ID Task Nombre de tarea Duration Start Finish Predecessors

14 Feb '22 21 Feb '22 28 Feb '22


Mode W T F S S M T W T F S S M T W T F
1 BALDONE 372 days? Tue 30/08/22Wed 31/01/24
2 ORDEN DE 61 days Tue Tue
COMPRA 30/08/22 22/11/22
(IMPORTACION
3 TORRE SUR 59 days Thu 21/07/22Tue 11/10/22
4 NIVEL 1 AL 20 32 days Thu 21/07/22Fri 2/09/22
14 TORRE NORTE 76 days Tue 30/08/22Tue 13/12/22
15 NIVEL 1 26 days Tue 30/08/22Tue 4/10/22
25 NIVEL 2 33 days Fri 2/09/22 Tue 18/10/22
35 NIVEL 3 40 days Wed 7/09/22Tue 1/11/22
45 NIVEL 4 47 days Mon 12/09/22Tue 15/11/22
55 NIVEL 5 54 days Thu 15/09/22Tue 29/11/22
65 NIVEL 6 61 days Tue 20/09/22Tue 13/12/22
75 PLANTA URBANA 30 days Tue 30/08/22Mon 10/10/22
76 NIVEL 1 30 days Tue 30/08/22Mon 10/10/22
77 TEMPLADOS 15 days Tue 30/08/22Mon 19/09/22
78 NIVEL 1 10 days Tue 30/08/22Mon 12/09/22
79 NIVEL 20 15 days Tue 30/08/22Mon 19/09/22
80 ROMPEVIENTOS 15 days? Thu 22/12/22Wed 11/01/23
81 INSTALACION 15 days Thu 22/12/22Wed 11/01/23

Tarea Tarea manual


División Sólo duración
Hito Informe de resumen manual
Resumen Resumen manual
Proyecto: BALDONE Resumen del proyecto Sólo el comienzo
Fecha: Tue 24/01/23
Tareas externas Sólo fin
Hito externo Fecha límite
Tarea inactiva Progreso
Hito inactivo Manual Progress
Resumen inactivo

Página 1