65.32 25.13 1,641.45
WHITE ML
DEKO WALL PANEL COLOR POR DEFINIR. PROVEEDOR: DEKOMUNDO (9) M2 Luis L 14.35 346.14 4,967.09
PISCINA
PEPELMA x DEFINIR M2 Luis L 32.28 158.91
06.04 FACHADAS
06.03.01 CERAMICOS Y PORCELANATOS -
PORCELANATO ALAPLANA VILEMA ROBLE 23X120 (FACHADAS) M2 Luis L 331.86 159.06 52,785.05
-
07 PINTURA Y REVESTIMIENTOS - 728,765.24
07.01 SOTANOS -
07.01.01 PINTURA -
Miguel P 182.52 17.50 3,194.02
MUROS - EMPASTADO Y PINTADO CON 2 MANOS DE BASE Y 2 MANOS DE PINTURA LATEX M2
CIELO RASO - EMPASTADO Y PINTADO CON 2 MANOS DE BASE Y 2 MANOS DE PINTURA
Miguel P 81.44 17.50 1,425.17
LATEX M2
SOLAQUEADO CON EMPORRADO DE LECHADA DE CEMENTO Y CAL NIEVE M2 Luis L 8,857.92 12.00 106,294.98
NUEVO LINEAS DE CAJON e=0.10m - COLOR AMARILLO ML Miguel P 2,172.00 20.46 44,440.00
Miguel P 647.00 65.00 42,055.00
NUEVO CEBRA PEATONAL L=1.20m Ancho=0.25m cada 0.25m - COLOR BLANCO (recomendamos) ML
NUMERACION DE ESTACIONAMIENTO EN PISO CIRCUNFERENCIA SIN FONDO (BORDE) Miguel P 135.00 45.00 6,075.00
NUEVO D=0.40M , H DE NUMERO 0.15M - COLOR AMARILLO UND
NUMERACION DE ESTACIONAMIENTO EN MURO CIRCUNFERENCIA SIN FONDO (BORDE) Miguel P 135.00 45.00 6,075.00
NUEVO D=0.40M , H DE NUMERO 0.15M - COLOR AMARILLO UND
NUEVO PINTADO DE TOPELLANTAS L=1.50M H=0.12M - COLOR AMARILLO UND Miguel P 135.00 60.00 8,100.00
Miguel P 58.00 38.00 2,204.00
NUEVO FLECHAS DIRECCIONALES O BIDIRECCIONALES L=1.60M - COLOR BLANCO (recomendamos) UND
PINTADO EN COLUMNAS TIPO CEBRA EN DIAGONAL - COLOR AMARILLO Y NEGRO, Miguel P 41.80 50.00 2,090.00
NUEVO H=1.20M M2
NUEVO ESTACIONAMIENTO DE BICICLETAS - PINTADO DE PISO - COLOR VERDE (MATIZADO) M2 Miguel P 76.14 70.00 5,329.80
Miguel P 184.00 70.00 12,880.00
NUEVO ESTACIONAMIENTO DE BICICLETAS - PINTADO DE PARED - COLOR VERDE (MATIZADO) M2
07.02 TORRE - Departamentos y Areas Comunes -
07.02.01 PINTURA -
Miguel P 6,099.37 17.50 106,738.93
MUROS - EMPASTADO Y PINTADO CON 2 MANOS DE BASE Y 2 MANOS DE PINTURA LATEX M2
CIELO RASO - EMPASTADO Y PINTADO CON 2 MANOS DE BASE Y 2 MANOS DE PINTURA
Luis L 9,708.56 17.50 169,899.80
LATEX M2
07.03 EXTERIORES Y AREAS SOCIALES -
07.03.01 PINTURA -
Miguel P 49.59 17.50 867.74
MUROS - EMPASTADO Y PINTADO CON 2 MANOS DE BASE Y 2 MANOS DE PINTURA LATEX M2
CIELO RASO - EMPASTADO Y PINTADO CON 2 MANOS DE BASE Y 2 MANOS DE PINTURA Miguel P 1,319.17 17.00 22,425.85
LATEX M2
07.03.02 REVESTIMIENTOS -
Luis L 4,415.68 25.50 112,599.84
PAPEL TAPIZ COLOR BLANCO GRIS MODELO POR DEFINIR M2
MICROCEMENTO GRIS CLARO M2 Miguel P 106.85 70.00 7,479.23
MICROCEMENTO GRIS OSCURO M2 Miguel P 63.78 70.00 4,464.57
Miguel P 32.36 346.14 11,201.04
CIELO RASO - REVESTIDO CON BALDOSAS DE PVC - LOBBY - PROVEEDOR:DEKOMUNDO M2
TERRAZO LAVADO EN BANCAS DE ZONA DE FUEGO (M-18) M2 Miguel P 22.16 70.00 1,551.21
TERRAZO LAVADO EN BORDE DE PISCINA (R-12) ML Miguel P 6.74 70.00 471.80
NUEVO TERRAZO LAVADO EN BORDE DE PETS (MO-20) ML Miguel P 19.49 70.00 1,364.41

07.04 FACHADAS -
07.04.01 PINTURA -
Miguel P 670.35 17.50 11,731.11
MUROS - EMPASTADO Y PINTADO CON 2 MANOS DE BASE Y 2 MANOS DE PINTURA LATEX M2
SOLAQUEADO CON EMPORRADO DE LECHADA DE CEMENTO Y CAL NIEVE M2 Miguel P 2,160.39 17.50 37,806.74

08 COBERTURAS - 81,676.30
08.01 TORRE - -
PASTELERO -
ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL

01 MUROS Y TABIQUES - King Block - 1,688,089.02


M2 Miguel P 288.04 38.00 10,945.52
COBERTURA LADRILLO PASTELERO ASENTADO CON MEZCLA EN DERRAMES DE MUROS
APLICACIÓN ADITIVO IMPERMEABILIZANTE EN TECHOS PREVIO AL ACABADO
M2 Miguel P 288.04 14.50 4,176.58
NUEVO PASTELERO/ENCHAPE TERRAZAS ULTIMO NIVEL
EXTERIORES Y AREAS SOCIALES -
PASTELERO -

M. VENTA 27.50 -
COBERTURA LADRILLO PASTELERO ASENTADO CON MEZCLA EN DERRAMES DE MUROS ML
TECHO VERDE
M2 Miguel P 635.07 35.00 22,227.45
TIERRA DE CHACRA (h=0.30)
M2 Miguel P 635.07 25.00 15,876.75
JARDIN AMERICANO
ARBOL PEQUEÑO UND Miguel P 20.00 650.00 13,000.00
AZOTEA
NUEVO COBERTURA DE SUPERBOARD UND Miguel P 6.00 650.00 3,900.00
NUEVO REJILLA EN DUCTO IISS UND Miguel P 11.00 1,050.00 11,550.00

09 CARPINTERIA DE MADERA - 3,151,320.81


09.01 SOTANOS -
09.01.01 PUERTAS -
PUERTA CONTRAPLACADA: P- 08 UND Luis L 1.00 1,573.95 1,573.95
PUERTA CONTRAPLACADA: P- 09 UND Luis L 3.00 812.14 2,436.42
PUERTA CONTRAPLACADA: P- 10 UND Luis L 56.00 877.14 49,119.84
PUERTA CONTRAPLACADA: P- 11 UND Luis L 4.00 2,135.87 8,543.49
PUERTA CONTRAPLACADA: P- 12 UND Luis L 4.00 2,315.32 9,261.28
PUERTA CONTRAPLACADA: P- 13 UND Luis L 5.00 2,144.63 10,723.13
PUERTA CONTRAPLACADA: P- 14 UND Luis L 4.00 1,177.36 4,709.42
NUEVO PUERTA CONTRAPLACADA: P- 14C Luis L 1.00 1,177.36 1,177.36
PUERTA CONTRAPLACADA: P- 15 UND Luis L 4.00 792.20 3,168.79
PUERTA CONTRAPLACADA: P- 16 UND Luis L 2.00 1,807.61 3,615.23
PUERTA CONTRAPLACADA: P- 17 UND Luis L 4.00 1,278.02 5,112.09
PUERTA CONTRAPLACADA: P- 18 UND Luis L 2.00 2,096.48 4,192.96
PUERTA CONTRAPLACADA: P- 19 UND Luis L 3.00 1,785.73 5,357.19
PUERTA CONTRAPLACADA: P- 20 UND Luis L 2.00 1,313.04 2,626.07
PUERTA CONTRAPLACADA: P- 21 UND Luis L 1.00 1,663.18 1,663.18
PUERTA CONTRAPLACADA: P- 22 UND Luis L 1.00 1,829.50 1,829.50
PUERTA CONTRAPLACADA: P- 23 UND Luis L 1.00 1,663.18 1,663.18
PUERTA CONTRAPLACADA: P- 25 UND Luis L 1.00 1,938.92 1,938.92
PUERTA CONTRAPLACADA: P- 26 UND Luis L 5.00 897.24 4,486.20
PUERTA CONTRAPLACADA: P- 27 UND Luis L 1.00 1,028.54 1,028.54
PUERTA CONTRAPLACADA: P- 28 UND Luis L 1.00 442.06 442.06
PUERTA CONTRAPLACADA: P- 29 UND Luis L 1.00 914.75 914.75
NUEVO PUERTA CONTRAPLACADA: P- 31 UND Luis L 3.00 914.75 2,744.25
09.01.02 CERRAJERIA -
BISAGRA PARA PUERTA DE MADERA - Interior UND Luis L 492.00 10.82 5,325.41
CERRADURA P/ PUERTA DE MADERA - Interior UND Luis L 110.00 30.94 3,403.13
09.01.03 MELAMINA - MUEBLES DE COCINA -
DIVISION EN CAMERINO DE DAMAS GLB Luis L 1.00 9,792.57 9,792.57
DIVISION EN CAMERINO DE VARONES GLB Luis L 1.00 10,768.10 10,768.10
09.02 TORRE - Departamentos y Areas Comunes -
09.02.01 PUERTAS -
PUERTA CONTRAPLACADA: P- 01 UND Luis L 128.00 1,149.48 147,133.44
PUERTA CONTRAPLACADA: P- 05 UND Luis L 315.00 750.85 236,517.75
PUERTA CONTRAPLACADA: P- 06 UND Luis L 363.00 815.85 296,153.55
PUERTA CONTRAPLACADA: P- 07 UND Luis L 91.00 844.63 76,861.33
NUEVO PUERTA DE MADERA APERSIANADA: P- 22A UND Luis L 5.00 1,573.95 7,869.75
NUEVO PUERTA DE MADERA APERSIANADA: P- 22B UND Luis L 2.00 1,652.65 3,305.30
NUEVO PUERTA DE MADERA APERSIANADA: P- 22C UND Luis L 1.00 1,652.65 1,652.65
NUEVO PUERTA DE MADERA APERSIANADA: P- 22D UND Luis L 1.00 1,735.28 1,735.28
09.02.02 CERRAJERIA -
BISAGRA PARA PUERTA DE MADERA - Principal UND Miguel P 384.00 14.43 5,541.89
BISAGRA PARA PUERTA DE MADERA - Interior UND Miguel P 2,307.00 10.82 24,970.97
CERRADURA P/ PUERTA DE MADERA - Principal UND Miguel P 128.00 168.71 21,595.20
CERRADURA P/ PUERTA DE MADERA - Interior UND Miguel P 769.00 30.94 23,790.94
09.02.03 MELAMINA - MUEBLES DE COCINA -
MUEBLE ALTO & BAJO - TIPO 102 UND Miguel P 1.00 8,627.88 8,627.88
MUEBLE ALTO & BAJO - TIPO 107 UND Miguel P 1.00 7,638.29 7,638.29
MUEBLE ALTO & BAJO - TIPICO X01 UND Miguel P 10.00 10,461.43 104,614.32
MUEBLE ALTO & BAJO - TIPICO X02 UND Miguel P 8.00 11,683.80 93,470.40
MUEBLE ALTO & BAJO - TIPICO X03 UND Miguel P 9.00 10,976.95 98,792.57
MUEBLE ALTO & BAJO - TIPICO X04 UND Miguel P 9.00 5,948.21 53,533.91
MUEBLE ALTO & BAJO - TIPICO X05 UND Miguel P 8.00 10,949.89 87,599.16
MUEBLE ALTO & BAJO - TIPICO X06 UND Miguel P 9.00 8,560.51 77,044.58
MUEBLE ALTO & BAJO - TIPICO X07 UND Miguel P 9.00 8,560.51 77,044.58
MUEBLE ALTO & BAJO - TIPICO X08 UND Miguel P 9.00 10,473.82 94,264.36
MUEBLE ALTO & BAJO - TIPICO X09 UND Miguel P 10.00 10,745.31 107,453.13
MUEBLE ALTO & BAJO - TIPICO X10 UND Miguel P 9.00 11,844.91 106,604.23
MUEBLE ALTO & BAJO - TIPICO X11 UND Miguel P 8.00 8,772.78 70,182.26
MUEBLE ALTO & BAJO - TIPICO X12 UND Miguel P 9.00 8,432.12 75,889.08
MUEBLE ALTO & BAJO - TIPICO X13 UND Miguel P 9.00 8,622.21 77,599.91
MUEBLE ALTO & BAJO - TIPO 1005 UND Miguel P 1.00 7,930.47 7,930.47
MUEBLE ALTO & BAJO - TIPO 1006 UND Miguel P 1.00 9,212.14 9,212.14
MUEBLE ALTO & BAJO - TIPO 1007 UND Miguel P 1.00 10,771.83 10,771.83
MUEBLE ALTO & BAJO - TIPO 1008 UND Miguel P 1.00 9,468.87 9,468.87
MUEBLE ALTO & BAJO - TIPO 1009 UND Miguel P 1.00 9,886.13 9,886.13
MUEBLE ALTO & BAJO - TIPO 1010 UND Miguel P 1.00 7,890.82 7,890.82
MUEBLE ALTO & BAJO - TIPO 1013 UND Miguel P 1.00 8,580.66 8,580.66
MUEBLE ALTO & BAJO - TIPO 1014 UND Miguel P 1.00 7,850.21 7,850.21
MUEBLE ALTO & BAJO - TIPO 1015 UND Miguel P 1.00 9,601.56 9,601.56
MUEBLE ALTO & BAJO - TIPO 1016 UND Miguel P 1.00 7,834.17 7,834.17
09.02.04 MELAMINA - CLOSETS & WC -
W.C. - DORM. PRINCIPAL - TIPO 102 UND Miguel P 1.00 2,027.52 2,027.52
W.C. - DORM. SECUNDARIO - TIPO 102 UND Miguel P 1.00 3,500.64 3,500.64
W.C. - DORM. PRINCIPAL - TIPO 107 UND Miguel P 1.00 2,455.20 2,455.20
CLOSET - DORM. SECUNDARIO - TIPO 107 UND Miguel P 1.00 1,934.24 1,934.24
CLOSET - DORM. PRINCIPAL - TIPICO X01 UND Miguel P 10.00 3,650.88 36,508.78
CLOSET - DORM. SECUNDARIO - TIPICO X01 UND Miguel P 10.00 1,813.35 18,133.50
W.C. - DORM. PRINCIPAL - TIPICO X02 UND Miguel P 8.00 3,025.44 24,203.52
CLOSET - DORM. SECUNDARIO - TIPICO X02 UND Miguel P 8.00 1,813.35 14,506.80
W.C. - DORM. PRINCIPAL - TIPICO X03 UND Miguel P 9.00 2,455.20 22,096.80
CLOSET - DORM. SECUNDARIO - TIPICO X03 UND Miguel P 9.00 1,934.24 17,408.16
W.C. - DORM. PRINCIPAL - TIPICO X04 UND Miguel P 9.00 3,405.60 30,650.40
W.C. - DORM. PRINCIPAL - TIPICO X05 UND Miguel P 8.00 3,405.60 27,244.80
CLOSET - DORM. SECUNDARIO - TIPICO X05 UND Miguel P 8.00 1,934.24 15,473.92
W.C. - DORM. PRINCIPAL - TIPICO X06 UND Miguel P 9.00 3,904.56 35,141.04
ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL

01 MUROS Y TABIQUES - King Block - 1,688,089.02


CLOSET - DORM. SECUNDARIO - TIPICO X06 UND Miguel P 9.00 1,934.24 17,408.16
W.C. - DORM. PRINCIPAL - TIPICO X07 UND Miguel P 9.00 3,239.28 29,153.52
CLOSET - DORM. SECUNDARIO - TIPICO X07 UND Miguel P 9.00 1,934.24 17,408.16
W.C. - DORM. PRINCIPAL - TIPICO X08 UND Miguel P 9.00 3,405.60 30,650.40
CLOSET - DORM. SECUNDARIO - TIPICO X08 UND Miguel P 9.00 1,934.24 17,408.16
W.C. - DORM. PRINCIPAL - TIPICO X09 UND Miguel P 10.00 3,405.60 34,056.00
CLOSET - DORM. SECUNDARIO - TIPICO X09 UND Miguel P 10.00 1,402.32 14,023.24
W.C. - DORM. PRINCIPAL - TIPICO X10 UND Miguel P 9.00 3,801.60 34,214.40
W.C. - DORM. PRINCIPAL - TIPICO X11 UND Miguel P 8.00 2,930.40 23,443.20
CLOSET - DORM. SECUNDARIO - TIPICO X11 UND Miguel P 8.00 2,538.69 20,309.52
W.C. - DORM. PRINCIPAL - TIPICO X12 UND Miguel P 9.00 2,455.20 22,096.80
CLOSET - DORM. SECUNDARIO - TIPICO X12 UND Miguel P 9.00 1,148.46 10,336.10
W.C. - DORM. PRINCIPAL - TIPICO X13 UND Miguel P 9.00 2,217.60 19,958.40
CLOSET - DORM. SECUNDARIO - TIPICO X13 UND Miguel P 9.00 2,417.80 21,760.20
W.C. - DORM. PRINCIPAL - TIPO 1005 UND Miguel P 1.00 3,405.60 3,405.60
CLOSET - DORM. SECUNDARIO - TIPO 1005 UND Miguel P 1.00 2,176.02 2,176.02
W.C. - DORM. PRINCIPAL - TIPO 1006 UND Miguel P 1.00 2,257.20 2,257.20
CLOSET - DORM. SECUNDARIO - TIPO 1006 UND Miguel P 1.00 2,357.36 2,357.36
W.C. - DORM. PRINCIPAL - TIPO 1007 UND Miguel P 1.00 3,508.56 3,508.56
CLOSET - DORM. SECUNDARIO - TIPO 1007 UND Miguel P 1.00 2,030.95 2,030.95
W.C. - DORM. PRINCIPAL - TIPO 1008 UND Miguel P 1.00 3,516.48 3,516.48
CLOSET - DORM. SECUNDARIO - TIPO 1008 UND Miguel P 1.00 1,871.38 1,871.38
W.C. - DORM. PRINCIPAL - TIPO 1009 UND Miguel P 1.00 2,138.40 2,138.40
CLOSET - DORM. SECUNDARIO - TIPO 1009 UND Miguel P 1.00 2,417.80 2,417.80
W.C. - DORM. PRINCIPAL - TIPO 1010 UND Miguel P 1.00 3,405.60 3,405.60
CLOSET - DORM. SECUNDARIO - TIPO 1010 UND Miguel P 1.00 2,176.02 2,176.02
W.C. - DORM. PRINCIPAL - TIPO 1013 UND Miguel P 1.00 1,148.40 1,148.40
CLOSET - DORM. SECUNDARIO - TIPO 1013 UND Miguel P 1.00 1,952.37 1,952.37
W.C. - DORM. PRINCIPAL - TIPO 1014 UND Miguel P 1.00 1,512.72 1,512.72
CLOSET - DORM. SECUNDARIO - TIPO 1014 UND Miguel P 1.00 1,825.44 1,825.44
W.C. - DORM. PRINCIPAL - TIPO 1015 UND Miguel P 1.00 1,267.20 1,267.20
CLOSET - DORM. SECUNDARIO - TIPO 1015 UND Miguel P 1.00 1,958.42 1,958.42
W.C. - DORM. PRINCIPAL - TIPO 1016 UND Miguel P 1.00 2,534.40 2,534.40
CLOSET - DORM. SECUNDARIO - TIPO 1016 UND Miguel P 1.00 2,067.22 2,067.22
09.02.05 MELAMINA - MUEBLES DE SSHH -
MUEBLE SSHH - PRINCIPAL - TIPO 102 UND Miguel P 1.00 348.15 348.15
MUIEBLE SSHH - SECUNDARIO - TIPO 102 UND Miguel P 1.00 348.15 348.15
MUEBLE SSHH - PRINCIPAL - TIPO 107 UND Miguel P 1.00 348.15 348.15
MUIEBLE SSHH - SECUNDARIO - TIPO 107 UND Miguel P 1.00 348.15 348.15
MUIEBLE SSHH - VISITA - TIPO 107 UND Miguel P 1.00 348.15 348.15
MUEBLE SSHH - PRINCIPAL - TIPICO X01 UND Miguel P 10.00 348.15 3,481.50
MUIEBLE SSHH - SECUNDARIO - TIPICO X01 UND Miguel P 10.00 348.15 3,481.50
MUIEBLE SSHH - VISITA - TIPICO X01 UND Miguel P 10.00 348.15 3,481.50
MUEBLE SSHH - PRINCIPAL - TIPICO X02 UND Miguel P 8.00 348.15 2,785.20
MUIEBLE SSHH - SECUNDARIO - TIPICO X02 UND Miguel P 8.00 348.15 2,785.20
MUIEBLE SSHH - VISITA - TIPICO X02 UND Miguel P 8.00 348.15 2,785.20
MUEBLE SSHH - PRINCIPAL - TIPICO X03 UND Miguel P 9.00 348.15 3,133.35
MUIEBLE SSHH - SECUNDARIO - TIPICO X03 UND Miguel P 9.00 348.15 3,133.35
MUIEBLE SSHH - VISITA - TIPICO X03 UND Miguel P 9.00 348.15 3,133.35
MUEBLE SSHH - PRINCIPAL - TIPICO X04 UND Miguel P 9.00 348.15 3,133.35
MUIEBLE SSHH - VISITA - TIPICO X04 UND Miguel P 9.00 348.15 3,133.35
MUEBLE SSHH - PRINCIPAL - TIPICO X05 UND Miguel P 8.00 348.15 2,785.20
MUIEBLE SSHH - SECUNDARIO - TIPICO X05 UND Miguel P 8.00 348.15 2,785.20
MUIEBLE SSHH - VISITA - TIPICO X05 UND Miguel P 8.00 348.15 2,785.20
MUEBLE SSHH - PRINCIPAL - TIPICO X06 UND Miguel P 9.00 348.15 3,133.35
MUIEBLE SSHH - SECUNDARIO - TIPICO X06 UND Miguel P 9.00 348.15 3,133.35
MUIEBLE SSHH - VISITA - TIPICO X06 UND Miguel P 9.00 348.15 3,133.35
MUEBLE SSHH - PRINCIPAL - TIPICO X07 UND Miguel P 9.00 348.15 3,133.35
MUIEBLE SSHH - SECUNDARIO - TIPICO X07 UND Miguel P 9.00 348.15 3,133.35
MUIEBLE SSHH - VISITA - TIPICO X07 UND Miguel P 9.00 348.15 3,133.35
MUEBLE SSHH - PRINCIPAL - TIPICO X08 UND Miguel P 9.00 348.15 3,133.35
MUIEBLE SSHH - SECUNDARIO - TIPICO X08 UND Miguel P 9.00 348.15 3,133.35
MUIEBLE SSHH - VISITA - TIPICO X08 UND Miguel P 9.00 348.15 3,133.35
MUEBLE SSHH - PRINCIPAL - TIPICO X09 UND Miguel P 10.00 348.15 3,481.50
MUIEBLE SSHH - SECUNDARIO - TIPICO X09 UND Miguel P 10.00 348.15 3,481.50
MUIEBLE SSHH - VISITA - TIPICO X09 UND Miguel P 10.00 348.15 3,481.50
MUEBLE SSHH - PRINCIPAL - TIPICO X10 UND Miguel P 9.00 348.15 3,133.35
MUIEBLE SSHH - VISITA - TIPICO X10 UND Miguel P 9.00 348.15 3,133.35
MUEBLE SSHH - PRINCIPAL - TIPICO X11 UND Miguel P 8.00 348.15 2,785.20
MUIEBLE SSHH - SECUNDARIO - TIPICO X11 UND Miguel P 8.00 348.15 2,785.20
MUEBLE SSHH - PRINCIPAL - TIPICO X12 UND Miguel P 9.00 348.15 3,133.35
MUIEBLE SSHH - SECUNDARIO - TIPICO X12 UND Miguel P 9.00 348.15 3,133.35
MUEBLE SSHH - PRINCIPAL - TIPICO X13 UND Miguel P 9.00 348.15 3,133.35
MUIEBLE SSHH - SECUNDARIO - TIPICO X13 UND Miguel P 9.00 348.15 3,133.35
MUEBLE SSHH - PRINCIPAL - TIPO 1005 UND Miguel P 1.00 348.15 348.15
MUIEBLE SSHH - SECUNDARIO - TIPO 1005 UND Miguel P 1.00 348.15 348.15
MUEBLE SSHH - PRINCIPAL - TIPO 1006 UND Miguel P 1.00 348.15 348.15
MUIEBLE SSHH - SECUNDARIO - TIPO 1006 UND Miguel P 1.00 348.15 348.15
MUEBLE SSHH - PRINCIPAL - TIPO 1007 UND Miguel P 1.00 348.15 348.15
MUIEBLE SSHH - SECUNDARIO - TIPO 1007 UND Miguel P 1.00 348.15 348.15
MUEBLE SSHH - PRINCIPAL - TIPO 1008 UND Miguel P 1.00 348.15 348.15
MUIEBLE SSHH - SECUNDARIO - TIPO 1008 UND Miguel P 1.00 348.15 348.15
MUEBLE SSHH - PRINCIPAL - TIPO 1009 UND Miguel P 1.00 348.15 348.15
MUIEBLE SSHH - SECUNDARIO - TIPO 1009 UND Miguel P 1.00 348.15 348.15
MUEBLE SSHH - PRINCIPAL - TIPO 1010 UND Miguel P 1.00 348.15 348.15
MUIEBLE SSHH - SECUNDARIO - TIPO 1010 UND Miguel P 1.00 348.15 348.15
MUEBLE SSHH - PRINCIPAL - TIPO 1013 UND Miguel P 1.00 348.15 348.15
MUIEBLE SSHH - SECUNDARIO - TIPO 1013 UND Miguel P 1.00 348.15 348.15
MUEBLE SSHH - PRINCIPAL - TIPO 1014 UND Miguel P 1.00 348.15 348.15
MUIEBLE SSHH - SECUNDARIO - TIPO 1014 UND Miguel P 1.00 348.15 348.15
MUEBLE SSHH - PRINCIPAL - TIPO 1015 UND Miguel P 1.00 348.15 348.15
MUIEBLE SSHH - SECUNDARIO - TIPO 1015 UND Miguel P 1.00 348.15 348.15
MUEBLE SSHH - PRINCIPAL - TIPO 1016 UND Miguel P 1.00 348.15 348.15
MUIEBLE SSHH - SECUNDARIO - TIPO 1016 UND Miguel P 1.00 348.15 348.15
09.02.06 MELAMINA - PUERTAS DE LAVANDERIA -
PUERTA P-22A (1.40) - TIPO 102 UND Miguel P 1.00 612.75 612.75
PUERTA P-22A (1.40) - TIPICO X11 UND Miguel P 8.00 612.75 4,902.00
PUERTA P-22A (1.40) - TIPICO X12 UND Miguel P 9.00 612.75 5,514.75
PUERTA P-22A (1.40) - TIPICO X13 UND Miguel P 9.00 612.75 5,514.75
PUERTA P-22A (1.40) - TIPO 1005 UND Miguel P 1.00 612.75 612.75
PUERTA P-22C (1.33) - TIPO 1006 UND Miguel P 1.00 582.11 582.11
PUERTA P-22A (1.40) - TIPO 1007 UND Miguel P 1.00 612.75 612.75
PUERTA P-22A (1.40) - TIPO 1008 UND Miguel P 1.00 612.75 612.75
PUERTA P-22C (1.33) - TIPO 1009 UND Miguel P 1.00 582.11 582.11
PUERTA P-22A (1.40) - TIPO 1010 UND Miguel P 1.00 612.75 612.75
PUERTA P-22A (1.40) - TIPO 1013 UND Miguel P 1.00 612.75 612.75
PUERTA P-22B (1.30) - TIPO 1014 UND Miguel P 1.00 568.98 568.98
ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL

01 MUROS Y TABIQUES - King Block - 1,688,089.02


PUERTA P-22 (1.20) - TIPO 1015 UND Miguel P 1.00 525.21 525.21
PUERTA P-22A (1.40) - TIPO 1016 UND Miguel P 1.00 612.75 612.75
09.02.07 VARIOS - MADERA
PASOS & CONTRAPASOS EN ESCALERAS DE DUPLEX UND Miguel P 10.00 6,280.00 62,800.00
09.03 EXTERIORES Y AREAS SOCIALES -
09.03.01 PUERTAS
PUERTA CONTRAPLACADA: P- 02 UND Luis L 2.00 812.14 1,624.28
PUERTA CONTRAPLACADA: P- 03 UND Luis L 2.00 812.14 1,624.28
09.03.02 MELAMINE
COUNTER PRINCIPAL GLB Miguel P 1.00 13,200.00 13,200.00
09.03.03 VARIOS - MADERA
SOL Y SOMBRA EN ZONA PARRILLA 1 M2 Miguel P 1.00 14,960.00 14,960.00
SOL Y SOMBRA EN ZONA PARRILLA 2 M2 Miguel P 1.00 14,960.00 14,960.00
SOL Y SOMBRA EN PISCINA M2 Miguel P 1.00 7,480.00 7,480.00
CELOSIA EN COWORKING - PUMAQUIRO 2"x4" M2 Miguel P 11.97 269.50 3,225.92
RECUBRIMIENTO DE BANCAS EN PATIO INTERIOR - PUMAQUIRO 1 1/2" M2 Miguel P 30.90 391.12 12,085.48
BANCA DE MADERA EN SUM UND Miguel P 2.00 880.00 1,760.00
09.03.04 VARIOS - DEKOPANEL (Proveedor: DEKOMUNDO)
LOBBY - CELOSIA EN ZONA ALTA DEL COUNTER - DEKOMUNDO M2 Miguel P 54.41 346.14 18,833.39
M2 Miguel P 25.78 346.14 8,923.45
COWORKING - CELOSIA EN ZONA DE MUEBLES - DEKOMUNDO
M2 Miguel P 5.69 346.14 1,969.53
PARRILLAS - CELOSIA EN MUEBLES BAJOS - DEKOMUNDO
09.04 FACHADAS -
09.04.01 VARIOS - DEKOPANEL (Proveedor: DEKOMUNDO)
M2 Miguel P 22.20 346.14 7,684.27
EXTERIOR PRIMER NIVEL - TERRAZA DPTO. 101 - DEKOMUNDO
-
10 CARPINTERIA METALICA - 1,194,543.58
10.01 SOTANOS -
10.01.01 BARANDAS
BARANDA METALICA EN ESCALERA DE EVACUACION H=1.10m ML Luis L 40.40 445.00 17,978.00
PASAMANOS METALICO EN ESCALERA DE EVACUACION H=1.10m ML Luis L 44.32 180.00 7,977.60
10.01.02 VARIOS
RACK PARA ESTACIONAMIENTO DE BICICLETAS (POSTE METALICO) UND Miguel P 64.00 280.00 17,920.00
NUEVO RACK PARA ESTACIONAMIENTO DE BICICLETAS (EN MUROS) UND Luis L 180.00 240.00 43,200.00
TAPA METALICA CORRUGADA DE 1.00 X 060 (Inspeccion) UND Miguel P 1.00 850.00 850.00
ESCALERA DE GATO - CISTERNAS UND Miguel P 1.00 897.00 897.00
TAPA METALICA HERMETICA REMOVIBLE CON MARCO Y BASE FIERRO CAMARA
Miguel P 1.00 1,840.00 1,840.00
SUMIDERO UND
CANALETA DE REJILLA SUMIDERO (RAMPAS) 3/4" X 3/16" ML Luis L 138.14 289.00 39,922.46
COLUMNAS CON ESQUINEROS DE FE 2X2" ENCASTRADAS, PINTADAS HASTA 1.20M CON Miguel P 22.00 75.00 1,650.00
FRANJAS A 45° UND
PUERTA METALICA - CUARTO DE BASURA (0.90 x 2.10) UND Miguel P 1.00 1,300.00 1,300.00
10.01.03 PUERTAS CORTAFUEGO
PUERTA DE CORTAFUEGO - PC-01 - (F - 135) 1.00 X 2.10m ( Escalera Evac.+ Bombas) UND Luis L 27.00 1,340.10 36,182.70
PUERTA DE CORTAFUEGO - PC-02 - (F - 120) 1.00 X 2.10m ( Escalera Evac.) UND Luis L 1.00 1,340.10 1,340.10
10.02 TORRE - Departamentos y Areas Comunes -
10.02.01 BARANDAS
BARANDA METALICA EN ESCALERA DE EVACUACION H=1.10m ML Luis L 112.40 445.00 50,018.00
PASAMANOS METALICO EN ESCALERA DE EVACUACION H=1.10m ML Luis L 121.88 180.00 21,938.40
BALCONES: BARANDAS DE FIERRO PINTADAS DE COLOR NEGRO. "V" INVERTIDA EN
PLATINAS DE 3/16"X1", PASAMANO TUBULAR DE SECCIÓN RECTANGULAR DE 2"X1" Y EN ML Luis L 969.97 480.00 465,585.60
BASE PLATINA DE 3/8"X1.5.

ESC. DUPLEX: BARANDA H=1.10m DE TUBODE FIERRO DE 2". ELEMENTOS HORIZONTALES ML Luis L 68.00 445.00 30,260.00
DE TUBO REDONDO LISO DE 3/4" Y ELEMENTOS VERTICALES EN PLATINAS DE 2" e= 1CM.,
CON CANOPLAS RECTANGULARES DE PLANCHA DE FIERRO COLOR NEGRO
ESC. DUPLEX: PASAMANO DE TUBO DE FIERRO DE 2" ANCLADO A MURO, CON CANOPLAS ML Luis L 66.00 195.00 12,870.00
CIRCULARES DE PLANCHA DE FIERRO COLOR NEGRO.
10.02.02 VARIOS
REJILLA INOX EN DUCHAS ML Luis L 269.77 295.00 79,582.15
BARRA DE CONTENCION Y DIRECCION - PISO 01 ML Luis L 1.00 650.00 650.00
10.02.03 PUERTAS CORTAFUEGO
PUERTA DE CORTAFUEGO - PC-01 - (F - 135) 1.00 X 2.10m ( Escalera Evac.) UND Miguel P 11.00 1,340.10 14,741.10
PUERTA DE CORTAFUEGO - PC-02 - (F - 120) 1.00 X 2.10m ( Escalera Evac.) UND Miguel P 10.00 1,340.10 13,401.00
PUERTA DE CORTAFUEGO - PC-03 - (F - 90) - Ducto Electrico UND Miguel P 10.00 4,863.71 48,637.13
PUERTA DE CORTAFUEGO - PC-04 - (F - 90) - Ducto Sanitario UND Miguel P 10.00 7,332.71 73,327.13
PUERTA DE CORTAFUEGO - PC-05 - (F - 90) - Ducto Sanitario UND Miguel P 18.00 2,431.84 43,773.08
PUERTA DE CORTAFUEGO - PC-06 - (F - 90) - Ducto Electrico UND Miguel P 18.00 2,469.00 44,442.00
PUERTA DE CORTAFUEGO - PC-07 - (F - 90) - Ducto Sanitario UND Miguel P 10.00 4,863.71 48,637.13

10.03 EXTERIORES Y AREAS SOCIALES -


10.03.01 PUERTAS
PUERTA SECCIONABLE - INGRESO VEHICULAR UND Miguel P 1.00 11,250.00 11,250.00
10.03.02 VARIOS
ESCALERA DE GATO C/BARANDILLA DE SEGURIDAD - AZOTEA UND Miguel P 1.00 1,400.00 1,400.00
PARRILLA DE ACERO INOXIDABLE UND Miguel P 2.00 850.00 1,700.00
MESA DE FUEGO UND Miguel P 1.00 5,625.00 5,625.00

10.04 EQUIPAMIENTO -
10.04.01 ASCENSOR
VIGAS DIVISORIAS UND Miguel P 19.00 1,190.00 22,610.00
REJA DIVISORIA EN PIT UND Miguel P 1.00 1,920.00 1,920.00
ESCALERA DE GATO C/BARANDILLA DE SEGURIDAD - AZOTEA UND Miguel P 1.00 1,800.00 1,800.00
CANCAMOS DE IZAJE GLB Miguel P 6.00 368.00 2,208.00
CONTRATRAMPA UND Miguel P 2.00 1,820.00 3,640.00
10.04.02 SUB ESTACION ELECTRICA
TAPA METALICA (2.10 x 1.35) - INGRESO DE TRANSFORMADOR UND Miguel P 1.00 1,520.00 1,520.00
REJILLA METALICA (1.25 x 0.85) - INGRESO DE AIRE UND Miguel P 1.00 710.00 710.00
TAPA METALICA (1.65 x 0.95) - INGRESO DE EQUIPOS & VENTILACION UND Miguel P 1.00 1,050.00 1,050.00
TAPA METALICA (1.65 x 0.95) - INGRESO DE PERSONAL UND Miguel P 1.00 1,050.00 1,050.00
ESCALERA DE GATO UND Miguel P 1.00 2,720.00 2,720.00
CARPINTERIA INTERIOR GLB Miguel P 1.00 16,420.00 16,420.00
-
11 CARPINTERIA DE ALUMINIO - 1,305,986.41
11.01 SOTANOS -
11.01.01 MAMPARAS - Series 25. Cristal Templado 6mm
11.01.01.01 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-03 UND Miguel P 1.00 1,984.50 1,984.50
11.01.02 REJILLAS DE GAS
11.01.02.01 REJILLAS - ALUMINIO NEGRO MATE- R-01 UND Miguel P 20.00 218.63 4,372.50
11.02 TORRE - Departamentos y Areas Comunes -
11.02.01 VENTANAS - Serie 38.25, Vidrios Crudo de 4mm
11.02.01.01 VENTANAS - SERIE 25 - ALUMINIO NEGRO MATE- V-01 UND Miguel P 28.00 84.00 2,352.00
11.02.01.02 VENTANAS - SERIE 25 - ALUMINIO NEGRO MATE- V-01 B UND Miguel P 7.00 84.00 588.00
11.02.01.03 VENTANAS - SERIE 25 - ALUMINIO NEGRO MATE- V-03 UND Miguel P 1.00 471.24 471.24
11.02.02 MAMPARAS - Series 25. Cristal Templado 6mm
ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL

01 MUROS Y TABIQUES - King Block - 1,688,089.02


11.02.02.01 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-01 UND Miguel P 9.00 1,727.25 15,545.25
11.02.02.02 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-02 UND Miguel P 10.00 1,764.00 17,640.00
11.02.02.03 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-03 UND Miguel P 8.00 1,984.50 15,876.00
11.02.02.04 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-04 UND Miguel P 13.00 1,396.50 18,154.50
11.02.02.05 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-05 UND Miguel P 2.00 1,830.15 3,660.30
11.02.02.06 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-06 UND Miguel P 4.00 1,580.25 6,321.00
11.02.02.07 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-07 UND Miguel P 2.00 1,320.35 2,640.70
11.02.02.08 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-08 UND Miguel P 14.00 1,837.50 25,725.00
11.02.02.09 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-09 UND Miguel P 5.00 1,617.00 8,085.00
11.02.02.10 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-10 UND Miguel P 9.00 1,925.70 17,331.30
11.02.02.11 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-11 UND Miguel P 2.00 1,293.60 2,587.20
11.02.02.12 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-12 UND Miguel P 4.00 1,690.50 6,762.00
11.02.02.13 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-13 UND Miguel P 1.00 1,911.00 1,911.00
11.02.02.14 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-14 UND Miguel P 2.00 1,499.40 2,998.80
11.02.02.15 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-15 UND Miguel P 2.00 852.60 1,705.20
11.02.02.16 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-16 UND Miguel P 7.00 2,146.20 15,023.40
11.02.02.17 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-17 UND Miguel P 2.00 2,352.00 4,704.00
11.02.02.18 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-18 UND Miguel P 2.00 2,352.00 4,704.00
11.02.02.19 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-19 UND Miguel P 6.00 639.45 3,836.70
11.02.02.20 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-20 UND Miguel P 10.00 1,747.20 17,472.00
11.02.02.21 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-21 UND Miguel P 1.00 2,016.00 2,016.00
11.02.02.22 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-22 UND Miguel P 33.00 1,596.00 52,668.00
11.02.02.23 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-23 UND Miguel P 1.00 2,755.20 2,755.20
11.02.02.24 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-24 UND Miguel P 16.00 1,604.40 25,670.40
11.02.02.25 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-25 UND Miguel P 17.00 2,007.60 34,129.20
11.02.02.26 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-26 UND Miguel P 9.00 2,587.45 23,287.08
11.02.02.27 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-27 UND Miguel P 9.00 4,149.60 37,346.40
11.02.02.28 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-28 UND Miguel P 9.00 2,478.00 22,302.00
11.02.02.29 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-29 UND Miguel P 9.00 2,284.80 20,563.20
11.02.02.30 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-30 UND Miguel P 6.00 1,327.20 7,963.20
11.02.02.31 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-31 UND Miguel P 90.00 1,411.20 127,008.00
11.02.02.32 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-32 UND Miguel P 8.00 2,200.80 17,606.40
11.02.02.33 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-33 UND Miguel P 30.00 1,125.60 33,768.00
11.02.02.34 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-34 UND Miguel P 30.00 8,988.00 269,640.00
11.02.02.35 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-35 UND Miguel P 8.00 1,722.40 13,779.20
11.02.02.36 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-36 UND Miguel P 8.00 4,216.80 33,734.40
11.02.02.37 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-37 UND Miguel P 1.00 1,043.70 1,043.70
11.02.02.38 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-38 UND Miguel P 1.00 3,134.10 3,134.10
11.02.02.39 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-42 UND Miguel P 1.00 2,293.20 2,293.20
11.02.02.40 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-43 UND Miguel P 10.00 1,580.25 15,802.50
11.02.02.41 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-44 UND Miguel P 2.00 1,789.20 3,578.40
11.02.02.42 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-45 UND Miguel P 4.00 2,012.85 8,051.40
11.02.02.43 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-46 UND Miguel P 5.00 1,938.30 9,691.50
11.02.02.44 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-47 UND Miguel P 1.00 1,602.83 1,602.83
11.02.02.45 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-48 UND Miguel P 1.00 1,915.94 1,915.94
11.02.02.46 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-49 UND Miguel P 1.00 1,416.45 1,416.45
11.02.02.47 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-50 UND Miguel P 1.00 1,058.61 1,058.61
11.02.02.48 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-51 UND Miguel P 1.00 1,552.53 1,552.53
11.02.02.49 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-52 UND Miguel P 1.00 864.78 864.78
11.02.02.50 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-53 UND Miguel P 1.00 1,520.82 1,520.82
11.02.02.51 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-54 UND Miguel P 2.00 1,953.21 3,906.42
11.02.02.52 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-55 UND Miguel P 2.00 2,609.25 5,218.50
11.02.02.53 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-56 UND Miguel P 2.00 2,176.86 4,353.72
11.02.02.54 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-57 UND Miguel P 2.00 954.24 1,908.48
11.02.02.55 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-58 UND Miguel P 1.00 2,557.07 2,557.07
11.02.02.56 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-59 UND Miguel P 1.00 2,385.60 2,385.60
11.02.02.57 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-60 UND Miguel P 1.00 1,592.50 1,592.50
11.02.02.58 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-61-B UND Miguel P 1.00 1,162.53 1,162.53
11.02.02.59 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-61 A UND Miguel P 2.00 1,342.73 2,685.45
11.02.02.60 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-61 B UND Miguel P 2.00 1,069.16 2,138.31
11.02.02.61 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-61 C UND Miguel P 1.00 1,239.18 1,239.18
11.02.02.62 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-62 UND Miguel P 1.00 1,202.34 1,202.34
11.02.02.64 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-64 UND Miguel P 1.00 2,030.44 2,030.44
11.02.02.65 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-65 UND Miguel P 1.00 2,027.03 2,027.03
11.02.02.66 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-66 UND Miguel P 2.00 1,824.81 3,649.62
11.02.02.67 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-67 UND Miguel P 2.00 1,492.40 2,984.80
11.02.02.68 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-68 UND Miguel P 1.00 2,291.63 2,291.63
11.02.02.69 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-69 UND Miguel P 1.00 2,011.54 2,011.54
11.02.02.70 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-70 UND Miguel P 4.00 757.68 3,030.72
11.02.02.71 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-71 UND Miguel P 1.00 1,977.59 1,977.59
11.02.02.72 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-72 UND Miguel P 1.00 923.65 923.65
11.02.02.73 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-73 UND Miguel P 1.00 2,149.88 2,149.88
11.02.02.74 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-79 UND Miguel P 1.00 5,534.67 5,534.67
11.02.02.75 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-80 UND Miguel P 1.00 2,012.59 2,012.59
11.02.02.76 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-82 UND Miguel P 1.00 2,886.40 2,886.40
11.02.02.77 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-83 UND Miguel P 1.00 577.28 577.28
11.02.02.78 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-84 UND Miguel P 1.00 1,792.00 1,792.00
11.02.02.79 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-85 UND Miguel P 1.00 1,515.61 1,515.61
11.02.03 REJILLAS DE GAS
11.02.03.01 MAMPARAS - ALUMINIO NEGRO MATE- R-02 UND Miguel P 10.00 218.63 2,186.25
11.02.03.02 MAMPARAS - ALUMINIO NEGRO MATE- R-03 UND Miguel P 10.00 218.63 2,186.25
11.02.04 MAMPARAS DE SSHH
11.02.04.01 MAMPARA DUCHA SSHH - PRINCIPAL - TIPO 102 UND Miguel P 1.00 665.85 732.44
11.02.04.02 MAMPARA DUCHA SSHH - SECUNDARIO - TIPO 102 UND Miguel P 1.00 405.36 445.90
11.02.04.03 MAMPARA DUCHA SSHH - PRINCIPAL - TIPO 107 UND Miguel P 1.00 665.85 732.44
11.02.04.04 MAMPARA DUCHA SSHH - SECUNDARIO - TIPO 107 UND Miguel P 1.00 455.36 500.89
11.02.04.05 MAMPARA DUCHA SSHH - PRINCIPAL - TIPICO X01 UND Miguel P 10.00 665.85 732.44
11.02.04.06 MAMPARA DUCHA SSHH - SECUNDARIO - TIPICO X01 UND Miguel P 10.00 455.36 500.89
11.02.04.07 MAMPARA DUCHA SSHH - PRINCIPAL - TIPICO X02 UND Miguel P 8.00 665.85 732.44
11.02.04.08 MAMPARA DUCHA SSHH - SECUNDARIO - TIPICO X02 UND Miguel P 8.00 455.36 500.89
11.02.04.09 MAMPARA DUCHA SSHH - PRINCIPAL - TIPICO X03 UND Miguel P 9.00 665.85 732.44
11.02.04.10 MAMPARA DUCHA SSHH - SECUNDARIO - TIPICO X03 UND Miguel P 9.00 455.36 500.89
11.02.04.11 MAMPARA DUCHA SSHH - PRINCIPAL - TIPICO X04 UND Miguel P 9.00 665.85 732.44
11.02.04.12 MAMPARA DUCHA SSHH - PRINCIPAL - TIPICO X05 UND Miguel P 8.00 665.85 732.44
11.02.04.13 MAMPARA DUCHA SSHH - SECUNDARIO - TIPICO X05 UND Miguel P 8.00 455.36 500.89
11.02.04.14 MAMPARA DUCHA SSHH - PRINCIPAL - TIPICO X06 UND Miguel P 9.00 665.85 732.44
11.02.04.15 MAMPARA DUCHA SSHH - SECUNDARIO - TIPICO X06 UND Miguel P 9.00 455.36 500.89
11.02.04.16 MAMPARA DUCHA SSHH - PRINCIPAL - TIPICO X07 UND Miguel P 9.00 665.85 732.44
11.02.04.17 MAMPARA DUCHA SSHH - SECUNDARIO - TIPICO X07 UND Miguel P 9.00 455.36 500.89
11.02.04.18 MAMPARA DUCHA SSHH - PRINCIPAL - TIPICO X08 UND Miguel P 9.00 665.85 732.44
11.02.04.19 MAMPARA DUCHA SSHH - SECUNDARIO - TIPICO X08 UND Miguel P 9.00 455.36 500.89
11.02.04.20 MAMPARA DUCHA SSHH - PRINCIPAL - TIPICO X09 UND Miguel P 10.00 665.85 732.44
11.02.04.21 MAMPARA DUCHA SSHH - SECUNDARIO - TIPICO X09 UND Miguel P 10.00 455.36 500.89
11.02.04.22 MAMPARA DUCHA SSHH - PRINCIPAL - TIPICO X10 UND Miguel P 9.00 665.85 732.44
11.02.04.23 MAMPARA DUCHA SSHH - PRINCIPAL - TIPICO X11 UND Miguel P 8.00 665.85 732.44
11.02.04.24 MAMPARA DUCHA SSHH - SECUNDARIO - TIPICO X11 UND Miguel P 8.00 455.36 500.89
11.02.04.25 MAMPARA DUCHA SSHH - PRINCIPAL - TIPICO X12 UND Miguel P 9.00 665.85 732.44
ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL

01 MUROS Y TABIQUES - King Block - 1,688,089.02


11.02.04.26 MAMPARA DUCHA SSHH - SECUNDARIO - TIPICO X12 UND Miguel P 9.00 455.36 500.89
11.02.04.27 MAMPARA DUCHA SSHH - PRINCIPAL - TIPICO X13 UND Miguel P 9.00 665.85 732.44
11.02.04.28 MAMPARA DUCHA - SECUNDARIO - TIPICO X13 UND Miguel P 9.00 455.36 500.89
11.02.04.29 MAMPARA DUCHA SSHH - PRINCIPAL - TIPO 1005 UND Miguel P 1.00 665.85 732.44
11.02.04.30 MAMPARA DUCHA SSHH - SECUNDARIO - TIPO 1005 UND Miguel P 1.00 455.36 500.89
11.02.04.31 MAMPARA DUCHA SSHH - PRINCIPAL - TIPO 1006 UND Miguel P 1.00 665.85 732.44
11.02.04.32 MAMPARA DUCHA SSHH - SECUNDARIO - TIPO 1006 UND Miguel P 1.00 455.36 500.89
11.02.04.33 MAMPARA DUCHA SSHH - PRINCIPAL - TIPO 1007 UND Miguel P 1.00 665.85 732.44
11.02.04.34 MAMPARA DUCHA SSHH - SECUNDARIO - TIPO 1007 UND Miguel P 1.00 455.36 500.89
11.02.04.35 MAMPARA DUCHA SSHH - PRINCIPAL - TIPO 1008 UND Miguel P 1.00 665.85 732.44
11.02.04.36 MAMPARA DUCHA SSHH - SECUNDARIO - TIPO 1008 UND Miguel P 1.00 455.36 500.89
11.02.04.37 MAMPARA DUCHA SSHH - PRINCIPAL - TIPO 1009 UND Miguel P 1.00 665.85 732.44
11.02.04.38 MAMPARA DUCHA SSHH - SECUNDARIO - TIPO 1009 UND Miguel P 1.00 455.36 500.89
11.02.04.39 MAMPARA DUCHA SSHH - PRINCIPAL - TIPO 1010 UND Miguel P 1.00 665.85 732.44
11.02.04.40 MAMPARA DUCHA SSHH - SECUNDARIO - TIPO 1010 UND Miguel P 1.00 455.36 500.89
11.02.04.41 MAMPARA DUCHA SSHH - PRINCIPAL - TIPO 1013 UND Miguel P 1.00 665.85 732.44
11.02.04.42 MAMPARA DUCHA SSHH - SECUNDARIO - TIPO 1013 UND Miguel P 1.00 455.36 500.89
11.02.04.43 MAMPARA DUCHA SSHH - PRINCIPAL - TIPO 1014 UND Miguel P 1.00 665.85 732.44
11.02.04.44 MAMPARA DUCHA SSHH - SECUNDARIO - TIPO 1014 UND Miguel P 1.00 455.36 500.89
11.02.04.45 MAMPARA DUCHA SSHH - PRINCIPAL - TIPO 1015 UND Miguel P 1.00 665.85 732.44
11.02.04.46 MAMPARA DUCHA SHH - SECUNDARIO - TIPO 1015 UND Miguel P 1.00 455.36 500.89
11.02.04.47 MAMPARA DUCHA SSHH - PRINCIPAL - TIPO 1016 UND Miguel P 1.00 665.85 732.44
11.02.04.48 MAMPARA DUCHA - SECUNDARIO - TIPO 1016 UND Miguel P 1.00 455.36 500.89
11.02.05 BARANDAS
ML Miguel P 60.81 826.90 50,283.91
11.02.05.01 BARANDAS EMPOTRADAS EN TERRAZAS PRIMER NIVEL - PATIO INTERIOR
11.03 EXTERIORES Y AREAS SOCIALES -
11.03.01 VENTANAS - Serie 38.25, Vidrios Crudo de 4mm
11.03.01.01 VENTANAS - SERIE 25 - ALUMINIO NEGRO MATE- V-01 C UND Miguel P 2.00 168.00 336.00
11.03.01.02 VENTANAS - SERIE 25 - ALUMINIO NEGRO MATE- V-02 UND Miguel P 1.00 1,008.70 1,008.70
11.03.02 MAMPARAS - Series 25. Cristal Templado 6mm
11.03.02.01 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-39 UND Miguel P 1.00 3,116.40 3,116.40
11.03.02.02 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-40 UND Miguel P 1.00 44,070.00 44,070.00
11.03.02.03 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-41 UND Miguel P 1.00 714.24 714.24
11.03.02.04 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-74 UND Miguel P 1.00 2,146.50 2,146.50
11.03.02.05 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-75 UND Miguel P 1.00 3,578.40 3,578.40
11.03.02.06 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-76 UND Miguel P 1.00 2,587.20 2,587.20
11.03.02.07 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-77 UND Miguel P 1.00 1,317.12 1,317.12
11.03.02.08 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-78 UND Miguel P 1.00 5,644.80 5,644.80
11.03.02.09 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-81 UND Miguel P 1.00 1,512.00 1,512.00
11.03.02.10 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- P-31 UND Miguel P 1.00 945.00 945.00
11.03.03 ESPEJOS
11.03.02.01 ESPEJO SIN BISEL DE 6MM PEGADO A MURO - GYM UND Miguel P 4.00 812.50 3,250.00
ESPEJO SIN BISEL DE 6MM CON INCLINACIÓN DE 2° CON MARCO DE ACERO INOX.(SH UND Miguel P 1.00 562.50 562.50
11.03.02.02 DISC.)
11.03.04 BARANDAS EN AZOTEA
B-01 UND Miguel P 1.00 2,970.63 2,970.63
B-02 UND Miguel P 1.00 2,970.63 2,970.63
B-03 UND Miguel P 1.00 3,206.85 3,206.85
B-04 UND Miguel P 1.00 3,014.38 3,014.38
B-05 UND Miguel P 1.00 2,970.63 2,970.63
B-06 UND Miguel P 1.00 2,970.63 2,970.63
B-07 UND Miguel P 1.00 2,563.75 2,563.75
B-08 UND Miguel P 1.00 2,406.25 2,406.25
B-09 UND Miguel P 1.00 3,552.50 3,552.50
B-10 UND Miguel P 1.00 2,590.00 2,590.00
B-11 UND Miguel P 1.00 9,416.96 9,416.96
B-12 UND Miguel P 1.00 6,137.60 6,137.60
B-13 UND Miguel P 1.00 1,962.24 1,962.24
B-14 UND Miguel P 1.00 5,559.68 5,559.68
B-15 UND Miguel P 1.00 7,087.36 7,087.36
B-16 UND Miguel P 1.00 5,440.40 5,440.40
11.03.05 CELOSIAS EN MUROS PERIMETRALES
SOBRE ALTURA DE MUROS PERIMETRALES - CELOSIAS M2 Miguel P 90.87 418.00 37,983.66
-
12 TABLEROS DE CUARZO - 336,507.56
12.01 TORRE - Departamentos y Areas Comunes -
12.01.01 TABLEROS DE COCINAS
TABLERO DE COCINA CUARZO KLIPEN NOVO BIANCO (MO-05) ML Miguel P 542.37 431.25 233,897.06
12.01.02 TABLEROS DE SSHH
TABLERO PARA LAVATORIO DE CUARZO KLIPEN NOVO BIANCO (MO-07) ML Luis L 213.18 412.50 87,936.75
12.02 EXTERIORES Y AREAS SOCIALES -
12.02.01 TABLEROS DE COUNTER
COUNTER ENCHAPADO CON CUARZO CALACATTA BLACK (MO-01) ML Miguel P 8.16 1,148.90 9,375.00
12.02.02 TABLEROS DE ZONA DE PARRILAS - AZOTEA
TABLERO DE CUARZO CALACATTA BLACK (MO-16) ML Miguel P 7.85 675.00 5,298.75
-
13 EQUIPAMIENTO SANITARIO - 554,717.63
13.01 SOTANOS - Camerinos -
13.01.01 SUMINISTRO DE APARATOS SANITARIOS
SSHH: LAVATORIO OVALIN DE SOBREPONER MODELO MAUI MARCA TREBOL UND Miguel P 3.00 81.10 243.31
SSHH: INODORO ONE PIECE VAINSA STELLA, SISTEMA DUAL DESCARGA 4.8/3L
Miguel P 3.00 195.35 586.04
61x36.5x72CM UND
SSHH: URINARIO BÁVARO, COD: BSV.60.B.021. VAINSA. UND Miguel P 1.00 185.51 185.51
13.01.02 SUMINISTRO DE GRIFERIAS
SSHH: MONOCOMANDO PARA LAVATORIO POR CONFIRMAR (SH SOTANOS) UND Miguel P 2.00 492.07 984.14
SSHH: MONOCOMANDO PARA DUCHA POR CONFIRMAR (SH SOTANOS) UND Miguel P 2.00 474.99 949.97
13.02 TORRE - Departamentos y Areas Comunes -
13.02.01 SUMINISTRO DE APARATOS SANITARIOS
COCINA: LAVADERO TEKA DE EMPOTRAR TETUAN 1 POZA SIN ESCURRIDOR 43.3X43.3X18 Miguel P 65.00 203.04 13,197.61
CM UND
COCINA: LAVADERO TEKA DE EMPOTRAR SUANCES 2 POZAS SIN ESCURRIDOR Miguel P 63.00 626.26 39,454.29
77.9X46.4X20 CM UND
LAVANDERIA: LAVATORIO DECA DE COLGAR SERIE TQ02 BLANCO 53.5X51X29.5 CM UND Miguel P 128.00 134.29 17,188.86
SSHH: LAVATORIO BOWL KLIPEN EVA BLANCO 49x38x13CM UND Miguel P 329.00 56.67 18,645.09
SSHH: INODORO ONE PIECE VAINSA STELLA, SISTEMA DUAL DESCARGA 4.8/3L
Miguel P 329.00 195.35 64,268.81
61x36.5x72CM UND
13.02.02 SUMINISTRO DE GRIFERIAS
COCINA: MONOCOMANDO VERTICAL COLOR NEGRO MATE MODELO DESIGN MARCA
Miguel P 128.00 458.13 58,640.50
STRETTO UND
SSHH: MONOCOMANDO DE LAVATORIO ALTA STRETTO COLOR NEGRO MATE, MODELO
Miguel P 329.00 492.07 161,891.19
DESSIN MOSAICO UND
SSHH: MONOCOMANDO DE DUCHA COLOR NEGRO MATTE MODELO DESSIN, MARCO
Miguel P 238.00 474.99 113,046.50
STRETTO UND
LAVANDERIA: LLAVE JARDÍN CIM 34 1/2" CON SALIDA PARA MANGUERA UND Miguel P 128.00 38.50 4,928.00
13.02.03 SUMINISTRO DE ACCESORIOS SANITARIOS
SUMIDERO DE ACERO INOX. ACABADO SATINADO DE 2" UND Miguel P 4.00 26.01 104.03
ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL

01 MUROS Y TABIQUES - King Block - 1,688,089.02


REGISTRO DE ACERO INOX. ACABADO SATINADO DE 2" UND Miguel P 6.00 32.63 195.76
13.03 EXTERIORES Y AREAS SOCIALES -
13.03.01 SUMINISTRO DE APARATOS SANITARIOS
SSHH: LAVATORIO OVALIN DE SOBREPONER MODELO MAUI MARCA TREBOL UND Miguel P 3.00 81.10 243.31
SSHH: LAVATORIO PARA DISCAPACITADOS UND Miguel P 1.00 233.05 233.05
SSHH: INODORO ONE PIECE VAINSA STELLA, SISTEMA DUAL DESCARGA 4.8/3L Miguel P 4.00 195.35 781.38
61x36.5x72CM UND
PARRILLAS: LAVADERO MAGNUM REDONDO EMPOTRADO PARA COCINA 37CMx17" DE Miguel P 2.00 214.41 428.81
ACERO INOXIDABLE UND
13.03.02 SUMINISTRO DE GRIFERIAS
SSHH: MONOCOMANDO DE LAVATORIO ALTA STRETTO COLOR NEGRO MATE, MODELO Miguel P 1.00 492.07 492.07
DESSIN MOSAICO UND
SSHH: MONOCOMANDO DE DUCHA COLOR NEGRO MATTE MODELO DESSIN, MARCO Miguel P 1.00 474.99 474.99
STRETTO UND
SSHH: MONOCOMANDO PARA LAVATOIO POR CONFIRMAR (SH AZOTEA) UND Miguel P 2.00 237.71 475.42
Miguel P 2.00 237.71 475.42
PARRILLAS: MONOCOMANDO PARA LAVADERO POR CONFIRMAR (ZONA DE PARRILLAS) UND
13.03.03 SUMINISTRO DE ACCESORIOS SANITARIOS
SUMIDERO DE ACERO INOX. ACABADO SATINADO DE 2" UND Miguel P 1,072.00 26.01 27,881.08
REGISTRO DE ACERO INOX. ACABADO SATINADO DE 2" UND Miguel P 851.00 32.63 27,765.68
DISPENSADOR DE PAPEL HIGIENICO MARCA KIMBERLY CLARK, COLOR BLANCO UND Miguel P 5.00 129.58 647.88
BARRA DE APOYO ABATIBEL EN ACERO INOX. SATINADOD DE 760mm x 40mm de ∅ UND Miguel P 2.00 154.47 308.93
-
14 EQUIPAMIENTO ELECTRICO - 335,720.50
14.01 SOTANOS -
14.01.01 SUMINISTRO DE EQUIPOS DE ALUMBRADO
Luis L 118.00 65.00 7,670.00
NUEVO LUMINARIA L01a ESTACIONAMIENTOS UND
Luis L 1.00 65.00 65.00
NUEVO LUMINARIA L01b- PIT ASCENSORES UND
Luis L 31.00 65.00 2,015.00
NUEVO LUMINARIA L01c - depositos UND
Luis L 7.00 65.00 455.00
NUEVO LUMINARIA L01d - depositos UND
Luis L 15.00 65.00 975.00
NUEVO LUMINARIA L02a - estacionamiento bicicleta UND
NUEVO LUMINARIA L03a - escalera UND Luis L 71.00 65.00 4,615.00
NUEVO LUMINARIA L03b - UND Luis L 30.00 65.00 1,950.00
14.01.02 EQUIPAMIENTO DE INTERRUPTORES
Luis L 122.00 19.00 2,318.00
INTERRUPTOR UNIPOLAR 1 GOLPE UND
14.01.03 EQUIPAMIENTO DE TOMACORRIENTES
TOMACORRIENTE DOBLE C/PUESTA A TIERRA UND Luis L 214.00 26.50 5,671.00
14.02 TORRE - Departamentos y Areas Comunes -
14.02.01 SUMINISTRO DE EQUIPOS DE ALUMBRADO
Luis L 658.00 65.00 42,770.00
NUEVO LUMINARIA P01a/P03 - iluminacion general UND
Luis L 31.00 65.00 2,015.00
NUEVO LUMINARIA P02 - iluminacion puntual UND
Luis L 42.00 65.00 2,730.00
NUEVO LUMINARIA P05a y b - area de mesas UND
Luis L 1.00 65.00 65.00
NUEVO LUMINARIA P06 - Coworking UND
Luis L 1.00 65.00 65.00
NUEVO LUMINARIA P07 - Coworking UND
Luis L 264.00 65.00 17,160.00
NUEVO LUMINARIA P08 - ingreso a departamento UND
Luis L 17.00 65.00 1,105.00
NUEVO LUMINARIA P09a y P10 - administracion y baños UND
Luis L 4.00 65.00 260.00
NUEVO LUMINARIA P09b - caja ascensor UND
Luis L 487.00 65.00 31,655.00
NUEVO LUMINARIA D01a UND
Luis L 50.00 65.00 3,250.00
NUEVO LUMINARIA D01b UND
Luis L 270.00 65.00 17,550.00
NUEVO LUMINARIA D02 UND
Luis L 65.00 65.00 4,225.00
NUEVO LUMINARIA D06a UND
Luis L 51.00 65.00 3,315.00
NUEVO LUMINARIA D06b UND
Luis L 12.00 65.00 780.00
NUEVO LUMINARIA D07a UND
Luis L 6.00 65.00 390.00
NUEVO LUMINARIA D07b UND
Luis L 11.00 65.00 715.00
NUEVO LUMINARIA P04 UND
Luis L 2.00 65.00 130.00
NUEVO LUMINARIA P05c UND
Luis L 19.00 65.00 1,235.00
NUEVO LUMINARIA D05b UND
Luis L 28.00 65.00 1,820.00
NUEVO LUMINARIA P10b UND
Luis L 9.00 65.00 585.00
NUEVO LUMINARIA P10c UND
Luis L 5.00 65.00 325.00
NUEVO LUMINARIA P13 UND
Luis L 14.00 65.00 910.00
NUEVO LUMINARIA P14 UND
14.02.02 EQUIPAMIENTO DE INTERRUPTORES
Miguel P 98.00 19.00 1,862.00
INTERRUPTOR UNIPOLAR 1 GOLPE UND
INTERRUPTOR UNIPOLAR 2 GOLPE UND Miguel P 53.00 22.00 1,166.00
Miguel P 27.00 25.00 675.00
INTERRUPTOR UNIPOLAR 3 GOLPE UND
INTERRUPTOR 1 GOLPE ( CONMUTACION) UND Miguel P 44.00 24.50 1,078.00
14.02.03 EQUIPAMIENTO DE TOMACORRIENTES
TOMACORRIENTE DOBLE C/PUESTA A TIERRA UND Luis L 1,153.00 26.50 30,554.50
14.03 EXTERIORES Y AREAS SOCIALES -
14.03.01 SUMINISTRO DE EQUIPOS DE ALUMBRADO
Miguel P 1.00 9,500.00 9,500.00
LUMINARIAS VARIAS GLB
Miguel P 60.00 155.00 9,300.00
LUMINARIA TIPO APLIQUE PARA EXTERIORES UND
14.03.02 EQUIPAMIENTO DE INTERRUPTORES
Miguel P 880.00 19.00 16,720.00
INTERRUPTOR UNIPOLAR 1 GOLPE UND
ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL

01 MUROS Y TABIQUES - King Block - 1,688,089.02


INTERRUPTOR UNIPOLAR 2 GOLPE UND Miguel P 480.00 22.00 10,560.00
Miguel P 241.00 25.00 6,025.00
INTERRUPTOR UNIPOLAR 3 GOLPE UND
INTERRUPTOR 1 GOLPE ( CONMUTACION) UND Miguel P 397.00 24.50 9,726.50
INTERRUPTOR DE COMMUTACION DOBLE PTO Miguel P 28.00 31.50 882.00
INTERRUPTOR DOBLE(SIMPLE+CONMUTACION) PTO Miguel P 180.00 36.50 6,570.00
14.03.03 EQUIPAMIENTO DE TOMACORRIENTES
TOMACORRIENTE DOBLE C/PUESTA A TIERRA UND Miguel P 1,854.00 26.50 49,131.00
Miguel P 653.00 35.50 23,181.50
NUEVO TOMACORRIENTE MONOFASICO DOBLE A PRUEBA DE AGUA UND
-
15 EQUIPAMIENTO COCINA - 188,550.14
15.01 TORRE - Departamentos y Areas Comunes -
15.01.01 SUMINISTRO DE EQUIPOS DE COCINA
HORNO FDV CLASS UND Miguel P 128.00 813.05 104,070.14
ENCIMERA FDV UND Miguel P 128.00 457.12 58,510.85
CAMPANA FDV UND Miguel P 128.00 202.88 25,969.15
-
16 VARIOS - 366,819.82
16.01 SOTANOS -
16.01.01 MOBILIARIO FIJO
TOPELLANTAS UND Miguel P 144.00 45.00 6,480.00
16.01.02 VARIOS INDECI
SELLO CORTAFUEGO DE PASE DE MANGUERAS CGBVP UND Miguel P 4.00 79.00 316.00
Miguel P 859.20 58.13 49,940.95
SELLO CORTAFUEGO EN MUROS RF ML
EXTINTOR POLVO QUIMICO CO2 12LBS UND Miguel P 16.00 150.00 2,400.00
16.01.03 OTROS
SEÑALETICA UND Miguel P 151.00 9.50 1,434.50
16.02 TORRE - Departamentos y Areas Comunes -
16.02.01 MOBILIARIO FIJO
SARDINEL DE CONCRETO EN MONTANTES h=0.10m ML Miguel P 112.70 85.00 9,579.50
16.02.02 VARIOS INDECI
SELLO CORTAFUEGO DE PASE DE MANGUERAS CGBVP UND Miguel P 11.00 79.00 869.00
Miguel P 2,255.40 58.13 131,094.99
SELLO CORTAFUEGO EN MUROS RF ML
EXTINTOR POLVO QUIMICO CO2 12LBS UND Miguel P 55.00 150.00 8,250.00
16.02.03 LIMPIEZA
LIMPIEZA DE DEPARTAMENTOS UND Miguel P 128.00 350.00 44,800.00
LIMPIEZA DE AREAS COMUNES GLB Miguel P 1.00 35,900.00 35,900.00
16.02.04 OTROS
SEÑALETICA UND Miguel P 591.00 9.50 5,614.50
NUMERACION DE DEPARTAMENTOS DE BRONCE UND Miguel P 128.00 55.00 7,040.00
16.03 EXTERIORES Y AREAS SOCIALES -
16.03.01 MOBILIARIO FIJO - CONCRETO
BANCAS DE CONCRETO EN PATIO INTERIOR - JARDINERAS ML Miguel P 31.68 85.00 2,692.80
SARDINEL DE CONCRETO EN JARDINERAS h=0.35m ML Miguel P 83.77 39.00 3,266.84
BANCAS DE CONCRETO, - ZONA DE FUEGO UND Miguel P 1.00 6,000.00 6,000.00
MESA DE CONCRETO - ZONA DE FUEGO UND Miguel P 1.00 750.00 750.00
MESAS DE CONCRETO EN ZONA DE PARRILLAS UND Miguel P 2.00 7,000.00 14,000.00
MUEBLES DE CONCRETO EN ZONA DE PARRILLAS UND Miguel P 2.00 4,500.00 9,000.00
JARDINERAS VERTICALES EN LOBBY UND Miguel P 15.00 550.00 8,250.00
SARDINEL DE 30 cm ML Miguel P 227.41 39.00 8,869.15
16.03.03 REPOSICION DE VEREDAS
CONCRETO PREMEZCLADO F'C=210 KG/CM2 M3 Miguel P 23.25 354.15 8,233.99
Miguel P 31.00 31.95 990.45
ENCOFRADO Y DESENCOFRADO ML
SARDINEL DE CONCRETO (ACERO, ENCOFRADO, CONCRETO ML Miguel P 26.85 39.00 1,047.15
-

COSTO DIRECTO S/. 14,377,168.34


Partida 01.06.05 PISO DE CERAMICA 0.45 X 0.45 cm - CELIMA CEMENTO PLUS GRIS

Rendimiento m2/DIA MO. 9.0000 EQ. 9.0000

Código Descripción Recurso Unidad

SC MO ENCHAPE

Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02250201230001 CER GALA DIAMANTE BLANCO 46 X 46 - DECOR CENTER m2

0263030005 CRUCETAS 2mm und

Partida 01.06.05 ZÓCALO DE PORCELANATO BLANCO 45X45

Rendimiento m2/DIA MO. 9.0000 EQ. 9.0000

Código Descripción Recurso Unidad

SC MO ENCHAPE

Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02250201230001 ZÓCALO DE PORCELANATO BLANCO 45X45 m2

0263030005 CRUCETAS 2mm und

Partida 01.06.05 GRES PORCELÁNICO DALTILE PURE ORIGAMI MATE RECTIFICADO, ALTO RELIEVE 45x9

Rendimiento m2/DIA MO. 9.0000 EQ. 9.0000

Código Descripción Recurso Unidad

SC MO ENCHAPE

Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02250201230001 GRES PORCELÁNICO DALTILE PURE ORIGAMI MATE RECTIFICADO, ALTO RELIEVE m2
45x90
0263030005 CRUCETAS 2mm und

Partida 01.06.05 CERÁMICO EQUIPE METRO WHITE BRILLANTE, NO RECTIFICADO, BISCELADO 7.5x15

Rendimiento m2/DIA MO. 9.0000 EQ. 9.0000

Código Descripción Recurso Unidad

SC MO ENCHAPE

Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02250201230001 CERÁMICO EQUIPE METRO WHITE BRILLANTE, NO RECTIFICADO, BISCELADO m2
7.5x15
CERÁMICO EQUIPE METRO WHITE BRILLANTE, NO RECTIFICADO, BISCELADO
7.5x15
0263030005 CRUCETAS 2mm und

Partida 01.06.05 CERÁMICO ITAGRES KASSOS BIANCO MATE, RECTIFICADO 30.5X60.5

Rendimiento m2/DIA MO. 9.0000 EQ. 9.0000

Código Descripción Recurso Unidad


Mano de Obra

SC MO ENCHAPE

Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02250201230001 CERÁMICO ITAGRES KASSOS BIANCO MATE, RECTIFICADO 30.5X60.5 m2

0263030005 CRUCETAS 2mm und

Partida 01.06.05 BAÑO: CERÁMICO KLIPEN NEVADO BLANCO, MATE COLOR BLANCO

Rendimiento m2/DIA MO. 9.0000 EQ. 9.0000

Código Descripción Recurso Unidad


Mano de Obra

SC MO ENCHAPE

Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02250201230001 BAÑO: CERÁMICO KLIPEN NEVADO BLANCO, MATE COLOR BLANCO m2

0263030005 CRUCETAS 2mm und

Partida 01.06.05 PEPELMA x DEFINIR

Rendimiento m2/DIA MO. 9.0000 EQ. 9.0000

Código Descripción Recurso Unidad


Mano de Obra

SC MO ENCHAPE

Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02250201230001 PEPELMA x DEFINIR m2

0263030005 CRUCETAS 2mm und

Partida 01.06.05 PORCELANATO ALAPLANA VILEMA ROBLE 23X120 (FACHADAS)

Rendimiento m2/DIA MO. 9.0000 EQ. 9.0000


Código Descripción Recurso Unidad
Mano de Obra

SC MO ENCHAPE

Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02250201230001 PORCELANATO ALAPLANA VILEMA ROBLE 23X120 (FACHADAS) m2

0263030005 CRUCETAS 2mm und

Partida 01.06.06 PISO PORCELANATO GRAIMAN OAKLAND GREY

Rendimiento m2/DIA MO. 9.0000 EQ. 9.0000

Código Descripción Recurso Unidad


Mano de Obra

SC MO ENCHAPE

Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02280500370038 PISO PORCELANATO GRAIMAN OAKLAND GREY m2

0263030005 CRUCETAS 2mm und

Partida 01.05.05 CONTRAZÓCALO DE MADERA TEÑIDO SIMILAR AL PROCELANATO GRAIMAN OAKLAND

Rendimiento ml/DIA MO. 18.0000 EQ. 18.0000

Código Descripción Recurso Unidad


Mano de Obra

SC MO ENCHAPE

Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02280500400051 CONTRAZÓCALO DE MADERA TEÑIDO SIMILAR AL PROCELANATO GRAIMAN m2
OAKLAND GREY
0263030005 CRUCETAS 2mm und

Partida 01.06.06 PISO PORCELANATO GRAIMAN CIPRES WHITE

Rendimiento m2/DIA MO. 9.0000 EQ. 9.0000

Código Descripción Recurso Unidad


Mano de Obra

SC MO ENCHAPE

Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02280500370038 PISO PORCELANATO GRAIMAN CIPRES WHITE m2
0263030005 CRUCETAS 2mm und

Partida 01.05.05 CONTRAZÓCALO DE MADERA TEÑIDO SIMILAR AL PORCELANATO GRAIMAN CIPRES W

Rendimiento ml/DIA MO. 9.5490 EQ. 9.5490

Código Descripción Recurso Unidad


Mano de Obra

SC MO ENCHAPE

Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02280500400051 CONTRAZÓCALO DE MADERA TEÑIDO SIMILAR AL PORCELANATO GRAIMAN m2
CIPRES WHITE
0263030005 CRUCETAS 2mm und

Partida 01.06.06 PISO PORCELANATO ESMALTADO FILO BIANCO MATE

Rendimiento m2/DIA MO. 9.0000 EQ. 9.0000

Código Descripción Recurso Unidad


Mano de Obra

SC MO ENCHAPE

Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02280500370038 PISO PORCELANATO ESMALTADO FILO BIANCO MATE m2

0263030005 CRUCETAS 2mm und

Partida 01.06.06 PISO PORCELANATO ESMALTADO TRAVERTINO NAVONA

Rendimiento m2/DIA MO. 9.0000 EQ. 9.0000

Código Descripción Recurso Unidad


Mano de Obra

SC MO ENCHAPE

Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02280500370038 PISO PORCELANATO ESMALTADO TRAVERTINO NAVONA m2

0263030005 CRUCETAS 2mm und

Partida 01.05.05 CONTRAZÓCALO DE MADERA TEÑIDO SIMILAR AL PORCELANATO ESMALTADO TRAVE

Rendimiento ml/DIA MO. 18.0000 EQ. 18.0000

Código Descripción Recurso Unidad


Mano de Obra

SC MO ENCHAPE
Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02280500400051 CONTRAZÓCALO DE MADERA TEÑIDO SIMILAR AL PORCELANATO ESMALTADO m2
TRAVERTINO NAVONA
0263030005 CRUCETAS 2mm und

SUM
PUERTAS
PUERTA CONTRAPLACADA: P- 08 UND Miguel P 1.00 1,298.95
PUERTA CONTRAPLACADA: P- 09 UND Miguel P 3.00 537.14
PUERTA CONTRAPLACADA: P- 10 UND Miguel P 56.00 602.14
PUERTA CONTRAPLACADA: P- 11 UND Miguel P 4.00
PUERTA CONTRAPLACADA: P- 12 UND Miguel P 4.00
PUERTA CONTRAPLACADA: P- 13 UND Miguel P 5.00
PUERTA CONTRAPLACADA: P- 14 UND Miguel P 4.00
PUERTA CONTRAPLACADA: P- 14C Miguel P 1.00
PUERTA CONTRAPLACADA: P- 15 UND Miguel P 4.00
PUERTA CONTRAPLACADA: P- 16 UND Miguel P 2.00
PUERTA CONTRAPLACADA: P- 17 UND Miguel P 4.00
PUERTA CONTRAPLACADA: P- 18 UND Miguel P 2.00
PUERTA CONTRAPLACADA: P- 19 UND Miguel P 3.00
PUERTA CONTRAPLACADA: P- 20 UND Miguel P 2.00
PUERTA CONTRAPLACADA: P- 21 UND Miguel P 1.00
PUERTA CONTRAPLACADA: P- 22 UND Miguel P 1.00
PUERTA CONTRAPLACADA: P- 23 UND Miguel P 1.00
PUERTA CONTRAPLACADA: P- 25 UND Miguel P 1.00
PUERTA CONTRAPLACADA: P- 26 UND Miguel P 5.00
PUERTA CONTRAPLACADA: P- 27 UND Miguel P 1.00
PUERTA CONTRAPLACADA: P- 28 UND Miguel P 1.00
PUERTA CONTRAPLACADA: P- 29 UND Miguel P 1.00
PUERTA CONTRAPLACADA: P- 31 UND Miguel P 3.00
CERRAJERIA
BISAGRA PARA PUERTA DE MADERA - Interior UND Miguel P 492.00
CERRADURA P/ PUERTA DE MADERA - Interior UND Miguel P 110.00
MELAMINA - MUEBLES DE COCINA
DIVISION EN CAMERINO DE DAMAS GLB Miguel P 1.00
DIVISION EN CAMERINO DE VARONES GLB Miguel P 1.00
TORRE - Departamentos y Areas Comunes
PUERTAS
PUERTA CONTRAPLACADA: P- 01 UND Miguel P 128.00 874.48
PUERTA CONTRAPLACADA: P- 05 UND Miguel P 315.00 475.85
PUERTA CONTRAPLACADA: P- 06 UND Miguel P 363.00 540.85
PUERTA CONTRAPLACADA: P- 07 UND Miguel P 91.00 569.63
PUERTA DE MADERA APERSIANADA: P- 22A UND Miguel P 5.00
PUERTA DE MADERA APERSIANADA: P- 22B UND Miguel P 2.00
PUERTA DE MADERA APERSIANADA: P- 22C UND Miguel P 1.00
PUERTA DE MADERA APERSIANADA: P- 22D UND Miguel P 1.00

PUERTA CONTRAPLACADA: P- 02 UND Miguel P 2.00 537.14


PUERTA CONTRAPLACADA: P- 03 UND Miguel P 2.00 537.14
CANT PCF
SOTANO Miguel P
PUERTAS CORTAFUEGO Miguel P
DE CORTAFUEGO - PC-01 - (F - 135) 1.00 X 2.10m ( Escalera Evac.+ Bombas) UND Miguel P 27.00 1,115.10
EDIFICIO Miguel P
PUERTAS CORTAFUEGO Miguel P
PUERTA DE CORTAFUEGO - PC-01 - (F - 135) 1.00 X 2.10m ( Escalera Evac.) UND Miguel P 14.00 1,115.10
PUERTA DE CORTAFUEGO - PC-02 - (F - 120) 1.00 X 2.10m ( Escalera Evac.) UND Miguel P 14.00 1,115.10
PUERTA DE CORTAFUEGO - PC-03 - (F - 90) - Ducto Electrico UND Miguel P 40.00 4,413.71
PUERTA DE CORTAFUEGO - PC-04 - (F - 90) - Ducto Sanitario UND Miguel P 60.00 6,657.71
PUERTA DE CORTAFUEGO - PC-05 - (F - 90) - Ducto Sanitario UND Miguel P 20.00 2,206.84
PUERTA DE CORTAFUEGO - PC-06 - (F - 90) - Ducto Electrico UND Miguel P 29.00 2,244.00
PUERTA DE CORTAFUEGO - PC-07 - (F - 90) - Ducto Sanitario UND Miguel P 40.00 4,413.71
Costo unitario directo por : m2 S/ 65.98 0.00 65.98

Cuadrilla Cantidad Precio S/ Parcial S/

32.00

0.4000 8.28 3.31 FRAGUA WEBER


0.2500 20.37 5.09 PEGAMENTO WEBER
1.1000 22.90 25.19

10.0000 0.04 0.39 CRUCETA 2MM BOLSA 500

Costo unitario directo por : m2 S/ 88.00 0.00 88.00

Cuadrilla Cantidad Precio S/ Parcial S/

32.00

0.4000 8.28 3.31 FRAGUA WEBER


0.2500 20.37 5.09 PEGAMENTO WEBER
1.1000 42.91 47.20

10.0000 0.04 0.39 CRUCETA 2MM BOLSA 500

ALTO RELIEVE 45x90

Costo unitario directo por : m2 S/ 88.00 #REF! #REF!

Cuadrilla Cantidad Precio S/ Parcial S/

32.00

0.4000 8.28 3.31 FRAGUA WEBER


0.2500 20.37 5.09 PEGAMENTO WEBER
1.1000 42.91 47.20

10.0000 0.04 0.39 CRUCETA 2MM BOLSA 500

SCELADO 7.5x15

Costo unitario directo por : m2 S/ 185.48 0.00 185.48

Cuadrilla Cantidad Precio S/ Parcial S/

32.00

0.4000 8.28 3.31


0.2500 20.37 5.09
1.1000 131.53 144.68
10.0000 0.04 0.39

Costo unitario directo por : m2 S/ 139.86 0.00 139.86

Cuadrilla Cantidad Precio S/ Parcial S/

32.00

0.4000 8.28 3.31 FRAGUA WEBER


0.0600 20.37 1.22 PEGAMENTO WEBER
1.1000 93.58 102.94

10.0000 0.04 0.39 CRUCETA 2MM BOLSA 500

Costo unitario directo por : m2 S/ 72.29 0.00 72.29

Cuadrilla Cantidad Precio S/ Parcial S/

32.00

0.4000 8.28 3.31 FRAGUA WEBER


0.2500 20.37 5.09 PEGAMENTO WEBER
1.1000 28.64 31.50

10.0000 0.04 0.39 CRUCETA 2MM BOLSA 500

Costo unitario directo por : m2 S/ 158.91 0.39 158.53

Cuadrilla Cantidad Precio S/ Parcial S/

32.00

0.4000 8.28 3.31 FRAGUA WEBER


0.2500 20.37 5.09 PEGAMENTO WEBER
1.1000 107.38 118.12

10.0000 0.04 0.39 CRUCETA 2MM BOLSA 500

Costo unitario directo por : m2 S/ 159.06 #REF! #REF!


Cuadrilla Cantidad Precio S/ Parcial S/

32.00

0.4000 8.28 3.31 FRAGUA WEBER


0.2500 20.37 5.09 PEGAMENTO WEBER
1.1000 107.51 118.26

10.0000 0.04 0.39 CRUCETA 2MM BOLSA 500

Costo unitario directo por : m2 S/ 121.44

Cuadrilla Cantidad Precio S/ Parcial S/

32.00

0.4000 8.28 3.31 FRAGUA WEBER


0.2500 20.37 5.09 PEGAMENTO WEBER
1.1000 73.31 80.64

10.0000 0.04 0.39 CRUCETA 2MM BOLSA 500 UN

GRAIMAN OAKLAND GREY

Costo unitario directo por : ml S/ 25.13

Cuadrilla Cantidad Precio S/ Parcial S/

16.00

0.0800 8.28 0.66


0.0500 20.37 1.02
0.1000 73.31 7.33

3.0000 0.04 0.12

Costo unitario directo por : m2 S/ 121.44 0.00 121.44

Cuadrilla Cantidad Precio S/ Parcial S/

32.00

0.4000 8.28 3.31


0.2500 20.37 5.09
1.1000 73.31 80.64
10.0000 0.04 0.39

GRAIMAN CIPRES WHITE

Costo unitario directo por : ml S/ 25.13 35.55 -10.42

Cuadrilla Cantidad Precio S/ Parcial S/

16.00

0.0800 8.28 0.66


0.0500 20.37 1.02
0.1000 73.31 7.33

3.0000 0.04 0.12

Costo unitario directo por : m2 S/ 120.41 0.00 120.41

Cuadrilla Cantidad Precio S/ Parcial S/

32.00

0.1000 8.28 0.83


0.0600 20.37 1.22
0.0630 153.09 9.64

3.0000 0.04 0.12

Costo unitario directo por : m2 S/ 209.51 0.00 209.51

Cuadrilla Cantidad Precio S/ Parcial S/

32.00

0.4000 8.28 2.80


0.2500 20.37 5.91
1.1000 153.09 168.40

10.0000 0.04 0.40

SMALTADO TRAVERTINO NAVONA

Costo unitario directo por : ml S/ 33.55

Cuadrilla Cantidad Precio S/ Parcial S/


16.00

0.0800 8.28 0.70


0.0500 20.37 1.42
0.1000 153.09 15.31

3.0000 0.04 0.12

INST ACABADO TOTAL

180 95 1,573.95
180 95 812.14
180 95 877.14
2,349.46 2,135.87
2,546.85 2,315.32
2,359.09 2,144.63
1,295.09 1,177.36
1,295.09 1,177.36
871.42 792.20
1,988.37 1,807.61
1,405.82 1,278.02
2,306.13 2,096.48
1,964.30 1,785.73
1,444.34 1,313.04
1,829.50 1,663.18
2,012.45 1,829.50
1,829.50 1,663.18
2,132.81 1,938.92
986.96 897.24
1,131.39 1,028.54
486.27 442.06
1,006.23 914.75
1,006.23 914.75
-

-
10,771.83 9,792.57
11,844.91 10,768.10

180 95 1,149.48
180 95 750.85
180 95 815.85
180 95 844.63
1,573.95 1,573.95 similar dimensiones
1,652.65
1,652.65
1,735.28

180 95 812.14
180 95 812.14
INSTALA BARR ANTICIERRA PUERTA

225 1,340.10 SI SI 1
-
-
225 1,340.10 SI SI 1
225 1,340.10 SI SI 1
450 4,863.71 NO NO 2
675 7,332.71 NO NO 3
225 2,431.84 NO NO 1
225 2,469.00 NO NO 1
450 4,863.71 NO NO 2
BER

OLSA 500 UND

BER

OLSA 500 UND

BER

OLSA 500 UND


BER

OLSA 500 UND

BER

OLSA 500 UND

BER

OLSA 500 UND


BER

OLSA 500 UND

SA 500 UND
C & V INVERSIONES INMOBILIARIAS
Cl. Narciso de la Colina N° 421, Of. 1401, Miraflores
www.cyvperu.com
HOJA DE PRESUPUESTO DETALLADO
OBRA: CONSTRUCCION DEL CONDOMINIO PORTOFINO
ESPECIALIDAD: INSTALACIONES ELECTRICAS
PROPIET. : PROPIA
LUGAR: Av. Santa Cruz 1550, Miraflores
FECHA: 20 de Enero del 2022
MONEDA: Nuevos Soles

ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL


01 ALUMBRADO 257,791.80
01.01 SALIDA PARA DICROICOS PTO 3,203.00 52.47 168,055.00
01.02 SALIDA PARA CENTRO DE LUZ PTO 381.00 50.46 19,225.56
01.03 SALIDA PARA BRAQUETE PTO 700.00 36.58 25,603.76
01.04 SALIDA PARA CINTA LED PTO 172.00 36.58 6,291.21
01.05 SALIDA PARA ESTACA PTO 55.00 73.27 4,029.74
01.06 SALIDA PARA FLUORESCENTE PTO 196.00 68.07 13,341.33
01.07 SALIDA PARA POSTE PTO 55.00 56.42 3,103.10
01.08 SALIDA PARA LUMINARIA SUMERGIBLE PTO 5.00 36.58 182.88
01.09 SALIDA PARA SENSOR DE MOVIMIENTO PTO 226.00 36.58 8,266.36
01.10 SALIDA PARA LUZ DE EMERGENCIA PTO 265.00 36.58 9,692.85
02 INTERRUPTORES 0.00 219,761.68
02.01 SALIDA PARA INTERRUPTORE SIMPLE PTO 978.00 78.47 76,741.70
02.02 SALIDA PARA INTERRUPTORE DOBLE PTO 533.00 78.47 41,823.44
02.03 SALIDA PARA INTERRUPTORE TRIPLE PTO 268.00 78.47 21,029.42
02.04 SALIDA PARA INTERRUPTOR DE COMMUTACION SIMPLE PTO 441.00 78.47 34,604.39
02.05 SALIDA PARA INTERRUPTOR DE COMMUTACION DOBLE PTO 28.00 78.47 2,197.10
02.06 SALIDA PARA INTERRUPTOR DOBLE(SIMPLE+CONMUTACION) PTO 180.00 105.51 18,991.44
02.07 INTERRUPTOR BIPOLAR CON FUSIBLE DE 2 X20A PTO 259.00 62.98 16,312.44
02.08 INTERRUPTOR BIPOLAR CON FUSIBLE DE 3 X30A PTO 128.00 62.98 8,061.75
03 DISTRIBUCION ELECTRICA 0.00 0.00 212,861.11
03.01 TOMACORRIENTE MONOFASICO DOBLE PTO 1,854.00 67.03 124,269.91
03.02 TOMACORRIENTE MONOFASICO DOBLE A PRUEBA DE AGUA PTO 653.00 135.67 88,591.20
04 DISTRIBUCION ELECTRICA 0.00 0.00 109,428.14
04.01 SALIDA PARA EXTRACTOR AXIAL EN BAÑOS PTO 370.00 61.87 22,891.75
04.02 SALIDA PARA EXTRACTOR AXIAL EN VESTIBULO PTO 11.00 125.58 1,381.38
04.03 SALIDA PARA INYECTOR AXIAL EN VESTIBULO PTO 11.00 125.58 1,381.38
04.04 SALIDA PARA ASCENSOR PTO 2.00 255.06 510.12
04.05 SALIDA PARA PULSADOR DE TIMBRE PTO 128.00 88.87 11,375.10
04.06 SALIDA PARA CAMPANILLA DE TIMBRE PTO 128.00 83.50 10,688.20
04.07 SALIDA PARA COCINA ELÉCTRICA PTO 128.00 125.27 16,034.30
04.08 SALIDA PARA CALENTADOR ELÉTRICO PTO 128.00 125.27 16,034.30
04.09 SALIDA PARA LAVADORA PTO 130.00 61.82 8,036.29
04.10 SALIDA PARA PUERTA SECCIONABLE PTO 2.00 120.24 240.49
04.11 SALIDA PARA CACI PTO 1.00 135.76 135.76
04.13 SALIDA PARA BACI PTO 1.00 114.87 114.87
04.14 SALIDA PARA BOMBA JOCKEY PTO 1.00 130.64 130.64
04.15 SALIDA PARA BOMBA AGUA PTO 10.00 203.48 2,034.76
04.16 SALIDA PARA BOMBA SUMIDERO PTO 5.00 111.84 559.21
04.17 SALIDA PARA BOMBA PTAG PTO 8.00 203.27 1,626.14
04.18 SALIDA PARA FILTRO PTAG PTO 1.00 71.28 71.28
04.19 SALIDA PARA VALVULA PTO 1.00 58.19 58.19
04.20 SALIDA PARA EXTRACTOR DE DEPOSITOS PTO 99.00 107.79 10,670.77
04.21 SALIDA PARA CONTROL DE NIVEL PTO 10.00 88.87 888.68
04.22 SALIDA PARA GRUPO ELÉCTROGENO PTO 1.00 135.67 135.67
04.23 SALIDA PARA CHAPA ELÉCTRICA PTO 1.00 58.19 58.19
04.24 SALIDA PARA PORTERO ELÉCTRICO PTO 1.00 120.07 120.07
04.25 SALIDA PARA EXTRACTOR EN SOT1 PTO 2.00 71.19 142.38
04.26 SALIDA PARA EXTRACTOR EN C.B. PTO 1.00 78.47 78.47
04.27 SALIDA PARA INYECTOR EN C.B. PTO 1.00 88.87 88.87
04.28 SALIDA PARA EXTRACTOR CENTRIFUGA 3 HP PTO 9.00 217.92 1,961.29
04.29 SALIDA PARA INYECTOR CENTRIFUGA 3 HP PTO 6.00 217.92 1,307.53
04.30 SALIDA PARA INYECTOR CENTRIFUGA 6 HP PTO 1.00 217.92 217.92
04.31 SALIDA PARA EXTRACTOR EN C.BASURA Y BICICLETA PTO 2.00 151.38 302.76
04.32 SALIDA PARA BOMBA PISCINA PTO 1.00 151.38 151.38
05 CAJA DE F.G. PESADO 0.00 0.00 93,215.83
05.01 CAJA DE PASE OCTAGONAL 100X40 UND 381.00 28.18 10,738.10
05.03 CAJA DE PASE DE 650X350X150 UND 4.00 359.27 1,437.07
05.04 CAJA DE PASE DE 700X600X300 UND 11.00 359.27 3,951.95
05.05 CAJA DE PASE DE 600X500X300 UND 19.00 210.84 4,005.94
05.16 CAJA DE PASE DE 600X600X150 UND 2.00 210.84 421.68
05.06 CAJA DE PASE DE 500X500X300 UND 9.00 182.47 1,642.21
05.09 CAJA DE PASE DE 400X400X100 UND 3.00 122.98 368.94
05.10 CAJA DE PASE DE 350X350X150 UND 3.00 89.25 267.76
05.11 CAJA DE PASE DE 300X300X100 UND 43.00 58.38 2,510.13
05.12 CAJA DE PASE DE 250X250X100 UND 97.00 51.54 4,999.61
05.13 CAJA DE PASE DE 200X200X100 UND 89.00 33.44 2,975.80
05.14 CAJA DE PASE DE 150X150X75 UND 678.00 32.01 21,703.59
05.15 CAJA DE PASE DE 100X100X50 UND 22.00 26.47 582.30
05.17 CAJA DE PASE DE 650X350X150 CON PUERTA UND 88.00 416.58 36,659.25
05.18 CAJA DE PASE DE 800X500X150 CON PUERTA UND 2.00 475.75 951.50
06 TABLEROS ELECTRICOS 0.00 0.00 265,298.25
06.01 TSG UND 1.00 16,070.08 16,070.08
06.03 T-PATG UND 1.00 3,998.80 3,998.80
06.12 ST1A UND 1.00 10,270.47 10,270.47
06.13 ST1B UND 1.00 4,772.56 4,772.56
06.14 ST2A UND 1.00 4,772.56 4,772.56
C & V INVERSIONES INMOBILIARIAS
Cl. Narciso de la Colina N° 421, Of. 1401, Miraflores
www.cyvperu.com
HOJA DE PRESUPUESTO DETALLADO
OBRA: CONSTRUCCION DEL CONDOMINIO PORTOFINO
ESPECIALIDAD: INSTALACIONES ELECTRICAS
PROPIET. : PROPIA
LUGAR: Av. Santa Cruz 1550, Miraflores
FECHA: 20 de Enero del 2022
MONEDA: Nuevos Soles

ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL


06.15 ST2B UND 1.00 5,905.12 5,905.12
06.16 ST3A UND 1.00 3,998.80 3,998.80
06.17 ST3B UND 1.00 3,998.80 3,998.80
06.18 ST4A UND 1.00 3,998.80 3,998.80
06.19 ST4B UND 1.00 4,772.56 4,772.56
06.20 ST5 UND 1.00 3,998.80 3,998.80
06.21 ST6 UND 1.00 3,998.80 3,998.80
06.22 ST6A UND 1.00 11,310.47 11,310.47
06.23 ST6B UND 1.00 11,310.47 11,310.47
06.24 ST7 UND 1.00 4,772.56 4,772.56
06.25 TTA-1 UND 1.00 6,078.80 6,078.80
06.26 TTA-2 UND 1.00 6,078.80 6,078.80
06.27 TGEL UND 1.00 4,772.56 4,772.56
06.30 STAZ1 UND 1.00 6,078.80 6,078.80
06.31 STAZ2 UND 1.00 6,078.80 6,078.80
06.32 STASC1 UND 1.00 3,998.80 3,998.80
06.33 STASC2 UND 1.00 3,998.80 3,998.80
06.34 TD- TABLERO DTOS UND 128.00 1,017.68 130,263.24
07 COMUNICACIONES Y SISTEMA 0.00 0.00 122,694.65
07.01 SALIDA PARA TELEFONO EXTERNO PTO 440.00 74.24 32,663.49
07.02 SALIDA PARA TELEFONO INTERNO PTO 267.00 74.24 19,820.80
07.03 SALIDA PARA CABLE TV PTO 344.00 65.99 22,699.87
07.05 SALIDA PARA DETECTOR DE FLUJO PTO 4.00 55.59 222.35
07.06 SALIDA PARA CO PTO 43.00 55.59 2,390.28
07.07 SALIDA PARA PARA PORTERO INTERCOMUNICADOR PTO 1.00 62.87 62.87
07.08 SALIDA PARA DETECTOR DE HUMO PTO 368.00 56.02 20,617.13
07.09 SALIDA PARA DETECTOR DE TEMPERATURA PTO 202.00 56.02 11,317.01
07.10 SALIDA PARA PULSADOR MANUAL PTO 41.00 56.02 2,297.02
07.11 SALIDA PARA SIRENA CON PROTECTOR PTO 184.00 56.05 10,312.39
07.12 SALIDA PARA CACI PTO 1.00 67.34 67.34
07.13 SALIDA PARA CONTROL DE ROCIADORES PTO 4.00 56.02 224.10
08 CANALIZACION (TUBO) 0.00 0.00 248,055.55
08.01 TUBO DE 20mm PVC -P M 11,751.00 5.67 66,604.67
08.02 TUBO DE 25mm PVC-P M 12,334.00 7.86 96,974.84
08.03 TUBO DE 35mm PVC-P M 1,883.00 11.96 22,520.68
08.04 TUBO DE 40mm PVC-P M 822.00 14.33 11,780.25
08.05 TUBO DE 55mm PVC-P M 309.00 17.44 5,389.21
08.06 TUBO DE 65mm PVC-P M 64.00 21.27 1,361.15
08.07 TUBO DE 80mm PVC-P M 109.00 22.88 2,493.92
08.08 TUBO DE 105mm PVC -P M 549.00 42.07 23,095.33
08.09 TUBO DE 20mm IMC M 67.00 36.66 2,456.22
08.10 TUBO DE 25mm IMC M 49.00 42.07 2,061.33
08.11 TUBO DE 40mm FoGo M 180.00 52.50 9,449.86
08.12 TUBO DE 80mm FoGo M 29.00 73.36 2,127.49
08.13 TUBO DE 105mm IMC M 17.00 102.39 1,740.60
09 ALIMENTADORES 0.00 0.00 535,086.66
09.01 DE BM a TABLERO TSG: 3{(3-1x185mm² N2XOH +1x35mm² N2XOH /T } M 54.00 400.40 21,621.60
09.02 DE TABLERO TSG a TABLERO ST1A: 3-1x25mm² N2XOH+1x10mm² N2XOH(T) M 16.00 68.38 1,094.08
09.03 DE TABLERO TSG a TABLERO ST1B: 3-1x25mm² N2XOH+1x10mm² N2XOH(T) M 42.00 68.38 2,871.96
09.04 DE TABLERO TSG a TABLERO ST2A: 3-1x10mm² N2XOH+1x10mm² N2XOH(T) M 14.00 36.98 517.75
09.05 DE TABLERO TSG a TABLERO ST2B: 3-1x35mm² N2XOH+1x10mm² N2XOH(T) M 46.00 99.27 4,566.33
09.06 DE TABLERO TSG a TABLERO ST3A: 3-1x25mm² N2XOH+1x10mm² N2XOH(T) M 17.00 68.38 1,162.46
09.07 DE TABLERO TSG a TABLERO ST3B: 3-1x35mm² N2XOH+1x10mm² N2XOH(T) M 48.00 99.27 4,764.86
09.08 DE TABLERO TSG a TABLERO ST4A: 3-1x6mm² NH80+1x6mm² NH80(T) M 22.00 46.95 1,032.80
09.09 DE TABLERO TSG a TABLERO ST4B: 3-1x35mm² N2XOH+1x10mm² N2XOH(T) M 50.00 99.27 4,963.40
09.10 DE TABLERO TSG a TABLERO TTA2: 3-1x185mm² N2XOH+1x185mm² N2XOH(T) M 28.00 400.40 11,211.20
09.11 DE TABLERO TSG a TABLERO ST6: 3-1x25mm² N2XOH+1x10mm² N2XOH(T) M 28.00 68.38 1,914.64
09.12 DE TABLERO TSG a TABLERO ST7: 3-1x16mm² NH80+1x10mm² NH80(T) M 59.00 57.67 3,402.41
09.13 DE TABLERO TSG a TABLERO STASC 1: 3-1x16mm² NH80 +1x10mm² NH80 /T M 54.00 57.67 3,114.07
09.14 DE TABLERO TSG a TABLERO STASC 2: 3-1x16mm² NH80 +1x10mm² NH80 /T M 55.00 57.67 3,171.74
09.15 DE TABLERO TSG a TABLERO TTA1: 3-1x10mm² NH80 +1x10mm² NH80 /T M 17.00 47.38 805.50
09.16 DE TABLERO TSG a TABLERO STFV: 3-1x10mm² NH80+1x10mm² NH80(T) M 9.00 47.38 426.44
09.17 DE TABLERO ST1A a TABLERO STEX1A: 3-1x4mm² NH80 +1x4mm² NH80 /T M 11.00 26.47 291.15
09.18 DE TABLERO ST1A a TABLERO STIN1A: 3-1x4mm² NH80 +1x4mm² NH80 /T M 47.00 26.47 1,244.00
09.19 DE TABLERO ST1B a TABLERO STEX1B: 3-1x4mm² NH80 +1x4mm² NH80 /T M 25.00 26.47 661.70
09.20 DE TABLERO ST1B a TABLERO STIN1B: 3-1x4mm² NH80 +1x4mm² NH80 /T M 31.00 26.47 820.51
09.21 DE TABLERO ST2A a TABLERO STEX2A: 3-1x4mm² NH80 +1x4mm² NH80 /T M 12.00 26.47 317.62
09.22 DE TABLERO ST2A a TABLERO STIN2A: 3-1x4mm² NH80 +1x4mm² NH80 /T M 46.00 26.47 1,217.53
09.23 DE TABLERO ST2B a TABLERO STEX2B: 3-1x4mm² NH80 +1x4mm² NH80 /T M 21.00 26.47 555.83
09.24 DE TABLERO ST2B a TABLERO STIN2B: 3-1x4mm² NH80 +1x4mm² NH80 /T M 31.00 26.47 820.51
09.25 DE TABLERO ST3A a TABLERO STEX3A: 3-1x4mm² NH80 +1x4mm² NH80 /T M 12.00 26.47 317.62
09.26 DE TABLERO ST3A a TABLERO STIN3A: 3-1x4mm² NH80 +1x4mm² NH80 /T M 46.00 26.47 1,217.53
09.27 DE TABLERO ST3B a TABLERO STEX3B: 3-1x4mm² NH80 +1x4mm² NH80 /T M 21.00 26.47 555.83
09.28 DE TABLERO ST3B a TABLERO STIN3B: 3-1x4mm² NH80 +1x4mm² NH80 /T M 31.00 26.47 820.51
09.29 DE TABLERO ST4A a TABLERO STEX4A: 3-1x4mm² NH80 +1x4mm² NH80 /T M 12.00 26.47 317.62
09.30 DE TABLERO ST4A a TABLERO STIN4A: 3-1x4mm² NH80 +1x4mm² NH80 /T M 46.00 26.47 1,217.53
09.31 DE TABLERO ST4B a TABLERO STEX4B: 3-1x4mm² NH80 +1x4mm² NH80 /T M 21.00 26.47 555.83
09.32 DE TABLERO ST4B a TABLERO STIN4B: 3-1x4mm² NH80 +1x4mm² NH80 /T M 31.00 26.47 820.51
09.33 DE TABLERO ST6 a TABLERO ST6A: 3-1x6mm² NH80 +1x6mm² NH80 /T M 25.00 36.55 913.64
09.34 DE TABLERO ST6 a TABLERO ST6B: 3-1x6mm² NH80 +1x6mm² NH80 /T M 15.00 36.55 548.18
09.35 DE TABLERO ST7 a TABLERO STBP: 2-1x4mm² NH80+1x4mm² NH80(T) M 9.00 26.47 238.21
09.36 DE TABLERO ST7 a TABLERO STAZ1: 2-1x4mm² NH80+1x4mm² NH80(T) M 13.00 26.47 344.08
09.37 DE TABLERO ST7 a TABLERO STAZ2: 2-1x4mm² NH80+1x4mm² NH80(T) M 24.00 26.47 635.23
09.38 DE G.E. 125 KVA a TABLERO TGEL: 3-1x185mm² N2XOH +1x35mm² N2XOH/T M 12.00 436.95 5,243.35
09.39 DE TABLERO TGEL a TABLERO TTA1: 3-1x10mm² N2XOH +1x10mm² N2XOH(T) M 50.00 36.98 1,849.12
09.40 DE TABLERO TTA1 a TABLERO STIEV: 3-1x6mm² NH80 +1x6mm² NH80/T M 9.00 36.55 328.91
09.41 DE TABLERO STIEV a TABLERO TVF1: 3-1x4mm² NH80 +1x4mm² NH80/T M 68.00 26.47 1,799.82
09.42 DE TABLERO TGEL a TABLERO TTA2: 3-1x185mm² N2XOH+1x35mm² N2XOH(T) M 62.00 400.40 24,824.80
09.43 DE TABLERO TTA2 a TABLERO ST5: 3-1x185mm² N2XOH+1x35mm²N2XOH/T M 17.00 400.40 6,806.80
09.44 DE TABLERO ST5 a TABLERO STBA1: 3-1x25mm² NH80 +1x10mm² NH80 /T M 12.00 68.38 820.56
09.45 DE TABLERO ST5 a TABLERO STBA2: 3-1x25mm² NH80 +1x10mm² NH80 /T M 12.00 68.38 820.56
09.46 DE TABLERO ST5 a TABLERO STBA3: 3-1x16mm² NH80 +1x10mm² NH80 /T M 14.00 57.67 807.35
09.47 DE TABLERO ST5 a TABLERO STBA4: 3-1x16mm² NH80 +1x10mm² NH80 /T M 14.00 57.67 807.35
09.48 DE TABLERO ST5 a TABLERO STBD1: 3-1x25mm² NH80 +1x10mm² NH80 /T M 13.00 68.38 888.94
09.49 DE TABLERO ST5 a TABLERO STBD2: 3-1x10mm² NH80 +1x10mm² NH80 /T M 24.00 36.98 887.58
09.50 DE TABLERO ST5 a TABLERO PATG: 3-1x10mm² NH80 +1x10mm² NH80 /T M 30.00 36.98 1,109.47
C & V INVERSIONES INMOBILIARIAS
Cl. Narciso de la Colina N° 421, Of. 1401, Miraflores
www.cyvperu.com
HOJA DE PRESUPUESTO DETALLADO
OBRA: CONSTRUCCION DEL CONDOMINIO PORTOFINO
ESPECIALIDAD: INSTALACIONES ELECTRICAS
PROPIET. : PROPIA
LUGAR: Av. Santa Cruz 1550, Miraflores
FECHA: 20 de Enero del 2022
MONEDA: Nuevos Soles

ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL


09.51 DE TABLERO ST5 a TABLERO STCB: 3-1x4mm² NH80 +1x4mm² NH80 /T M 9.00 26.47 238.21
09.52 DE TABLERO ST5 a TABLERO ST-BJ: 3-1x4mm² NH80 +1x4mm² NH80 /T M 30.00 26.47 794.04
09.53 DE BM a TABLERO STBCI: 3-1x120mm² N2XOH +1x35mm² N2XOH/T M 29.00 177.38 5,144.09
09.54 DE BM a TABLERO DPTOS: 2-1x10mm² NH80 +1x10mm² NH80/T M 10,903.00 26.47 288,580.60
09.55 Montante Alumbrado y tomacorriente: 2-1x2.5mm² NH80+1x2.5mm² NH80(T) M 6,822.00 16.07 109,615.90
09.56 Montante Fuerza: 2-1x4mm² NH80 +1x4mm² NH80/T M 100.00 26.47 2,646.80
10 CANALETAS F.G. 0.00 0.00 109,789.24
10.01 BANDEJA PORTACABLES DE 250x100mm - COMUNICACIONES M 91.20 260.47 23,754.68
10.02 BANDEJA PORTACABLES DE 350x100mm - COMUNICACIONES M 36.00 333.27 11,997.65
10.03 BANDEJA PORTACABLES DE 500x100mm - ELÉCTRICAS M 110.39 400.87 44,251.82
10.06 BANDEJA PORTACABLES DE 400x100mm - ELÉCTRICAS M 26.40 333.27 8,798.28
10.04 BANDEJA PORTACABLES DE 350x100mm - ELÉCTRICAS M 14.40 333.27 4,799.06
10.05 BANDEJA PORTACABLES DE 250x100mm - ELÉCTRICAS M 31.20 333.27 10,397.96
10.07 CURVA HORIZONTAL 90° DE 500x100mm UND 10.00 156.47 1,564.68
10.08 CURVA HORIZONTAL 90° DE 400x100mm UND 4.00 156.47 625.87
10.09 CURVA HORIZONTAL 90° DE 350x100mm UND 4.00 156.47 625.87
10.10 CURVA HORIZONTAL 90° DE 250x100mm UND 13.00 156.47 2,034.08
10.11 CURVA HORIZONTAL 45° DE 500x100mm UND 2.00 156.47 312.94
10.12 TEE HORIZONTAL DE 250x350x350mm UND 2.00 125.27 250.54
10.13 TEE HORIZONTAL DE 500x5000x500mm UND 2.00 125.27 250.54
10.14 CRUZ HORIZONTAL 90° DE 500x100mm UND 1.00 125.27 125.27
11 MEDIDORES 0.00 0.00 18,720.00
11.01 MEDIDORES DE LUZ UND 10.00 1,872.00 18,720.00
12 TRABAJOS PRELIMINARES 0.00 0.00 41,372.61
12.01 TRAZO Y REPLANTEO M2 225.00 6.32 1,422.72
12.02 EXCAVACION DE ZANJA (MANUAL) M3 289.58 59.52 17,235.27
12.03 RELLENO Y COMPACTACION DE ZANJA M3 200.81 67.83 13,620.87
12.04 ACARREO DE DESMONTE M3 88.76 102.45 9,093.75
13 VARIOS 0.00 0.00 47,153.76
13.01 PRUEBAS ELECTRICAS (MEGADO X TABLEROS ) UND 174.00 31.20 5,428.80
13.02 INSTALACION DE LUMINARIAS EN AREAS COMUNES UND 1,076.00 26.47 28,479.57
13.03 INSTALACION DE LUCES DE EMERGENCIA UND 265.00 26.47 7,014.02
13.04 INSTALACION DE SENSOR DE MOVIMIENTO UND 226.00 16.07 3,631.37
13.05 PLANOS AS BUILT GLB 1.00 2,600.00 2,600.00
14 POZO A TIERRA 0.00 51,246.58
14.01 POZO DE TIERRA A R< 10OHM UND 7.00 1,378.00 9,646.00
14.02 1-1x70mm² NH80 (T) M 41.00 56.68 2,323.88
14.03 1-1x50mm² NH80 (T) M 544.00 52.25 28,423.78
14.04 1-1x35mm² NH80 (T) M 238.00 18.15 4,319.22
14.05 1-1x25mm² Desnudo (T) M 352.00 12.95 4,557.70
14.07 CAJA EQUIPOTENCIAL UND 2.00 988.00 1,976.00

COSTO DIRECTO S/. 2,332,475.86


C & V INVERSIONES INMOBILIARIAS
Cl. Narciso de la Colina N° 421, Of. 1401, Miraflores
www.cyvperu.com
HOJA DE PRESUPUESTO DETALLADO
OBRA: CONSTRUCCION DEL CONDOMINIO PORTOFINO
ESPECIALIDAD: INSTALACIONES SANITARIAS
PROPIET. : PROPIA
LUGAR: Av. Santa Cruz 1550, Miraflores
FECHA: 20 de Enero del 2022
MONEDA: Nuevos Soles

ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL


01 SISTEMA DE AGUA FRIA 0.00
01.01 TUBERIA DE DISTRIBUCION EMPOTRADA 0.00 177,606.21
01.01.01 TUBERÍA DE POLIPROPILENO 20MM R3 PN-10 (1/2") ML 5,220.00 9.94 51,899.33
01.01.02 TUBERÍA DE POLIPROPILENO 25MM R3 PN-10 (3/4") ML 2,900.00 13.06 37,880.96
01.01.03 TUBERÍA DE POLIPROPILENO 32MM R3 PN-10 (1") ML 5,800.00 15.14 87,825.92
01.02 TUBERIAS DE DISTRIBUCCION COLGADAS - ADOSADAS 0.00 0.00 28,567.78
01.02.01 TUBERÍA DE POLIPROPILENO 50MM R3 PN-10 (1.1/2") ADOSADA ML 23.20 32.88 762.93
01.02.02 TUBERÍA DE POLIPROPILENO 63MM R3 PN-10 (2") COLGADA ML 27.45 40.65 1,115.94
01.02.03 TUBERÍA DE POLIPROPILENO 63MM R3 PN-10 (2") ADOSADA ML 25.35 38.50 976.00
01.02.04 TUBERÍA DE POLIPROPILENO75MM R3 PN-10 (2.1/2") ADOSADA ML 47.70 46.42 2,214.01
01.02.05 TUBERÍA DE POLIPROPILENO 90MM R3 PN-10 (3") COLGADA ML 137.00 64.24 8,800.99
01.02.06 TUBERÍA DE POLIPROPILENO 90MM R3 PN-10 (3") ADOSADA ML 111.30 62.09 6,910.39
01.02.07 TUBERÍA DE POLIPROPILENO 110MM R3 PN-10 (4") COLGADA ML 57.31 87.46 5,012.56
01.02.08 TUBERÍA DE POLIPROPILENO 110MM R3 PN-10 (4") ADOSADA ML 36.15 76.76 2,774.96
01.03 SALIDA DE AGUA FRIA 0.00 115,965.49
01.03.01 SALIDA DE AGUA FRIA TUBERIA DE 1/2" pto 1,760.00 61.42 108,103.42
01.03.02 SALIDA DE AGUA FRIA TUBERIA DE 3/4" pto 128.00 61.42 7,862.07
01.04 VALVULAS 0.00 0.00 17,009.54
01.04.01 LLAVE DE PASO 20mm Met. Azul und 326.00 34.75 11,327.33
01.04.02 LLAVE DE PASO 25mm Met. Azul und 6.00 39.16 234.94
01.04.03 LLAVE DE PASO 32mm Met. Azul und 128.00 42.56 5,447.27
01.05 VARIOS 0.00 0.00 51,641.14
01.05.01 GRIFO DE RIEGO DE 1/2" und 18.00 43.77 787.92
01.05.02 CONTOMETRO DE 1" und 126.00 325.26 40,982.76
01.05.03 VALVULA ELIMINADORA DE AIRE 1" und 6.00 278.83 1,673.01
01.05.04 CONEXION A MEDIDOR EXISTENTE und 2.00 1,437.27 2,874.54
01.05.06 VALVULA DE CORTE DE 2" und 4.00 219.14 876.55
01.05.07 BATERIA DE CONTOMETROS und 37.00 120.17 4,446.36
01.06 PRUEBAS HIDRAULICAS Y DESINFECCION DE TUBERIAS 0.00 31,993.73
01.06.01 PRUEBA HIDRAULICA Y DESINFECCION DEL SISTEMA DE AGUA mL 13,920.00 2.30 31,993.73
02.00 SISTEMA DE AGUA CALIENTE 0.00 0.00
02.01 TUBERIA DE AGUA CALIENTE 0.00 0.00 70,832.07
02.01.01 TUBERIA DE 20mm R3 PN-16 (1/2") ml 2,945.35 17.25 50,817.89
02.01.02 TUBERIA DE 25mm R3 PN-16 (3/4") ml 1,160.00 17.25 20,014.18
02.02 SALIDA DE AGUA CALIENTE 0.00 0.00 70,492.55
02.02.01 SALIDA AGUA CALIENTE DE 1/2" pto 1,354.00 47.48 64,282.50
02.02.02 SALIDA AGUA CALIENTE DE 3/4" pto 128.00 48.52 6,210.05
02.03 VALVULAS 0.00 0.00 11,327.33
02.03.01 LLAVE DE PASO 16mm Met. Roja ml 326.00 34.75 11,327.33
02.04 PRUEBAS HIDRAULICAS Y DESINFECCION DE TUBERIAS 0.00 0.00 9,435.74
02.04.01 PRUEBA HIDRAULICA Y DESINFECCION DEL SISTEMA DE AGUA ml 4,105.35 2.30 9,435.74
03.00 SISTEMA DE DESAGUE 0.00 0.00
03.01 TRABAJOS PRELIMINARES 0.00 0.00 12,573.32
03.01.01 TRAZO Y REPLANTEO ML 205.25 6.32 1,297.84
03.01.02 EXCAVACION Y RELLENO DE ZANJA. M3 55.22 59.52 3,286.65
03.01.03 RELLENO Y COMPACTACIÓN DE ZANJA M3 6.87 67.83 465.98
03.01.04 CAMA DE APOYO PARA TUBERIAS M3 48.35 38.58 1,865.54
03.01.05 ELIMINACIÓN DE DESMONTE M3 55.22 102.45 5,657.31
03.02 TUBERIAS COLECTORAS EMPOTRADAS Y ENTERRADAS 0.00 0.00 98,702.29
03.02.01 TUBERIA PVC 2" ML 926.27 16.88 15,634.70
03.02.02 TUBERIA PVC 3" ML 135.58 19.08 2,587.41
03.02.03 TUBERIA PVC 4" ML 664.92 21.05 13,996.30
03.02.04 TUBERIA PVC 6" ML 30.15 53.18 1,603.23
03.02.05 TUBERIA PVC 2" VENTILACION ML 3,462.00 18.74 64,880.65
03.03 TUBERIA COLECTORAS COLGADAS - ADOSADAS 0.00 0.00 52,749.11
03.03.01 TUBERIA PVC 2" COLGADA ML 25.36 27.88 707.10
03.03.02 TUBERIA PVC 3" COLGADA ML 458.56 32.82 15,051.04
03.03.03 TUBERIA PVC 4" COLGADA ML 654.25 41.03 26,842.57
03.03.04 TUBERIA PVC 6" COLGADA ML 85.63 71.06 6,085.14
03.03.05 TUBERIA PVC 8" COLGADA ML 32.45 125.22 4,063.26
03.04 MONTANTES DE DESAGUE Y VENTILACION 0.00 0.00 176,514.03
03.04.01 MONTANTE DE VENTILACION PVC SAP 4" ADOSADA ML 1,254.25 59.90 75,134.59
03.04.02 MONTANTE DE DESAGUE PVC PESADA DE 4" ADOSADA ML 1,254.25 62.03 77,795.61
03.04.03 TUBERIA PVC-CL 10 DE 2" IMPULSION ADOSADA ML 24.56 42.03 1,032.17
03.04.04 MONTANTE DE DESAGUE PVC PESADA DE 3" ADOSADA ML 234.78 48.03 11,275.83
03.04.05 MONTANTE DE VENTILACION PVC SAP 3" ML 234.78 48.03 11,275.83
03.05 CAJA DE REGISTROS 0.00 0.00 4,313.92
03.05.01 CAJAS DE REGISTRO DE DESAGUE 24" x 24" UND. 8.00 126.88 1,015.04
03.05.02 CAJAS DE REGISTRO DE DESAGUE 24" x 12" UND. 14.00 199.68 2,795.52
03.05.03 BUZONETA DE REGISTRO DE DESAGUE 24" UND. 2.00 251.68 503.36
03.06 SALIDA DE DESAGÜE 0.00 0.00 151,783.88
03.06.01 SALIDA PARA DESAGUE 2" UND 1,145.85 50.50 57,868.18
03.06.02 SALIDA PARA DESAGUE 3" UND 15.00 58.60 879.06
03.06.03 SALIDA PARA DESAGUE 4" UND 326.00 70.98 23,140.84
03.06.04 SALIDA PARA DESAGUE 2" VENTILACION UND 1,450.00 48.20 69,895.80
03.07 REGISTROS Y SUMIDEROS 0.00 0.00 97,207.16
03.07.01 REGISTRO DE BRONCE ROSCADO DE PISO 2" UND 478.00 37.08 17,722.33
03.07.02 REGISTRO DE BRONCE ROSCADO DE PISO 3" UND 26.00 42.07 1,093.77
03.07.03 REGISTRO DE BRONCE ROSCADO DE PISO 4" UND 368.00 49.63 18,263.40
03.07.04 REGISTRO DE BRONCE ROSCADO DE PISO 6" UND 2.00 71.51 143.02
03.07.05 SUMIDERO DE BRONCE ROSCADO 2" UND 865.00 48.41 41,876.38
03.07.06 SUMIDERO DE BRONCE ROSCADO 3" UND 115.00 59.54 6,847.10
03.07.07 SUMIDERO DE BRONCE ROSCADO 6" UND 2.00 79.68 159.37
03.07.08 REGISTRO DE BRONCE COLGADO 2" UND 12.00 61.07 732.83
03.07.09 REGISTRO DE BRONCE COLGADO 3" UND 30.00 62.77 1,883.23
03.07.10 REGISTRO DE BRONCE COLGADO 4" UND 65.00 78.80 5,122.05
03.07.11 REGISTRO DE BRONCE COLGADO 6" UND 20.00 126.33 2,526.58
03.07.12 REGISTRO DE BRONCE COLGADO 8" UND 5.00 167.42 837.10
03.08 PRUEBA HIDRAULICA DEL SISTEMA 0.00 0.00 20,125.37
03.08.01 PRUEBA HIDRAULICA DEL SISTEMA (TOTAL) UND 8,756.25 2.30 20,125.37
03.09 INSTALACION DE APARATOS SANITARIOS 0.00 0.00 79,156.59
03.09.01 INSTALACION DE INODOROS-SOLO MANO DE OBRA UND 326.00 47.57 15,507.69
03.09.02 INSTALACION DE LAVATORIOS-SOLO MANO DE OBRA UND 326.00 71.99 23,468.35
03.09.03 INSTALACION DE LAVADERO DE ROPA-SOLO MANO DE OBRA UND 128.00 71.99 9,214.57
03.09.04 INSTALACION DE LAVADERO DE POSA-SOLO MANO DE OBRA UND 128.00 71.25 9,120.05
03.09.05 INSTALACION DE URINARIOS-SOLO MANO DE OBRA UND 1.00 34.68 34.68
C & V INVERSIONES INMOBILIARIAS
Cl. Narciso de la Colina N° 421, Of. 1401, Miraflores
www.cyvperu.com
HOJA DE PRESUPUESTO DETALLADO
OBRA: CONSTRUCCION DEL CONDOMINIO PORTOFINO
ESPECIALIDAD: INSTALACIONES SANITARIAS
PROPIET. : PROPIA
LUGAR: Av. Santa Cruz 1550, Miraflores
FECHA: 20 de Enero del 2022
MONEDA: Nuevos Soles

ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL


03.09.06 INSTALACION DE FLUXOMETRO-SOLO MANO DE OBRA UND 2.00 34.68 69.37
03.09.07 INSTALACION DE CANOPLAS DE DUCHA-SOLO MANO DE OBRA UND 238.00 27.75 6,603.83
03.09.08 INSTALACION DE GRIFERIAS UND 582.00 26.01 15,138.05
03.10 SOMBREROS DE VENTILACIÓN 0.00 0.00 1,048.94
03.10.01 SOMBRERO DE VENTILACIÓN DE PVC DE 2" UND 10.00 26.68 266.76
03.10.02 SOMBRERO DE VENTILACIÓN DE PVC DE 3" UND 6.00 28.96 173.78
03.10.03 SOMBRERO DE VENTILACIÓN DE PVC DE 4" UND 18.00 33.80 608.40
03.11 PASES EN LOSA 0.00 0.00 18,002.40
03.11.01 PASE EN LOSA PARA TUBERÍA DE 2" UND 45.00 156.00 7,020.00
03.11.02 PASE EN LOSA PARA TUBERÍA DE 4" UND 66.00 166.40 10,982.40
03.12 CUARTO DE BOMBA 0.00 0.00 26,772.72
03.12.01 TUBERIA DE Fº Gº 6" UND 6.00 312.00 1,872.00
03.12.02 BRIDA ROMPE AGUA 6" CON NIPLE SOLDADO UND 8.00 930.80 7,446.40
03.12.03 BRIDA ROMPE AGUA 4" CON NIPLE SOLDADO UND 3.00 816.40 2,449.20
03.12.04 BRIDA ROMPE AGUA 3" CON NIPLE SOLDADO UND 8.00 707.20 5,657.60
03.12.05 BRIDA ROMPE AGUA 2" CON NIPLE SOLDADO UND 5.00 572.00 2,860.00
03.12.06 BRIDA ROMPE AGUA 1 1/2" CON NIPLE SOLDADO UND 3.00 520.00 1,560.00
03.12.07 TUBERIA DE PVC CP DE 6" UND 6.00 306.80 1,840.80
03.12.08 TUBERIA DE PVC CP DE 3" UND 4.00 197.60 790.40
03.12.09 CODO PVC 6 " UND 6.00 29.12 174.72
03.12.10 VALVULO 3" PARA LIMPIAR LA CISTERNA UND 3.00 707.20 2,121.60

COSTO DIRECTO S/. 1,323,821.31


C & V INVERSIONES INMOBILIARIAS
Cl. Narciso de la Colina N° 421, Of. 1401, Miraflores
www.cyvperu.com
HOJA DE PRESUPUESTO DETALLADO
OBRA: CONSTRUCCION DEL CONDOMINIO PORTOFINO
ESPECIALIDAD: INSTALACIONES DE GAS
PROPIET. : PROPIA
LUGAR: Av. Santa Cruz 1550, Miraflores
FECHA: 20 de Enero del 2022
MONEDA: Nuevos Soles

ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL


01 INSTALACIONES REDES DE GAS - RED INTERNA 147,200.00
01.01 Instalacion de Red Interna PEALPE - Tendido en losa Dptos. 128.00 650.00 83,200.00
128.00 200.00
01.02 Instalacion de Llaves de corte de Artefacto y Montante a azotea Und. 25,600.00
01.03 Instalacion de Gabinetes incluida llave de corte general Und. 128.00 300.00 38,400.00

02 INSTALACIONES REDES DE GAS - MONTANTE 14,800.00


02.01 Instalacion de Montante - Red de Cobre 1" Glb. 1.00 14,800.00 14,800.00
0.00

COSTO DIRECTO S/. 162,000.00


CONSIDERACIONES PU DOLARES PU SOLES
C & V INVERSIONES INMOBILIARIAS
Cl. Narciso de la Colina N° 421, Of. 1401, Miraflores
www.cyvperu.com
HOJA DE PRESUPUESTO DETALLADO
OBRA: CONSTRUCCION DEL CONDOMINIO PORTOFINO
ESPECIALIDAD: EQUIPAMIENTO
PROPIET. : PROPIA
LUGAR: Av. Santa Cruz 1550, Miraflores
FECHA: 20 de Enero del 2022
MONEDA: Nuevos Soles

ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL


01 ASCENSORES (SUMINISTRO & INSTALACION) 0.00 349,500.00
01.01 ASCENSORES (SUMINISTRO & INSTALACION) GLB 1.00 349,500.00 349,500.00
0.00
02 SISTEMA DE INTERCOMUNICADORES 0.00 54,375.00
02.01 SISTEMA DE INTERCOMUNICADORES GLB 1.00 54,375.00 54,375.00
0.00
03 SISTEMA DE ALARMA CONTRAINCENDIO 0.00 115,423.88
03.01 SISTEMA DE ALARMA CONTRAINCENDIO GLB 1.00 115,423.88 115,423.88
0.00
SISTEMA DE AGUA CONTRA INCENDIO - ACI (Incl.
04 Bomba) 0.00 739,789.46
SISTEMA DE AGUA CONTRA INCENDIO - ACI (Incl.
1.00
04.01 Bomba) GLB 739,789.46 739,789.46
0.00
05 SISTEMA DE BOMBEO DE AGUA POTABLE 0.00 108,654.90
05.01 SISTEMA DE BOMBEO DE AGUA POTABLE GLB 1.00 108,654.90 108,654.90
0.00
06 SISTEMA DE BOMBAS SUMIDERO 0.00 165,250.65
06.01 SISTEMA DE BOMBAS SUMIDERO GLB 1.00 165,250.65 165,250.65
0.00
07 GRUPO ELECTROGENO 0.00 104,154.60
GRUPO ELECTROGENO (SUMINISTRO & 1.00
07.01 INSTALACION) GLB 104,154.60 104,154.60
0.00
07 PISCINA 0.00 20,733.20
INSTALACION Y SUMINISTRO PISCINA
07.01 (EQUIPAMIENTO) GLB 1.00 20,733.20 20,733.20

07 PANELES SOLARES
INSTALACION Y SUMINISTRO PANALES SOLARES 0.00 52,366.88
07.01 (EQUIPAMIENTO) GLB 1.00 52,366.88 52,366.88

08 SISTEMAS DE VETILACION MECANICA 0.00 566,675.59


SISTEMA DE EXTRACCIÓN DE MONÓXIDO DE
CARBONO 1.00 268,723.47 268,723.47

SISTEMA DE VENTILACIÓN CUARTO DE BOMBAS 1.00 1,393.47 1,393.47

SISTEMA DE VENTILACIÓN CUARTO DE BASURA 1.00 997.16 997.16

SISTEMA DE VENTILACIÓN ZONA DE BICICLETAS 1.00 984.38 984.38

SISTEMA DE VENTILACIÓN CAMERINO HOMBRES


Y MUJERES 1.00 1,137.78 1,137.78
SISTEMA DE VENTILACIÓN LAVANDERIA Y SPA 1.00 1,137.78 1,137.78

SISTEMA DE VENTILACIÓN VESTIBULOS PREVIOS 1.00 26,605.82 26,605.82


SISTEMA DE INYECCIÓN DE AIRE A ESCALERA 1.00 16,163.35 16,163.35
SISTEMA DE VENTILACIÓN SSHH, LAVANDERIA,
SECADO 1.00 151,964.20 151,964.20
SISTEMA DE VENTILACIÓN COCINA 1.00 97,568.18 97,568.18
0.00
09 SISTEMA DE CONTROL DE INGRESO 0.00 85,280.00
09.01 SISTEMA DE INGRESO VEHICULAR GLB 1.00 85,280.00 85,280.00
0.00
10 CCTV 0.00 65,000.00
10.01 CCTV GLB 1.00 65,000.00 65,000.00
0.00
11 ACELEROGRAFO 0.00 60,000.00
11.01 ACELEROGRAFO GLB 1.00 60,000.00 60,000.00
0.00
12 SISTEMA DE TRATAMIENTO DE AGUAS SERVIDAS 0.00 244,500.00
12.01 SISTEMA DE TRATAMIENTO DE AGUAS SERVIDAS GLB 1.00 244,500.00 244,500.00
0.00
0.00

COSTO DIRECTO S/. 2,731,704.16


S. 3.75

CONSIDERACIONES PU DOLARES PU SOLES

Se considera cotizacion del SC SCHINDLER $93,200.00 S. 349,500.00

Se considera cotizacion del SC INTERSISTEM FERMAX $14,500.00 S. 54,375.00

Se considera cotizacion del SC CORPORACION G&O $30,779.70 S. 115,423.88

Se considera cotizacion del SC HIDROMEC $197,277.19 S. 739,789.46

Se considera cotizacion del SC HIDROMEC $28,974.64 S. 108,654.90

Se considera cotizacion del SC HIDROMEC $44,066.84 S. 165,250.65

Se considera cotizacion del SC VIELCO $27,774.56 S. 104,154.60

Se considera cotizacion del SC AQUAZUL S. 20,733.20

Se considera cotizacion del SC TRIANON $13,964.50 S. 52,366.88

Se considera cotizacion del SC ASPIRATEK S. 261,155.28


$69,641.41
Se considera cotizacion del SC ASPIRATEK S. 1,393.47
$371.59
Se considera cotizacion del SC ASPIRATEK S. 997.16
$265.91
Se considera cotizacion del SC ASPIRATEK S. 984.38
$262.50
Se considera cotizacion del SC ASPIRATEK $2,018.18 S. 7,568.18
Se considera cotizacion del SC ASPIRATEK S. 1,137.78
$303.41
Se considera cotizacion del SC ASPIRATEK $303.41 S. 1,137.78
Se considera cotizacion del SC ASPIRATEK S. 26,605.82
$7,094.89
Se considera cotizacion del SC ASPIRATEK $4,310.23 S. 16,163.35
Se considera cotizacion del SC ASPIRATEK S. 151,964.20
$40,523.79
Se considera cotizacion del SC ASPIRATEK $26,018.18 S. 97,568.18

NO SE ENCONTRO ALCANCE TECNICO, SE CONSIDERA MISMO MONTO DEL PPTO VENTA

NO SE ENCONTRO ALCANCE TECNICO, SE CONSIDERA MISMO MONTO DEL PPTO VENTA

NO SE ENCONTRO ALCANCE TECNICO, SE CONSIDERA MISMO MONTO DEL PPTO VENTA

Se considera cotizacion del SC ACCUA PRODUCT $65,200.00 S. 244,500.00


ANALISIS DE GASTOS GENERALES

OBRA: CONSTRUCCION DEL CONDOMINIO PORTOFINO


PROPIET. : PROPIA
LUGAR: Av. Santa Cruz 1550, Miraflores
FECHA: 20 de Enero del 2022
MONEDA: Nuevos Soles PLAZO: 11.0 meses
TC

Unidad Cantidad P.U. Parcial Subtotal Total


S/. S/. S/. S/.
GASTOS FIJOS (No relacionados directamente con el tiempo de ejecución) 612,231.93
1.1 Gastos Financieros 134,471.93 134,471.93
Carta Fianza Fiel cumplimiento (10%) mes 0.00
Carta Fianza Garantía del Adelanto en efectivo (20%) mes 0.00
Carta Fianza Adelanto Materiales (0%) mes 8.25 0.00 0.00
Carta Fianza Beneficios Sociales (10%) mes 11.00 0.00 0.00
Póliza de Seguro Construction All Risk (0.3%) und 1.00 53,975.36 53,975.36
Sencico (0.2%) und 1.00 80,496.57 80,496.57

1.2 Gastos Indirectos Centrales: 477,760.00 477,760.00


- Gastos BACK OFFICE mes 16.00 29,860.00 477,760.00

GASTOS VARIABLES (Relacionados directamente con el tiempo de ejecución de la obra) 1,477,486.91


2.1 Gastos de Administración de Obra: 908,286.91
- Gastos de Staff Tecnico Oficina 775,952.86
Ingeniero Residente de Obra mes 16.00 16,287.27 260,596.32 ###
Ingeniero Civil de Campo mes 10.00 9,500.91 95,009.10 ###
Arquitecto de Campo mes 8.00 7,465.00 59,720.00 ###
Maestro mes 15.00 7,465.00 111,975.00 ###
Arquitecto de Calidad mes 11.00 5,429.09 59,719.99
Tecnico de Calidad mes 6.00 2,714.55 16,287.30 ###
Jefe de Seguridad mes 16.00 5,700.55 91,208.80 ###
Ingeniero de Costos S10 mes 15.00 5,429.09 81,436.35 ###

- Gastos de Staff Administrativo 132,334.05


Administrador mes 15.00 4,750.45 71,256.75 ###
Almacenero mes 15.00 4,071.82 61,077.30 ###

2.2 Equipos y Vehiculos 13,300.00 13,300.00


Computadoras y Software und 10.00 1,080.00 10,800.00 1 Computa
Impresoras / Ploter und 1.00 2,500.00 2,500.00 ###

2.3 Comunicaciones 22,000.00 22,000.00


Equipos de Comunicación Movil und 12.00 500.00 6,000.00
Consumo de Comunicación Movil mes 16.00 640.00 10,240.00
Internet Speedy mes 16.00 360.00 5,760.00

2.4 Sistema de Contro de Costos (S-10) 48,000.00 48,000.00


Modulo - Gerencia mes 16.00 1,200.00 19,200.00
Modulo - Logistica mes 16.00 600.00 9,600.00
Modulo - Almacen mes 16.00 600.00 9,600.00
Modulo - Nominas mes 16.00 600.00 9,600.00

2.5 Gastos Varios 485,900.00 485,900.00


Papeleria mes 16.00 400.00 6,400.00
Utiles de Escritorio mes 16.00 300.00 4,800.00
Movilidades mes 16.00 700.00 11,200.00
Copias de Planos y Documentos glb 1.00 4,500.00 4,500.00
Planos de Replanteo glb 1.00 4,500.00 4,500.00
Trámites Municipales glb 1.00 4,500.00 4,500.00
Gastos Varios(vecinos, contingencias) glb 1.00 450,000.00 450,000.00

TOTAL DE GASTOS GENERALES ( I + II ) 2,089,718.84

693975448.xlsx 09/26/2023
COSTO DEL PERSONAL
Salario Básico Gratificación Subtotal CTS Subtotal Impuestos Total Costo Mes Costo S/.
Mensual 12 1 No. 1 1 No. 2 9%+2%-CTS /11 1.00

GASTOS GENERALES DE OBRA


DIRECCION TECNICA DE OBRA
RESIDENTE DE OBRA 10,500 126,000 10,500 136,500 5,250 141,750 15,015 156,765 14,251 14,251.36
PRODUCCION
INGENIERO DE CAMPO 6,500 78,000 6,500 84,500 3,250 87,750 9,295 97,045 8,822 8,822.27
ARQUITECTO DE CAMPO 5,000 60,000 5,000 65,000 2,500 67,500 7,150 74,650 6,786 6,786.36
MAESTRO DE OBRA 6,000 72,000 6,000 78,000 3,000 81,000 8,580 89,580 8,144 8,143.64
ADMINISTRACION
ADMINISTRADOR DE OBRA 3,200 38,400 3,200 41,600 1,600 43,200 4,576 47,776 4,343 4,343.27
ALMACENERO 2,400 28,800 2,400 31,200 1,200 32,400 3,432 35,832 3,257 3,257.45
CALIDAD
ARQUITECTO DE CALIDAD 5,500 66,000 5,500 71,500 2,750 74,250 7,865 82,115 7,465 7,465.00
TECNICO DE CALIDAD 3,500 42,000 3,500 45,500 1,750 47,250 5,005 52,255 4,750 4,750.45
SEGURIDAD
JEFE SSOMA 4,500 54,000 4,500 58,500 2,250 60,750 6,435 67,185 6,108 6,107.73
CONTROL DE PROYECTOS
INGENIERO DE OT 5,000 60,000 5,000 65,000 2,500 67,500 7,150 74,650 6,786 6,786.36

GASTOS GENERALES BACK OFFICE


DIRECCION TECNICA DE OBRA
GERENTE DE PROYECTOS (100% 14,000 168,000 14,000 182,000 7,000 189,000 20,020 209,020 19,002 19,001.82
LOGISTICA
JEFA DE LOGISTICA (100%) 4,000 48,000 4,000 52,000 2,000 54,000 5,720 59,720 5,429 5,429.09

También podría gustarte