1.00 DEMOLICION S/. 61,108.28 S/. 61,108.28 S/. 82,708.81 -21,600.53 EN S10
2.00 OBRAS PROVISIONALES & TRABAJOS PRELIMINARES S/. 2,256,582.94 S/. 2,256,582.94 S/. 1,882,639.33 373,943.61 EN S10
3.00 ESTRUCTURAS S/. 11,724,494.33 S/. 13,286,994.11 S/. 13,172,206.84 -1,447,712.51 EN S10
4.00 ARQUITECTURA S/. 12,655,060.90 S/. 12,655,060.90 S/. 14,377,168.34 -1,722,107.44 EN EXCEL
5.00 INSTALACIONES SANITARIAS S/. 1,323,821.31 S/. 1,323,821.31 S/. 1,331,208.48 -7,387.17 EN S10
6.00 INSTALACIONES ELECTRICAS S/. 2,332,475.86 S/. 2,332,475.86 S/. 2,093,336.69 239,139.17 EN S10
7.00 INSTALACIONES DE GAS S/. 162,000.00 S/. 162,000.00 S/. 162,000.00 0.00 EN S10
8.00 EQUIPAMIENTO S/. 3,423,911.22 S/. 3,423,911.22 S/. 2,731,704.16 692,207.06 EN S10
OBRAS COMPLEMENTARIAS S/. 360,000.00 S/. 360,000.00 S/. 360,000.00 0.00 PPTO VENTA
PRESUPUESTO
CONDOMINIO PORTOFINO
20 DE ENERO DEL 2022
Costo HH por categoria
l HH
0.00
Se considera cotizacion del SC GARCIA, incluyendo adicionales facturados a excepcion del adicional CAMA
BAJA, a causa de paralizacion no prevista en el ppto venta
REAL VENTA META BRECHA V BRECHA M
DEMOLICION UND METRADO P.U. TOTAL PPTO DEMOLICION
Demolicion y eliminacion de casa existente, pared perimetricas, area 1451 m2 glb 1.0 S/. 49,870.00 S/ 49,870.00 S/ 52,270.00 S/ 64,150.00 -S/ 12,854.24 -S/ 974.24 ya ejecutado, avance al 85%
colocacion de malla rashell con parantes de eucalipto - protec. A terceros glb 1.0 3,800.00 S/ 3,800.00 S/ 8,838.28 S/ 8,838.28 S/ 5,038.28 S/ 5,038.28 no valorizado ejecutado con personal de casa, SI considerado en ppto meta
EXCAVACION PPTO EXC MASIVA
EXCAVACION MASIVA C/EQUIPO INC. ELIMINACION m3 19,485.00 24.30 S/ 473,485.50 S/ 512,633.42 S/ 559,597.90 S/ 21,067.92 S/ 68,032.40 ahorro de 68k
EXCAVACION LOCALIZADA Y ELIMINACION ZAPATAS CIMIENTOS DE MURO ANCLADOglb 640.85 27.40 S/ 17,559.29 S/ 60,201.90 S/ 27,305.88 S/ 42,642.61 S/ 9,746.59 ahorro de 9k
CONTROL DE POLVOS CON CISTERNA PARA DEMOLICION(ayudante,motobomba)6 glb 6.00 430.00 S/ 2,580.00 no se valorizara,no considerado en ppto meta
demolicion de zapata existente colindante alos vecinos area 1451 m2 m2 194.00 70.00 S/ 13,580.00 S/ 13,580.00 S/ - no ahorro, no perdida
HORAS MÁQUINA
HORAS MÁQUINA HM 487.00 200.00 S/ 97,400.00
SUB-TOTAL S/ 662,774.79
IGV S/ 119,299.46
TOTAL S/ 782,074.25
ADICIONAL 01 - DEMOLICION
SC CERTIFICACION S/ 9,800.00 no considerado en el CC contractual
SC CAMBIO DE RUTA ELIMINACION S/ 4,480.00 no considerado en el CC contractual
SC CAMA BAJA S/ 974.24 Perdida, no considerado en el ppto meta
136.00
4.00
34.00
80.00
32.00
48.00
363.72
S/. 2,400.00
2.00
6.00
207.84
207.84
S/. 304.00
S/. 76.00
0.1429
0.1667
S/. 22,671.00
415.68
S/. 26,403.67
207.84
S/. 9,600.00
70.72
371.18
1,454.88
727.44
34.00
415.68
1,870.56
1,870.56
S/. 17.00
PRESUPUESTO DE SEGURIDAD, SALUD OCUPACIONAL Y MEDIO AMBIENTE
2022 2023
JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE
HISTOGRAMA DE TRABAJADORES (STAFF GG Y POR CASA)
mes 01 mes 02 mes 03 mes 04 mes 05 mes 06 mes 07 mes 08 mes 09 mes 10 mes 11 mes 12 mes 13 mes 14 mes 15
Personal Staff 6 6 6 7 7 8 8 9 9 9 10 10 10 7 3
RESIDENTE DE OBRA GASTOS GENERALES C&V 1 1 1 1 1 1 1 1 1 1 1 1 1 1 14
INGENIERO DE CAMPO GASTOS GENERALES C&V 1 1 1 1 1 1 1 1 8
ARQUITECTO DE CAMPO GASTOS GENERALES C&V 1 1 1 1 1 1 1 1 8
MAESTRO DE OBRA GASTOS GENERALES C&V 1 1 1 1 1 1 1 1 1 1 1 1 1 13
ARQUITECTO DE CALIDAD GASTOS GENERALES C&V 1 1 1 1 1 1 1 1 1 1 1 11
TECNICO DE CALIDAD GASTOS GENERALES C&V 1 1 1 1 4
JEFE SSOMA GASTOS GENERALES C&V 1 1 1 1 1 1 1 1 1 1 1 1 1 13
INGENIERO DE OT GASTOS GENERALES C&V 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 15
ADMINISTRADOR DE OBRA GASTOS GENERALES C&V 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 15
ALMACENERO GASTOS GENERALES C&V 1 1 1 1 1 1 1 1 1 1 1 1 1 1 14
TRAB. PRELIMINARES
MUROS ANCLADOS CIMENTACIONES CISTERNA LOSA CONTRATERRENO
ESTRUCTURA
SC TORRE GRUA SC ELEVADOR
ACABADOS HUMEDOS
ACABADOS SECOS
OBRAS EXTERIORES
CONCRETEROS CONCRETO SC
ENCOFRADORES ENCOFRADO SC
8 8 8 9 11 14 14 15 15 15 29 41 39 36 12
S/. 4,905.00 S/. 363.40 S/. 1,945.00 S/. 363.40 S/. 3,563.80 S/. 1,330.20 S/. 4,843.00 S/. 2,032.20 S/. 5,713.20 S/. 2,032.20 S/. 8,728.30 S/. 10,569.70 S/. 12,459.30 S/. 9,871.30 S/. 3,861.30 S/. 72,581.30
S/. 3,200.00 S/. 3,200.00 S/. 0.00 S/. 3,200.00 S/. 55,739.53 S/. 5,080.00 S/. 320.00 S/. 2,130.00 S/. 0.00 S/. 700.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 73,569.53
S/. 7,286.23 S/. 7,286.23 S/. 0.00 S/. 4,016.15 S/. 847.50 S/. 4,691.95 S/. 847.50 S/. 4,016.15 S/. 847.50 S/. 1,523.30 S/. 847.50 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 32,210.00
S/. - S/. - S/. - S/. - S/. 350 S/. - S/. 350 S/. 350 S/. 350 S/. - S/. - S/. - S/. - S/. - S/. - S/. 1,400.00
6) RECURSOS PARA RESPUESTA ANTE EMERGENCIA EN SEGURIDAD Y SALUD DURANTE EL TRABAJO - CANTIDAD
Descripción mes 01 mes 02 mes 03 mes 04 mes 05 mes 06 mes 07 mes 08 mes 09 mes 10 mes 11 mes 12 mes 13 mes 14 mes 15
RECARGA DE EXTINTORES x 12Kg. - - - 2.00 - - 2.00 - - 2.00 - - 6.00
EXTINTOR DE POLVO QUIMICO SECO (PQS) DE 1 5.00 5.00 - 3.00 3.00 - - - - 16.00
CAMILLA RIGIDA 1.00 1.00 - - - - - - - - - - 2.00
BOTIQUIN MADERA BLANCO 30x40 1.00 1.00 - - - - - - - - - - 2.00
MANTA 1.00 1.00 - - - - - - - - - - 2.00
CAMILLA METALICA TIPO CANASTA DE RESCATE 1.00 1.00 - - - - - - - - - - 2.00
COLLARINES DE CABEZA 1.00 1.00 - - - - - - - - - - 2.00
CONTENEDO PARA BASURA 5.00 5.00 - - - - - - - - - - 10.00
RECARGA DE MEDICINAS PARA BOTIQUIN - - - - - 1.00 - - - - - 1.00
FUMIGACION - - - - - - - - - - - 1.00 - 1.00
6) RECURSOS PARA RESPUESTA ANTE EMERGENCIA EN SEGURIDAD Y SALUD DURANTE EL TRABAJO - COSTOS
Descripción Precio x Und mes 01 mes 02 mes 03 mes 04 mes 05 mes 06 mes 07 mes 08 mes 09 mes 10 mes 11 mes 12 mes 13 mes 14 mes 15 Total
RECARGA DE EXTINTORES x S/. 33.90 S/ - S/ - S/ - S/ 67.80 S/ - S/ - S/ 67.80 S/ - S/ - S/ 67.80 S/ - S/ - S/ - S/ - S/ - S/. 203.40 ###
EXTINTOR DE POLVO QUIMI S/. 425.00 S/ 2,125.00 S/ 2,125.00 S/ - S/ 1,275.00 S/ - S/ 1,275.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 6,800.00 ###
CAMILLA RIGIDA S/. 186.44 S/ 186.44 S/ 186.44 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 372.88 ###
BOTIQUIN MADERA BLANC S/. 570.00 S/ 570.00 S/ 570.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 1,140.00 ###
MANTA S/. 35.00 S/ 35.00 S/ 35.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 70.00 ###
CAMILLA METALICA TIPO S/. 250.00 S/ 250.00 S/ 250.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 500.00 ###
COLLARINES DE CABEZA S/. 53.45 S/ 53.45 S/ 53.45 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 106.90 ###
CONTENEDO PARA BASUR S/. 150.00 S/ 750.00 S/ 750.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 1,500.00 ###
RECARGA DE MEDICINAS S/. 100.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ 100.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/. 100.00 ###
FUMIGACION S/. 1,000.00 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 1,000.00 S/ - S/ - S/ - S/. 1,000.00 ###
S/. 3,969.89 S/. 3,969.89 S/. 0.00 S/. 1,342.80 S/. 0.00 S/. 1,275.00 S/. 167.80 S/. 0.00 S/. 0.00 S/. 67.80 S/. 0.00 S/. 1,000.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 11,793.18
S/. 680.00 S/. 680.00 S/. 0.00 S/. 85.00 S/. 170.00 S/. 255.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,870.00
6 6 6 7 7 8 8 9 9 9 10 10 10 7 3
6 6 0 1 0 1 S/ 208,424.01
2 2 0 0 2 2 0 0 0 0 13 12 -2 0 -20
2 2 0 0 2 2 0 0 0 0 0 0
C & V INVERSIONES INMOBILIARIAS
Cl. Narciso de la Colina N° 421, Of. 1401, Miraflores
www.cyvperu.com
HOJA DE PRESUPUESTO DETALLADO
OBRA: CONSTRUCCION DEL CONDOMINIO PORTOFINO
ESPECIALIDAD: OBRAS PROVISIONALES & TRABAJOS PRELIMINARES
PROPIET. : PROPIA
LUGAR: Av. Santa Cruz 1550, Miraflores
FECHA: 20 de Enero del 2022
MONEDA: Nuevos Soles
96,857.29 -1.78
11,883,760.03 -1,561,687.74
610,613.96 48.16
24,431.54 0.89
1,319,479.20 44.71
19.43 6,524.83
55.50 2,710.51
685.02 3,918.86
0.00
0.00
7.50 168.75
55.50 140.42
0.00
7.50 62.86
55.50 64.55
0.00
0.00
0.00
0.00
15.00 355.50
1.50 65.63
0.00
0.00
0.00
7.77 396.63
15.00 469.50
1,376,527.45 129.91
2,137,409.67 -1,562,287.80
2,212.00 12,654.41
2,317,991.22 175.09
2,647,935.96 164.62
1,199,796.88 25.64
63,515.86 4.06
178,149.00 5.09
7,909.29 1.89
70,789.28 0.00
4,305.00 8.3810
2,173.98 1.1630
209.97 11.0582
209.97 40.0194
8.00 276.4800
24.30 335.8984
600.00 23.7000
162.00 43.7500
49.36 335.8983
779.41 5.7208
209.97 4.2920
4,422.36 51.0468
450.00 31.3000
- #DIV/0!
- #DIV/0! S/. 0.0605
23.31 395.3544
490.27 310.1187
17.25 386.9814
2,804.27 56.0367
779.41 68.0367
174,547.92 5.7208
- #DIV/0!
- #DIV/0!
314.67 382.0966
623.43 355.8481
4,839.92 39.9100
816.58 48.8379 S/. 25.11
334.96 -
S/. 27,532.43 270,320.94 -
S/. 30,285.68 - #DIV/0!
- #DIV/0!
1,011.90 336.7791
6,657.65 107.8400
220,147.30 5.7208
- #DIV/0!
- #DIV/0!
1,721.00 286.7466
8,605.01 8.0700
8,605.01 43.6200
213,358.09 5.7208
S/. 8,553.50 8,553.50 55.5102
585.05 0.9667
585.05 12.2300
585.05 7.0200
585.05 4.4500
- #DIV/0!
- #DIV/0!
504.56 286.7470
5,922.08 8.0700
5,922.08 43.6200
53,872.24 5.7208
S/. 328.88 328.88 69.4482
S/. 5,469.93 5,469.93 76.4172
- #DIV/0!
- #DIV/0!
40.68 393.7402
268.02 46.0229
6,147.31 5.7208
- #DIV/0!
- #DIV/0!
179.64 359.1977
778.76 59.6256
11,243.56 5.7208
122.46 23.4500
- #DIV/0!
- #DIV/0!
6.21 382.4058
65.00 48.8348
412.91 5.7208
- #DIV/0!
- #DIV/0!
34,252.28 0.9100
272.00 67.0000
1,011.21 12.8200
544.00 15.5000
#DIV/0!
ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL
07.04 FACHADAS -
07.04.01 PINTURA -
Miguel P 670.35 17.50 11,731.11
MUROS - EMPASTADO Y PINTADO CON 2 MANOS DE BASE Y 2 MANOS DE PINTURA LATEX M2
SOLAQUEADO CON EMPORRADO DE LECHADA DE CEMENTO Y CAL NIEVE M2 Miguel P 2,160.39 17.50 37,806.74
08 COBERTURAS - 81,676.30
08.01 TORRE - -
PASTELERO -
ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL
M. VENTA 27.50 -
COBERTURA LADRILLO PASTELERO ASENTADO CON MEZCLA EN DERRAMES DE MUROS ML
TECHO VERDE
M2 Miguel P 635.07 35.00 22,227.45
TIERRA DE CHACRA (h=0.30)
M2 Miguel P 635.07 25.00 15,876.75
JARDIN AMERICANO
ARBOL PEQUEÑO UND Miguel P 20.00 650.00 13,000.00
AZOTEA
NUEVO COBERTURA DE SUPERBOARD UND Miguel P 6.00 650.00 3,900.00
NUEVO REJILLA EN DUCTO IISS UND Miguel P 11.00 1,050.00 11,550.00
ESC. DUPLEX: BARANDA H=1.10m DE TUBODE FIERRO DE 2". ELEMENTOS HORIZONTALES ML Luis L 68.00 445.00 30,260.00
DE TUBO REDONDO LISO DE 3/4" Y ELEMENTOS VERTICALES EN PLATINAS DE 2" e= 1CM.,
CON CANOPLAS RECTANGULARES DE PLANCHA DE FIERRO COLOR NEGRO
ESC. DUPLEX: PASAMANO DE TUBO DE FIERRO DE 2" ANCLADO A MURO, CON CANOPLAS ML Luis L 66.00 195.00 12,870.00
CIRCULARES DE PLANCHA DE FIERRO COLOR NEGRO.
10.02.02 VARIOS
REJILLA INOX EN DUCHAS ML Luis L 269.77 295.00 79,582.15
BARRA DE CONTENCION Y DIRECCION - PISO 01 ML Luis L 1.00 650.00 650.00
10.02.03 PUERTAS CORTAFUEGO
PUERTA DE CORTAFUEGO - PC-01 - (F - 135) 1.00 X 2.10m ( Escalera Evac.) UND Miguel P 11.00 1,340.10 14,741.10
PUERTA DE CORTAFUEGO - PC-02 - (F - 120) 1.00 X 2.10m ( Escalera Evac.) UND Miguel P 10.00 1,340.10 13,401.00
PUERTA DE CORTAFUEGO - PC-03 - (F - 90) - Ducto Electrico UND Miguel P 10.00 4,863.71 48,637.13
PUERTA DE CORTAFUEGO - PC-04 - (F - 90) - Ducto Sanitario UND Miguel P 10.00 7,332.71 73,327.13
PUERTA DE CORTAFUEGO - PC-05 - (F - 90) - Ducto Sanitario UND Miguel P 18.00 2,431.84 43,773.08
PUERTA DE CORTAFUEGO - PC-06 - (F - 90) - Ducto Electrico UND Miguel P 18.00 2,469.00 44,442.00
PUERTA DE CORTAFUEGO - PC-07 - (F - 90) - Ducto Sanitario UND Miguel P 10.00 4,863.71 48,637.13
10.04 EQUIPAMIENTO -
10.04.01 ASCENSOR
VIGAS DIVISORIAS UND Miguel P 19.00 1,190.00 22,610.00
REJA DIVISORIA EN PIT UND Miguel P 1.00 1,920.00 1,920.00
ESCALERA DE GATO C/BARANDILLA DE SEGURIDAD - AZOTEA UND Miguel P 1.00 1,800.00 1,800.00
CANCAMOS DE IZAJE GLB Miguel P 6.00 368.00 2,208.00
CONTRATRAMPA UND Miguel P 2.00 1,820.00 3,640.00
10.04.02 SUB ESTACION ELECTRICA
TAPA METALICA (2.10 x 1.35) - INGRESO DE TRANSFORMADOR UND Miguel P 1.00 1,520.00 1,520.00
REJILLA METALICA (1.25 x 0.85) - INGRESO DE AIRE UND Miguel P 1.00 710.00 710.00
TAPA METALICA (1.65 x 0.95) - INGRESO DE EQUIPOS & VENTILACION UND Miguel P 1.00 1,050.00 1,050.00
TAPA METALICA (1.65 x 0.95) - INGRESO DE PERSONAL UND Miguel P 1.00 1,050.00 1,050.00
ESCALERA DE GATO UND Miguel P 1.00 2,720.00 2,720.00
CARPINTERIA INTERIOR GLB Miguel P 1.00 16,420.00 16,420.00
-
11 CARPINTERIA DE ALUMINIO - 1,305,986.41
11.01 SOTANOS -
11.01.01 MAMPARAS - Series 25. Cristal Templado 6mm
11.01.01.01 MAMPARAS - SERIE 25 - ALUMINIO NEGRO MATE- M-03 UND Miguel P 1.00 1,984.50 1,984.50
11.01.02 REJILLAS DE GAS
11.01.02.01 REJILLAS - ALUMINIO NEGRO MATE- R-01 UND Miguel P 20.00 218.63 4,372.50
11.02 TORRE - Departamentos y Areas Comunes -
11.02.01 VENTANAS - Serie 38.25, Vidrios Crudo de 4mm
11.02.01.01 VENTANAS - SERIE 25 - ALUMINIO NEGRO MATE- V-01 UND Miguel P 28.00 84.00 2,352.00
11.02.01.02 VENTANAS - SERIE 25 - ALUMINIO NEGRO MATE- V-01 B UND Miguel P 7.00 84.00 588.00
11.02.01.03 VENTANAS - SERIE 25 - ALUMINIO NEGRO MATE- V-03 UND Miguel P 1.00 471.24 471.24
11.02.02 MAMPARAS - Series 25. Cristal Templado 6mm
ITEM PARTIDA UND CANT P.U. PARCIAL TOTAL
SC MO ENCHAPE
Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02250201230001 CER GALA DIAMANTE BLANCO 46 X 46 - DECOR CENTER m2
SC MO ENCHAPE
Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02250201230001 ZÓCALO DE PORCELANATO BLANCO 45X45 m2
Partida 01.06.05 GRES PORCELÁNICO DALTILE PURE ORIGAMI MATE RECTIFICADO, ALTO RELIEVE 45x9
SC MO ENCHAPE
Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02250201230001 GRES PORCELÁNICO DALTILE PURE ORIGAMI MATE RECTIFICADO, ALTO RELIEVE m2
45x90
0263030005 CRUCETAS 2mm und
Partida 01.06.05 CERÁMICO EQUIPE METRO WHITE BRILLANTE, NO RECTIFICADO, BISCELADO 7.5x15
SC MO ENCHAPE
Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02250201230001 CERÁMICO EQUIPE METRO WHITE BRILLANTE, NO RECTIFICADO, BISCELADO m2
7.5x15
CERÁMICO EQUIPE METRO WHITE BRILLANTE, NO RECTIFICADO, BISCELADO
7.5x15
0263030005 CRUCETAS 2mm und
SC MO ENCHAPE
Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02250201230001 CERÁMICO ITAGRES KASSOS BIANCO MATE, RECTIFICADO 30.5X60.5 m2
Partida 01.06.05 BAÑO: CERÁMICO KLIPEN NEVADO BLANCO, MATE COLOR BLANCO
SC MO ENCHAPE
Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02250201230001 BAÑO: CERÁMICO KLIPEN NEVADO BLANCO, MATE COLOR BLANCO m2
SC MO ENCHAPE
Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02250201230001 PEPELMA x DEFINIR m2
SC MO ENCHAPE
Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02250201230001 PORCELANATO ALAPLANA VILEMA ROBLE 23X120 (FACHADAS) m2
SC MO ENCHAPE
Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02280500370038 PISO PORCELANATO GRAIMAN OAKLAND GREY m2
SC MO ENCHAPE
Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02280500400051 CONTRAZÓCALO DE MADERA TEÑIDO SIMILAR AL PROCELANATO GRAIMAN m2
OAKLAND GREY
0263030005 CRUCETAS 2mm und
SC MO ENCHAPE
Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02280500370038 PISO PORCELANATO GRAIMAN CIPRES WHITE m2
0263030005 CRUCETAS 2mm und
SC MO ENCHAPE
Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02280500400051 CONTRAZÓCALO DE MADERA TEÑIDO SIMILAR AL PORCELANATO GRAIMAN m2
CIPRES WHITE
0263030005 CRUCETAS 2mm und
SC MO ENCHAPE
Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02280500370038 PISO PORCELANATO ESMALTADO FILO BIANCO MATE m2
SC MO ENCHAPE
Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02280500370038 PISO PORCELANATO ESMALTADO TRAVERTINO NAVONA m2
SC MO ENCHAPE
Materiales
0213070001 FRAGUA kg
02220800010003 PEGAMENTO CELIMA BLANCO FLEXIBLE PORCELANATO X 25 Kg. * bol
02280500400051 CONTRAZÓCALO DE MADERA TEÑIDO SIMILAR AL PORCELANATO ESMALTADO m2
TRAVERTINO NAVONA
0263030005 CRUCETAS 2mm und
SUM
PUERTAS
PUERTA CONTRAPLACADA: P- 08 UND Miguel P 1.00 1,298.95
PUERTA CONTRAPLACADA: P- 09 UND Miguel P 3.00 537.14
PUERTA CONTRAPLACADA: P- 10 UND Miguel P 56.00 602.14
PUERTA CONTRAPLACADA: P- 11 UND Miguel P 4.00
PUERTA CONTRAPLACADA: P- 12 UND Miguel P 4.00
PUERTA CONTRAPLACADA: P- 13 UND Miguel P 5.00
PUERTA CONTRAPLACADA: P- 14 UND Miguel P 4.00
PUERTA CONTRAPLACADA: P- 14C Miguel P 1.00
PUERTA CONTRAPLACADA: P- 15 UND Miguel P 4.00
PUERTA CONTRAPLACADA: P- 16 UND Miguel P 2.00
PUERTA CONTRAPLACADA: P- 17 UND Miguel P 4.00
PUERTA CONTRAPLACADA: P- 18 UND Miguel P 2.00
PUERTA CONTRAPLACADA: P- 19 UND Miguel P 3.00
PUERTA CONTRAPLACADA: P- 20 UND Miguel P 2.00
PUERTA CONTRAPLACADA: P- 21 UND Miguel P 1.00
PUERTA CONTRAPLACADA: P- 22 UND Miguel P 1.00
PUERTA CONTRAPLACADA: P- 23 UND Miguel P 1.00
PUERTA CONTRAPLACADA: P- 25 UND Miguel P 1.00
PUERTA CONTRAPLACADA: P- 26 UND Miguel P 5.00
PUERTA CONTRAPLACADA: P- 27 UND Miguel P 1.00
PUERTA CONTRAPLACADA: P- 28 UND Miguel P 1.00
PUERTA CONTRAPLACADA: P- 29 UND Miguel P 1.00
PUERTA CONTRAPLACADA: P- 31 UND Miguel P 3.00
CERRAJERIA
BISAGRA PARA PUERTA DE MADERA - Interior UND Miguel P 492.00
CERRADURA P/ PUERTA DE MADERA - Interior UND Miguel P 110.00
MELAMINA - MUEBLES DE COCINA
DIVISION EN CAMERINO DE DAMAS GLB Miguel P 1.00
DIVISION EN CAMERINO DE VARONES GLB Miguel P 1.00
TORRE - Departamentos y Areas Comunes
PUERTAS
PUERTA CONTRAPLACADA: P- 01 UND Miguel P 128.00 874.48
PUERTA CONTRAPLACADA: P- 05 UND Miguel P 315.00 475.85
PUERTA CONTRAPLACADA: P- 06 UND Miguel P 363.00 540.85
PUERTA CONTRAPLACADA: P- 07 UND Miguel P 91.00 569.63
PUERTA DE MADERA APERSIANADA: P- 22A UND Miguel P 5.00
PUERTA DE MADERA APERSIANADA: P- 22B UND Miguel P 2.00
PUERTA DE MADERA APERSIANADA: P- 22C UND Miguel P 1.00
PUERTA DE MADERA APERSIANADA: P- 22D UND Miguel P 1.00
32.00
32.00
32.00
SCELADO 7.5x15
32.00
32.00
32.00
32.00
32.00
32.00
16.00
32.00
16.00
32.00
32.00
180 95 1,573.95
180 95 812.14
180 95 877.14
2,349.46 2,135.87
2,546.85 2,315.32
2,359.09 2,144.63
1,295.09 1,177.36
1,295.09 1,177.36
871.42 792.20
1,988.37 1,807.61
1,405.82 1,278.02
2,306.13 2,096.48
1,964.30 1,785.73
1,444.34 1,313.04
1,829.50 1,663.18
2,012.45 1,829.50
1,829.50 1,663.18
2,132.81 1,938.92
986.96 897.24
1,131.39 1,028.54
486.27 442.06
1,006.23 914.75
1,006.23 914.75
-
-
10,771.83 9,792.57
11,844.91 10,768.10
180 95 1,149.48
180 95 750.85
180 95 815.85
180 95 844.63
1,573.95 1,573.95 similar dimensiones
1,652.65
1,652.65
1,735.28
180 95 812.14
180 95 812.14
INSTALA BARR ANTICIERRA PUERTA
225 1,340.10 SI SI 1
-
-
225 1,340.10 SI SI 1
225 1,340.10 SI SI 1
450 4,863.71 NO NO 2
675 7,332.71 NO NO 3
225 2,431.84 NO NO 1
225 2,469.00 NO NO 1
450 4,863.71 NO NO 2
BER
BER
BER
BER
BER
SA 500 UND
C & V INVERSIONES INMOBILIARIAS
Cl. Narciso de la Colina N° 421, Of. 1401, Miraflores
www.cyvperu.com
HOJA DE PRESUPUESTO DETALLADO
OBRA: CONSTRUCCION DEL CONDOMINIO PORTOFINO
ESPECIALIDAD: INSTALACIONES ELECTRICAS
PROPIET. : PROPIA
LUGAR: Av. Santa Cruz 1550, Miraflores
FECHA: 20 de Enero del 2022
MONEDA: Nuevos Soles
07 PANELES SOLARES
INSTALACION Y SUMINISTRO PANALES SOLARES 0.00 52,366.88
07.01 (EQUIPAMIENTO) GLB 1.00 52,366.88 52,366.88
693975448.xlsx 09/26/2023
COSTO DEL PERSONAL
Salario Básico Gratificación Subtotal CTS Subtotal Impuestos Total Costo Mes Costo S/.
Mensual 12 1 No. 1 1 No. 2 9%+2%-CTS /11 1.00