METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : MODULO 1 AULA

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD

OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES

LIMPIEZA, TRAZO Y REPLANTEO GENERAL

LIMPIEZA DE TERRENO MANUAL/ EQUIPO m2 84.09


1.00 1.00 10.85 7.75 84.09

TRAZO Y REPLANTEO

TRAZO Y REPLANTEO TOPOGRAFICO m2 84.09


1.00 1.00 10.85 7.75 84.09

ESTRUCTURAS

MOVIMIENTO DE TIERRAS

EXCAVACIONES

EXCAVACION DE ZANJAS Y ZAPATAS MANUAL m3 36.19


ZAPATAS
ZAPATA - 01 1.00 1.00 1.50 1.20 1.60 2.88
ZAPATA - 02 1.00 2.00 1.40 1.00 1.60 4.48
ZAPATA - 03 1.00 3.00 1.30 1.30 1.60 8.11
ZAPATA - 04 1.00 2.00 2.00 1.10 1.60 7.04
CIMIENTO CORRIDO + VIGA DE CIMENTACIÓN
EJE A-A ENTRE 2-3(CORTE 1 - 1) 1.00 1.00 3.12 0.50 1.00 1.56
EJE A-A ENTRE 1-2(CORTE 1 - 1) 1.00 1.00 2.97 0.50 1.00 1.49
EJE A-A ENTRE 1-2(CORTE 2-2) 1.00 1.00 0.80 0.50 1.00 0.40
EJE C-C ENTRE 2-3 (CORTE 3-3) 1.00 1.00 3.15 0.60 1.00 1.89
EJE C-C ENTRE 1-2 (CORTE 3-3) 1.00 1.00 3.50 0.60 1.00 2.10
EJE 1-1 ENTRE A-B (CORTE 5-5) 1.00 1.00 1.40 0.60 1.00 0.84
EJE 1-1 ENTRE B-C (CORTE 5-5) 1.00 1.00 1.15 0.60 1.00 0.69
EJE 3-3 ENTRE A-B (CORTE 4-4) 1.00 1.00 1.50 0.60 1.00 0.90
EJE 3-3 ENTRE B-C (CORTE 4-4) 1.00 1.00 1.15 0.60 1.00 0.69
CIMIENTO CORRIDO
EJE A-1 Y B-1 (DIVISION DE SSHH Y DEPOISTO) CORTE 6-6 1.00 2.00 1.36 0.60 0.65 1.06
EJE 3-1 (DIVISION DE SSHH Y DEPOSITO) CORTE 6-6 1.00 1.00 5.28 0.60 0.65 2.06

CORTES

CORTE DE TERRENO CON MAQUINARIA m3 88.29


MODULO DE 01 AULA (VER CORTE AB-AB) 1.00 1.00 1.05 84.09 88.29

RELLENOS

RELLENO CON MATERIAL DE PRÉSTAMO DE AFIRMADO m3 14.44


AULA + SS HH 1.00 1.00 0.20 59.97 11.99
VEREDA 1.00 1.00 10.85 1.50 0.15 2.44
METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : MODULO 1 AULA

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

RELLENO CON MATERIAL PROPIO PARA ZANJAS m3 13.47


ZAPATAS
ZAPATA - 01 1.00 1.00 1.50 0.48 1.00 0.71
ZAPATA - 01 1.00 2.00 0.78 0.48 1.00 0.74
ZAPATA - 02 1.00 4.00 1.40 0.38 1.00 2.10
ZAPATA - 03 1.00 3.00 1.30 0.53 1.00 2.05
ZAPATA - 03 1.00 3.00 1.05 0.53 1.00 1.65
ZAPATA - 04 1.00 2.00 2.00 0.43 1.00 1.70
ZAPATA - 04 1.00 2.00 1.75 0.43 1.00 1.49
CIMIENTO CORRIDO + VIGA DE CIMENTACIÓN
EJE A-A ENTRE 2-3(CORTE 1 - 1) 1.00 1.00 3.12 0.25 0.35 0.27
EJE A-A ENTRE 1-2(CORTE 1 - 1) 1.00 1.00 2.97 0.25 0.35 0.26
EJE A-A ENTRE 1-2(CORTE 2-2) 1.00 1.00 0.80 0.25 0.35 0.07
EJE C-C ENTRE 2-3 (CORTE 3-3) 1.00 1.00 3.15 0.35 0.35 0.39
EJE C-C ENTRE 1-2 (CORTE 3-3) 1.00 1.00 3.50 0.35 0.35 0.43
EJE 1-1 ENTRE A-B (CORTE 5-5) 1.00 1.00 1.40 0.35 0.35 0.17
EJE 1-1 ENTRE B-C (CORTE 5-5) 1.00 1.00 1.15 0.35 0.35 0.14
EJE 3-3 ENTRE A-B (CORTE 4-4) 1.00 1.00 1.50 0.35 0.35 0.18
EJE 3-3 ENTRE B-C (CORTE 4-4) 1.00 1.00 1.15 0.35 0.35 0.14
CIMIENTO CORRIDO
EJE A-1 Y B-1 (DIVISION DE SSHH Y DEPOISTO) CORTE 6-6 1.00 2.00 1.36 0.35 0.35 0.33
EJE 3-1 (DIVISION DE SSHH Y DEPOSITO) CORTE 6-6 1.00 1.00 5.28 0.35 0.35 0.65

ELIMINACION DE EXCAVACIONES

ACARREO INTERNO DE MATERIAL PROCEDENTE DE DEMOLICIONES Y


m3 138.76
EXCAVACIONES
1.00 1.00 111.01 1.25 138.76

ELIMINACION DEMATERIAL EXCEDENTE PROCEDENTE DE DEMOLICION


m3 138.76
Y EXCAVACIONES

1.00 1.00 138.76 138.76

NIVELACION INTERIOR Y COMPACTADO

NIVELACION INTERIOR Y COMPACTADO m2 76.25


AULAS + SS.HH. 1.00 1.00 59.97 59.97
VEREDAS 1.00 1.00 10.85 1.50 16.28

CONCRETO SIMPLE

FALSOS CIMIENTOS

SOLADOS

SOLADO PARA CIMIENTOS Y ZAPATAS: CONCRETO C:H 1:12 e=4".. m2 14.07


ZAPATAS
ZAPATA - 01 1.00 1.00 1.50 1.20 1.80
ZAPATA - 02 1.00 2.00 1.40 1.00 2.80
ZAPATA - 03 1.00 3.00 1.30 1.30 5.07
ZAPATA - 04 1.00 2.00 2.00 1.10 4.40

FALSA CIMENTACION: CONCRETO C:H 1:12 . m3 4.26


CIMIENTO CORRIDO +VIGA DE CIMENTACIÓN
EJE A-A ENTRE 2-3(CORTE 1 - 1) 1.00 1.00 4.45 0.50 0.20 0.45
EJE A-A ENTRE 1-2(CORTE 1 - 1) 1.00 1.00 3.55 0.50 0.20 0.36
EJE A-A ENTRE 1-2(CORTE 2-2) 1.00 1.00 1.20 0.50 0.20 0.12
EJE C-C ENTRE 2-3 (CORTE 3-3) 1.00 1.00 4.45 0.60 0.20 0.53
EJE C-C ENTRE 1-2 (CORTE 3-3) 1.00 1.00 4.45 0.60 0.20 0.53
EJE 1-1 ENTRE A-B (CORTE 5-5) 1.00 1.00 2.35 0.60 0.20 0.28
EJE 1-1 ENTRE B-C (CORTE 5-5) 1.00 1.00 2.35 0.60 0.20 0.28
EJE 3-3 ENTRE A-B (CORTE 4-4) 1.00 1.00 2.35 0.60 0.20 0.28
EJE 3-3 ENTRE B-C (CORTE 4-4) 1.00 1.00 2.35 0.60 0.20 0.28
CIMIENTO CORRIDO
EJE A-1 Y B-1 (DIVISION DE SSHH Y DEPOISTO) CORTE 6-6 1.00 2.00 1.90 0.60 0.20 0.46
EJE 3-1 (DIVISION DE SSHH Y DEPOSITO) CORTE 6-6 1.00 1.00 5.75 0.60 0.20 0.69
METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : MODULO 1 AULA

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

CIMIENTOS CORRIDOS

CIMIENTO CORRIDO: CONCRETO C:H 1:10+30% P.G. m3 11.79


CIMIENTO CORRIDO +VIGA DE CIMENTACIÓN
EJE A-A ENTRE 2-3(CORTE 1 - 1) 1.00 1.00 4.45 0.50 0.50 1.11
EJE A-A ENTRE 1-2(CORTE 1 - 1) 1.00 1.00 3.55 0.50 0.50 0.89
EJE A-A ENTRE 1-2(CORTE 2-2) 1.00 1.00 1.20 0.50 0.50 0.30
EJE C-C ENTRE 2-3 (CORTE 3-3) 1.00 1.00 4.45 0.60 0.50 1.34
EJE C-C ENTRE 1-2 (CORTE 3-3) 1.00 1.00 4.45 0.60 0.50 1.34
EJE 1-1 ENTRE A-B (CORTE 5-5) 1.00 1.00 2.35 0.60 0.60 0.85
EJE 1-1 ENTRE B-C (CORTE 5-5) 1.00 1.00 2.35 0.60 0.60 0.85
EJE 3-3 ENTRE A-B (CORTE 4-4) 1.00 1.00 2.35 0.60 0.60 0.85
EJE 3-3 ENTRE B-C (CORTE 4-4) 1.00 1.00 2.35 0.60 0.60 0.85
CIMIENTO CORRIDO
EJE A-1 Y B-1 (DIVISION DE SSHH Y DEPOISTO) CORTE 6-6 1.00 2.00 1.90 0.60 0.60 1.37
EJE 3-1 (DIVISION DE SSHH Y DEPOSITO) CORTE 6-6 1.00 1.00 5.75 0.60 0.60 2.07

SOBRECIMIENTOS

SOBRECIMIENTO: CONCRETO C:H 1:8+25% P.M. m3 1.65


SOBRECIMIENTO E=0.25
EJE A-A ENTRE 2-3(CORTE 1 - 1) 1.00 1.00 4.10 0.15 0.30 0.18
EJE A-A ENTRE 1-2(CORTE 1 - 1) 1.00 1.00 2.18 0.15 0.30 0.10
EJE A-A ENTRE 1-2(CORTE 2-2) 1.00 1.00 0.90 0.15 0.30 0.04
EJE C-C ENTRE 2-3 (CORTE 3-3) 1.00 1.00 3.96 0.15 0.30 0.18
EJE C-C ENTRE 1-2 (CORTE 3-3) 1.00 1.00 4.10 0.15 0.30 0.18
EJE 1-1 ENTRE A-B (CORTE 5-5) 1.00 1.00 2.32 0.25 0.30 0.17
EJE 1-1 ENTRE B-C (CORTE 5-5) 1.00 1.00 2.32 0.25 0.30 0.17
EJE 3-3 ENTRE A-B (CORTE 4-4) 1.00 1.00 2.17 0.25 0.30 0.16
EJE 3-3 ENTRE B-C (CORTE 4-4) 1.00 1.00 2.17 0.25 0.30 0.16
SOBRECIMEINTO E=0.15
EJE A-1 Y B-1 (DIVISION DE SSHH Y DEPOISTO) CORTE 6-6 1.00 2.00 1.90 0.15 0.30 0.17
EJE 3-1 (DIVISION DE SSHH Y DEPOSITO) CORTE 6-6 1.00 1.00 2.61 0.15 0.30 0.12

ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTOS m2 17.24


SOBRECIMIENTO E=0.25
EJE A-A ENTRE 2-3(CORTE 1 - 1) 1.00 2.00 4.10 0.30 2.46
EJE A-A ENTRE 1-2(CORTE 1 - 1) 1.00 2.00 2.18 0.30 1.31
EJE A-A ENTRE 1-2(CORTE 2-2) 1.00 2.00 0.90 0.30 0.54
EJE C-C ENTRE 2-3 (CORTE 3-3) 1.00 2.00 3.96 0.30 2.38
EJE C-C ENTRE 1-2 (CORTE 3-3) 1.00 2.00 4.10 0.30 2.46
EJE 1-1 ENTRE A-B (CORTE 5-5) 1.00 2.00 2.32 0.30 1.39
EJE 1-1 ENTRE B-C (CORTE 5-5) 1.00 2.00 2.32 0.30 1.39
EJE 3-3 ENTRE A-B (CORTE 4-4) 1.00 2.00 2.17 0.30 1.30
EJE 3-3 ENTRE B-C (CORTE 4-4) 1.00 2.00 2.17 0.30 1.30
SOBRECIMEINTO E=0.15
EJE A-1 Y B-1 (DIVISION DE SSHH Y DEPOISTO) CORTE 6-6 1.00 2.00 1.90 0.30 1.14
EJE 3-1 (DIVISION DE SSHH Y DEPOSITO) CORTE 6-6 1.00 2.00 2.61 0.30 1.57

DADOS DE CONCRETO

DADOS DE CONCRETO F`c = 175kg/cm2 m2 0.05


1.00 130.00 0.08 0.08 0.08 0.05

ENCOFRADO Y DESENCOFRADO DE DADOS DE CONCRETO m2 3.66


1.00 130.00 0.38 0.08 3.66

FALSO PISO

FALSO PISO DE 4" DE CONCRETO 1:10 m2 58.66


AULA 6 1.00 1.00 47.98 47.98
SS.HH. 1.00 2.00 2.95 5.90
DEPOSITO 1.00 1.00 4.78 4.78
METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : MODULO 1 AULA

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

CONCRETO ARMADO

ZAPATAS

CONCRETO f'c= 210 kg/cm2 EN ZAPATAS m3 7.04


Zapata - 01 1.00 1.00 1.50 1.20 0.50 0.90
Zapata - 02 1.00 2.00 1.40 1.00 0.50 1.40
Zapata - 03 1.00 3.00 1.30 1.30 0.50 2.54
Zapata - 04 1.00 2.00 2.00 1.10 0.50 2.20

ENCOFRADO Y DESENCOFRADO EN ZAPATAS m3 25.80


Zapata - 01 1.00 1.00 5.40 0.60 3.24
Zapata - 02 1.00 2.00 4.80 0.60 5.76
Zapata - 03 1.00 3.00 5.20 0.60 9.36
Zapata - 04 1.00 2.00 6.20 0.60 7.44

ACERO ESTRUCTURAL TRABAJADO PARA ZAPATAS kg Long. #varillas Coef. 194.04


Z - 01 1/2" 1.00 1.00 1.45 7.00 0.99 10.05
1/2" 1.00 1.00 1.15 9.00 0.99 10.25
Z - 02 1/2" 1.00 2.00 1.35 6.00 0.99 16.04
1/2" 1.00 2.00 0.95 9.00 0.99 16.93
Z - 03 1/2" 1.00 3.00 1.25 7.00 0.99 25.99
1/2" 1.00 3.00 1.25 13.00 0.99 48.26
Z - 04 1/2" 1.00 2.00 1.95 7.00 0.99 27.03
1/2" 1.00 2.00 1.05 19.00 0.99 39.50

VIGA DE CIMENTACION

CONCRETO f'c=210 kg/cm2 PARA VIGAS DE CIMENTACION m3 3.44


EJE A-A ENTRE 2-3(CORTE 1 - 1) 1.00 1.00 4.45 0.25 0.50 0.56
EJE A-A ENTRE 1-2(CORTE 1 - 1) 1.00 1.00 3.55 0.25 0.50 0.44
EJE A-A ENTRE 1-2(CORTE 2-2) 1.00 1.00 1.20 0.25 0.50 0.15
EJE C-C ENTRE 2-3 (CORTE 3-3) 1.00 1.00 4.45 0.25 0.50 0.56
EJE C-C ENTRE 1-2 (CORTE 3-3) 1.00 1.00 4.45 0.25 0.50 0.56
EJE 1-1 ENTRE A-B (CORTE 5-5) 1.00 1.00 2.35 0.25 0.50 0.29
EJE 1-1 ENTRE B-C (CORTE 5-5) 1.00 1.00 2.35 0.25 0.50 0.29
EJE 3-3 ENTRE A-B (CORTE 4-4) 1.00 1.00 2.35 0.25 0.50 0.29
EJE 3-3 ENTRE B-C (CORTE 4-4) 1.00 1.00 2.35 0.25 0.50 0.29

ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACION m2 27.50


EJE A-A ENTRE 2-3(CORTE 1 - 1) 1.00 2.00 4.45 0.50 4.45
EJE A-A ENTRE 1-2(CORTE 1 - 1) 1.00 2.00 3.55 0.50 3.55
EJE A-A ENTRE 1-2(CORTE 2-2) 1.00 2.00 1.20 0.50 1.20
EJE C-C ENTRE 2-3 (CORTE 3-3) 1.00 2.00 4.45 0.50 4.45
EJE C-C ENTRE 1-2 (CORTE 3-3) 1.00 2.00 4.45 0.50 4.45
EJE 1-1 ENTRE A-B (CORTE 5-5) 1.00 2.00 2.35 0.50 2.35
EJE 1-1 ENTRE B-C (CORTE 5-5) 1.00 2.00 2.35 0.50 2.35
EJE 3-3 ENTRE A-B (CORTE 4-4) 1.00 2.00 2.35 0.50 2.35
EJE 3-3 ENTRE B-C (CORTE 4-4) 1.00 2.00 2.35 0.50 2.35

ACERO CORRUGADO FY=4200 KG/CM2 PARA VIGAS DE CIMENTACION kg


3
N° DE N° DE LONGITUD POR /
VIGA DE CIMENTACION UNIDAD Ø 1/4" 3/8" 1/2" 5/8"
ELEMENTOS PIEZAS PIEZA(M) 4
"
Kg 0.25 0.56 0.99 1.56 ###
MODULO 01 AULA
EJE A-A: BARRAS LONGITUDINALES 1/2 1.00 6.00 11.45 68.01
EJE A-A: ESTRIBOS 3/8 1.00 58.00 1.45 47.10
EJE C-C: BARRAS LONGITUDINALES 1/2 1.00 6.00 11.45 68.01
EJE C-C: ESTRIBOS 3/8 1.00 58.00 1.45 47.10
EJE 1-1: BARRAS LONGITUDINALES 1/2 1.00 6.00 6.25 37.13
EJE 1-1: ESTRIBOS 3/8 1.00 36.00 1.45 29.23
EJE 3-3: BARRAS LONGIDUTINALES 1/2 1.00 6.00 6.25 37.13
EJE 3-3: ESTRIBOS 3/8 1.00 36.00 1.45 29.23
METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : MODULO 1 AULA

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

COLUMNAS

CONCRETO EN COLUMNAS f'c=210 kg/cm2 CARAVISTA m3 10.23


ENTRE EL EJE 1-1 Y EL EJE a-a (C - 01) 1.00 1.00 0.25 0.55 5.95 0.82
ENTRE EL EJE B-B Y EL EJE 3-3 (C-02) 1.00 1.00 0.25 0.50 6.55 0.82
ENTRE EL EJE B-B Y EL EJE 1-1 (C-02) 1.00 1.00 0.25 0.50 6.55 0.82
ENTRE EL EJE A-A Y EL EJE 3-3 (C-03) 1.00 1.00 0.85 0.25 5.95 1.26
ENTRE EL EJE C-C, EL EJE 3-3, Y EL EJE 1-1(C-03) 1.00 2.00 0.85 0.25 7.20 3.06
ENTRE EL EJE A-A Y EL EJE 2-2 (C-04) 1.00 1.00 1.05 0.25 5.95 1.56
ENTRE EL EJE C-C Y EL EJE 2-2 (C-04) 1.00 1.00 1.05 0.25 7.20 1.89

ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS CARAVISTA m2 Perímetro 108.13


ENTRE EL EJE 1-1 Y EL EJE a-a (C - 01) 1.00 1.00 1.60 5.95 9.52
ENTRE EL EJE B-B Y EL EJE 3-3 (C-02) 1.00 1.00 1.50 6.55 9.83
ENTRE EL EJE B-B Y EL EJE 1-1 (C-02) 1.00 1.00 1.50 6.55 9.83
ENTRE EL EJE A-A Y EL EJE 3-3 (C-03) 1.00 1.00 2.20 5.95 13.09
ENTRE EL EJE C-C, EL EJE 3-3, Y EL EJE 1-1(C-03) 1.00 2.00 2.20 7.20 31.68
ENTRE EL EJE A-A Y EL EJE 2-2 (C-04) 1.00 1.00 2.60 5.95 15.47
ENTRE EL EJE C-C Y EL EJE 2-2 (C-04) 1.00 1.00 2.60 7.20 18.72

ACERO CORRUGADO FY=4200 KG/CM2 PARA COLUMNAS kg


3
N° DE N° DE LONGITUD POR /
COLUMNAS UNIDAD Ø 1/4" 3/8" 1/2" 5/8"
ELEMENTOS PIEZAS PIEZA(M) 4
"
0.25 0.56 0.99 1.56 ###
MODULO 01 AULA
(C - 01) - ACERO LONGITUDINAL 5/8 1.00 2.00 6.45 20.12
(C - 01) - ACERO LONGITUDINAL 1/2 1.00 2.00 6.45 12.77
EN ESTRIBOS 3/8 1.00 53.00 1.64 48.68

(C - 02) - ACERO LONGITUDINAL 5/8 2.00 2.00 7.05 43.99


(C - 02) - ACERO LONGITUDINAL 1/2 2.00 2.00 7.05 27.92
EN ESTRIBOS 3/8 2.00 73.00 1.54 125.91

(C - 03) - ACERO LONGITUDINAL 5/8 1.00 8.00 6.45 80.50


(C - 03) - ACERO LONGITUDINAL 1/2 1.00 4.00 6.45 25.54
EN ESTRIBOS 3/8 2.00 55.00 3.08 189.73

(C - 03) - ACERO LONGITUDINAL 5/8 2.00 8.00 7.70 192.19


(C - 03) - ACERO LONGITUDINAL 1/2 2.00 4.00 7.70 60.98
EN ESTRIBOS 3/8 4.00 85.00 3.08 586.43

(C - 04) - ACERO LONGITUDINAL 5/8 1.00 8.00 6.45 80.50


(C - 04) - ACERO LONGITUDINAL 1/2 1.00 6.00 6.45 38.31
EN ESTRIBOS 3/8 1.00 62.00 3.68 127.77

(C - 04) - ACERO LONGITUDINAL 5/8 1.00 8.00 7.05 87.98


(C - 04) - ACERO LONGITUDINAL 1/2 1.00 4.00 7.05 27.92
EN ESTRIBOS 3/8 1.00 85.00 3.68 175.17

COLUMNETAS

CONCRETO F'C=175 KG/CM2 EN COLUMNETAS m3 1.42


EJE A-A TIPO C-A-1 1.00 6.00 0.25 0.15 1.70 0.38
EJE C-C TIPO C-A-1 1.00 5.00 0.25 0.15 2.30 0.43
EJE 3-3TIPO C-A-1 1.00 2.00 0.25 0.15 3.25 0.24
EJE 3-1 TIPO C-A 1.00 5.00 0.15 0.15 3.25 0.37

ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNETAS m2 25.64


EJE A-A TIPO C-A-1 1.00 6.00 0.65 1.70 6.63
EJE C-C TIPO C-A-1 1.00 5.00 0.65 2.30 7.48
EJE 3-3TIPO C-A-1 1.00 2.00 0.65 3.25 4.23
EJE 3-1 TIPO C-A 1.00 5.00 0.45 3.25 7.31
METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : MODULO 1 AULA

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 en COLUMNETAS kg


3
N° DE N° DE LONGITUD POR /
COLUMNETAS UNIDAD Ø 1/4" 3/8" 1/2" 5/8"
ELEMENTOS PIEZAS PIEZA(M) 4
"
0.25 0.56 0.99 1.56 ###
MODULO 1 AULA
EJE A-A TIPO C-A-1 3/8 6.00 6.00 2.35 47.38
estribos 1/4 6.00 12.00 0.76 13.68
EJE C-C TIPO C-A-1 3/8 5.00 6.00 2.95 49.56
estribos 1/4 5.00 16.00 0.76 15.20
EJE 3-3TIPO C-A-1 3/8 2.00 6.00 3.90 26.21
estribos 1/4 2.00 21.00 0.76 7.98
EJE 3-1 TIPO C-A 3/8 5.00 4.00 3.90 43.68
estribos 1/4 5.00 21.00 0.56 14.70

VIGAS

CONCRETO F'C=210 KG/CM2 EN VIGAS CARAVISTA m3 6.45


VP - 101 (0.30x0.50)
EJE 2-2 ENTRE A-C 1.00 1.00 5.49 0.25 0.50 0.69
VP - 4(0.25x0.40)
EJE A-A ENTRE 1-2 1.00 1.00 4.45 0.25 0.40 0.45
EJE A-A ENTRE 2-3 1.00 1.00 4.45 0.25 0.40 0.45
EJE C-C ENTRE 1-2 1.00 2.00 4.45 0.25 0.40 0.89
EJE C-C ENTRE 2-3 1.00 2.00 4.45 0.25 0.40 0.89
EJE 3-3 1.00 2.00 2.33 0.25 0.40 0.47
EJE 1-1 1.00 2.00 2.33 0.25 0.40 0.47
VS - 2 (0.25x0.40)
EJE 3-3 1.00 2.00 2.38 0.25 0.40 0.48
EJE 1-1 1.00 2.00 2.38 0.25 0.40 0.48
VP-3 (0.25xVAR.)
EJE 1-1 1.00 1.00 1.45 0.25 0.50 0.18
EJE 2-2 1.00 1.00 1.45 0.25 0.50 0.18
VP-5 (0.15X0.40)
ENTRE 1-2 1.00 1.00 5.00 0.15 0.60 0.45
ENTR 2-3 1.00 1.00 4.45 0.15 0.60 0.40

ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 58.51


VP - 101 (0.30x0.60)
EJE 2-2 ENTRE A-C 1.00 1.00 5.49 1.25 6.86
VP - 4(0.25x0.40)
EJE A-A ENTRE 1-2 1.00 2.00 4.45 0.40 3.56
EJE A-A ENTRE 2-3 1.00 2.00 4.45 0.40 3.56
EJE C-C ENTRE 1-2 1.00 4.00 4.45 0.40 7.12
EJE C-C ENTRE 2-3 1.00 4.00 4.45 0.40 7.12
EJE 3-3 1.00 4.00 2.33 0.40 3.73
EJE 1-1 1.00 4.00 2.33 0.40 3.73
VS - 2 (0.25x0.40)
EJE 3-3 1.00 4.00 2.38 0.40 3.81
EJE 1-1 1.00 4.00 2.38 0.40 3.81
VP-3 (0.25xVAR.)
EJE 1-1 1.00 2.00 1.45 0.75 2.18
EJE 2-2 1.00 2.00 1.45 0.75 2.18
VP-5 (0.15X0.40)
ENTRE 1-2 1.00 1.00 5.00 1.15 5.75
ENTR 2-3 1.00 1.00 4.45 1.15 5.12
METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : MODULO 1 AULA

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

ACERO CORRUGADO fy=4200 kg/cm2 PARA VIGAS kg


3
N° DE N° DE LONGITUD POR /
VIGAS UNIDAD Ø 1/4" 3/8" 1/2" 5/8"
ELEMENTOS PIEZAS PIEZA(M) 4
"
0.25 0.56 0.99 1.56 ###
MODULO 01 AULA
EJE 2-2 VP1 (0.25X0.50) Y VP-3 (0.25XVAR.)
ACERO LONGITUDINAL 5/8 1.00 2.00 8.43 26.30
5/8 1.00 2.00 7.46 23.28
5/8 1.00 1.00 3.00 4.68
5/8 1.00 2.00 2.62 8.17
ESTRIBOS DE A-C 3/8 1.00 37.00 1.38 28.59
ESTRIBOS ALERO 3/8 2.00 10.00 1.88 21.06
EJE A-A VP-4 (0.25X0.40)
ACERO LONGITUDINAL 5/8 1.00 4.00 11.25 70.20
5/8 1.00 1.00 2.85 4.45
ESTRIBOS DE 1-2 3/8 1.00 32.00 1.18 21.15
ESTRIBOS DE2-3 3/8 1.00 32.00 1.18 21.15
EJE c-c VP-4 (0.25X0.40)
ACERO LONGITUDINAL 5/8 2.00 4.00 11.25 140.40
ACERO LONGITUDINAL 5/8 2.00 1.00 2.85 8.89
ESTRIBOS 1-2 3/8 2.00 32.00 1.18 42.29
ESTRIBOS 2-3 3/8 2.00 32.00 1.18 42.29
EJES 1-1Y 3-3 (VP-4 0.25X0.40)
ACERO LONGITUDINAL 5/8 2.00 4.00 6.63 82.74
ESTRIBOS B-C 3/8 2.00 12.00 1.18 15.86
ESTRIBOS B-A 3/8 2.00 12.00 1.18 15.86
EJES 1-1 (VS-2 0.25X0.40) Y VP-3 (0.25XVAR.)
ACERO LONGITUDINAL 5/8 1.00 2.00 8.43 26.30
ACERO LONGITUDINAL 5/8 1.00 2.00 7.91 24.68
ESTRIBOS A-B Y B-C 3/8 1.00 24.00 1.18 15.86
ESTRIBOS EN ALERO 3/8 1.00 10.00 1.88 10.53
EJES 1-1 (VS-2 0.25X0.40)
ACERO LONGITUDINAL 5/8 1.00 4.00 6.76 42.18
ESTRIBOS A-B Y B-C 3/8 1.00 24.00 1.18 15.86
VIGA VP-5 Y DRENAJE FLUVIAL
ACERO LONGITUDINAL 1/2 1.00 4.00 11.25 44.55
ESTRIBOS 3/8 1.00 65.00 0.98 35.67
LONGITUDINAL DRENAJE PLUVIAL 3/8 1.00 4.00 11.25 25.20
TRANSVERSAL 3/8 1.00 55.00 0.50 15.40

VIGAS DE AMARRE

CONCRETO F'C=175 KG/CM2 EN VIGAS DE AMARRE m3 0.66


V-A
EJE A-A TRAMO 2-3 1.00 1.00 1.27 0.13 0.25 0.04
1.00 1.00 2.38 0.13 0.25 0.08
EJE A-A TRAMO 1-2 1.00 1.00 2.23 0.13 0.25 0.07
1.00 1.00 0.55 0.13 0.25 0.02
EJE C-C TRAMO 2-3 1.00 1.00 1.26 0.13 0.25 0.04
1.00 1.00 2.40 0.13 0.25 0.08
EJE C-C TRAMO 1-2 1.00 1.00 3.89 0.13 0.25 0.13
EJE A-1 Y EJE B-1 1.00 2.00 1.89 0.13 0.25 0.12
EJE 3-1 1.00 1.00 0.38 0.13 0.25 0.01
1.00 1.00 1.68 0.13 0.25 0.05
1.00 1.00 0.55 0.13 0.25 0.02
METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : MODULO 1 AULA

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE AMARRE m2 9.24


V-A
EJE A-A TRAMO 2-3 1.00 1.00 1.27 0.50 0.64
1.00 1.00 2.38 0.50 1.19
EJE A-A TRAMO 1-2 1.00 1.00 2.23 0.50 1.12
1.00 1.00 0.55 0.50 0.28
EJE C-C TRAMO 2-3 1.00 1.00 1.26 0.50 0.63
1.00 1.00 2.40 0.50 1.20
EJE C-C TRAMO 1-2 1.00 1.00 3.89 0.50 1.95
EJE A-1 Y EJE B-1 1.00 1.00 1.89 0.50 0.95
EJE 3-1 1.00 1.00 0.38 0.50 0.19
1.00 1.00 1.68 0.50 0.84
1.00 1.00 0.55 0.50 0.28

ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 en VIGAS DE AMARRE kg


3
N° DE N° DE LONGITUD POR /
VIGAS DE AMARRE UNIDAD Ø 1/4" 3/8" 1/2" 5/8"
ELEMENTOS PIEZAS PIEZA(M) 4
"
0.25 0.56 0.99 1.56 ###
MODULO DE 01 AULA
EJE A-A TRAMO 2-3 1/2 1.00 2.00 4.70 9.31
estribos (S) 1/4 1.00 29.00 0.28 2.01
EJE A-A TRAMO 1-2 1/2 1.00 2.00 3.83 7.58
estribos 1/4 1.00 26.00 0.28 1.80
EJE C-C TRAMO 2-3 1/2 1.00 2.00 4.71 9.33
estribos 1/4 1.00 29.00 0.28 2.01
EJE C-C TRAMO 1-2 1/2 1.00 2.00 4.70 9.31
estribos 1/4 1.00 25.00 0.28 1.73
EJE A-1 Y EJE B-1 1/2 2.00 2.00 2.60 10.30
estribos 1/4 2.00 14.00 0.28 1.94
EJE 3-1 1/2 1.00 2.00 4.61 9.13
estribos 1/4 1.00 21.00 0.28 1.45

LOSAS ALIGERADAS

CONCRETO EN LOSA ALIGERADA f'c=210 kg/cm2 m3 5.72


Entre los ejes 1-2 con los ejes A-B 1.00 1.00 5.75 5.05 0.09 2.54
Entre los ejes 2-3 con los ejes A-B 1.00 1.00 5.75 5.05 0.09 2.54
ALERO entre los ejes 1-2 1.00 1.00 5.05 1.45 0.09 0.64

ENCOFRADO Y DESENCOFRADO PARA LOSAS ALIGERADAS m2 65.40


Entre los ejes 1-2 con los ejes A-B 1.00 1.00 5.75 5.05 29.04
Entre los ejes 2-3 con los ejes A-B 1.00 1.00 5.75 5.05 29.04
ALERO entre los ejes 1-2 1.00 1.00 5.05 1.45 7.32

ACERO CORRUGADO FY=4200 KG/CM2 PARA LOSA ALIGERADA kg


5
N° DE LONGITUD
DETALLE DE /
LOSA ALIGERADA UNIDAD Ø ELEMENT N° DE PIEZAS POR 1/4" 3/8" 1/2"
ACEROS 8
OS PIEZA(M)
"
0.25 0.56 0.99 ###
PABELLON A
Entre los ejes 1-2 y los EJES A-C (Incluye ALERO) ACERO DE REFUERZO
ACERO + (inc.traslape)
1/2 1.00 12.00 7.70 91.48
ACERO - 1/2 1.00 12.00 4.15 49.30
ACERO - 1/2 1.00 12.00 3.90 46.33
ACERO - 1/2 1.00 12.00 1.35 16.04
ACERO - 3/8 1.00 12.00 3.25 21.84
Entre los ejes 2-3 y ejes A-C ACERO DE REFUERZO
ACERO + (inc.traslape)
1/2 1.00 12.00 6.10 72.47
ACERO - 1/2 1.00 12.00 4.15 49.30
ACERO - 1/2 1.00 12.00 1.35 16.04
ACERO - 1/2 1.00 12.00 1.35 16.04
ACERO - 3/8 1.00 12.00 3.25 21.84
ACERO DE TEMPERATURA
Entre los ejes 1-2 y los ejes A-C ACERO LONGITUDINAL
1/4 1.00 21.00 5.45 28.61
Entre los ejes 2-3 y los ejes A-C ACERO LONGITUDINAL
1/4 1.00 21.00 5.45 28.61
Entre los ejes 1-2 (ALERO) ACERO LONGITUDINAL
1/4 1.00 6.00 5.45 8.18
METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : MODULO 1 AULA

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

LADRILLO ARCILLA PARA TECHO 15X30X30 CM Unid. 545.00


Entre los ejes 1-2 con los ejes A-B 1.00 1.00 5.75 5.05 8.33 242.00
Entre los ejes 2-3 con los ejes A-B 1.00 1.00 5.75 5.05 8.33 242.00
ALERO entre los ejes 1-2 1.00 1.00 5.05 1.45 8.33 61.00

ESTRUCTURA DE MADERA Y COBERTURA

CORREAS DE MADERA TORNILLO DE 2"X1" m3 80.30


Modulo de 01 Aula 1.00 7.00 10.85 75.95
1.00 1.00 4.35 4.35

COBERTURA DE FIBRO CEMENTO m2 75.97


Modulo de 01 Aula 1.00 1.00 10.85 6.40 69.44
0 1.00 1.00 4.35 1.50 6.53
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO 2 AULAS

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD

OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES

LIMPIEZA, TRAZO Y REPLANTEO GENERAL

LIMPIEZA DE TERRENO MANUAL/ EQUIPO m2 167.31


PABELLON 2 1.00 1.00 21.45 7.80 167.31

TRAZO Y REPLANTEO

TRAZO Y REPLANTEO TOPOGRAFICO m2 167.31


PABELLON 2 1.00 1.00 21.45 7.80 167.31

ESTRUCTURA
MOVIMIENTO DE TIERRA
EXCAVACIONES
EXCAVACION DE ZANJAS Y ZAPATAS MANUAL 76.38
CIMIENTO CORRIDO + VIGA DE CIMENTACIÓN
EJE A-A ENTRE 1-2 y 3-4(CORTE 1 - 1) m3 1.00 2.00 2.98 0.50 1.00 2.98
EJE A-A ENTRE 2-3 y 4-5(CORTE 1 - 1) m3 1.00 2.00 3.34 0.50 1.00 3.34
EJE A-A ENTRE 1-2 y 3-4(CORTE 2-2) m3 1.00 2.00 0.70 0.50 1.00 0.70
EJE C-C ENTRE 1-2 y 2-3 (CORTE 3-3) m3 1.00 2.00 3.35 0.60 1.00 4.02
EJE C-C ENTRE 2-3 y 4-5 (CORTE 3-3) m3 1.00 2.00 3.33 0.60 1.00 4.00
EJE 1-1 y EJE 5-5 ENTRE A-B (CORTE 4-4) m3 1.00 2.00 1.40 0.65 1.00 1.82
EJE 1-1 Y EJE 5-5 ENTRE B-C (CORTE 4-4) m3 1.00 2.00 0.85 0.65 1.00 1.11
EJE 3-3 ENTRE A-B (CORTE 5-5) m3 1.00 1.00 1.35 0.75 1.00 1.01
EJE 3-3 ENTRE B-C (CORTE 5-5) m3 1.00 1.00 1.23 0.75 1.00 0.92
CIMIENTO CORRIDO
EJE A-1 Y B-1 (DIVISION DE SSHH Y DEPOISTO) CORTE 6-6 m3 1.00 4.00 1.51 0.60 1.00 3.62
EJE 3-1 (DIVISION DE SSHH Y DEPOSITO) CORTE 6-6 m3 1.00 2.00 5.28 0.60 1.00 6.34
ZAPATAS
Z1 m3 1.00 1.00 1.20 1.50 1.60 2.88
Z2 m3 1.00 3.00 1.20 1.40 1.60 8.06
Z3 m3 1.00 4.00 1.60 1.60 1.60 16.38
Z4 m3 1.00 5.00 1.20 2.00 1.60 19.20

CORTES
CORTE DE TERRENO CON MAQUINARIA 158.94

PABELLON 2
m3 1.00 1.00 21.45 7.80 0.95 158.94
RELLENOS
RELLENO COMPACTADO CON MATERIAL PROPIO PARA ZANJAS 28.38

RELLENO DE ZANJAS PARA VC


EJE A-A ENTRE 1-2 y 3-4(CORTE 1 - 1) m3 1.00 2.00 2.98 0.25 0.35 0.52
EJE A-A ENTRE 2-3 y 4-5(CORTE 1 - 1) m3 1.00 2.00 3.34 0.25 0.35 0.58
EJE A-A ENTRE 1-2 y 3-4(CORTE 2-2) m3 1.00 2.00 0.70 0.25 0.35 0.12
EJE C-C ENTRE 1-2 y 2-3 (CORTE 3-3) m3 1.00 2.00 3.35 0.35 0.35 0.82
EJE C-C ENTRE 2-3 y 4-5 (CORTE 3-3) m3 1.00 2.00 3.33 0.35 0.35 0.82
EJE 1-1 y EJE 5-5 ENTRE A-B (CORTE 4-4) m3 1.00 2.00 1.40 0.40 0.35 0.39
EJE 1-1 Y EJE 5-5 ENTRE B-C (CORTE 4-4) m3 1.00 2.00 0.85 0.40 0.35 0.24
EJE 3-3 ENTRE A-B (CORTE 5-5) m3 1.00 1.00 1.35 0.50 0.35 0.24
EJE 3-3 ENTRE B-C (CORTE 5-5) m3 1.00 1.00 1.23 0.50 0.35 0.22
CIMIENTO CORRIDO
EJE A-1 Y B-1 (DIVISION DE SSHH Y DEPOISTO) CORTE 6-6 m3 1.00 4.00 1.51 0.25 0.35 0.53
EJE 3-1 (DIVISION DE SSHH Y DEPOSITO) CORTE 6-6 m3 1.00 2.00 5.28 0.25 0.35 0.92
ZAPATAS
Z1 (C1) m3 1.00 1.00 1.20 0.48 1.00 0.57
M3 1.00 1.00 1.83 0.47 1.00 0.86
Z2 (C2) m3 1.00 6.00 1.40 0.47 1.00 3.96
Z3 (C3) m3 1.00 4.00 1.60 0.52 1.00 3.34
m3 1.00 4.00 1.45 0.82 1.00 4.76
Z4 (C4) m3 1.00 2.00 2.00 0.38 1.00 1.50
m3 1.00 2.00 2.00 0.58 1.00 2.30
m3 1.00 3.00 2.00 0.95 1.00 5.70

RELLENO CON MATERIAL DE PRESTAMO DE AFIRMADO 28.98

AULAS + SS.HH. m3 1.00 1.00 0.20 120.76 24.15


VEREDAS 1.00 1.00 21.44 1.50 0.15 4.82
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO 2 AULAS

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

ELIMINACION DE EXCAVACIONES

ACARREO INTERNO DE MATERIAL PROCEDENTE DE DEMOLICIONES Y


m3 volumen Coef. 258.68
EXCAVACIONES
1.00 1.00 206.95 1.25 258.68

ELIMINACION DE MATERIAL EXCEDENTE 258.68


ELIMINACION m3 1.00 1.00 258.68 258.68

NIVELACION INTERIOR Y COMPACTADO

NIVELACION INTERIOR Y COMPACTADO m2 152.92

AULAS + SS.HH. m2 1.00 1.00 120.76 120.76


VEREDAS m2 1.00 1.00 21.44 1.50 32.16

OBRAS DE CONCRETO SIMPLE

FALSOS CIMIENTOS

SOLADOS

SOLADO PARA CIMIENTOS Y ZAPATAS: CONCRETO C:H 1:12 e=4".. m2 29.08

en zapatas
Z1 m2 1.00 1.00 1.20 1.50 1.80
Z2 m2 1.00 3.00 1.20 1.40 5.04
Z3 m2 1.00 4.00 1.60 1.60 10.24
Z4 m2 1.00 5.00 1.20 2.00 12.00

FALSA CIMENTACION: CONCRETO C:H 1:12 . m3 8.29


CIMIENTO CORRIDO + VIGA DE CIMENTACION
EJE A-A ENTRE 1-2 y 3-4(CORTE 1 - 1) m3 1.00 2.00 4.75 0.50 0.20 0.95
EJE A-A ENTRE 2-3 y 4-5(CORTE 1 - 1) m3 1.00 2.00 4.44 0.50 0.20 0.89
EJE C-C ENTRE 1-2 y 2-3 (CORTE 3-3) m3 1.00 2.00 4.44 0.60 0.20 1.07
EJE C-C ENTRE 2-3 y 4-5 (CORTE 3-3) m3 1.00 2.00 4.45 0.60 0.20 1.07
EJE 1-1 y EJE 5-5 ENTRE A-B (CORTE 4-4) m3 1.00 2.00 2.33 0.65 0.20 0.61
EJE 1-1 Y EJE 5-5 ENTRE B-C (CORTE 4-4) m3 1.00 2.00 2.33 0.65 0.20 0.61
EJE 3-3 ENTRE A-B (CORTE 5-5) m3 1.00 1.00 2.33 0.75 0.20 0.35
EJE 3-3 ENTRE B-C (CORTE 5-5) m3 1.00 1.00 2.33 0.75 0.20 0.35
CIMIENTO CORRIDO
EJE A-1 Y B-1 (DIVISION DE SSHH Y DEPOISTO) CORTE 6-6 m3 1.00 4.00 2.04 0.60 0.20 0.98
EJE 3-1 (DIVISION DE SSHH Y DEPOSITO) CORTE 6-6 m3 1.00 2.00 5.95 0.60 0.20 1.43

CIMIENTOS CORRIDOS

CIMIENTO CORRIDO: CONCRETO C:H 1:10+30% P.G. m3 24.87


CIMIENTO CORRIDO + VIGA DE CIMENTACION
EJE A-A ENTRE 1-2 y 3-4(CORTE 1 - 1) 1.00 2.00 4.75 0.50 0.60 2.85
EJE A-A ENTRE 2-3 y 4-5(CORTE 1 - 1) 1.00 2.00 4.44 0.50 0.60 2.66
EJE C-C ENTRE 1-2 y 2-3 (CORTE 3-3) 1.00 2.00 4.44 0.60 0.60 3.20
EJE C-C ENTRE 2-3 y 4-5 (CORTE 3-3) 1.00 2.00 4.45 0.60 0.60 3.20
EJE 1-1 y EJE 5-5 ENTRE A-B (CORTE 4-4) 1.00 2.00 2.33 0.65 0.60 1.82
EJE 1-1 Y EJE 5-5 ENTRE B-C (CORTE 4-4) 1.00 2.00 2.33 0.65 0.60 1.82
EJE 3-3 ENTRE A-B (CORTE 5-5) 1.00 1.00 2.33 0.75 0.60 1.05
EJE 3-3 ENTRE B-C (CORTE 5-5) 1.00 1.00 2.33 0.75 0.60 1.05
CIMIENTO CORRIDO
EJE A-1 Y B-1 (DIVISION DE SSHH Y DEPOISTO) CORTE 6-6 1.00 4.00 2.04 0.60 0.60 2.94
EJE 3-1 (DIVISION DE SSHH Y DEPOSITO) CORTE 6-6 1.00 2.00 5.95 0.60 0.60 4.28
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO 2 AULAS

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

SOBRECIMIENTOS

SOBRECIMIENTO: CONCRETO C:H 1:8+25% P.M. m3 2.87


CIMIENTO CORRIDO + VIGA DE CIMENTACION
EJE A-A ENTRE 1-2 y 3-4(CORTE 1 - 1) 1.00 2.00 2.78 0.15 0.30 0.25
EJE A-A ENTRE 2-3 y 4-5(CORTE 1 - 1) 1.00 2.00 3.65 0.15 0.30 0.33
EJE C-C ENTRE 1-2 y 2-3 (CORTE 3-3) 1.00 2.00 3.90 0.15 0.30 0.35
EJE C-C ENTRE 2-3 y 4-5 (CORTE 3-3) 1.00 2.00 3.66 0.15 0.30 0.33
EJE 1-1 y EJE 5-5 ENTRE A-B (CORTE 4-4) 1.00 2.00 2.32 0.25 0.30 0.35
EJE 1-1 Y EJE 5-5 ENTRE B-C (CORTE 4-4) 1.00 2.00 2.32 0.25 0.30 0.35
EJE 3-3 ENTRE A-B (CORTE 5-5) 1.00 1.00 2.32 0.25 0.30 0.17
EJE 3-3 ENTRE B-C (CORTE 5-5) 1.00 1.00 2.32 0.25 0.30 0.17
SOBRECIMEINTO E=0.15
EJE A-1 Y B-1 (DIVISION DE SSHH Y DEPOISTO) CORTE 6-6 1.00 4.00 1.74 0.15 0.30 0.31
EJE 3-1 (DIVISION DE SSHH Y DEPOSITO) CORTE 6-6 1.00 2.00 2.80 0.15 0.30 0.25

ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTOS m2 32.68


CIMIENTO CORRIDO + VIGA DE CIMENTACION
EJE A-A ENTRE 1-2 y 3-4(CORTE 1 - 1) 1.00 4.00 2.78 0.30 3.34
EJE A-A ENTRE 2-3 y 4-5(CORTE 1 - 1) 1.00 4.00 3.65 0.30 4.38
EJE C-C ENTRE 1-2 y 2-3 (CORTE 3-3) 1.00 4.00 3.90 0.30 4.68
EJE C-C ENTRE 2-3 y 4-5 (CORTE 3-3) 1.00 4.00 3.66 0.30 4.39
EJE 1-1 y EJE 5-5 ENTRE A-B (CORTE 4-4) 1.00 4.00 2.32 0.30 2.78
EJE 1-1 Y EJE 5-5 ENTRE B-C (CORTE 4-4) 1.00 4.00 2.32 0.30 2.78
EJE 3-3 ENTRE A-B (CORTE 5-5) 1.00 2.00 2.32 0.30 1.39
EJE 3-3 ENTRE B-C (CORTE 5-5) 1.00 2.00 2.32 0.30 1.39
SOBRECIMEINTO E=0.15
EJE A-1 Y B-1 (DIVISION DE SSHH Y DEPOISTO) CORTE 6-6 1.00 8.00 1.74 0.30 4.18
EJE 3-1 (DIVISION DE SSHH Y DEPOSITO) CORTE 6-6 1.00 4.00 2.80 0.30 3.36

DADOS DE CONCRETO

DADOS DE CONCRETO F`c = 175kg/cm2 m2 0.11


DADOS 1.00 261.00 0.08 0.08 0.08 0.11

ENCOFRADO Y DESENCOFRADO DE DADOS DE CONCRETO m2 7.34


DADOS 1.00 261.00 0.38 0.08 7.34

FALSO PISO

FALSO PISO DE 4" DE CONCRETO 1:10 120.76


PABELLON 2 m2 1.00 1.00 120.76 120.76

OBRAS DE CONCRETO ARMADO


ZAPATAS
CONCRETO f'c= 210 kg/cm2 EN ZAPATAS 14.54

Z1 m3 1.00 1.00 1.20 1.50 0.50 0.90


Z2 m3 1.00 3.00 1.20 1.40 0.50 2.52
Z3 m3 1.00 4.00 1.60 1.60 0.50 5.12
Z4 m3 1.00 5.00 1.20 2.00 0.50 6.00

ENCOFRADO Y DESENCOFRADO EN ZAPATAS 39.30

Z1 m3 1.00 1.00 5.40 0.50 2.70


Z2 m3 1.00 3.00 5.20 0.50 7.80
Z3 m3 1.00 4.00 6.40 0.50 12.80
Z4 m3 1.00 5.00 6.40 0.50 16.00

N° DE LONGITUD
N° DE
ACERO ESTRUCTURAL TRABAJADO PARA ZAPATAS KG ELEMENTO POR Coef. 370.80
PIEZAS
S PIEZA(M)

Z1
INF:Ø1/2"@0.15 Kg 1.00 9.00 1.13 0.99 10.02
INF:Ø1/2"@0.15 Kg 1.00 7.00 1.43 0.99 9.88
Z2
INF:Ø1/2"@0.15 Kg 3.00 9.00 1.13 0.99 30.07
INF:Ø1/2"@0.15 Kg 3.00 7.00 1.33 0.99 27.55
Z3
INF:Ø1/2"@0.15 Kg 4.00 10.00 1.53 0.99 60.39
INF:Ø1/2"@0.15 Kg 4.00 10.00 1.53 0.99 60.39
Z4
INF:Ø1/2"@0.10 Kg 5.00 19.00 1.13 0.99 105.81
INF:Ø1/2"@0.15 Kg 5.00 7.00 1.93 0.99 66.70
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO 2 AULAS

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

VIGA DE CIMENTACIÓN
CONCRETO f'c= 210 kg/cm2 EN VIGA DE CIMENTACIÓN m3 6.27

EJE A-A ENTRE 1-2 y 3-4(CORTE 1 - 1) m3 1.00 2.00 4.75 0.25 0.50 1.19
EJE A-A ENTRE 2-3 y 4-5(CORTE 1 - 1) m3 1.00 2.00 4.44 0.25 0.50 1.11
EJE C-C ENTRE 1-2 y 2-3 (CORTE 3-3) m3 1.00 2.00 4.44 0.25 0.50 1.11
EJE C-C ENTRE 2-3 y 4-5 (CORTE 3-3) m3 1.00 2.00 4.45 0.25 0.50 1.11
EJE 1-1 y EJE 5-5 ENTRE A-B (CORTE 4-4) m3 1.00 2.00 2.33 0.25 0.50 0.58
EJE 1-1 Y EJE 5-5 ENTRE B-C (CORTE 4-4) m3 1.00 2.00 2.33 0.25 0.50 0.58
EJE 3-3 ENTRE A-B (CORTE 5-5) m3 1.00 1.00 2.33 0.25 0.50 0.29
EJE 3-3 ENTRE B-C (CORTE 5-5) m3 1.00 1.00 2.33 0.25 0.50 0.29

ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACION m2 50.14

EJE A-A ENTRE 1-2 y 3-4(CORTE 1 - 1) m2 1.00 4.00 4.75 ---- 0.50 9.50
EJE A-A ENTRE 2-3 y 4-5(CORTE 1 - 1) m2 1.00 4.00 4.44 ---- 0.50 8.88
EJE C-C ENTRE 1-2 y 2-3 (CORTE 3-3) m2 1.00 4.00 4.44 ---- 0.50 8.88
EJE C-C ENTRE 2-3 y 4-5 (CORTE 3-3) m2 1.00 4.00 4.45 ---- 0.50 8.90
EJE 1-1 y EJE 5-5 ENTRE A-B (CORTE 4-4) m2 1.00 4.00 2.33 ---- 0.50 4.66
EJE 1-1 Y EJE 5-5 ENTRE B-C (CORTE 4-4) m2 1.00 4.00 2.33 ---- 0.50 4.66
EJE 3-3 ENTRE A-B (CORTE 5-5) m2 1.00 2.00 2.33 ---- 0.50 2.33
EJE 3-3 ENTRE B-C (CORTE 5-5) m2 1.00 2.00 2.33 ---- 0.50 2.33

N° DE LONGITUD
N° DE
ACERO CORRUGADO FY=4200 KG/CM2 PARA VIGAS DE CIMENTACION Kg ELEMENTO POR COEF. 672.42
PIEZAS
S PIEZA(M)
ACERO LONG. ∅ 1/2"
EJES A-A Y EJE C-C Kg 2.00 6.00 22.48 0.99 267.06
EJES 1-1, EJE 3-3 y EJE5-5 Kg 3.00 6.00 6.68 0.99 119.04

ESTRIBOS [ ]1Ø5/8"@ 0.05, 4@0.10,3@0.15, RESTO A 20


EJES A-A Y EJE C-C Kg 8.00 28.00 1.54 0.56 193.18
EJES 1-1, EJE 3-3 y EJE5-5 Kg 6.00 18.00 1.54 0.56 93.14

COLUMNAS
CONCRETO f'c= 210 kg/cm2 EN COLUMNAS 17.66

Eje A-A y EJE 1-1 (C-1) m3 1.00 1.00 0.55 0.25 5.95 0.82
EJE B-B, EJE 1-1, EJE 3-3, EJE 5-5 (C-2) m3 1.00 3.00 0.50 0.25 6.55 2.46
EJE C-C, EJE 1-1, EJE 3-3, EJE 5-5 (C-3) m3 1.00 2.00 0.85 0.25 7.20 3.06
EJE A-A , EJE 3-3 Y EJE 5-5 (C-3) m3 1.00 2.00 0.85 0.25 5.95 2.53
EJE A-A , EJE 2-2 Y EJE 4-4 (C-4) m3 1.00 2.00 1.05 0.25 5.95 3.12
EJE C-C, EJE 2-2,EJE 3-3 Y EJE 4-4 (C-4) m3 1.00 3.00 1.05 0.25 7.20 5.67

ENCOFRADO Y DESENCOFRADO EN COLUMNAS PERIMETRO 183.96

Eje A-A y EJE 1-1 (C-1) m3 1.00 1.00 1.60 5.95 9.52
EJE B-B, EJE 1-1, EJE 3-3, EJE 5-5 (C-2) m3 1.00 3.00 1.50 6.55 29.48
EJE C-C, EJE 1-1, EJE 3-3, EJE 5-5 (C-3) m3 1.00 2.00 2.20 7.20 31.68
EJE A-A , EJE 3-3 Y EJE 5-5 (C-3) m4 1.00 2.00 2.20 5.95 26.18
EJE A-A , EJE 2-2 Y EJE 4-4 (C-4) m5 1.00 2.00 2.60 5.95 30.94
EJE C-C, EJE 2-2,EJE 3-3 Y EJE 4-4 (C-4) m6 1.00 3.00 2.60 7.20 56.16

N° DE LONGITUD
N° DE
ACERO CORRUGADO FY=4200 KG/CM2 PARA COLUMNAS Kg ELEMENTO POR Coef. 2,864.99
PIEZAS
S PIEZA(M)
ACERO LONG. ∅ 5/8"
C-1 Kg 1.00 4.00 6.45 1.55 40.04
C-2 Kg 3.00 4.00 7.05 1.55 131.30
C-3 Kg 2.00 8.00 7.70 1.55 191.21
Kg 2.00 8.00 6.45 1.55 160.17
C-4 Kg 2.00 8.00 6.45 1.55 160.17
Kg 3.00 8.00 7.70 1.55 286.81
ACERO LONG. ∅ 1/2"
C-1 Kg 1.00 4.00 6.45 0.99 25.65
C-2 Kg 3.00 4.00 7.05 0.99 84.09
C-3 Kg 2.00 4.00 7.70 0.99 61.23
Kg 2.00 4.00 6.45 0.99 51.29
C-4 Kg 2.00 6.00 6.45 0.99 76.94
Kg 3.00 6.00 7.70 0.99 137.77
ESTRIBOS [ ] Ø3/8",1@5 + 5@10,; RESTO @ 0.20
C-1 Kg 1.00 53.00 1.48 0.56 43.93
C-2 Kg 3.00 73.00 1.38 0.56 169.24
C-3 Kg 2.00 85.00 2.96 0.56 281.79
Kg 2.00 55.00 2.96 0.56 182.34
C-4 Kg 2.00 62.00 3.68 0.56 255.54
Kg 3.00 85.00 3.68 0.56 525.50
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO 2 AULAS

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

COLUMNAS DE AMARRE
CONCRETO F'C=175 KG/CM2 EN COLUMNETAS m3 2.85

MODULO DE 02 AULAS
EJE A-A TIPO C-A-1 m3 1.00 12.00 0.25 0.15 1.70 0.77
EJE C-C TIPO C-A-1 m3 1.00 10.00 0.25 0.15 2.30 0.86
EJE 1-1, EJE 3-3 Y EJE 5-5 TIPO C-A-1 m3 1.00 4.00 0.25 0.15 3.25 0.49
EJE 3-1 y EJE 5-1 TIPO C-A m3 1.00 10.00 0.15 0.15 3.25 0.73

ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNETAS m2 PERIMETRO 51.29

MODULO DE 02 AULAS
EJE A-A TIPO C-A-1 m2 1.00 12.00 0.65 1.70 13.26
EJE C-C TIPO C-A-1 m2 1.00 10.00 0.65 2.30 14.95
EJE 1-1, EJE 3-3 Y EJE 5-5 TIPO C-A-1 m2 1.00 4.00 0.65 3.25 8.45
EJE 3-1 y EJE 5-1 TIPO C-A m2 1.00 10.00 0.45 3.25 14.63

N° DE LONGITUD
N° DE
ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 en COLUMNETAS ELEMENTO POR COEF. 436.36
PIEZAS
S PIEZA(M)
ACERO LONG. ∅ 3/8" CORRUGADO
EJE A-A TIPO C-A-1 Kg 12.00 6.00 2.35 0.56 94.75
EJE C-C TIPO C-A-1 Kg 10.00 6.00 2.95 0.56 99.12
EJE 1-1, EJE 3-3 Y EJE 5-5 TIPO C-A-1 Kg 4.00 6.00 3.90 0.56 52.42
EJE 3-1 y EJE 5-1 TIPO C-A Kg 10.00 4.00 3.90 0.56 87.36
ESTRIBOS [ ] 1/4" 1@.05, 3@.10 R .20
EJE A-A TIPO C-A-1 Kg 12.00 12.00 0.76 0.25 27.25
EJE C-C TIPO C-A-1 Kg 10.00 16.00 0.76 0.25 30.28
EJE 1-1, EJE 3-3 Y EJE 5-5 TIPO C-A-1 Kg 4.00 21.00 0.76 0.25 15.90
EJE 3-1 y EJE 5-1 TIPO C-A Kg 10.00 21.00 0.56 0.25 29.28

VIGAS
CONCRETO F'C=210 KG/CM2 EN VIGAS m3 12.33
VP - 1 (0.30x0.50)
EJE 2-2 y EJE 4-4 ENTRE A-C 1.00 2.00 5.49 0.25 0.50 1.37
VP - 4(0.25x0.40)
EJE A-A ENTRE 1-2 Y 3-4 1.00 2.00 4.80 0.25 0.40 0.96
EJE A-A ENTRE 2-3 Y 4-5 1.00 2.00 4.45 0.25 0.40 0.89
EJE C-C ENTRE 1-2, 3-4 1.00 4.00 4.45 0.25 0.40 1.78
EJE C-C ENTRE 2-3 Y 4-5 1.00 4.00 4.45 0.25 0.40 1.78
EJE 3-3 1.00 2.00 2.33 0.25 0.40 0.47
EJE 1-1 1.00 2.00 2.33 0.25 0.40 0.47
EJE 5-5 1.00 2.00 2.33 0.25 0.40 0.47
VS - 2 (0.25x0.40)
EJE 3-3 1.00 2.00 2.38 0.25 0.40 0.48
EJE 1-1 1.00 2.00 2.38 0.25 0.40 0.48
EJE 5-5 1.00 2.00 2.38 0.25 0.40 0.48
VP-3 (0.25xVAR.)
EJE 1-1, 3-3 y 5-5 1.00 3.00 1.45 0.25 0.50 0.54
EJE 2-2 y 4-4 1.00 2.00 1.45 0.25 0.50 0.36
VP-5 (0.15X0.40)
ENTRE 1-2 y 3-4 1.00 2.00 5.05 0.15 0.60 0.91
ENTR 2-3 y 4-5 1.00 2.00 5.05 0.15 0.60 0.91

ENCOFRADO Y DESENCOFRADO EN VIGAS m2 PERIMETRO 125.42


VP - 101 (0.25x0.50)
EJE 2-2 y EJE 4-4 ENTRE A-C 1.00 2.00 5.49 1.25 13.71
VP - 4(0.25x0.40)
EJE A-A ENTRE 1-2 Y 3-4 1.00 2.00 4.80 1.05 10.08
EJE A-A ENTRE 2-3 Y 4-5 1.00 2.00 4.45 1.05 9.35
EJE C-C ENTRE 1-2, 3-4 1.00 4.00 4.45 1.05 18.69
EJE C-C ENTRE 2-3 Y 4-5 1.00 4.00 4.45 1.05 18.69
EJE 3-3 1.00 2.00 2.33 0.80 3.73
EJE 1-1 1.00 2.00 2.33 0.80 3.73
EJE 5-5 1.00 2.00 2.33 0.80 3.73
VS - 2 (0.25x0.40)
EJE 3-3 1.00 2.00 2.38 0.80 3.81
EJE 1-1 1.00 2.00 2.38 0.80 3.81
EJE 5-5 1.00 2.00 2.38 0.80 3.81
VP-3 (0.25xVAR.)
EJE 1-1, 3-3 y 5-5 1.00 3.00 1.45 1.25 5.44
EJE 2-2 y 4-4 1.00 2.00 1.45 1.25 3.63
VP-5 (0.15X0.40)
ENTRE 1-2 y 3-4 1.00 2.00 5.05 1.15 11.62
ENTR 2-3 y 4-5 1.00 2.00 5.05 1.15 11.62
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO 2 AULAS

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

N° DE LONGITUD
N° DE
ACERO CORRUGADO fy=4200 kg/cm2 PARA VIGAS Kg ELEMENTO POR coef. 1,586.99
PIEZAS
S PIEZA(M)
ACERO LONG. ∅ 5/8"
EJES 2-2 y 4-4 VP-1 y VP-3 Kg 2.00 2.00 8.43 1.552 52.33
Kg 2.00 2.00 7.46 1.552 46.31
Kg 2.00 1.00 3.00 1.552 9.31
Kg 2.00 2.00 2.62 1.552 16.26
EJES A-A Y C-C VP-4 Kg 3.00 4.00 23.06 1.552 429.47
EJE 1-1, 3-3 Y 5-5 VP-4 Kg 3.00 4.00 6.63 1.552 123.48
EJE 1-1, 3-3 Y 5-5 VP-4 Y VP-3 Kg 3.00 2.00 8.43 1.552 78.50
Kg 3.00 4.00 7.91 1.552 147.32
ACERO LONG. ∅ 1/2"
EJES A-A Y C-C VP-4 Kg 3.00 3.00 2.85 0.994 25.50
ENTRE 1-2, 2-3, 3-4 Y 4-5 Kg 1.00 4.00 22.76 0.994 90.49
ACERO LONG. ∅ 3/8"
Kg 1.00 4.00 22.46 0.56 50.31
Kg 1.00 108.00 0.50 0.56 30.24
ESTRIBOS [ ] ∅ 3/8" 2@5, 10@10,3@15, Rsto @25 A/E
EJES 2-2 y 4-4 VP-1 y VP-3 Kg 2.00 37.00 1.38 0.56 57.19
ESTRIBOS [ ] ∅ 3/8" 1@5, 8@10, 3@15 Rsto. @ 20 A/E
EJE A-A, EJE C-C VP-4 Kg 3.00 128.00 1.18 0.56 253.75
ESTRIBOS [ ] ∅ 3/8" 1@5, Rsto. @120
EJE 1-1, 3-3 Y 5-5 VP-4 Kg 3.00 24.00 1.18 0.56 47.58
EJE 1-1, 3-3 Y 5-5 VS-2 Kg 3.00 24.00 1.18 0.56 47.58
ESTRIBOS [ ] ∅ 3/8" 1@5, 6@10, Rsto. @ 20 A/E
EJE 1-1, 2-2, 3-3, 4-4 Y 5-5 VP-3 Kg 5.00 10.00 1.38 0.56 38.64
ESTRIBOS [ ] Ø3/8" 1@0.05, 10@.075; 5@.15, RESTO @ 0.20 A/E
EJE 1-1, 2-2, 3-3, 4-4 Y 5-5 VP-5 Kg 1.00 72.00 1.06 0.56 42.74

VIGA DE AMARRE
CONCRETO F'C=175 KG/CM2 EN VIGAS DE AMARRE 1.32
EJE A-A TRAMO 2-3 1.00 2.00 1.27 0.13 0.25 0.08
1.00 2.00 2.38 0.13 0.25 0.15
EJE A-A TRAMO 1-2 1.00 2.00 2.23 0.13 0.25 0.14
1.00 2.00 0.55 0.13 0.25 0.04
EJE C-C TRAMO 2-3 1.00 2.00 1.26 0.13 0.25 0.08
1.00 2.00 2.40 0.13 0.25 0.16
EJE C-C TRAMO 1-2 1.00 2.00 3.89 0.13 0.25 0.25
EJE A-1 Y EJE B-1 1.00 4.00 1.89 0.13 0.25 0.25
EJE 3-1 1.00 2.00 0.38 0.13 0.25 0.02
1.00 2.00 1.68 0.13 0.25 0.11
1.00 2.00 0.55 0.13 0.25 0.04

ENCOFRADO Y DESENCOFRADO EN VIGAS DE AMARRE 20.37

EJE A-A TRAMO 2-3 m2 1.00 2.00 1.27 ---- 0.50 1.27
m2 1.00 2.00 2.38 ---- 0.50 2.38
EJE A-A TRAMO 1-2 m2 1.00 2.00 2.23 ---- 0.50 2.23
m3 1.00 2.00 0.55 ---- 0.50 0.55
EJE C-C TRAMO 2-3 m4 1.00 2.00 1.26 ---- 0.50 1.26
m5 1.00 2.00 2.4 ---- 0.50 2.40
EJE C-C TRAMO 1-2 m6 1.00 2.00 3.89 ---- 0.50 3.89
EJE A-1 Y EJE B-1 m7 1.00 4.00 1.89 ---- 0.50 3.78
EJE 3-1 m8 1.00 2.00 0.38 ---- 0.50 0.38
m9 1.00 2.00 1.68 ---- 0.50 1.68
m10 1.00 2.00 0.55 ---- 0.50 0.55

N° DE LONGITUD
N° DE
ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 en VIGAS DE AMARRE Kg ELEMENTO POR COEF. 129.28
PIEZAS
S PIEZA(M)
ACERO LONG. ∅ 1/2" CORRUGADO
EJE A-A Kg 2.00 2.00 4.74 0.99 18.85
Kg 2.00 2.00 3.87 0.99 15.39
EJE C-C Kg 4.00 2.00 4.74 0.99 37.69
EJE A-1 Y EJE B-1 4.00 2.00 2.38 0.99 18.93
EJE 3-1 2.00 2.00 1.29 0.99 5.13
2.00 2.00 2.14 0.99 8.51
2.00 2.00 1.29 0.99 5.13
ESTRIBOS [ ] 1/4" 1@.05, 4@.10 ,R .20
EJE A-A TRAMO 2-3 Kg 2.00 10.00 0.28 0.25 1.39
Kg 2.00 15.00 0.28 0.25 2.09
EJE A-A TRAMO 1-2 Kg 2.00 14.00 0.28 0.25 1.95
2.00 6.00 0.28 0.25 0.84
EJE C-C TRAMO 2-3 2.00 10.00 0.28 0.25 1.39
2.00 15.00 0.28 0.25 2.09
EJE C-C TRAMO 1-2 2.00 23.00 0.28 0.25 3.21
EJE A-1 Y EJE B-1 4.00 13.00 0.28 0.25 3.63
EJE 3-1 2.00 4.00 0.28 0.25 0.56
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO 2 AULAS

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

2.00 12.00 0.28 0.25 1.67


2.00 6.00 0.28 0.25 0.84

LOSA ALIGERADA
CONCRETO EN LOSA ALIGERADA f'c=210 kg/cm2 m3 AREA CONCRETO M3/M2 12.73

TRAMO 1-2, 2-3, 3-4 Y 4-5 (AULA) m3 1.00 4.00 29.04 0.0875 10.16
TRAMO 1-2, 2-3, 3-4 Y 4-5 (ALERO) m3 1.00 4.00 7.32 0.0875 2.56
ENCOFRADO Y DESENCOFRADO PARA LOSAS ALIGERADAS m2 145.44

TRAMO 1-2, 2-3, 3-4 Y 4-5 (AULA) m2 1.00 4.00 29.04 ---- 116.15
TRAMO 1-2, 2-3, 3-4 Y 4-5 (ALERO) m2 1.00 4.00 7.32 ---- 29.29
N° DE LONGITUD
N° DE
ACERO CORRUGADO FY=4200 KG/CM2 PARA LOSA ALIGERADA kg ELEMENTO POR coef. 1,049.10
PIEZAS
S PIEZA(M)
VIGUETAS 1/2" (INCLUYE VIGUETAS EN ALERO)
TRAMO 1-2,2-3,3-4 Y 4-5 (AULA Y ALERO) kg 4.00 12.00 7.70 0.99 367.38
4.00 12.00 4.15 0.99 198.00
4.00 12.00 3.90 0.99 186.08
4.00 12.00 1.35 0.99 64.41
VIGUETAS 1/2" (INCLUYE VIGUETAS EN ALERO)
TRAMO 1-2,2-3,3-4 Y 4-5 (AULA Y ALERO) 4.00 12.00 3.25 0.56 87.36
ACERO DE TEMPERATURA 1/4" (INCLUYE ALERO)
VIGUETAS 1/2" (INCLUYE VIGUETAS EN ALERO) kg 4.00 23.00 5.05 0.249 115.69
TRAMO 1-2,2-3,3-4 Y 4-5 (AULA Y ALERO) 4.00 6.00 5.05 0.249 30.18
LADRILLO ARCILLA PARA TECHO 15X30X30 CM UND AREA LAD/M2 1,212.00

UND 1.00 145.44 8.33 1,212.00

ESTRUCTURA DE MADERA Y COBERTURA

CORREAS DE MADERA TORNILLO DE 2"X1" m3 171.60


Modulo de 01 Aula 1.00 8.00 21.45 171.60

COBERTURA DE FIBRO CEMENTO m2 170.53


Modulo de 01 Aula 1.00 1.00 21.45 7.95 170.53
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO SUM-ADMINISTRATIVO

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD

OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES

LIMPIEZA, TRAZO Y REPLANTEO GENERAL

LIMPIEZA DE TERRENO MANUAL/ EQUIPO m2 165.37


MODULO SUM-ADMINISTRATIVO 1.00 1.00 20.58 6.30 129.65
7.85 4.55 35.72
TRAZO Y REPLANTEO

TRAZO Y REPLANTEO TOPOGRAFICO m2 165.37


MODULO SUM - ADMINISTRATIVO 1.00 1.00 20.58 6.30 129.65
7.85 4.55 35.72
ESTRUCTURA
MOVIMIENTO DE TIERRA
EXCAVACIONES
EXCAVACION DE ZANJAS Y ZAPATAS MANUAL 138.49

CIMIENTO CORRIDO + VIGA DE CIMENTACION


EJES 1-1 ENTRE A-B(CORTE 1-1) m3 1.00 1.00 4.40 0.75 1.00 3.30
EJES 1-1 ENTRE B-C (CORTE 1-1) m3 1.00 1.00 1.15 0.75 1.00 0.86
EJE 3-3 ENTRE A Y B (CORTE 2-2) m3 1.00 1.00 4.10 0.75 1.00 3.08
EJE B-B ENTRE 4 - 5 (CORTE 10-10) m3 1.00 1.00 2.20 0.60 1.00 1.32
EJE B-B ENTRE 5-6 (CORTE 9-9) m3 1.00 1.00 4.38 0.60 1.00 2.63
EJE D-D ENTRE 4-5 (CORTE 8-8) m3 1.00 1.00 2.40 0.75 1.00 1.80
EJE D-D ENTRE 4-5 (CORTE 8-8) m3 1.00 1.00 4.28 0.75 1.00 3.21
CIMIENTO CORRIDO
EJE C-1 ENTRE 1-3 m3 1.00 1.00 4.38 0.50 1.00 2.19
EJE 2-1 ENTRE C-D m3 1.00 1.00 1.17 0.50 1.00 0.59
EJE 4-1 ENTRE B-D (CORTE 5-5) m3 1.00 1.00 3.52 0.50 1.00 1.76
EJE C-C ENTRE 5-6 (CORTE 4-4) m3 1.00 1.00 5.03 0.50 1.00 2.52
EJE 5-1 ENTRE B-C (CORTE 6-6) m3 1.00 1.00 1.68 0.50 1.00 0.84
ZAPATAS
Z1 m3 1.00 1.00 6.50 1.50 1.60 15.60
Z2 m3 1.00 2.00 2.00 1.30 1.60 8.32
Z3 m3 1.00 1.00 2.50 2.00 1.60 8.00
Z4 m3 1.00 1.00 2.10 2.10 1.60 7.06
Z5 m3 1.00 3.00 1.80 1.80 1.60 15.55
Z6 m3 1.00 3.00 2.00 1.30 1.60 12.48
Z7 m3 1.00 1.00 2.50 2.00 1.60 8.00
PLATEA DE CIMENTACION
CIMENTACION COLUMNAS, ESCALERA Y CISTERNA
ENTRE LOS EJES 3-4 Y EL EJE C-D m3 1.00 1.00 5.60 3.35 2.10 39.40

CORTES
CORTE DE TERRENO CON MAQUINARIA 140.57
MODULO SUM - ADMINISTRATIVO m3 1.00 1.00 20.58 6.30 0.85 110.21
1.00 1.00 7.85 4.55 0.85 30.36
RELLENOS
RELLENO COMPACTADO CON MATERIAL PROPIO PARA ZANJAS 48.68

CIMIENTO CORRIDO + VIGA DE CIMENTACION


EJES 1-1 ENTRE A-B(CORTE 1-1) m3 1.00 1.00 4.40 0.50 0.35 0.77
EJES 1-1 ENTRE B-C (CORTE 1-1) m3 1.00 1.00 1.15 0.50 0.35 0.20
EJE 3-3 ENTRE A Y B (CORTE 2-2) m3 1.00 1.00 4.10 0.50 0.35 0.72
EJE B-B ENTRE 4 - 5 (CORTE 10-10) m3 1.00 1.00 2.20 0.35 0.35 0.27
EJE B-B ENTRE 5-6 (CORTE 9-9) 1.00 1.00 4.38 0.35 0.35 0.54
EJE D-D ENTRE 4-5 (CORTE 8-8) m3 1.00 1.00 2.40 0.50 0.35 0.42
EJE D-D ENTRE 4-5 (CORTE 8-8) m3 1.00 1.00 4.28 0.50 0.35 0.75
CIMIENTO CORRIDO
EJE C-1 ENTRE 1-3 m3 1.00 1.00 4.38 0.25 0.35 0.38
EJE 2-1 ENTRE C-D m3 1.00 1.00 1.17 0.25 0.35 0.10
EJE 4-1 ENTRE B-D (CORTE 5-5) m3 1.00 1.00 3.52 0.25 0.35 0.31
EJE C-C ENTRE 5-6 (CORTE 4-4) m3 1.00 1.00 5.03 0.25 0.35 0.44
EJE 5-1 ENTRE B-C (CORTE 6-6) m3 1.00 1.00 1.68 0.25 0.35 0.15
ZAPATAS
Z1 m3 1.00 1.00 6.50 0.63 1.00 4.06
1.00 1.00 5.75 0.63 1.00 3.59
Z2 m3 1.00 2.00 2.00 1.05 1.00 4.20
Z3 m3 1.00 1.00 2.50 0.88 1.00 2.19
Z4 m3 1.00 1.00 0.78 2.10 1.00 1.63
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO SUM-ADMINISTRATIVO

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

m3 1.00 2.00 1.07 1.07 1.00 2.29


Z5 m3 1.00 3.00 0.63 1.80 1.00 3.38
m3 1.00 6.00 0.93 0.93 1.00 5.13
Z6 m3 1.00 6.00 0.53 0.53 1.00 1.69
Z7 m3 1.00 1.00 1.17 2.00 1.00 2.34
m3 1.00 2.00 1.17 0.88 1.00 2.05
PLATEA DE CIMENTACION
m3 1.00 1.00 1.17 0.88 1.50 1.54
m3 1.00 1.00 3.35 0.88 1.50 4.40
m3 1.00 1.00 3.35 0.88 1.50 4.40
m3 1.00 1.00 1.17 0.88 0.75 0.77

RELLENO CON MATERIAL DE PRESTAMO DE AFIRMADO 24.94


AULA 6 m3 1.00 1.00 0.20 59.75 11.95
ADMINISTRATIVO Y SS.HH. 1.00 1.00 0.20 43.90 8.78
VEREDAS 1.00 1.00 0.15 28.05 4.21
ELIMINACION DE EXCAVACIONES

ACARREO INTERNO DE MATERIAL PROCEDENTE DE DEMOLICIONES Y


m3 volumen Coef. 287.96
EXCAVACIONES
AULAS + ADMINISTRATIVO 1.00 1.00 230.37 1.25 287.96

ELIMINACION DE MATERIAL EXCEDENTE 287.96


ELIMINACION m3 1.00 1.00 287.96 287.96

NIVELACION INTERIOR Y COMPACTADO

NIVELACION INTERIOR Y COMPACTADO m2 131.70


AULA + SS.HH. 1.00 1.00 59.75 59.75
ADMINISTRATIVO Y SS.HH. 1.00 1.00 43.90 43.90
VEREDAS 1.00 1.00 28.05 28.05

OBRAS DE CONCRETO SIMPLE

FALSOS CIMIENTOS

SOLADOS

SOLADO PARA CIMIENTOS Y ZAPATAS: CONCRETO C:H 1:12 e=4".. m2 65.64


ZAPATAS
Z1 m2 1.00 1.00 6.50 1.50 9.75
Z2 m2 1.00 2.00 2.00 1.30 5.20
Z3 m2 1.00 1.00 2.50 2.00 5.00
Z4 m2 1.00 1.00 2.10 2.10 4.41
Z5 m2 1.00 3.00 1.80 1.80 9.72
Z6 m2 1.00 3.00 2.00 1.30 7.80
Z7 m2 1.00 1.00 2.50 2.00 5.00
PLATEA DE CIMENTACION
CIMENTACION COLUMNAS, ESCALERA Y CISTERNA
ENTRE LOS EJES 3-4 Y EL EJE C-D m3 1.00 1.00 5.60 3.35 18.76

FALSA CIMENTACION: CONCRETO C:H 1:12 . m3 13.31

CIMIENTO CORRIDO + VIGA DE CIMENTACION


EJE 1-1 ENTRE A-B m3 1.00 1.00 5.60 0.75 0.20 0.84
EJE 1-1 ENTRE B-C m3 1.00 1.00 3.60 0.75 0.20 0.54
EJE 3-3 ENTRE A-B m3 1.00 1.00 5.60 0.75 0.20 0.84
EJES 5-5 y 6-6, ENTRE B-C m3 1.00 2.00 1.55 0.75 0.20 0.47
EJES 5-5 y 6-6, ENTRE C-D m3 1.00 2.00 1.65 0.75 0.20 0.50
EJE B-B ENTRE 3-4 m3 1.00 1.00 3.35 0.50 0.20 0.34
EJE B-B ENTRE 4-5 m3 1.00 1.00 3.55 0.50 0.20 0.36
EJE B-B ENTRE 5.6 m3 1.00 1.00 5.78 0.50 0.20 0.58
EJE D-D ENTRE 1-3 m3 1.00 1.00 4.65 0.75 0.20 0.70
EJE D-D ENTRE 4-5 m3 1.00 1.00 2.97 0.75 0.20 0.45
EJE D-D ENTRE 5-6 m3 1.00 1.00 5.48 0.75 0.20 0.82
CIMIENTO CORRIDO
EJE C-1 ENTRE 1-3 m3 1.00 1.00 5.85 0.50 0.20 0.59
EJE 2-1 ENTRE C-D m3 1.00 2.00 1.85 0.50 0.20 0.37
EJE 4-1 ENTRE B-D (CORTE 5-5) m3 1.00 1.00 4.20 0.50 0.20 0.42
EJE C-C ENTRE 5-6 (CORTE 4-4) m3 1.00 1.00 6.08 0.50 0.20 0.61
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO SUM-ADMINISTRATIVO

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

EJE 5-1 ENTRE B-C (CORTE 6-6) m3 1.00 1.00 2.12 0.50 0.20 0.21
PLATEA DE CIMENTACION
EJES 3-3 Y 4-4 ENTRE B-C m3 1.00 2.00 1.55 0.75 0.65 1.51
EJES 3-3 Y 4-4 ENTRE C-D m3 1.00 2.00 1.65 0.75 0.65 1.61
RELLENO DE CONCRETO SIMPLE M3 1.00 2.00 3.35 1.18 0.20 1.58

CIMIENTOS CORRIDOS

CIMIENTO CORRIDO: CONCRETO C:H 1:10+30% P.G. m3 28.48


CIMIENTO CORRIDO + VIGA DE CIMENTACION
EJE 1-1 ENTRE A-B 1.00 1.00 5.60 0.75 0.60 2.52
EJE 1-1 ENTRE B-C 1.00 1.00 3.60 0.75 0.60 1.62
EJE 3-3 ENTRE A-B 1.00 1.00 5.60 0.75 0.60 2.52
EJES 5-5 y 6-6, ENTRE B-C 1.00 2.00 1.55 0.75 0.60 1.40
EJES 5-5 y 6-6, ENTRE C-D 1.00 2.00 1.65 0.75 0.60 1.49
EJE B-B ENTRE 3-4 1.00 1.00 3.35 0.50 0.60 1.01
EJE B-B ENTRE 4-5 1.00 1.00 3.55 0.50 0.60 1.07
EJE B-B ENTRE 5.6 1.00 1.00 5.78 0.50 0.60 1.73
EJE D-D ENTRE 1-3 1.00 1.00 4.15 0.75 0.60 1.87
EJE D-D ENTRE 4-5 1.00 1.00 2.97 0.75 0.60 1.34
EJE D-D ENTRE 5-6 1.00 1.00 5.48 0.75 0.60 2.47
CIMIENTO CORRIDO
EJE C-1 ENTRE 1-3 1.00 1.00 5.85 0.50 0.60 1.76
EJE 2-1 ENTRE C-D 1.00 2.00 1.85 0.50 0.60 1.11
EJE 4-1 ENTRE B-D (CORTE 5-5) 1.00 1.00 4.20 0.50 0.60 1.26
EJE C-C ENTRE 5-6 (CORTE 4-4) 1.00 1.00 6.08 0.50 0.60 1.82
EJE 5-1 ENTRE B-C (CORTE 6-6) 1.00 1.00 2.12 0.50 0.60 0.64
PLATEA DE CIMENTACION
EJES 3-3 Y 4-4 ENTRE B-C 1.00 2.00 1.55 0.75 0.60 1.40
EJES 3-3 Y 4-4 ENTRE C-D 1.00 2.00 1.65 0.75 0.60 1.49

SOBRECIMIENTOS

SOBRECIMIENTO: CONCRETO C:H 1:8+25% P.M. m3 3.73


CIMIENTO CORRIDO + VIGA DE CIMENTACION
EJE 1-1 ENTRE A-B 1.00 1.00 4.81 0.25 0.30 0.36
EJE 1-1 ENTRE B-C 1.00 1.00 2.81 0.25 0.30 0.21
EJE 3-3 ENTRE A-B 1.00 1.00 3.63 0.25 0.30 0.27
EJES 5-5 y 6-6, ENTRE B-C 1.00 2.00 1.55 0.25 0.30 0.23
EJES 5-5 y 6-6, ENTRE C-D 1.00 2.00 1.65 0.25 0.30 0.25
EJE B-B ENTRE 3-4 1.00 1.00 0.65 0.15 0.30 0.03
EJE B-B ENTRE 4-5 1.00 1.00 0.65 0.15 0.30 0.03
EJE B-B ENTRE 5.6 1.00 1.00 4.21 0.15 0.30 0.19
EJE D-D ENTRE 1-3 1.00 1.00 4.35 0.25 0.30 0.33
EJE D-D ENTRE 4-5 1.00 1.00 3.40 0.25 0.30 0.26
EJE D-D ENTRE 5-6 1.00 1.00 5.48 0.25 0.30 0.41
CIMIENTO CORRIDO
EJE C-1 ENTRE 1-3 1.00 1.00 1.68 0.15 0.30 0.08
EJE 2-1 ENTRE C-D 1.00 2.00 1.85 0.15 0.30 0.17
EJE 4-1 ENTRE B-D (CORTE 5-5) 1.00 1.00 3.95 0.15 0.30 0.18
EJE C-C ENTRE 5-6 (CORTE 4-4) 1.00 1.00 4.81 0.15 0.30 0.22
EJE 5-1 ENTRE B-C (CORTE 6-6) 1.00 1.00 1.18 0.15 0.30 0.05
PLATEA DE CIMENTACION
EJES 3-3 Y 4-4 ENTRE B-C 1.00 2.00 1.55 0.25 0.30 0.23
EJES 3-3 Y 4-4 ENTRE C-D 1.00 2.00 1.65 0.25 0.30 0.25

ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTOS m2 32.95


CIMIENTO CORRIDO + VIGA DE CIMENTACION
EJE 1-1 ENTRE A-B 1.00 2.00 4.81 0.30 2.89
EJE 1-1 ENTRE B-C 1.00 2.00 2.81 0.30 1.69
EJE 3-3 ENTRE A-B 1.00 2.00 3.63 0.30 2.18
EJES 5-5 y 6-6, ENTRE B-C 1.00 4.00 1.55 0.30 1.86
EJES 5-5 y 6-6, ENTRE C-D 1.00 4.00 1.65 0.30 1.98
EJE B-B ENTRE 3-4 1.00 2.00 0.65 0.30 0.39
EJE B-B ENTRE 4-5 1.00 2.00 0.65 0.30 0.39
EJE B-B ENTRE 5.6 1.00 2.00 4.21 0.30 2.53
EJE D-D ENTRE 1-3 1.00 2.00 4.35 0.30 2.61
EJE D-D ENTRE 4-5 1.00 2.00 3.40 0.30 2.04
EJE D-D ENTRE 5-6 1.00 2.00 5.48 0.30 3.29
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO SUM-ADMINISTRATIVO

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

CIMIENTO CORRIDO
EJE C-1 ENTRE 1-3 1.00 2.00 1.68 0.30 1.01
EJE 2-1 ENTRE C-D 1.00 4.00 1.85 0.30 2.22
EJE 4-1 ENTRE B-D (CORTE 5-5) 1.00 2.00 3.95 0.30 2.37
EJE C-C ENTRE 5-6 (CORTE 4-4) 1.00 2.00 4.81 0.30 2.89
EJE 5-1 ENTRE B-C (CORTE 6-6) 1.00 2.00 1.18 0.30 0.71
PLATEA DE CIMENTACION
EJES 3-3 Y 4-4 ENTRE B-C 1.00 2.00 1.55 0.30 0.93
EJES 3-3 Y 4-4 ENTRE C-D 1.00 2.00 1.65 0.30 0.99

DADOS DE CONCRETO

DADOS DE CONCRETO F`c = 175kg/cm2 m2 0.25


DADOS m2 1.00 590.00 0.08 0.08 0.08 0.25

ENCOFRADO Y DESENCOFRADO DE DADOS DE CONCRETO m2 16.59


DADOS m2 1.00 590.00 0.38 0.08 16.59

FALSO PISO

FALSO PISO DE 4" DE CONCRETO 1:10 103.65


AULA + SS.HH. 1.00 1.00 59.75 59.75
ADMINISTRATIVO Y SS.HH. 1.00 1.00 43.90 43.90

OBRAS DE CONCRETO ARMADO


ZAPATAS
CONCRETO f'c= 210 kg/cm2 EN ZAPATAS m3 32.82

Z1 1.00 1.00 6.50 1.50 0.50 4.88


Z2 1.00 2.00 2.00 1.30 0.50 2.60
Z3 1.00 1.00 2.50 2.00 0.50 2.50
Z4 1.00 1.00 2.10 2.10 0.50 2.21
Z5 1.00 3.00 1.80 1.80 0.50 4.86
Z6 1.00 3.00 2.00 1.30 0.50 3.90
Z7 1.00 1.00 2.50 2.00 0.50 2.50
PLATEA DE CIMENTACION
ENTRE LOS EJES 3-4 Y EL EJE C-D 1.00 1.00 5.60 3.35 0.50 9.38

ENCOFRADO Y DESENCOFRADO EN ZAPATAS m2 Perimetro 57.45

Z1 1.00 1.00 16.00 0.50 8.00


Z2 1.00 2.00 6.60 0.50 6.60
Z3 1.00 1.00 9.00 0.50 4.50
Z4 1.00 1.00 8.40 0.50 4.20
Z5 1.00 3.00 7.20 0.50 10.80
Z6 1.00 3.00 6.60 0.50 9.90
Z7 1.00 1.00 9.00 0.50 4.50
PLATEA DE CIMENTACION
ENTRE LOS EJES 3-4 Y EL EJE C-D 1.00 1.00 17.90 0.50 8.95

N° DE LONGITUD
N° DE
ACERO ESTRUCTURAL TRABAJADO PARA ZAPATAS KG ELEMENTO POR Coef. 1,110.78
PIEZAS
S PIEZA(M)

Z1
INF:Ø1/2"@0.15 Kg 1.00 10.00 6.35 0.99 62.87
INF:Ø1/2"@0.15 Kg 1.00 44.00 1.35 0.99 58.81
Z2
INF:Ø1/2"@0.15 Kg 2.00 9.00 1.85 0.99 32.97
INF:Ø1/2"@0.15 Kg 2.00 14.00 1.15 0.99 31.88
Z3
INF:Ø1/2"@0.15 Kg 1.00 14.00 2.35 0.99 32.57
INF:Ø1/2"@0.15 Kg 1.00 17.00 1.85 0.99 31.14
Z4
INF:Ø1/2"@0.15 Kg 1.00 14.00 1.95 0.99 27.03
INF:Ø1/2"@0.15 Kg 1.00 14.00 1.95 0.99 27.03
Z5
INF:Ø1/2"@0.15 Kg 3.00 12.00 1.65 0.99 58.81
INF:Ø1/2"@0.15 Kg 3.00 12.00 1.65 0.99 58.81
Z6
INF:Ø1/2"@0.15 Kg 3.00 9.00 1.85 0.99 49.45
INF:Ø1/2"@0.15 Kg 3.00 14.00 1.15 0.99 47.82
Z7
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO SUM-ADMINISTRATIVO

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

INF:Ø1/2"@0.15 Kg 1.00 14.00 2.35 0.99 32.57


INF:Ø1/2"@0.15 Kg 1.00 17.00 1.85 0.99 31.14
PLATEA DE CIMENTACION
INF:Ø1/2"@0.15 Kg 1.00 45.00 5.85 0.99 260.62
INF:Ø1/2"@0.15 Kg 1.00 75.00 3.60 0.99 267.30

VIGA DE CIMENTACIÓN
CONCRETO f'c= 210 kg/cm2 EN VIGA DE CIMENTACIÓN m3 6.61

EJE 1-1 ENTRE A-B m3 1.00 1.00 5.60 0.25 0.50 0.70
EJE 1-1 ENTRE B-C m3 1.00 1.00 3.60 0.25 0.50 0.45
EJE 3-3 ENTRE A-B m3 1.00 1.00 5.60 0.25 0.50 0.70
EJES 5-5 y 6-6, ENTRE B-C m3 1.00 2.00 1.55 0.25 0.50 0.39
EJES 5-5 y 6-6, ENTRE C-D m3 1.00 2.00 1.65 0.25 0.50 0.41
EJE B-B ENTRE 3-4 m3 1.00 1.00 3.35 0.25 0.50 0.42
EJE B-B ENTRE 4-5 m3 1.00 1.00 3.55 0.25 0.50 0.44
EJE B-B ENTRE 5.6 m3 1.00 1.00 5.78 0.25 0.50 0.72
EJE D-D ENTRE 1-3 m3 1.00 1.00 4.15 0.25 0.50 0.52
EJE D-D ENTRE 4-5 m3 1.00 1.00 2.97 0.25 0.50 0.37
EJE D-D ENTRE 5-6 m3 1.00 1.00 5.48 0.25 0.50 0.69
PLATEA DE CIMENTACION
EJES 3-3 Y 4-4 ENTRE B-C 1.00 2.00 1.55 0.25 0.5 0.39
EJES 3-3 Y 4-4 ENTRE C-D 1.00 2.00 1.65 0.25 0.5 0.41

ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACION 52.88

EJE 1-1 ENTRE A-B m2 1.00 2.00 5.60 ---- 0.50 5.60
EJE 1-1 ENTRE B-C m2 1.00 2.00 3.60 ---- 0.50 3.60
EJE 3-3 ENTRE A-B m2 1.00 2.00 5.60 ---- 0.50 5.60
EJES 5-5 y 6-6, ENTRE B-C m2 1.00 4.00 1.55 ---- 0.50 3.10
EJES 5-5 y 6-6, ENTRE C-D m2 1.00 4.00 1.65 ---- 0.50 3.30
EJE B-B ENTRE 3-4 m2 1.00 2.00 3.35 ---- 0.50 3.35
EJE B-B ENTRE 4-5 m2 1.00 2.00 3.55 ---- 0.50 3.55
EJE B-B ENTRE 5.6 m2 1.00 2.00 5.78 ---- 0.50 5.78
EJE D-D ENTRE 1-3 m2 1.00 2.00 4.15 ---- 0.50 4.15
EJE D-D ENTRE 4-5 m2 1.00 2.00 2.97 ---- 0.50 2.97
EJE D-D ENTRE 5-6 m2 1.00 2.00 5.48 ---- 0.50 5.48
PLATEA DE CIMENTACION
EJES 3-3 Y 4-4 ENTRE B-C m2 1.00 4.00 1.55 ---- 0.50 3.10
EJES 3-3 Y 4-4 ENTRE C-D m2 1.00 4.00 1.65 ---- 0.50 3.30

N° DE LONGITUD
N° DE
ACERO CORRUGADO FY=4200 KG/CM2 PARA VIGAS DE CIMENTACION Kg ELEMENTO POR COEF. 686.76
PIEZAS
S PIEZA(M)
ACERO LONG. ∅ 1/2"
EJE 1-1 Kg 1.00 6.00 11.67 0.99 69.32
EJE 3-3 Kg 1.00 6.00 11.67 0.99 69.32
EJE 4-4 Kg 1.00 6.00 5.02 0.99 29.82
EJE 5-5 Kg 1.00 6.00 5.02 0.99 29.82
EJE 6-6 Kg 1.00 6.00 5.02 0.99 29.82
EJE D-D Kg 1.00 6.00 21.90 0.99 130.09
ESTRIBOS [ ] 3Ø5/8"@ 5CM, RESTO A 30
EJE 1-1 ENTRE A-B Kg 1.00 35.00 1.54 0.56 30.18
EJE 1-1 ENTRE B-C Kg 1.00 25.00 1.54 0.56 21.56
EJE 3-3 ENTRE A-B Kg 1.00 35.00 1.54 0.56 30.18
EJES 5-5 y 6-6, ENTRE B-C Kg 2.00 14.00 1.54 0.56 24.15
EJES 5-5 y 6-6, ENTRE C-D Kg 2.00 15.00 1.54 0.56 25.87
EJE B-B ENTRE 3-4 Kg 1.00 24.00 1.54 0.56 20.70
EJE B-B ENTRE 4-5 Kg 1.00 25.00 1.54 0.56 21.56
EJE B-B ENTRE 5.6 Kg 1.00 36.00 1.54 0.56 31.05
EJE D-D ENTRE 1-3 Kg 1.00 28.00 1.54 0.56 24.15
EJE D-D ENTRE 4-5 Kg 1.00 22.00 1.54 0.56 18.97
EJE D-D ENTRE 5-6 Kg 1.00 35.00 1.54 0.56 30.18
PLATEA DE CIMENTACION
EJES 3-3 Y 4-4 ENTRE B-C Kg 2.00 14.00 1.54 0.56 24.15
EJES 3-3 Y 4-4 ENTRE C-D Kg 2.00 15.00 1.54 0.56 25.87

SOBRECIMIENTO REFORZADO
CONCRETO f'c= 210 kg/cm2 EN SOBRECIMIENTO REFORZADO m3 1.41

EJE C-C ENTRE 3-4 m3 1.00 1.00 2.75 0.25 2.05 1.41

ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTO REFORZADO 11.28

EJE C-C ENTRE 3-4 m2 1.00 2.00 2.75 ---- 2.05 11.28
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO SUM-ADMINISTRATIVO

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

N° DE LONGITUD
N° DE
ACERO CORRUGADO FY=4200 KG/CM2 EN SOBRECIMIENTO REFORZADO Kg ELEMENTO POR COEF. 77.38
PIEZAS
S PIEZA(M)
EJE C-C ENTRE 3-4
AV: 2ø3/8"@.20 Kg 2.00 13.00 2.37 0.56 34.51
AH: 2ø3/8"@.20 Kg 2.00 11.00 3.48 0.56 42.87

COLUMNAS Y MUROS
CONCRETO f'c= 210 kg/cm2 EN COLUMNAS-MUROS m3 44.72

C-2 m3 1.00 4.00 0.50 0.25 9.70 4.85


m3 1.00 1.00 0.50 0.25 10.30 1.29
C-3 m3 1.00 3.00 0.85 0.25 9.15 5.83
m3 1.00 2.00 0.85 0.25 10.30 4.38
C-4 m3 1.00 1.00 1.05 0.25 9.15 2.40
m3 1.00 4.00 1.05 0.25 10.30 10.82
MURO DE CONCRETO ARMADO
EJE A-A (P1) m3 1.00 1.00 6.25 0.25 9.70 15.16

ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 PERIMETRO 436.37

C-2 m2 1.00 4.00 1.50 9.70 58.20


m2 1.00 1.00 1.50 10.30 15.45
C-3 m2 1.00 3.00 2.20 9.15 60.39
m2 1.00 2.00 2.20 10.30 45.32
C-4 m2 1.00 1.00 2.60 9.15 23.79
m2 1.00 4.00 2.60 10.30 107.12
MURO DE CONCRETO ARMADO
EJE A-A (P1) m2 1.00 1.00 13.00 9.70 126.10

N° DE LONGITUD
N° DE
ACERO CORRUGADO FY=4200 KG/CM2 PARA COLUMNAS Kg ELEMENTO POR Coef. 4,654.90
PIEZAS
S PIEZA(M)
ACERO LONG. ∅ 5/8"
C-2 Kg 4.00 4.00 10.20 1.55 253.29
Kg 1.00 4.00 10.80 1.55 67.05
C-3 Kg 3.00 8.00 9.65 1.55 359.44
Kg 2.00 8.00 10.80 1.55 268.19
C-4 Kg 1.00 8.00 9.65 1.55 119.81
Kg 4.00 8.00 10.80 1.55 536.37
MURO DE CONCRETO ARMADO
EJE A-A (P1) Kg 1.00 8.00 10.20 1.55 126.64
ACERO LONG. ∅ 1/2"
C-2 Kg 4.00 4.00 10.10 0.99 160.63
Kg 1.00 4.00 10.70 0.99 42.54
C-3 Kg 3.00 4.00 9.55 0.99 113.91
Kg 2.00 4.00 10.70 0.99 84.74
C-4 Kg 1.00 6.00 9.55 0.99 56.73
Kg 4.00 6.00 10.70 0.99 254.23
MURO DE CONCRETO ARMADO
EJE A-A (P1) Kg 1.00 8.00 10.10 0.99 79.99
ACERO LONG. ∅ 3/8"
ENCOFRADO Y DESENCOFRADO EN COLUMNAS Kg 1.00 46.00 10.10 0.56 260.18
ESTRIBOS [ ] Ø3/8",2@5 + 5@10,; RESTO @ 0.20
C-2 Kg 4.00 72.00 1.54 0.56 248.37
Kg 1.00 75.00 1.54 0.56 64.68
C-3 Kg 3.00 66.00 3.28 0.56 363.69
Kg 2.00 75.00 3.28 0.56 275.52
C-4 Kg 1.00 66.00 3.68 0.56 136.01
Kg 4.00 75.00 3.68 0.56 618.24
MURO DE CONCRETO ARMADO
EJE A-A (P1) Kg 1.00 60.00 4.90 0.56 164.64
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO SUM-ADMINISTRATIVO

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

COLUMNAS DE AMARRE
CONCRETO F'C=175 KG/CM2 EN COLUMNETAS m3 4.02

PRIMER PISO
EJE 1-1 TIPO C-A-1 1.00 6.00 0.25 0.15 2.40 0.54
EJE 3-3 TIPO C-A-1 1.00 3.00 0.25 0.15 1.70 0.19
EJE 3-3 TIPO C-A-1 1.00 2.00 0.25 0.15 2.40 0.18
EJE B-B TIPO C-A-1 1.00 3.00 0.25 0.15 1.70 0.19
EJE B-B TIPO C-A-1 1.00 4.00 0.25 0.15 2.40 0.36
EJE B-B TIPO C-A 1.00 3.00 0.15 0.15 3.40 0.23
EJE D-D TIPO C-A-1 1.00 2.00 0.25 0.15 3.40 0.26
DIVISIONES DE SS.HH TIPO C-A 1.00 5.00 0.15 0.15 3.40 0.38
DIVISIONES DE COCINA TIPO C-A-1 1.00 1.00 0.25 0.15 3.40 0.13
DIVISIONES DE COCINA TIPO C-A 1.00 4.00 0.15 0.15 3.40 0.31
SEGUNDO PISO
EJE 1-1 TIPO C-A-1 1.00 5.00 0.25 0.15 2.40 0.45
EJE 3-3 TIPO C-A-1 1.00 3.00 0.25 0.15 1.70 0.19
EJE B-B TIPO C-A-1 1.00 3.00 0.25 0.15 1.70 0.19
EJE B-B TIPO C-A-1 1.00 2.00 0.25 0.15 2.40 0.18
PSADIZO TIPO C-A 1.00 11.00 0.15 0.15 1.00 0.25

ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNETAS m2 PERIMETRO 47.46

PRIMER PISO
EJE 1-1 TIPO C-A-1 m2 1.00 6.00 0.50 2.10 6.30
EJE 3-3 TIPO C-A-1 m2 1.00 3.00 0.50 1.40 2.10
EJE 3-3 TIPO C-A-1 m3 1.00 2.00 0.50 2.10 2.10
EJE B-B TIPO C-A-1 m2 1.00 3.00 0.50 1.40 2.10
EJE B-B TIPO C-A-1 m2 1.00 4.00 0.50 2.10 4.20
EJE B-B TIPO C-A m2 1.00 3.00 0.30 3.10 2.79
EJE D-D TIPO C-A-1 m2 1.00 2.00 0.50 3.10 3.10
DIVISIONES DE SS.HH TIPO C-A m2 1.00 5.00 0.30 3.10 4.65
DIVISIONES DE COCINA TIPO C-A-1 m2 1.00 1.00 0.50 3.10 1.55
DIVISIONES DE COCINA TIPO C-A m2 1.00 4.00 0.30 3.10 3.72
SEGUNDO PISO
EJE 1-1 TIPO C-A-1 m2 1.00 5.00 0.50 2.10 5.25
EJE 3-3 TIPO C-A-1 m2 1.00 3.00 0.50 1.40 2.10
EJE B-B TIPO C-A-1 m2 1.00 3.00 0.50 1.40 2.10
EJE B-B TIPO C-A-1 m2 1.00 2.00 0.50 2.10 2.10
PSADIZO TIPO C-A m2 1.00 11.00 0.30 1.00 3.30

N° DE LONGITUD
N° DE
ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 en COLUMNETAS Kg ELEMENTO POR COEF. 1,768.91
PIEZAS
S PIEZA(M)
ACERO LONG. ∅ 13/8" CORRUGADO
PRIMER PISO
EJE 1-1 TIPO C-A-1 Kg 6.00 6.00 2.32 0.56 46.77
EJE 3-3 TIPO C-A-1 Kg 3.00 6.00 1.62 0.56 16.33
EJE 3-3 TIPO C-A-1 Kg 2.00 7.00 2.32 1.56 50.67
EJE B-B TIPO C-A-1 Kg 3.00 6.00 1.62 0.56 16.33
EJE B-B TIPO C-A-1 Kg 4.00 6.00 2.32 0.56 31.18
EJE B-B TIPO C-A Kg 3.00 4.00 3.32 0.56 22.31
EJE D-D TIPO C-A-1 Kg 2.00 6.00 3.32 0.56 22.31
DIVISIONES DE SS.HH TIPO C-A Kg 5.00 4.00 3.32 0.56 37.18
DIVISIONES DE COCINA TIPO C-A-1 Kg 1.00 6.00 3.32 0.56 11.16
DIVISIONES DE COCINA TIPO C-A Kg 4.00 4.00 3.32 0.56 29.75
SEGUNDO PISO
EJE 1-1 TIPO C-A-1 Kg 5.00 6.00 2.32 0.56 38.98
EJE 3-3 TIPO C-A-1 Kg 3.00 6.00 1.62 0.56 16.33
EJE B-B TIPO C-A-1 Kg 3.00 6.00 1.62 0.56 16.33
EJE B-B TIPO C-A-1 Kg 2.00 6.00 2.32 0.56 15.59
PSADIZO TIPO C-A Kg 11.00 4.00 1.22 0.56 30.06
ESTRIBOS [ ] 1/4" 1@.05, 4@.10 R .25
PRIMER PISO
EJE 1-1 TIPO C-A-1 Kg 6.00 10.00 0.84 0.25 12.55
EJE 3-3 TIPO C-A-1 Kg 3.00 7.00 0.84 1.25 22.03
EJE 3-3 TIPO C-A-1 Kg 2.00 10.00 0.84 2.25 37.78
EJE B-B TIPO C-A-1 Kg 3.00 7.00 0.84 2.25 39.67
EJE B-B TIPO C-A-1 Kg 4.00 10.00 0.84 3.25 109.17
EJE B-B TIPO C-A Kg 3.00 14.00 0.84 4.25 149.90
EJE D-D TIPO C-A-1 Kg 2.00 14.00 0.84 5.25 123.46
DIVISIONES DE SS.HH TIPO C-A Kg 5.00 14.00 0.84 6.25 367.44
DIVISIONES DE COCINA TIPO C-A-1 Kg 1.00 14.00 0.84 7.25 85.25
DIVISIONES DE COCINA TIPO C-A Kg 4.00 14.00 0.84 8.25 388.03
SEGUNDO PISO
EJE 1-1 TIPO C-A-1 Kg 5.00 10.00 0.84 0.25 10.46
EJE 3-3 TIPO C-A-1 Kg 3.00 8.00 0.84 0.25 5.02
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO SUM-ADMINISTRATIVO

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

EJE B-B TIPO C-A-1 Kg 3.00 8.00 0.84 0.25 5.02


EJE B-B TIPO C-A-1 Kg 2.00 10.00 0.84 0.25 4.18
PSADIZO TIPO C-A Kg 11.00 7.00 0.40 0.25 7.67

VIGAS
CONCRETO F'C=210 KG/CM2 EN VIGAS m3 25.30

PRIMER PISO
EJE 1-1 ENTRE A-B (VP-6) m3 1.00 1.00 5.60 0.25 0.50 0.70
EJE 1-1 ENTRE B-D (VP-1) m3 1.00 1.00 3.60 0.25 0.50 0.45
EJE 3-3 ENTRE A-B (VP-6) m3 1.00 1.00 5.60 0.25 0.50 0.70
EJE 3-3 ENTRE B-C Y C-D (VS-2) m3 1.00 1.00 3.60 0.25 0.50 0.45
EJES 4-4, 5-5 6-6 ENTRE B-C Y C-D VS-1 m3 1.00 3.00 3.32 0.25 0.40 1.00
EJES 4-4, 5-5 6-6 VP-3 m3 1.00 1.00 1.60 0.25 0.50 0.20
ALERO ENTRE A-B VP-5 m3 1.00 1.00 5.89 0.15 0.40 0.35
EJE A-A VS-1 m3 1.00 1.00 6.00 0.25 0.40 0.60
EJE A-A VP-3 m3 1.00 1.00 1.60 0.25 0.50 0.20
ALERO ENTRE 3-5 VP-5 m3 1.00 1.00 14.00 0.15 0.40 0.84
EJE B-B ENTRE 1-3 VP-1 m3 1.00 1.00 5.35 0.25 0.50 0.67
EJE B-B ENTRE 3-4 VP-1 m3 1.00 1.00 3.35 0.25 0.50 0.42
EJE B-B ENTRE 4-5 VP-1 m3 1.00 1.00 3.55 0.25 0.50 0.44
EJE B-B ENTRE 5-6VP-1 m3 1.00 1.00 5.78 0.25 0.50 0.72
EJE D-D ENTRE 1-2 VS-1 m3 1.00 1.00 2.33 0.25 0.40 0.23
EJE D-D ENTRE 2-3 VS-1 m3 1.00 1.00 2.33 0.25 0.40 0.23
EJE D-D ENTRE 3-4 VS-1 m3 1.00 1.00 2.75 0.25 0.40 0.28
EJE D-D ENTRE 4-5 VS-1 m3 1.00 1.00 3.55 0.25 0.40 0.36
EJE D-D ENTRE 5-6 VS-1 m3 1.00 1.00 5.48 0.25 0.40 0.55
SEGUNDO PISO
EJE 1-1 ENTRE A-B (VP-6) INCLUYE CUMBRERA m3 1.00 2.00 5.60 0.25 0.50 1.40
EJE 1-1 ENTRE B-D (VP-1) m3 1.00 2.00 3.60 0.25 0.50 0.90
EJE 3-3 ENTRE A-B (VP-6) m3 1.00 1.00 5.60 0.25 0.50 0.70
EJE 3-3 ENTRE B-C Y C-D (VS-2) m3 1.00 1.00 3.32 0.25 0.50 0.42
EJES 4-4, 5-5 6-6 ENTRE B-C Y C-D VP-4 m3 1.00 3.00 3.32 0.30 0.40 1.20
EJES 4-4, 5-5 6-6 ENTRE B-C Y C-D VS-1 m3 1.00 3.00 3.44 0.30 0.40 1.24
EJES 4-4, 5-5 6-6 VP-3 m3 1.00 1.00 1.60 0.25 0.50 0.20
EJE A-A VS-1 m3 1.00 1.00 6.15 0.25 0.40 0.62
EJE A-A VP-3 m3 1.00 1.00 1.60 0.25 0.50 0.20
ALERO ENTRE 3-5 VP-5 m3 1.00 1.00 11.60 0.15 0.40 0.70
EJE B-B ENTRE 1-3 VP-1 m3 1.00 1.00 5.48 0.25 0.50 0.69
EJE B-B ENTRE 3-4 VP-1 m3 1.00 1.00 3.35 0.25 0.50 0.42
EJE B-B ENTRE 4-5 VP-1 m3 1.00 1.00 3.55 0.25 0.50 0.44
EJE B-B ENTRE 5-6VP-1 m3 1.00 1.00 5.78 0.25 0.50 0.72
EJE D-D ENTRE 1-2 VS-1+ CUMBRERA m3 1.00 2.00 2.43 0.25 0.40 0.49
EJE D-D ENTRE 2-3 VS-1+ CUMBRERA m3 1.00 2.00 2.33 0.25 0.40 0.47
EJE D-D ENTRE 3-4 VS-1+CUMBRERA m3 1.00 2.00 2.75 0.25 0.70 0.96
EJE D-D ENTRE 4-5 VS-1+CUMBRERA m3 1.00 2.00 3.55 0.25 0.40 0.71
EJE D-D ENTRE 5-6 VS-1+CUMBRERA m3 1.00 2.00 5.48 0.25 0.40 1.10
VIGA DIAGONAL VP-7 m3 1.00 1.00 7.23 0.30 0.60 1.30
ALERO ENTRE 3-5 VP-5 m3 1.00 1.00 3.00 0.30 0.60 0.54
VIGA V-CH m3 1.00 1.00 4.15 0.50 0.25 0.52
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO SUM-ADMINISTRATIVO

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

ENCOFRADO Y DESENCOFRADO EN VIGAS m2 PERIMETRO 263.38

PRIMER PISO - -
EJE 1-1 ENTRE A-B (VP-6) 1.00 1.00 5.60 1.25 7.00
EJE 1-1 ENTRE B-D (VP-1) 1.00 1.00 3.60 1.25 4.50
EJE 3-3 ENTRE A-B (VP-6) 1.00 1.00 5.60 1.25 7.00
EJE 3-3 ENTRE B-C Y C-D (VS-2) 1.00 1.00 3.60 1.25 4.50
EJES 4-4, 5-5 6-6 ENTRE B-C Y C-D VS-1 1.00 3.00 3.32 0.80 7.97
EJES 4-4, 5-5 6-6 VP-3 1.00 1.00 1.60 1.25 2.00
ALERO ENTRE A-B VP-5 1.00 1.00 5.89 0.95 5.60
EJE A-A VS-1 1.00 1.00 6.00 1.05 6.30
EJE A-A VP-3 1.00 1.00 1.60 1.25 2.00
ALERO ENTRE 3-5 VP-5 1.00 1.00 14.00 0.95 13.30
EJE B-B ENTRE 1-3 VP-1 1.00 1.00 5.35 1.25 6.69
EJE B-B ENTRE 3-4 VP-1 1.00 1.00 3.35 1.25 4.19
EJE B-B ENTRE 4-5 VP-1 1.00 1.00 3.55 1.25 4.44
EJE B-B ENTRE 5-6VP-1 1.00 1.00 5.78 1.25 7.23
EJE D-D ENTRE 1-2 VS-1 1.00 1.00 2.33 0.80 1.86
EJE D-D ENTRE 2-3 VS-1 1.00 1.00 2.33 0.80 1.86
EJE D-D ENTRE 3-4 VS-1 1.00 1.00 2.75 0.80 2.20
EJE D-D ENTRE 4-5 VS-1 1.00 1.00 3.55 0.80 2.84
EJE D-D ENTRE 5-6 VS-1 1.00 1.00 5.48 0.80 4.38
SEGUNDO PISO
EJE 1-1 ENTRE A-B (VP-6) INCLUYE CUMBRERA 1.00 2.00 5.60 1.25 14.00
EJE 1-1 ENTRE B-D (VP-1) 1.00 2.00 3.60 1.25 9.00
EJE 3-3 ENTRE A-B (VP-6) 1.00 1.00 5.60 1.25 7.00
EJE 3-3 ENTRE B-C Y C-D (VS-2) 1.00 1.00 3.32 1.00 3.32
EJES 4-4, 5-5 6-6 ENTRE B-C Y C-D VP-4 1.00 3.00 3.32 1.25 12.45
EJES 4-4, 5-5 6-6 ENTRE B-C Y C-D VS-1 1.00 3.00 3.44 0.80 8.26
EJES 4-4, 5-5 6-6 VP-3 1.00 1.00 1.60 1.25 2.00
EJE A-A VS-1 1.00 1.00 6.15 0.95 5.84
EJE A-A VP-3 1.00 1.00 1.60 1.25 2.00
ALERO ENTRE 3-5 VP-5 1.00 1.00 11.60 2.65 30.74
EJE B-B ENTRE 1-3 VP-1 1.00 1.00 5.48 1.25 6.85
EJE B-B ENTRE 3-4 VP-1 1.00 1.00 3.35 1.25 4.19
EJE B-B ENTRE 4-5 VP-1 1.00 1.00 3.55 1.25 4.44
EJE B-B ENTRE 5-6VP-1 1.00 1.00 5.78 1.25 7.23
EJE D-D ENTRE 1-2 VS-1+ CUMBRERA 1.00 2.00 2.43 0.80 3.89
EJE D-D ENTRE 2-3 VS-1+ CUMBRERA 1.00 2.00 2.33 0.80 3.73
EJE D-D ENTRE 3-4 VS-1+CUMBRERA 1.00 2.00 2.75 0.80 4.40
EJE D-D ENTRE 4-5 VS-1+CUMBRERA 1.00 2.00 3.55 1.40 9.94
EJE D-D ENTRE 5-6 VS-1+CUMBRERA 1.00 2.00 5.48 0.80 8.77
VIGA DIAGONAL VP-7 1.00 1.00 7.23 1.50 10.85
ALERO ENTRE 3-5 VP-5 1.00 1.00 3.00 1.50 4.50
VIGA V-CH 1.00 1.00 4.15 1.00 4.15

N° DE LONGITUD
N° DE
ACERO CORRUGADO fy=4200 kg/cm2 PARA VIGAS Kg ELEMENTO POR coef. 3,140.90
PIEZAS
S PIEZA(M)
PRIMER PISO

ACERO LONG. ∅ 5/8"


EJE 1-1 1.00 4.00 11.23 1.552 69.72
1.00 1.00 3.60 1.552 5.59
1.00 1.00 2.60 1.552 4.04
1.00 2.00 3.05 1.552 9.47
1.00 1.00 1.60 1.552 2.48
1.00 2.00 1.93 1.552 5.99
EJE 3-3 1.00 4.00 11.23 1.552 69.72
1.00 1.00 3.60 1.552 5.59
1.00 1.00 2.60 1.552 4.04
1.00 2.00 3.05 1.552 9.47
1.00 2.00 1.93 1.552 5.99
EJE 4-4, 5-5, 6-6 3.00 2.00 6.91 1.552 64.35
3.00 2.00 5.25 1.552 48.89
3.00 2.00 6.91 1.552 64.35
3.00 2.00 2.50 1.552 23.28
3.00 1.00 2.50 1.552 11.64
EJE A-A 1.00 2.00 6.91 1.552 21.45
1.00 2.00 5.25 1.552 16.30
1.00 2.00 6.91 1.552 21.45
1.00 2.00 2.50 1.552 7.76
1.00 1.00 2.50 1.552 3.88
EJE B-B 1.00 4.00 21.98 1.552 136.45
1.00 2.00 2.75 1.552 8.54
1.00 1.00 2.78 1.552 4.31
1.00 1.00 3.78 1.552 5.87
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO SUM-ADMINISTRATIVO

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

1.00 2.00 1.23 1.552 3.82


EJE D-D 1.00 4.00 21.98 1.552 136.45
SEGUNDO PISO
EJE 1-1 2.00 4.00 11.23 1.552 139.43
2.00 1.00 3.60 1.552 11.17
2.00 1.00 2.60 1.552 8.07
2.00 1.00 1.60 1.552 4.97
EJE 3-3 1.00 4.00 11.23 1.552 69.72
1.00 1.00 3.60 1.552 5.59
1.00 1.00 2.60 1.552 4.04
EJE 4-4, 5-5, 6-6 3.00 4.00 5.30 1.552 98.71
3.00 2.00 7.16 1.552 66.67
3.00 2.00 6.67 1.552 62.11
3.00 2.00 2.81 1.552 26.17
EJE A-A 1.00 2.00 6.91 1.552 21.45
1.00 2.00 5.25 1.552 16.30
1.00 2.00 6.91 1.552 21.45
1.00 2.00 2.50 1.552 7.76
1.00 1.00 2.50 1.552 3.88
EJE B-B 1.00 4.00 6.59 1.552 40.91
1.00 1.00 3.00 1.552 4.66
1.00 4.00 15.70 1.552 97.47
1.00 1.00 3.78 1.552 5.87
1.00 2.00 2.78 1.552 8.63
EJE D-D 1.00 4.00 21.98 1.552 136.45
ACERO LONG. ∅ 1/2"
EJE D-D 1.00 2.00 4.40 0.994 8.75
VP-5 PRIMER PISO 1.00 4.00 6.80 0.994 27.04
VP-5 PRIMER PISO 1.00 4.00 15.40 0.994 61.23
VP-5 SEGUNDO PISO 1.00 4.00 5.27 0.994 20.95
VP-5 SEGUNDO PISO 1.00 4.00 13.02 0.994 51.77
V-CH 1.00 6.00 4.97 0.994 29.64
ACERO LONG. ∅ 3/8"
VP-5 1.00 2.00 37.85 0.56 42.39
VP-5 1.00 190.00 0.50 0.56 53.20
ESTRIBOS
EJE 1-1 1.00 68.00 1.54 0.56 58.64
EJE 3-3 1.00 56.00 1.54 0.56 48.29
EJE 4-4, 5-5, 6-6 3.00 18.00 1.34 0.56 40.52
3.00 15.00 1.54 0.56 38.81
EJE A-A 1.00 32.00 1.34 0.56 24.01
1.00 10.00 1.54 0.56 8.62
EJE B-B 1.00 124.00 1.54 0.56 106.94
EJE D-D 1.00 125.00 1.34 0.56 93.80
SEGUNDO PISO
EJE 1-1 2.00 68.00 1.54 0.56 117.29
EJE 3-3 1.00 56.00 1.54 0.56 48.29
EJE 4-4, 5-5, 6-6 3.00 18.00 1.34 0.56 40.52
3.00 18.00 1.34 0.56 40.52
3.00 10.00 1.54 0.56 25.87
EJE A-A 1.00 32.00 1.34 0.56 24.01
1.00 10.00 1.54 0.56 8.62
EJE B-B 1.00 125.00 1.54 0.56 107.80
EJE D-D 2.00 125.00 1.34 0.56 187.60
VP-5 PRIMER PISO 1.00 43.00 1.34 0.56 32.27
VP-5 PRIMER PISO 1.00 85.00 1.34 0.56 63.78
VP-5 SEGUNDO PISO 1.00 35.00 1.34 0.56 26.26
VP-5 SEGUNDO PISO 1.00 74.00 1.34 0.56 55.53
V-CH 1.00 34.00 0.82 0.56 15.61

VIGA DE AMARRE
CONCRETO F'C=175 KG/CM2 EN VIGAS DE AMARRE m3 2.68

PRIMER PISO
EJE 1-1 ENTRE A-B m3 1.00 1.00 4.80 0.15 0.25 0.18
EJE 1-1 ENTRE B-D m3 1.00 1.00 2.81 0.15 0.25 0.11
EJE 3-3 ENTRE A-B m3 1.00 1.00 3.63 0.15 0.25 0.14
EJE 3-3 ENTRE C-D m3 1.00 1.00 1.30 0.15 0.25 0.05
EJE B-B ENTRE 3-4 m3 1.00 1.00 0.65 0.15 0.25 0.02
EJE B-B ENTRE 4-5 m3 1.00 1.00 0.75 0.15 0.25 0.03
EJE B-B ENTRE 5-6 m3 1.00 1.00 4.21 0.15 0.25 0.16
DIVISIONES DE SS.HH AULA m3 1.00 1.00 2.15 0.15 0.25 0.08
m3 1.00 1.00 3.70 0.15 0.25 0.14
DIVISIONES DE SS.HH. OFICINAS m3 1.00 1.00 4.81 0.15 0.25 0.18
m3 1.00 1.00 5.48 0.15 0.25 0.21
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO SUM-ADMINISTRATIVO

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

SEGUNDO PISO
EJE 1-1 ENTRE A-B m3 1.00 1.00 4.80 0.15 0.25 0.18
EJE 1-1 ENTRE B-D m3 1.00 1.00 3.06 0.15 0.25 0.11
EJE 3-3 ENTRE A-B m3 1.00 1.00 3.63 0.15 0.25 0.14
EJE B-B ENTRE 4-5 m3 1.00 1.00 2.22 0.15 0.25 0.08
EJE B-B ENTRE 5-6 m3 1.00 1.00 4.21 0.15 0.25 0.16
PASADIZOS m3 1.00 1.00 11.85 0.15 0.25 0.44
1.00 1.00 4.25 0.15 0.25 0.16
1.00 2.00 1.55 0.15 0.25 0.12

ENCOFRADO Y DESENCOFRADO EN VIGAS DE AMARRE 34.93

PRIMER PISO
EJE 1-1 ENTRE A-B m2 1.00 2.00 4.80 ---- 0.25 2.40
EJE 1-1 ENTRE B-D m2 1.00 2.00 2.81 ---- 0.25 1.41
EJE 3-3 ENTRE A-B m2 1.00 2.00 3.63 ---- 0.25 1.82
EJE 3-3 ENTRE C-D m2 1.00 2.00 1.30 ---- 0.25 0.65
EJE B-B ENTRE 3-4 m2 1.00 2.00 0.65 ---- 0.25 0.33
EJE B-B ENTRE 4-5 m2 1.00 2.00 0.75 ---- 0.25 0.38
EJE B-B ENTRE 5-6 m2 1.00 2.00 4.21 ---- 0.25 2.11
DIVISIONES DE SS.HH AULA m2 1.00 2.00 2.15 ---- 0.25 1.08
m2 1.00 2.00 3.70 ---- 0.25 1.85
DIVISIONES DE SS.HH. OFICINAS m2 1.00 2.00 4.81 ---- 0.25 2.41
m2 1.00 2.00 5.48 ---- 0.25 2.74
SEGUNDO PISO
EJE 1-1 ENTRE A-B m2 1.00 2.00 4.80 ---- 0.25 2.40
EJE 1-1 ENTRE B-D m2 1.00 2.00 3.06 ---- 0.25 1.53
EJE 3-3 ENTRE A-B m2 1.00 2.00 3.63 ---- 0.25 1.82
EJE B-B ENTRE 4-5 m2 1.00 2.00 2.22 ---- 0.25 1.11
EJE B-B ENTRE 5-6 m2 1.00 2.00 4.21 ---- 0.25 2.11
PASADIZOS m2 1.00 2.00 11.85 ---- 0.25 5.93
m2 1.00 2.00 4.25 ---- 0.25 2.13
m2 1.00 2.00 1.55 ---- 0.25 0.78

N° DE LONGITUD
N° DE
ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 en VIGAS DE AMARRE Kg ELEMENTO POR COEF. 1,868.42
PIEZAS
S PIEZA(M)
ACERO LONG. ∅ 1/2" CORRUGADO
PRIMER PISO
EJE 1-1 ENTRE A-B Kg 1.00 2.00 5.14 0.99 10.22
EJE 1-1 ENTRE B-D Kg 1.00 2.00 3.15 1.99 12.56
EJE 3-3 ENTRE A-B Kg 1.00 2.00 3.97 2.99 23.77
EJE 3-3 ENTRE C-D Kg 1.00 2.00 1.64 3.99 13.10
EJE B-B ENTRE 3-4 Kg 1.00 2.00 0.99 4.99 9.89
EJE B-B ENTRE 4-5 Kg 1.00 2.00 1.09 5.99 13.11
EJE B-B ENTRE 5-6 Kg 1.00 2.00 4.55 6.99 63.65
DIVISIONES DE SS.HH AULA Kg 1.00 2.00 2.49 7.99 39.81
Kg 1.00 2.00 4.04 8.99 72.67
DIVISIONES DE SS.HH. OFICINAS Kg 1.00 2.00 5.15 9.99 102.94
Kg 1.00 2.00 5.82 10.99 127.97
SEGUNDO PISO
EJE 1-1 ENTRE A-B Kg 1.00 2.00 5.14 12.99 133.58
EJE 1-1 ENTRE B-D Kg 1.00 2.00 3.40 13.99 95.16
EJE 3-3 ENTRE A-B Kg 1.00 2.00 3.97 14.99 119.05
EJE B-B ENTRE 4-5 Kg 1.00 2.00 2.56 15.99 81.89
EJE B-B ENTRE 5-6 Kg 1.00 2.00 4.55 16.99 154.65
PASADIZOS Kg 1.00 2.00 12.19 17.99 438.69
Kg 1.00 2.00 4.59 18.99 174.36
Kg 2.00 2.00 1.89 19.99 151.15
ESTRIBOS [ ] 1/4" 1@.05, 4@.10 R .20
PRIMER PISO
EJE 1-1 ENTRE A-B Kg 1.00 28.00 0.28 0.25 1.95
EJE 1-1 ENTRE B-D Kg 1.00 18.00 0.28 0.25 1.25
EJE 3-3 ENTRE A-B Kg 1.00 22.00 0.28 0.25 1.53
EJE 3-3 ENTRE C-D Kg 1.00 10.00 0.28 0.25 0.70
EJE B-B ENTRE 3-4 Kg 1.00 6.00 0.28 0.25 0.42
EJE B-B ENTRE 4-5 Kg 1.00 7.00 0.28 0.25 0.49
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO SUM-ADMINISTRATIVO

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

EJE B-B ENTRE 5-6 Kg 1.00 25.00 0.28 0.25 1.74


DIVISIONES DE SS.HH AULA Kg 1.00 15.00 0.28 0.25 1.05
Kg 1.00 22.00 0.28 0.25 1.53
DIVISIONES DE SS.HH. OFICINAS Kg 1.00 28.00 0.28 0.25 1.95
Kg 1.00 31.00 0.28 0.25 2.16
SEGUNDO PISO
EJE 1-1 ENTRE A-B Kg 1.00 28.00 0.28 0.25 1.95
EJE 1-1 ENTRE B-D Kg 1.00 19.00 0.28 0.25 1.32
EJE 3-3 ENTRE A-B Kg 1.00 22.00 0.28 0.25 1.53
EJE B-B ENTRE 4-5 Kg 1.00 15.00 0.28 0.25 1.05
EJE B-B ENTRE 5-6 Kg 1.00 25.00 0.28 0.25 1.74
PASADIZOS Kg 1.00 63.00 0.28 0.25 4.39
Kg 1.00 25.00 0.28 0.25 1.74
Kg 2.00 12.00 0.28 0.25 1.67

LOSA ALIGERADA
CONCRETO EN LOSA ALIGERADA f'c=210 kg/cm2 m3 CONCRETO M3/M2 24.40

PRIMER PISO
1.00 1.00 5.75 5.89 0.0875 2.96
1.00 1.00 5.89 1.45 0.0875 0.75
1.00 1.00 5.75 4.20 0.0875 2.11
1.00 1.00 3.35 4.20 0.0875 1.23
1.00 1.00 4.28 4.20 0.0875 1.57
1.00 1.00 6.08 4.20 0.0875 2.23
1.00 1.00 1.75 1.45 0.0875 0.22
1.00 1.00 4.28 1.45 0.0875 0.54
1.00 1.00 6.08 1.45 0.0875 0.77
SEGUNDO PISO
1.00 1.00 5.75 5.89 0.0875 2.96
1.00 1.00 5.75 1.95 0.0875 0.98
1.00 1.00 4.45 1.45 0.0875 0.56
1.00 1.00 1.45 0.76 0.0875 0.10
1.00 1.00 3.90 2.75 0.0875 0.94
1.00 1.00 3.35 4.20 0.0875 1.23
1.00 1.00 4.28 4.20 0.0875 1.57
1.00 1.00 6.08 4.20 0.0875 2.23
1.00 1.00 0.88 1.45 0.0875 0.11
1.00 1.00 4.28 1.45 0.0875 0.54
1.00 1.00 6.08 1.45 0.0875 0.77

ENCOFRADO Y DESENCOFRADO PARA LOSAS ALIGERADAS 278.88

PRIMER PISO
1.00 1.00 5.75 5.89 33.87
1.00 1.00 5.89 1.45 8.54
1.00 1.00 5.75 4.20 24.15
1.00 1.00 3.35 4.20 14.07
1.00 1.00 4.28 4.20 17.96
1.00 1.00 6.08 4.20 25.54
1.00 1.00 1.75 1.45 2.54
1.00 1.00 4.28 1.45 6.20
1.00 1.00 6.08 1.45 8.82
SEGUNDO PISO
1.00 1.00 5.75 5.89 33.87
1.00 1.00 5.75 1.95 11.21
1.00 1.00 4.45 1.45 6.45
1.00 1.00 1.45 0.76 1.10
1.00 1.00 3.90 2.75 10.73
1.00 1.00 3.35 4.20 14.07
1.00 1.00 4.28 4.20 17.96
1.00 1.00 6.08 4.20 25.54
1.00 1.00 0.88 1.45 1.27
1.00 1.00 4.28 1.45 6.20
1.00 1.00 6.08 1.45 8.82

N° DE LONGITUD
N° DE
ACERO CORRUGADO FY=4200 KG/CM2 PARA LOSA ALIGERADA kg ELEMENTO POR coef. 2,168.62
PIEZAS
S PIEZA(M)
VIGUETAS 1/2" (INCLUYE VIGUETAS EN ALERO)
PRIMER PISO
1.00 14.00 7.70 0.99 107.15
1.00 14.00 4.15 0.99 57.75
1.00 14.00 3.90 0.99 54.27
1.00 14.00 1.35 0.99 18.79
1.00 14.00 3.25 0.56 25.48
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO SUM-ADMINISTRATIVO

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

1.00 10.00 6.10 0.99 60.63


1.00 10.00 4.15 0.99 41.25
1.00 10.00 1.40 0.99 13.92
1.00 10.00 1.35 0.99 13.42
1.00 10.00 3.25 0.56 18.20
1.00 35.00 6.14 0.99 213.61
1.00 35.00 2.62 0.99 91.15
1.00 35.00 3.90 0.99 135.68
1.00 35.00 1.35 0.99 46.97
1.00 35.00 1.72 0.56 33.71
SEGUNDO PISO
1.00 14.00 7.70 0.99 107.15
1.00 14.00 4.15 0.99 57.75
1.00 14.00 3.90 0.99 54.27
1.00 14.00 1.35 0.99 18.79
1.00 14.00 3.25 0.56 25.48
1.00 9.00 3.05 0.99 27.29
1.00 9.00 4.15 0.99 37.13
1.00 9.00 0.70 0.99 6.26
1.00 9.00 0.68 0.99 6.04
1.00 9.00 1.63 0.56 8.19
1.00 35.00 6.14 0.99 213.61
1.00 35.00 2.62 0.99 91.15
1.00 35.00 3.90 0.99 135.68
1.00 35.00 1.35 0.99 46.97
1.00 35.00 1.72 0.56 33.71
1.00 12.00 2.24 0.99 26.66
1.00 12.00 1.31 0.99 15.63
1.00 12.00 0.68 0.99 8.05
1.00 12.00 0.68 0.99 8.05
1.00 12.00 0.86 0.56 5.78
ACERO DE TEMPERATURA 1/4" (INCLUYE ALERO)
PRIMER PISO
1.00 23.00 10.34 0.249 59.22
1.00 6.00 5.89 0.249 8.80
1.00 24.00 14.08 0.249 84.14
SEGUNDO PISO
1.00 32.00 7.22 0.249 57.53
1.00 24.00 15.62 0.249 93.32

LADRILLO ARCILLA PARA TECHO 15X30X30 CM UND AREA LAD/M2 2,324.00

UND 1.00 278.88 8.33 2,324.00

ESCALERA
CONCRETO EN LOSA ALIGERADA f'c=210 kg/cm2 m3 3.86
Tramo i 1.00 1.00 1.60 1.01 1.62
Tramo II 1.00 1.00 1.60 0.22 0.35
Tramo III 1.00 1.00 1.60 0.29 0.46
Tramo IV 1.00 1.00 1.60 0.89 1.42
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : MODULO SUM-ADMINISTRATIVO

ESPECIALIDAD : ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

ENCOFRADO Y DESENCOFRADO PARA ESCALERAS 26.38

Pasos y Contrapasos
1.00 21.00 1.60 0.165 5.54
Lados -
1.00 2.00 3.52 0.33 2.32
1.00 2.00 1.10 0.2 0.44
1.00 2.00 3.40 0.33 2.24
1.00 2.00 1.50 0.2 0.60
Fondo

1.00 1.00 3.52 1.60 5.63


1.00 1.00 1.10 1.60 1.76
1.00 1.00 3.40 1.60 5.44
1.00 1.00 1.50 1.60 2.40

N° DE LONGITUD
N° DE
ACERO CORRUGADO FY=4200 KG/CM2 PARA ESCALERA kg ELEMENTO POR coef. 267.57
PIEZAS
S PIEZA(M)
Primer Tramo
ACERO ∅ 1/2" CORRUGADO 1.00 11.00 5.30 0.99 57.95
1.00 11.00 1.97 0.99 21.54
ACERO ∅ 3/8" CORRUGADO 1.00 11.00 2.10 0.56 12.94
1.00 11.00 2.60 0.56 16.02
1.00 38.00 1.60 0.56 34.05
Segundo Tramo
ACERO ∅ 1/2" CORRUGADO 1.00 11.00 6.50 0.99 71.07
1.00 4.00 2.50 0.99 9.94
ACERO ∅ 3/8" CORRUGADO 1.00 7.00 2.30 0.56 9.02
1.00 7.00 1.40 0.56 5.49
1.00 33.00 1.60 0.56 29.57

ESTRUCTURA DE MADERA Y COBERTURA

CORREAS DE MADERA TORNILLO DE 2"X1" m3 182.33


Modulo de 01 Aula 1.00 9.00 7.60 68.40
1.00 7.00 16.28 113.93

COBERTURA DE FIBRO CEMENTO m2 172.87


Modulo de 01 Aula 1.00 1.00 7.60 8.72 66.27
1.00 1.00 16.28 6.55 106.60
METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : CISTERNA

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

OBRAS PROVISIONALES,TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD

OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES

TRAZO Y REPLANTEO

TRAZO Y REPLANTEO TOPOGRAFICO m2 8.53


1.00 1.00 3.30 2.35 7.76
1.00 1.00 1.55 0.50 0.78

ESTRUCTURAS

CONCRETO SIMPLE

FALSOS CIMIENTOS

SOLADOS

RELLENO DE CONCRETO SIMPLE C:H 1:12 e=4".. m3 6.70


CISTERNA
1.00 2.00 2.85 1.18 6.70

DADOS DE CONCRETO

DADOS DE CONCRETO F´C=175 Kg/cm2 m3 0.01


CONCRETO F´C= 175 kg/cm2 1.00 22.00 0.08 0.08 0.08 0.01

ENCOFRADO Y DESENCOFRADO DE DADOS DE CONCRETO m2 0.62


1.00 22.00 0.38 0.08 0.62

CONCRETO ARMADO

LOSA DE CIMENTACIÓN

CONCRETO f'c=210 kg/cm2 PARA LOSA DE CIMENTACIÓN m3 1.19


Losa de Cimentación 1.00 2.00 2.35 1.15 0.15 0.81
Losa de Cimentación 1.00 2.00 2.35 0.20 0.10 0.09
Artesa 1.00 1.00 2.35 0.60 0.15 0.21
Caja de Rebose 1.00 1.00 1.55 0.50 0.10 0.08

ENCOFRADO Y DESENCOFRADO EN LOSA DE CIMENTACIÓN m2 2.49


Losa de Cimentación 1.00 2.00 2.35 0.15 0.71
Losa de Cimentación 1.00 2.00 3.30 0.15 0.99
Artesa 1.00 2.00 1.35 0.20 0.54
Caja de Rebose 1.00 1.00 1.55 0.10 0.16
Caja de Rebose 1.00 2.00 0.50 0.10 0.10

ACERO CORRUGADO FY=4200 KG/CM2 PARA LOSA DE CIMENTACIÓN kg #varillas long. Coef. 153.40

Losa de Cimentación
1/2" 1.00 26.00 2.68 0.99 69.26
1/2" 2.00 10.00 2.08 0.99 41.35
1/2" 1.00 10.00 2.25 0.99 22.37
1/2" 1.00 10.00 1.32 0.99 13.12

PLACAS

CONCRETO f'c=210 kg/cm2 PARA MUROS DE CISTERNA m3 3.25


Muro de Cisterna 1.00 2.00 3.30 0.20 1.40 1.85
Muros de Cisterna 1.00 2.00 1.95 0.20 1.40 1.09
Caja de Rebose 1.00 1.00 1.55 0.10 0.65 0.10
Caja de Rebose 1.00 2.00 0.50 0.10 0.65 0.07
Muros de la Tapa 1.00 4.00 0.70 0.10 0.50 0.14

ENCOFRADO Y DESENCOFRADO EN CISTERNA m2 33.07


METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : CISTERNA

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

Muro de Cisterna 1.00 4.00 3.30 1.40 18.48


Muros de Cisterna 1.00 4.00 1.95 1.40 10.92
Caja de Rebose 1.00 2.00 1.55 0.65 2.02
Caja de Rebose 1.00 4.00 0.50 0.65 1.30
Muros de Tapa 1.00 1.00 0.70 0.50 0.35

ACERO CORRUGADO FY=4200 KG/CM2 PARA CISTERNA kg Coef. 218.71


Muro de Cisterna
ACERO HORIZONTAL 3/8" 2.00 12.00 2.80 0.56 37.63
ACERO VERTICAL 3/8" 2.00 16.00 2.15 0.56 38.53
ACERO HORIZONTAL 3/8" 2.00 12.00 3.74 0.56 50.27
ACERO VERTICAL 3/8" 2.00 22.00 2.15 0.56 52.98
ACERO HORIZONTAL (TAPA) 3/8" 2.00 4.00 0.65 0.56 2.91
ACERO VERTICAL (TAPA) 3/8" 4.00 3.00 1.00 0.56 6.72
ACERO HORIZONTAL (CAJA DE REBOSE) 3/8" 1.00 6.00 2.70 0.56 9.07
ACERO VERTICAL (CAJA DE REBOSE) 3/8" 1.00 13.00 1.40 0.56 10.19

LOSA MACIZA

CONCRETO f'c=210 kg/cm2 PARA LOSA MACIZA m3 1.11


Losa Maciza 1.00 1.00 3.30 2.35 0.15 1.16
Tapa (restar) 1.00 - 1.00 0.60 0.60 0.15 - 0.05

ENCOFRADO Y DESENCOFRADO EN LOSA MACIZA m2 7.40


Losa Maciza 1.00 1.00 3.30 2.35 7.76
1.00 - 1.00 0.60 0.60 - 0.36

ACERO CORRUGADO FY=4200 KG/CM2 PARA LOSA MACIZA kg #varillas long. Coef. 174.41
Losa Maciza
1/2" 1.00 28.00 2.79 0.99 77.65
1/2" 1.00 15.00 3.49 0.99 52.04
1/2" 1.00 16.00 1.49 0.99 23.70
1/2" 1.00 8.00 1.60 0.99 12.72

COBERTURA Y ESTRUCTURA METÁLICA

ESTRUCTURA METÁLICA

ESCALERA TIPO GATO glb 1.00


Escalera tipo gato 1 1 1

REJILLA METALICA glb 1.00


Rejilla Metalica (según diseño)de 0.5x1.25 1 1 1

TAPA METALICA Und 1.00


Tapa Metalica De 0.50x0.50 según diseño 1 1 1
METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : TANQUE ELEVADO

ESPECIALIDAD : ESTRUCTURAS

DESCRIPCION UND REP.CANTIDADLARGO ANCHO ALTURA AREA PARCIAL TOTAL

OBRAS PROVISIONALES,TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD

OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES

TRAZO Y REPLANTEO

TRAZO Y REPLANTEO TOPOGRAFICO m2 7.20

1.00 1.00 3.35 2.15 7.20

ESTRUCTURAS

CONCRETO ARMADO

COLUMNAS

CONCRETO f'c= 210 kg/cm2 EN COLUMNAS m3 0.30


COLUMNAS C-2 0.25mx0.50m 1.00 2.00 0.50 0.25 1.20 0.30

ENCOFRADO Y DESENCOFRADO EN TANQUE ELEVADO m2 1.80


COLUMNAS C-2 0.25mx0.50m 1.00 2.00 0.50 1.20 1.20
1.00 2.00 0.25 1.20 0.60

ACERO CORRUGADO FY=4200 KG/CM2 PARA TANQUE ELEVADO kg 49.79


Columnas C-2
5/8" 2.00 1.00 4.00 1.45 1.55 18.00
1/2" 2.00 1.00 4.00 1.40 0.99 11.09
estribos 3/8" 2.00 1.00 12.00 1.54 0.56 20.70

VIGAS

CONCRETO f'c= 210 kg/cm2 EN VIGAS m3 0.92


VIGAS 0.25x0.30 (V-TE1)
1.00 2.00 1.65 0.25 0.30 0.25
VIGAS 0.25X0.40 (V-TE2)
1.00 2.00 3.35 0.25 0.40 0.67

ENCOFRADO Y DESENCOFRADO EN VIGAS m2 7.34


VIGAS 0.25x0.30 (V-TE1)
2.00 2.00 1.65 0.30 1.98
VIGAS 0.25X0.40 (V-TE2)
2.00 2.00 3.35 0.40 5.36

ACERO CORRUGADO FY=4200 KG/CM2 PARA VIGAS kg #varillas long. Coef. 113.27

VIGAS 0.25x0.30 (V-TE1) 1/2" 1.00 2.00 4.00 2.57 0.99 20.35
VIGAS 0.25X0.40 (V-TE2) 1/2" 1.00 2.00 4.00 3.77 0.99 29.86
estribos 3/8" 1.00 2.00 20.00 1.14 0.56 25.54
3/8" 1.00 2.00 25.00 1.34 0.56 37.52

LOSA MACIZA

CONCRETO f'c= 210 kg/cm2 EN LOSA MACIZA m3 1.91


LOSA MACIZA
1.00 1.00 3.75 2.55 0.20 1.91

ENCOFRADO Y DESENCOFRADO EN LOSA MACIZA m2 12.08


LOSA MACIZA
1.00 1.00 3.75 2.55 9.56
1.00 1.00 12.60 0.20 2.52

ACERO CORRUGADO FY=4200 KG/CM2 PARA LOSA MACIZA kg 161.01


LOSA MACIZA
HORIZONTAL 1/2" 1.00 2.00 11.00 3.82 0.99 83.20
1/2" 1.00 2.00 15.00 2.62 0.99 77.81

COBERTURA Y ESTRUCTURA METÁLICA


METRADO - ESTRUCTURAS

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA : MARZO 2021 AMBIENTES : TANQUE ELEVADO

ESPECIALIDAD : ESTRUCTURAS

DESCRIPCION UND REP.CANTIDADLARGO ANCHO ALTURA AREA PARCIAL TOTAL

ESTRUCTURA METÁLICA

ESCALERA TIPO GATO glb 1.00


1.00 1.00 1.00

BARANDA METALICA DE SEGURIDAD M 12.90


1.00 1.00 12.90 12.90

CORREA DE PROTECCION DEL TANQUE UND 1.00


1.00 1.00 1.00
METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : REMOCIONES Y DESMONTAJE

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP.CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

OBRAS PROVISIONALES,TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD

OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES

REMOCIONES

DESMONTAJE PUERTAS DE MADERA INC. MARCO m2 25.74

P - 01 1.00 1.00 2.55 2.55

P - 02 2.00 0.95 2.35 4.47

P - 03 2.00 0.85 2.08 3.54

P - 04 1.00 1.20 2.10 2.52

P - 05 1.00 0.80 2.00 1.60

P - 06 2.00 0.70 1.50 2.10

P - 07 1.00 0.90 2.10 1.89

P - 08 1.00 0.85 2.00 1.70

P - 09 1.00 1.00 2.00 2.00

P - 11 3.00 0.75 1.50 3.38

DESMONTAJE DE VENTANA m2 63.08

V - 01 1.00 3.20 1.47 4.70

V - 02 1.00 3.20 1.50 4.80

V - 03 1.00 3.20 0.38 1.22

V - 04 1.00 3.20 0.40 1.28

V - 05 2.00 1.50 1.10 3.30

V - 06 1.00 7.40 0.38 2.81

V - 07 2.00 1.50 1.10 3.30

V - 08 1.00 7.40 0.38 2.81

V - 09 1.00 2.26 1.30 2.94

V - 10 1.00 3.85 1.33 5.12

V - 11 1.00 2.65 1.33 3.52

V - 12 1.00 2.10 0.90 1.89

V - 13 1.00 2.10 0.90 1.89

V - 14 1.00 1.85 0.90 1.67

V - 15 1.00 1.85 0.90 1.67

V - 16 12.00 1.20 1.40 20.16

DESMONTAJE DE PORTON u 7.38

P - 10 (PORTON DE INGRESO) 1.00 2.95 2.50 7.38

DESMONTAJE DE TECHO DE QUINCHA (Cobertura de Caña Brava, Plástico,


m2 45.69
Estera)
ESTERIORES 1.00 45.69 45.69

DESMONTAJE DE COBERTURA DE CALAMINON, CALAMINA ETERNIT Y


m2 632.13
ALUZINC TIPO TR4
MODULO 1 (SS.HH.) 1.00 17.45 17.45

MODULO 2 (AULA) 1.00 48.50 48.50

MODULO 3 (AULA) 1.00 42.56 42.56

MODULO 4 (AULA) 1.00 42.56 42.56

MODULO 5 (ALMACEN) 1.00 35.00 35.00

MODULO 5 (COCINA) 1.00 35.00 35.00

MODULO 6 (AULA) 1.00 60.45 60.45

MODULO 8 (DEPOSITO) 1.00 10.04 10.04

MODULO 9 (DEPOSITO DE MATERIAL DESECHABLE) 1.00 51.10 51.10

MODULO 10 (AULA) 1.00 39.36 39.36

MODULO 11 (DIRECCION) 1.00 17.37 17.37

MODULO 12 (AULA) 1.00 44.44 44.44

PATIO 1.00 188.30 188.30


METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : REMOCIONES Y DESMONTAJE

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP.CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

DESMONTAJE DE COBERTURA DE MALLA RASCHEL m2 120.45

EXTERIORES 1.00 120.45 120.45

DESMONTAJE DE COLUMNA CIRCULAR METÁLICA u 12.00

EXTERIORES 12.00 12.00

DESMONTAJE DE VIGA METÁLICA u 28.00

MODULO 3 6.00 6.00

MODULO 4 6.00 6.00

MODULO 10 6.00 6.00

PATIO 10.00 10.00

DESMONTAJE DE VIGA DE MADERA u 24.00

MODULO 5 7.00 7.00

MODULO 9 12.00 12.00

MODULO 11 5.00 5.00

DESMONTAJE DE MUROS DE MADERA MACHIHEMBRADA , TRIPLAY m2 72.87

MODULO 3 1 6.70 2.45 16.42


1 5.60 2.55 14.28
1 7.50 3.50 26.25
MODULO 4 1 6.50 2.45 15.93
1 5.60 2.55 14.28
1 7.50 3.50 26.25
MODUO 5: ALMACEN 1 1.15 2.45 2.82
1 4.86 2.50 12.15
1 2.10 3.40 7.14
MODULO 5: COCINA 1 1.45 2.45 3.55
1 4.00 3.40 13.60
MODULO 8 1 1.95 2.74 5.34
MPDULO 9 1 8.20 3.00 24.60
2 6.40 3.20 40.96
MODULO 10 2 5.09 2.50 25.45
1 7.15 2.60 18.59
MODULO 11 1 2.85 2.50 7.13

DESMONTAJE DEL MODULO DE PRONIED Glb 1.00


Modulo Construido por el PRONIED, con estructura metalica y la rampa de acceso 1 1.00

DESMONTAJE DE APARATOS SANITARIOS u 5.00


Inodoros 5.00 5.00

DESMONTAJE DE ACCESOS ELECTRICOS u 52.00

en luminarias 1.00 25.00 25.00

en interruptores 1.00 12.00 12.00

en tomacorrientes 1.00 15.00 15.00

DESMONTAJE DE ASTA DE BANDERA u 1.00

1.00 1.00

DEMOLICION

DEMOLICION CIMIENTOS DE CONCRETO m3 54.99

MODULO 1

1.00 1.78 0.60 0.50 0.53

3.00 1.70 0.60 0.50 1.53

1.00 1.25 0.60 0.50 0.38

1.00 1.15 0.60 0.50 0.35

1.00 3.40 0.60 0.80 1.63

MODULO 2

2.00 8.60 0.60 0.60 6.19

2.00 6.70 0.60 0.60 4.82


METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : REMOCIONES Y DESMONTAJE

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP.CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

MODULO 12

1.00 6.04 0.60 0.60 2.17

1.00 8.60 0.60 0.60 3.10

CERCO DE ADOBE HACIA LA CALLE CARRION MATOS

1.00 34.00 0.80 0.80 21.76

CERCO DE LADRILLO EN LA FACHADA PRINCIPAL

1.00 12.80 0.60 0.80 6.14

1.00 13.30 0.60 0.80 6.38

DEMOLICION DE SOBRECIMIENTO DE CONCRETO m3 17.24

MODULO 1

1.00 1.78 0.15 0.50 0.13

3.00 1.70 0.15 0.50 0.38

1.00 1.25 0.15 0.50 0.09

1.00 1.15 0.15 0.50 0.09

1.00 3.40 0.25 0.50 0.43

MODULO 2

1.00 8.60 0.25 0.50 1.08

1.00 7.60 0.25 0.50 0.95

2.00 6.70 0.25 0.50 1.68

MODULO 12

1.00 6.04 0.25 0.50 0.76

1.00 7.60 0.25 0.50 0.95

CERCO DE ADOBE HACIA LA CALLE CARRION MATOS

1.00 34.00 0.40 0.50 6.80

CERCO DE LADRILLO EN LA FACHADA PRINCIPAL

1.00 12.80 0.25 0.60 1.92

1.00 13.30 0.25 0.60 2.00

DEMOLICION DE COLUMNAS DE CONCRETO m3 6.73

MODULO 2

C1 30X30 4.00 0.30 0.30 3.00 1.08

C1 30X30 4.00 0.30 0.30 3.80 1.37

MODULO 12

C1 30X30 4.00 0.30 0.30 3.00 1.08

C1 30X30 3.00 0.30 0.30 3.80 1.03

FACHADA

C2 25X25 6.00 0.25 0.25 2.80 1.05

MODULO 7

C2 25X25 6.00 0.25 0.25 3.00 1.13

DEMOLICION DE VIGAS DE CONCRETO m3 6.14

MODULO 2

V1 25X30 2.00 3.20 0.25 0.30 0.48

V1 25X30 2.00 4.38 0.25 0.30 0.66

V1 25X25 2.00 6.10 0.25 0.30 0.92

MODULO 12

V1 25X30 2.00 3.87 0.25 0.30 0.58

V1 25X30 2.00 4.38 0.25 0.30 0.66

V1 25X25 2.00 5.60 0.25 0.30 0.84

FACHADA

V2 25X25 1.00 5.40 0.25 0.25 0.34

V2 25X25 1.00 6.45 0.25 0.25 0.40

V2 25X25 1.00 6.00 0.25 0.25 0.38

V2 25X25 1.00 6.30 0.25 0.25 0.39

MODULO 7
METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : REMOCIONES Y DESMONTAJE

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP.CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

V 25X25 1.00 6.20 0.25 0.25 0.39

V 015X0.25 1.00 2.90 0.15 0.25 0.11

DEMOLICION DE TECHO ALIGERADO m3 2.34

MODULO 7

1.00 4.10 2.85 0.20 2.34

DEMOLICION DE PISOS DE CONCRETO INC. FALSO PISO m2 382.69

MODULO 1 (SS.HH.) 1.00 17.45 17.45

MODULO 2 (AULA) 1.00 48.50 48.50

MODULO 3 (AULA) 1.00 42.56 42.56

MODULO 4 (AULA) 1.00 42.56 42.56

MODULO 5 (ALMACEN) 1.00 35.00 35.00

MODULO 5 (COCINA) 1.00 35.00 35.00

MODULO 6 (AULA) 1.00 60.45 60.45

MODULO 10 (AULA) 1.00 39.36 39.36

MODULO 11 (DIRECCION) 1.00 17.37 17.37

MODULO 12 (AULA) 1.00 44.44 44.44

DEMOLICION DE PATIOS, VEREDAS Y CIRCULACIÓN DE E=0.15 m m2 217.89


PATIO 1.00 188.30 188.30

VEREDA 1.00 29.59 29.59

DEMOLICION DE MUROS DE ALBAÑILERIA m2 98.73

MODULO 1

3.00 1.68 1.70 8.57

1.00 1.22 1.70 2.07

1.00 1.15 1.70 1.96

MODULO 7

1.00 3.70 2.85 10.55

1.00 1.50 2.85 4.28

1.00 1.95 2.85 5.56

1.00 0.95 2.85 2.71

FACHADA

1.00 5.40 2.30 12.42

1.00 6.45 2.30 14.84

1.00 6.00 2.30 13.80

1.00 6.30 2.30 14.49

1.00 3.00 2.50 7.50

DEMOLICION DE MUROS DE ADOBE m2 216.04

MODULO 2

1.00 3.20 1.10 3.52

1.00 3.20 1.10 3.52

1.00 3.20 2.16 6.91

1.00 3.20 2.16 6.91

1.00 1.50 3.50 5.25

2.00 6.10 3.00 36.60

MODULO 12

1.00 2.67 1.20 3.20

1.00 3.87 1.20 4.64

1.00 3.87 3.50 13.55

1.00 3.95 3.50 13.83

1.00 5.37 3.00 16.11

CERCO DE ADOBE HACIA LA CALLE CARRION MATOS

1.00 34.00 3.00 102.00


METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : REMOCIONES Y DESMONTAJE

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP.CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

DEMOLICION DE URINARIOS Y BEBEDEROS ml 7.86


EN EL MODULO 1
BEBEDERO 1 1.5 1.50
URINARIO 1 1.68 1.68
EN EL MODULO 7
BEBEDERO 1 1.5 1.50
BEBEDERO 1 1.5 1.50
URINARIO 1 1.68 1.68

ELIMINACION DE EXCAVACIONES

ACARREO INTERNO DE MATERIAL PROCEDENTE DE DEMOLICIONES Y


m3 324.51
EXCAVACIONES
1.00 1.00 259.61 1.25 324.51

ELIMINACION DEMATERIAL EXCEDENTE PROCEDENTE DE DEMOLICION Y


m3 324.51
EXCAVACIONES
1.00 1.00 324.51 324.51
METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : CERCO PERIMÉTRICO Y PORTADA PRINCIPAL

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD

OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES

LIMPIEZA, TRAZO Y REPLANTEO GENERAL

LIMPIEZA DE TERRENO MANUAL/ EQUIPO m2 27.11


Cerco Perimetrico Tipo UNI 1.00 1.00 22.51 0.60 13.51
Cerco Perimetrico 1.00 1.00 13.11 0.50 6.56
Portada Principal 1.00 1.00 7.05 1.00 7.05

TRAZO Y REPLANTEO

TRAZO Y REPLANTEO TOPOGRAFICO m2 27.11


Cerco Perimetrico Tipo UNI 1.00 1.00 22.51 0.60 13.51
Cerco Perimetrico 1.00 1.00 13.11 0.50 6.56
Portada Principal 1.00 1.00 7.05 1.00 7.05

ESTRUCTURAS

MOVIMIENTO DE TIERRAS

EXCAVACIONES

EXCAVACION DE ZANJAS Y ZAPATAS MANUAL m3 23.34


EN ZAPATAS
Cerco perimetrico Tipo UNI (lado Izquierdo) 1.00 6.00 0.70 0.70 1.00 2.94
Cerco perimetrico Tipo UNI (lado Derecho) 1.00 8.00 0.70 0.70 1.00 3.92
Portada Principal 1.00 1.00 3.55 1.00 1.25 4.44
1.00 1.00 1.55 1.00 1.25 1.94
EN CIMIENTOS
Cerco perimetrico Tipo UNI (lado Izquierdo) 1.00 4.00 2.10 0.50 0.50 2.10
Cerco perimetrico Tipo UNI (lado Derecho) 1.00 1.00 7.30 0.50 0.50 1.83
Cerco Perimetrico de Ladrillo 1.00 1.00 12.88 0.60 0.80 6.18

RELLENOS

RELLENO C/MATERIAL PROPIO PARA RELLENAR ZANJAS m3 6.69


EN ZAPATAS
Cerco perimetrico Tipo UNI (lado Izquierdo) 1.00 6.00 0.70 0.40 0.30 0.50
Cerco perimetrico Tipo UNI (lado Derecho) 1.00 8.00 0.70 0.40 0.30 0.67
Portada Principal 1.00 1.00 0.65 3.23 2.10
1.00 1.00 0.65 1.43 0.93
EN CIMIENTOS
Cerco perimetrico Tipo UNI (lado Izquierdo) 1.00 4.00 2.10 0.20 0.30 0.50
Cerco perimetrico Tipo UNI (lado Derecho) 1.00 1.00 7.30 0.20 0.30 0.44
Cerco Perimetrico de Ladrillo 1.00 1.00 12.88 0.40 0.30 1.55

ELIMINACION DE EXCAVACIONES

ACARREO INTERNO DE MATERIAL PROCEDENTE DE DEMOLICIONES Y


m3 20.82
EXCAVACIONES
1.00 1.00 16.66 1.25 20.82

ELIMINACION DEMATERIAL EXCEDENTE PROCEDENTE DE DEMOLICION Y


m3 20.82
EXCAVACIONES
1.00 1.00 20.82 20.82
METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : CERCO PERIMÉTRICO Y PORTADA PRINCIPAL

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

NIVELACION INTERIOR Y APISONADO

NIVELACION INTERIOR Y APISONADO m2 27.54


EN ZAPATAS
Cerco perimetrico Tipo UNI (lado Izquierdo) 1.00 6.00 0.70 0.70 2.94
Cerco perimetrico Tipo UNI (lado Derecho) 1.00 8.00 0.70 0.70 3.92
Portada Principal 1.00 1.00 3.55 1.00 3.55
1.00 1.00 1.55 1.00 1.55
EN CIMIENTOS
Cerco perimetrico Tipo UNI (lado Izquierdo) 1.00 4.00 2.10 0.50 4.20
Cerco perimetrico Tipo UNI (lado Derecho) 1.00 1.00 7.30 0.50 3.65
Cerco Perimetrico de Ladrillo 1.00 1.00 12.88 0.60 7.73

CONCRETO SIMPLE

FALSO CIMIENTOS

SOLADOS

SOLADO PARA CIMIENTOS Y ZAPATAS: CONCRETO C:H 1:12 e=4".. m2 14.08

EN ZAPATAS
Cerco perimetrico Tipo UNI (lado Izquierdo) 1.00 6.00 0.70 0.70 2.94
Cerco perimetrico Tipo UNI (lado Derecho) 1.00 8.00 0.70 0.70 3.92
Portada Principal 1.00 1.00 3.55 1.00 3.55
1.00 1.00 1.55 1.00 1.55
Cerco perimetrico Tipo UNI (lado Izquierdo) 1.00 7.00 0.55 0.55 2.12

CIMIENTOS CORRIDOS

CIMIENTO CORRIDO: CONCRETO C:H 1:10+30% P.G. m3 3.90


CIMIENTO CORRIDO
Cerco Perimetrico de Ladrillo 1.00 1.00 11.83 0.55 0.60 3.90

SOBRECIMIENTOS

SOBRECIMIENTO: CONCRETO C:H 1:8+25% P.G. m3 0.89

Cerco Perimetrico de Ladrillo 1.00 1.00 11.83 0.15 0.50 0.89

ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS m3 11.83

Cerco Perimetrico de Ladrillo 1.00 2.00 11.83 0.50 11.83

DADOS DE CONCRETO

DADOS DE CONCRETO F`c = 175kg/cm2 m2 0.01


1.00 22.00 0.08 0.08 0.08 0.01

ENCOFRADO Y DESENCOFRADO DE DADOS DE CONCRETO m2 0.62


1.00 22.00 0.38 0.08 0.62

CONCRETO ARMADO

ZAPATAS

CONCRETO f'c= 175 kg/cm2 EN ZAPATAS m3 5.73


EN ZAPATAS
Cerco perimetrico Tipo UNI (lado Izquierdo) 1.00 6.00 0.70 0.70 0.65 1.91
Cerco perimetrico Tipo UNI (lado Derecho) 1.00 8.00 0.70 0.70 0.65 2.55
Cerco Perimetrico de Ladrillo 1.00 7.00 0.55 0.55 0.60 1.27

CONCRETO f'c= 210 kg/cm2 EN ZAPATAS m3 2.55


Portada Principal 1.00 1.00 3.55 1.00 0.50 1.78
1.00 1.00 1.55 1.00 0.50 0.78
METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : CERCO PERIMÉTRICO Y PORTADA PRINCIPAL

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

ENCOFRADO Y DESENCOFRADO EN ZAPATAS m3 perimetro 41.52


EN ZAPATAS
Cerco perimetrico Tipo UNI (lado Izquierdo) 1.00 6.00 2.80 0.65 10.92
Cerco perimetrico Tipo UNI (lado Derecho) 1.00 8.00 2.80 0.65 14.56
Portada Principal 1.00 1.00 9.10 0.50 4.55
1.00 1.00 4.50 0.50 2.25
Cerco Perimetrico de Ladrillo 1.00 7.00 2.20 0.60 9.24

ACERO ESTRUCTURAL TRABAJADO PARA ZAPATAS kg

N° DE N° DE LONGITUD POR
ZAPATAS UNIDAD Ø 1/4" 3/8" 1/2" 5/8"
ELEMENTOS PIEZAS PIEZA(M)

0.25 0.56 0.99 1.56


Cerco perimetrico Tipo UNI (lado Izquierdo) 3/8 6.00 2.00 1.05 7.06
Cerco perimetrico Tipo UNI (lado Derecho) 3/8 8.00 2.00 1.05 9.41
Portada Principal 1/2 1.00 24.00 1.15 27.32
1/2 1.00 6.00 3.70 21.98
1/2 1.00 8.00 1.15 9.11
1/2 1.00 6.00 1.70 10.10
Cerco Perimetrico de Ladrillo 3/8 7.00 6.00 0.50 11.76

VIGA DE CIMENTACION

CONCRETO f'c=175 kg/cm2 PARA VIGAS DE CIMENTACION m3 2.01


Cerco perimetrico Tipo UNI (lado Izquierdo) 1.00 1.00 10.08 0.30 0.30 0.91
Cerco perimetrico Tipo UNI (lado Derecho) 1.00 1.00 12.20 0.30 0.30 1.10

CONCRETO f'c=210 kg/cm2 PARA VIGAS DE CIMENTACION m3 0.76

Portada Principal 1.00 1.00 3.00 0.30 0.60 0.54


Portada Principal 1.00 1.00 1.20 0.30 0.60 0.22

ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACION m2 18.41


Cerco perimetrico Tipo UNI (lado Izquierdo) 1.00 2.00 10.08 0.30 6.05
Cerco perimetrico Tipo UNI (lado Derecho) 1.00 2.00 12.20 0.30 7.32
Portada Principal 1.00 2.00 3.00 0.60 3.60
Portada Principal 1.00 2.00 1.20 0.60 1.44

ACERO CORRUGADO FY=4200 KG/CM2 PARA VIGAS DE CIMENTACION kg

N° DE N° DE LONGITUD POR
VIGA DE CIMENTACION UNIDAD Ø 1/4" 3/8" 1/2" 5/8"
ELEMENTOS PIEZAS PIEZA(M)

Kg 0.25 0.56 0.99 1.56


VIGA DE CIMENTACION
Cerco perimetrico Tipo UNI (lado Izquierdo) 3/8 3.00 4.00 3.30 22.18
Cerco perimetrico Tipo UNI (lado Derecho) 3/8 4.00 4.00 3.30 29.57
Cerco perimetrico Tipo UNI (lado Izquierdo) 1/4 3.00 13.00 1.15 11.21
Cerco perimetrico Tipo UNI (lado Derecho) 1/4 4.00 13.00 1.15 14.95
Portada Principal 5/8 1.00 4.00 6.50 40.56
Portada Principal 1/2 1.00 2.00 5.75 11.39
Portada Principal 3/8 1.00 31.00 1.80 31.25

SOBRECIMIENTO REFORZADO

CONCRETO SOBRECIMIENTO REFORZADO f'c=175 kg/cm2 m3 4.04


Cerco perimetrico Tipo UNI (lado Izquierdo) 1.00 1.00 10.27 0.30 0.60 1.85
Cerco perimetrico Tipo UNI (lado Derecho) 1.00 1.00 12.20 0.30 0.60 2.20

ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTO REFORZADO m2 8.09

Cerco perimetrico Tipo UNI (lado Izquierdo) 1.00 2.00 10.27 0.30 0.60 3.70
Cerco perimetrico Tipo UNI (lado Derecho) 1.00 2.00 12.20 0.30 0.60 4.39

COLUMNAS
METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : CERCO PERIMÉTRICO Y PORTADA PRINCIPAL

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

CONCRETO EN COLUMNAS f'c=175 kg/cm2 CARAVISTA m3 4.44


BLOQUES DE CERCO TIPICO L=2.96, H=2.45
Cerco perimetrico Tipo UNI (lado Izquierdo) 3.50 16.00 0.14 0.08 2.65 1.66
3.50 12.00 0.11 0.08 0.08 0.03
3.50 3.00 0.12 0.08 0.08 0.01
Cerco perimetrico Tipo UNI (lado Derecho) 4.00 16.00 0.14 0.08 2.65 1.90
4.00 12.00 0.11 0.08 0.08 0.03
4.00 3.00 0.12 0.08 0.08 0.01
COLUMNAS DE CERCO PERIMETRICO DE LADRILLO
1.00 7.00 0.25 0.15 3.05 0.80

CONCRETO EN COLUMNAS f'c=210 kg/cm2 m3 2.16


COLUMNAS DE LA PORTADA PRINCIPAL
1.00 1.00 0.50 0.25 4.80 0.60
1.00 1.00 0.80 0.25 4.80 0.96
1.00 1.00 0.50 0.25 4.80 0.60

ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 perimetro 185.51


BLOQUES DE CERCO TIPICO L=2.96, H=2.45
Cerco perimetrico Tipo UNI (lado Izquierdo) 3.50 16.00 0.44 2.65 65.30
3.50 12.00 0.32 0.11 1.48
3.50 3.00 0.32 0.12 0.40
Cerco perimetrico Tipo UNI (lado Derecho) 4.00 16.00 0.44 2.65 74.62
4.00 12.00 0.32 0.11 1.69
4.00 3.00 0.32 0.12 0.46
COLUMNAS DE CERCO PERIMETRICO DE LADRILLO
1.00 7.00 0.80 3.05 17.08
COLUMNAS DE LA PORTADA PRINCIPAL
1.00 1.00 1.50 4.80 7.20
1.00 1.00 2.10 4.80 10.08
1.00 1.00 1.50 4.80 7.20

ACERO CORRUGADO FY=4200 KG/CM2 PARA COLUMNAS kg

N° DE N° DE LONGITUD POR
COLUMNAS UNIDAD Ø 1/4" 3/8" 1/2" 5/8"
ELEMENTOS PIEZAS PIEZA(M)

0.25 0.56 0.99 1.56


BLOQUES DE CERCO TIPICO L=2.96, H=2.45
Cerco perimetrico Tipo UNI (lado Izquierdo)
ACERO LONGITUDINAL 3/8 14.00 2.00 6.43 100.74
3/8 42.00 2.00 5.40
3/8 7.00 2.00 0.27
ESTRIBOS 1/4 56.00 25.00 0.20 70.00
1/4 14.00 10.00 0.72 25.20
Cerco perimetrico Tipo UNI (lado Derecho)
ACERO LONGITUDINAL 3/8 16.00 2.00 6.43 115.14
3/8 48.00 2.00 5.40
3/8 7.00 2.00 0.27
ESTRIBOS 1/4 64.00 25.00 0.20 80.00
1/4 16.00 10.00 0.72 28.80
COLUMNAS DEL CERCO PERIMETRICO DE LADRILLO
ACERO LONGITUDINAL 1/2 7.00 4.00 3.90 108.11
ESTRIBOS 1/4 7.00 20.00 0.84 29.40
COLUMNAS DE LA PORTADA PRINCIPAL
ACERO LONGITUDINAL 5/8 1.00 8.00 5.82 72.63
5/8 2.00 4.00 5.82 72.63
1/2 2.00 4.00 5.82 46.09
ESTRIBOS 3/8 1.00 35.00 2.18 42.73
3/8 2.00 29.00 1.58 51.32
METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : CERCO PERIMÉTRICO Y PORTADA PRINCIPAL

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

VIGAS

CONCRETO F'C=175 KG/CM2 EN VIGAS CARAVISTA m3 0.98


VIGAS DEL CERCO PERIMETRICO
1.00 1.00 11.83 0.13 0.15 0.23
VIGA EN LA POTADA PRINCIPAL
1.00 1.00 1.20 0.25 0.25 0.08
1.00 1.00 3.00 0.25 0.25 0.19
1.00 1.00 1.20 0.35 0.33 0.14
1.00 1.00 3.00 0.35 0.33 0.35

ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 perimetro 10.94


VIGAS DEL CERCO PERIMETRICO
1.00 1.00 11.83 0.30 3.55
VIGA EN LA POTADA PRINCIPAL
1.00 1.00 1.20 0.75 0.90
1.00 1.00 3.00 0.75 2.25
1.00 1.00 1.20 1.01 1.21
1.00 1.00 3.00 1.01 3.03

ACERO CORRUGADO fy=4200 kg/cm2 PARA VIGAS kg

N° DE N° DE LONGITUD POR
VIGAS UNIDAD Ø 1/4" 3/8" 1/2" 5/8"
ELEMENTOS PIEZAS PIEZA(M)

0.25 0.56 0.99 1.56


0 VIGAS DEL CERCO PERIMETRICO
ACERO LONGITUDINAL 1/2 1.00 2.00 12.10 23.96
ACERO LONGITUDINAL 1/2 1.00 2.00 12.10 23.96
ESTRIBOS 3/8 4.50 18.00 0.59 26.76
VIGA EN LA POTADA PRINCIPAL
ACERO LONGITUDINAL 1/2 1.00 4.00 6.42 25.42
ACERO LONGITUDINAL 1/2 1.00 4.00 6.42 25.42
ESTRIBOS 3/8 1.00 33.00 1.04 19.22
ESTRIBOS 3/8 1.00 33.00 1.65 30.49

ESTRUCTURA DE MADERA Y COBERTURA

COBERTURA C/TEJA DE ARCILLA EN CERCO DE LADRILLO ml 13.11


CERCO PERIMETRICO DE LADRILLO
1.00 1.00 13.11 13.11
METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : OBRAS EXTERIORES

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD

OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES

CONSTRUCCIONES PROVISIONALES

CARTEL DE OBRA DE 2.4 X 3.60 und 1.00


1.00 1.00 1.00
CERCO PROVISIONAL DE TRIPLAY DE 6.0 mm ml 63.35
1.00 1.00 63.35 63.35
COMEDOR PARA PERSONAL DE OBRA glb 1.00
ESTIMADA 1.00 1.00 1.00
ALAMCÉN DE OBRA glb 1.00
ESTIMADA 1.00 1.00 1.00
OFICINAS DE OBRA glb 1.00
ESTIMADA 1.00 1.00 1.00
CASETA DE GUARDIANIA glb 1.00
ESTIMADA 1.00 1.00 1.00
SERVICIOS HIGIENICOS glb 1.00
ESTIMADA 1.00 1.00 1.00

INSTALACIONES PROVISIONALES

AGUA PARA LA CONSTRUCCIÓN glb 1.00


ESTIMADA 1.00 1.00 1.00
ENERGÍA ELÉCTRICA PROVISIONAL, CONSUMO Y MANTENIMIENTO glb 1.00
ESTIMADA 1.00 1.00 1.00

LIMPIEZA, TRAZO Y REPLANTEO GENERAL

LIMPIEZA DE TERRENO MANUAL / CON EQUIPO m2 405.53


1.00 1.00 28.26 14.35 405.53

TRAZO, NIVEL Y REPLANTEO

TRAZO Y REPLANTEO ANTES Y DURANTE LA OBRA m2 402.80


PATIO 1.00 1.00 159.53 159.53
INGRESO - CIRCULACIÓN 1.00 1.00 74.37 74.37
CIRCULACION - VEREDAS 1.00 1.00 99.22 99.22
ZONA DE JUEGOS 1.00 1.00 67.97 67.97
SARDINELES PARA ÁREAS VERDES 1.00 1.00 1.71 1.71

MOVILIZACIÓN DE CAMPAMENTO, MAQUINARIA, HERRAMIENTAS Y MATERIALES

FLETE glb 1.00


1.00 1.00 1.00
MOVILIZACIÓN Y DESMOVILIZACIÓN DE HERRAMIENTAS Y EQUIPOS glb 1.00
1.00 1.00 1.00

SEGURIDAD Y SALUD
METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : OBRAS EXTERIORES

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

ELABORACIÓN, IMPLEMENTACIÓN Y ADMINISTRACIÓN DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO

PLAN DE SEGURIDAD Y SALUD EN OBRA glb 1.00


1.00 1.00 1.00
CAPACITACIÓN O CHARLAS INDUCTIVAS EN SEGURIDAD Y SALUD glb 1.00
1.00 1.00 1.00
EQUIPAMIENTO DE PROTECCIÓN INDIVIDUAL und 75.00
1.00 75.00 75.00
EQUIPAMIENTO DE PROTECCIÓN COLECTIVA glb 1.00
1.00 1.00 1.00
SEÑALIZACIÓN PARA SEGURIDAD EN OBRA glb 1.00
1.00 1.00 1.00
RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y
glb 1.00
SALUD DURANTE EL TRABAJO
1.00 1.00 1.00
MITIGACIÓN DEL IMPACTO AMBIENTAL glb 1.00
1.00 1.00 1.00

ESTRUCTURAS

MOVIMIENTO DE TIERRAS

EXCAVACIONES

EXCAVACION DE ZANJAS Y ZAPATAS MANUAL m3 28.80


ZAPATAS
ZAPATAS PARA COBERTURAS - PATIO Y ZONA DE JUEGOS 1.00 8.00 1.50 1.50 1.60 28.80

CORTES

CORTE DE TERRENO CON MAQUINARIA m3 284.94


PATIO m3 1.00 1.00 0.95 159.53 151.55
INGRESO - CIRCULACIÓN m3 1.00 1.00 0.15 74.37 11.16
CIRCULACIÓN - VEREDAS m3 1.00 1.00 0.85 99.22 84.34
ZONA DE JUEGOS m3 1.00 1.00 0.55 67.97 37.38
SARDINELES m3 1.00 1.00 0.30 1.71 0.51

RELLENOS

RELLENO CON MATERIAL DE PRÉSTAMO DE AFIRMADO m3 60.16


EXTERIOR 1.00 1.00 0.15 401.09 60.16

RELLENO CON MATERIAL PROPIO PARA ZANJAS m3 56.31


AREAS
PATIO 1.00 1.00 0.10 159.53 15.95
INGRESO - CIRCULACIÓN 1.00 1.00 0.10 74.37 7.44
CIRCULACIÓN - VEREDAS 1.00 1.00 0.10 99.22 9.92
ZONA DE JUEGOS 1.00 1.00 0.10 67.97 6.80
ZAPATAS
PATIO Y ZONA D EJUEGOS - ZAPATAS 8.00 1.00 1.00 2.03 16.20
METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : OBRAS EXTERIORES

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

ELIMINACIÓN DE MATERIAL EXCEDENTE

ACARREO INTERNO DE MATERIAL PROCEDENTE DE DEMOLICIONES Y


m3 volumen Coef. 321.79
EXCAVACIONES
1.00 1.00 257.43 1.25 321.79

ELIMINACION DE MATERIAL EXCEDENTE PROCEDENTE DE DEMOLICION


m3 volumen 321.79
Y EXCAVACIONES
1.00 1.00 321.79 321.79

NIVELACIÓN INTERIOR Y APISONADO

NIVELACIÓN INTERIOR Y APISONADO m2 420.80


AREAS
PATIO 1.00 1.00 159.53 159.53
INGRESO - CIRCULACION 1.00 1.00 74.37 74.37
CIRCULACIÓN- VEREDAS 1.00 1.00 99.22 99.22
ZONA DE JUEGOS 1.00 1.00 67.97 67.97
SARDINELES PARA ÁREAS VERDES 1.00 1.00 1.71 1.71
ZAPATAS
PATIO - ZOAN DE JUEGOS ZAPATAS 8.00 1.00 2.25 18.00

CONCRETO SIMPLE

FALSOS CIMIENTOS

SOLADOS

SOLADO PARA CIMIENTOS Y ZAPATAS: CONCRETO C:H 1:12 e=2".. m2 18.00

COLUMNAS DEL PATIO Y ZONA DE JUEGOS 1.00 8.00 1.50 1.50 18.00

CONCRETO ARMADO

ZAPATAS

CONCRETO f'c= 210 kg/cm2 EN ZAPATAS m3 9.00

PATIO Y ZONA DE JUEGOS Zapata - 1 1.00 8.00 1.50 1.50 0.50 9.00

ENCOFRADO Y DESENCOFRADO EN ZAPATAS m3 24.00


PATIO Y ZONA DE JUEGOS Zapata - 1 1.00 8.00 6.00 0.50 24.00

N° DE LONGITUD
ACERO ESTRUCTURAL TRABAJADO PARA ZAPATAS KG ELEMEN N° DE PIEZAS POR Coef. 158.40
TOS PIEZA(M)

∅1/2":1@0.25
PATIO Y ZONA DE JUEGOS Zapata - 1 KG 8.00 8.00 1.35 0.99 85.54
KG 8.00 8.00 1.15 0.99 72.86
METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : OBRAS EXTERIORES

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

PEDESTALES DE CONCRETO
CONCRETO f'c= 210 kg/cm2 EN PEDESTALES 3.96

PATIOS Y ZONA DE JUEGOS - PEDESTAL m3 1.00 8.00 0.50 0.45 2.20 3.96

ENCOFRADO Y DESENCOFRADO EN PEDESATLES 33.44

PATIOS Y ZONA DE JUEGOS - PEDESTAL m3 1.00 8.00 1.90 2.20 33.44

N° DE LONGITUD
ACERO CORRUGADO FY=4200 KG/CM2 PARA PEDESATLES kg ELEMEN N° DE PIEZAS POR Coef. 655.69
TOS PIEZA(M)
ACERO LONG. 3/4"
PATIOS Y ZONA DE JUEGOS - PEDESTAL KG 8.00 4.00 3.08 2.24 220.77
ACERO LONG. 5/8"
ACERO CORRUGADO FY=4200 KG/CM2 PARA PEDESATLES KG 8.00 6.00 3.08 1.56 230.63
ESTRIBOS Ø3/8":3@0.05; RESTO @ 0.10
PATIOS Y ZONA DE JUEGOS - PEDESTAL KG 8.00 24.00 1.90 0.56 204.29

MUROS DE CONCRETO ARMADO


CONCRETO f'c= 210 kg/cm2 EN MUROS DE COCRETO ARMADO 4.80

MURO EN LA ZONA DE INGRESO m3 2.00 1.00 6.15 0.15 1.00 1.85


m3 2.00 1.00 6.15 0.80 0.30 2.95

ENCOFRADO Y DESENCOFRADO EN MUROS DE CONCRETO ARMADO 31.98

MURO EN LA ZONA DE INGRESO m3 2.00 1.00 6.15 2.60 31.98

N° DE LONGITUD
ACERO CORRUGADO FY=4200 KG/CM2 EN MUROS DE CONCRETO ARMADO kg ELEMEN N° DE PIEZAS POR Coef. 165.76
TOS PIEZA(M)
ACERO LONG. 3/8"
MURO EN LA ZONA DE INGRESO KG 2.00 11.00 6.15 0.56 75.77
ACERO TRANSVERSAL ZAPATA 3/8"
MURO EN LA ZONA DE INGRESO KG 2.00 31.00 0.65 0.56 22.57
ACERO VERTICAL 3/8"
MURO EN LA ZONA DE INGRESO KG 2.00 43.00 1.40 0.56 67.42

ESTRUCTURAS METALICAS

COBERTURA METALICA

COLUMNA DE ACERO A500GrB DE 250X250X4.5mm L=2.70 m UND 8.00

PATIO Y ZONA DE JUEGOS 1.00 8.00 8.00

VIGA LATERAL TUBO RECT. DE 150X100X3MM ASTM A36 L=5.75 m UND 6.00

PATIO Y ZONA DE JUEGOS 2.00 3.00 6.00

UNION COLUMNA DE ACERO Y PEDESTAL DE C°A° C/PLANCHAS DE E=1/2" UND 8.00

PATIO Y ZONA DE JUEGOS 1.00 8.00 8.00

TIJERAL T-1 TIPO ARCO DE ESTRUCTURA METALICA C/TEMPALDORES ø


UND 4.00
3/4"COLGADORES DE ø 1/2"
PATIO Y ZONA DE JUEGOS 1.00 4.00 4.00

APOYO DE LOS TIJERALES T-1, CON CAJON DE PLANCHAS DE 5/8" UND 8.00

PATIO Y ZONA DE JUEGOS 1.00 8.00 8.00


METRADO - ESTRUCTURAS

PROYECTO RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR : ING. DAVID RODRIGUEZ MINAYA

FECHA MARZO 2021 AMBIENTES : OBRAS EXTERIORES

ESPECIALIDAD ESTRUCTURAS

ITEM DESCRIPCION UND REP. CANTIDAD LARGO ANCHO ALTURA AREA PARCIAL TOTAL

VIGUETA METALICA DE 40X60X2 mm (CORREAS) ML 846.00

PATIO Y ZONA DE JUEGOS 3.00 47.00 6.00 846.00

ARRIOSTRE METALICO P/VIGUETA DE 30X30X2 mm ML 38.25

PATIO Y ZONA DE JUEGOS 1.00 3.00 12.75 38.25

SUMINISTRO DE COB. C/ALUZIBC TR4 0.4 mm (TRNASLUCIDO) M2 235.24

PATIO Y ZONA DE JUEGOS 1.00 1.00 18.45 12.75 235.24

CANALETA CUADRADA DE ACERO GALVANIZADO ML 3.70

PATIO Y ZONA DE JUEGOS 1.00 1.00 3.70 3.70

TUBERIA DE BAJADA DE CANALETA CON SUS RESPECTIVOS ACCESORIOS


ML 6.30
PVC SAP ø 4"
PATIO Y ZONA DE JUEGOS 1.00 1.00 6.30 6.30
METRADO DE ESTRUCTURAS - RESUMEN

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR: ING. DAVID RODRIGUEZ MINAYA

FECHA : Mar-21

ESPECIALIDAD : ESTRUCTURAS

AMBIENTE : INSTITUCION EDUCATIVA

ESTRUCTURAS

METRADO

ITEM PARTIDAS UNIDAD 2 DEMOLIC TOTAL


MODULO CERCO
MODULO MODULO CISTERN TANQUE IONES Y EXTERIO
SUM- PERIMET
01 AULA S 02 A ELEVADO DESMON RES
ADM. RICO
AULAS TAJES
2
01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD

01.01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES

01.01.01 CONSTRUCCIONES PROVISIONALES

01.01.01.01 CARTEL DE OBRA DE 2.4 X 3.60 und 1.00 1.00

01.01.01.02 CERCO PROVISIONAL DE TRIPLAY DE 6.0 mm ml 63.35 63.35

01.01.01.03 COMEDOR PARA PERSONAL DE OBRA glb 1.00 1.00

01.01.01.04 ALMCÉN DE OBRA glb 1.00 1.00

01.01.01.05 OFICINAS DE OBRA glb 1.00 1.00

01.01.01.06 CASETA DE GUARDIANIA glb 1.00 1.00

01.01.01.07 SERVICIOS HIGIENICOS glb 1.00 1.00

01.01.02 INSTALACIONES PROVISIONALES

01.01.02.01 AGUA PARA LA CONSTRUCCIÓN glb 1.00 1.00


ENERGÍA ELÉCTRICA PROVISIONAL, CONSUMO Y
01.01.02.02 glb 1.00 1.00
MANTENIMIENTO

01.01.03 LIMPIEZA, TRAZO Y REPLANTEO GENERAL

01.01.03.01 LIMPIEZA DE TERRENO MANUAL / CON EQUIPO m2 84.09 334.62 165.37 27.11 405.53 1,016.72

01.01.04 REMOCIONES

01.01.04.01 DESMONTAJE PUERTAS DE MADERA INC. MARCO m2 25.74 25.74

01.01.04.02 DESMONTAJE DE VENTANA m2 63.08 63.08

01.01.04.03 DESMONTAJE DE PORTON und 7.38 7.38


DESMONTAJE DE TECHO DE QUINCHA (Cobertura de
01.01.04.04 m2 45.69 45.69
Caña Brava, Plástico, Estera)
DESMONTAJE DE COBERTURA DE CALAMINON,
01.01.04.05 m2 632.13 632.13
CALAMINA ETERNIT Y ALUZINC TIPO TR4
01.01.04.06 DESMONTAJE DE COBERTURA DE MALLA RASCHEL m2 120.45 120.45

01.01.04.07 DESMONTAJE DE COLUMNA CIRCULAR METÁLICA und 12.00 12.00

01.01.04.08 DESMONTAJE DE VIGA METÁLICA und 28.00 28.00

01.01.04.09 DESMONTAJE DE VIGA DE MADERA und 24.00 24.00


DESMONTAJE DE MUROS DE MADERA
01.01.04.10 m2 72.87 72.87
MACHIHEMBRADA , TRIPLAY
01.01.04.11 DESMONTAJE DEL MODULO DE PRONIED und 1.00 1.00

01.01.04.12 DESMONTAJE DE APARATOS SANITARIOS und 5.00 5.00

01.01.04.13 DESMONTAJE DE ACCESOS ELECTRICOS und 52.00 52.00

01.01.04.14 DESMONTAJE DE ASTA DE BANDERA und 1.00 1.00

01.01.05 DEMOLICION

01.01.05.01 DEMOLICION CIMIENTOS DE CONCRETO m3 54.99 54.99

01.01.05.02 DEMOLICION DE SOBRECIMIENTO DE CONCRETO m3 17.24 17.24

01.01.05.03 DEMOLICION DE COLUMNAS DE CONCRETO m3 6.73 6.73

01.01.05.04 DEMOLICION DE VIGAS DE CONCRETO m3 6.14 6.14

01.01.05.05 DEMOLICION DE TECHO ALIGERADO m3 2.34 2.34

01.01.05.06 DEMOLICION DE PISOS DE CONCRETO INC. FALSO PISO m3 382.69 382.69


METRADO DE ESTRUCTURAS - RESUMEN

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR: ING. DAVID RODRIGUEZ MINAYA

FECHA : Mar-21

ESPECIALIDAD : ESTRUCTURAS

AMBIENTE : INSTITUCION EDUCATIVA

ESTRUCTURAS

METRADO

ITEM PARTIDAS UNIDAD 2 DEMOLIC TOTAL


MODULO CERCO
MODULO MODULO CISTERN TANQUE IONES Y EXTERIO
SUM- PERIMET
01 AULA S 02 A ELEVADO DESMON RES
ADM. RICO
AULAS TAJES
DEMOLICION DE PATIOS, VEREDAS Y CIRCULACIÓN DE
01.01.05.07 m2 217.89 217.89
E=0.15 m
01.01.05.08 DEMOLICION DE MUROS DE ALBAÑILERIA m2 98.73 98.73

01.01.05.09 DEMOLICION DE MUROS DE ADOBE m2 216.04 216.04

01.01.05.10 DEMOLICION DE URINARIOS Y BEBEDEROS ml 7.86 7.86

01.01.06 ELIMINACION DE EXCAVACIONES


ACARREO INTERNO DE MATERIAL PROCEDENTE DE
01.01.06.01 m3 324.51 324.51
DEMOLICIONES Y EXCAVACIONES
ELIMINACION DEMATERIAL EXCEDENTE PROCEDENTE
01.01.06.02 m3 324.51 324.51
DE DEMOLICION Y EXCAVACIONES

01.01.07 TRAZO, NIVEL Y REPLANTEO

01.01.07.01 TRAZO Y REPLANTEO TOPOGRÁFICO m2 84.09 334.62 165.37 8.53 7.20 27.11 626.92

01.01.07.02 TRAZO Y REPLANTEO ANTES Y DURANTE LA OBRA m2 402.80 402.80

01.01.08 MOVILIZACIÓN DE CAMPAMENTO, MAQUINARIA, HERRAMIENTAS Y MATERIALES

01.01.08.01 FLETE glb 1.00 1.00


MOVILIZACIÓN Y DESMOVILIZACIÓN DE HERRAMIENTAS
01.01.08.02 glb 1.00 1.00
Y EQUIPOS

01.02 SEGURIDAD Y SALUD

01.02.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO

01.02.01.01 PLAN DE SEGURIDAD Y SALUD EN OBRA glb 1.00 1.00


CAPACITACIÓN O CHARLAS INDUCTIVAS EN
01.02.01.02 glb 1.00 1.00
SEGURIDAD Y SALUD
01.02.01.03 EQUIPAMIENTO DE PROTECCIÓN INDIVIDUAL und 75.00 75.00

01.02.01.04 EQUIPAMIENTO DE PROTECCIÓN COLECTIVA glb 1.00 1.00

01.02.01.05 SEÑALIZACIÓN PARA SEGURIDAD EN OBRA glb 1.00 1.00


RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS
01.02.01.06 EN SEGURIDAD Y glb 1.00 1.00
SALUD DURANTE EL TRABAJO
01.02.01.07 MITIGACIÓN DEL IMPACTO AMBIENTAL glb 1.00 1.00

02 ESTRUCTURAS

02.01 MOVIMIENTO DE TIERRAS

02.01.01 EXCAVACIONES

02.01.01.01 EXCAVACION DE ZANJAS Y ZAPATAS MANUAL m3 36.19 152.77 138.49 23.34 28.80 379.59

02.01.02 CORTES

02.01.02.01 CORTE DE TERRENO CON MAQUINARIA m3 88.29 317.89 140.57 284.94 831.69

02.01.03 RELLENOS

02.01.03.01 RELLENO CON MATERIAL DE PRESTAMO AFIRMADO m3 14.44 57.95 24.94 60.16 157.49

02.01.03.02 RELLENO CON MATERIAL PROPIO PARA ZANJAS m3 13.47 56.76 48.68 6.69 56.31 181.92

02.01.04 ELIMINACION DE EXCAVACIONES


ACARREO INTERNO DE MATERIAL PROCEDENTE DE
02.01.04.01 m3 138.76 517.37 287.96 324.51 20.82 321.79 1,611.21
DEMOLICIONES Y EXCAVACIONES
ELIMINACION DEMATERIAL EXCEDENTE PROCEDENTE
02.01.04.02 m3 138.76 517.37 287.96 324.51 20.82 321.79 1,611.21
DE DEMOLICION Y EXCAVACIONES

02.01.05 NIVELACION INTERIOR Y APISONADO


02.01.05.01 NIVELACION INTERIOR Y APISONADO m2 27.54 420.80 448.34
METRADO DE ESTRUCTURAS - RESUMEN

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR: ING. DAVID RODRIGUEZ MINAYA

FECHA : Mar-21

ESPECIALIDAD : ESTRUCTURAS

AMBIENTE : INSTITUCION EDUCATIVA

ESTRUCTURAS

METRADO

ITEM PARTIDAS UNIDAD 2 DEMOLIC TOTAL


MODULO CERCO
MODULO MODULO CISTERN TANQUE IONES Y EXTERIO
SUM- PERIMET
01 AULA S 02 A ELEVADO DESMON RES
ADM. RICO
AULAS TAJES
02.01.06 NIVELACIÓN INTERIOR Y COMPACTADO

02.01.06.01 NIVELACIÓN INTERIOR Y COMPACTADO m2 76.25 305.84 131.70 513.79

02.02 CONCRETO SIMPLE

02.02.01 FALSOS CIMIENTOS

02.02.01.01 SOLADOS
SOLADO PARA CIMIENTOS Y ZAPATAS: CONCRETO C:H
02.02.01.01.01 m2 14.07 58.16 65.64 14.08 151.95
1:12 e=4"..
SOLADO PARA CIMIENTOS Y ZAPATAS: CONCRETO C:H
02.02.01.01.02 m2 18.00 18.00
1:12 e=2"..
02.02.01.01.03 FALSA CIMENTACION: CONCRETO C:H 1:12 . m3 4.26 16.58 13.31 34.15
02.02.01.01.04 RELLENO DE CONCRETO SIMPLE C:H 1:12 e=4" m3 6.70 6.70

02.02.02 CIMIENTOS CORRIDOS

02.02.02.01 CIMIENTO CORRIDO: CONCRETO C:H 1:10+30% P.G. m3 11.79 49.74 28.48 3.90 93.91

02.02.03 SOBRECIMIENTOS
02.02.03.01 SOBRECIMIENTO: CONCRETO C:H 1:8+25% P.M. m3 1.65 5.74 3.73 0.89 12.00
02.02.03.02 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTOS m2 17.24 65.35 32.95 11.83 127.37

02.02.04 DADOS DE CONCRETO

02.02.04.01 DADOS DE CONCRETO F`c = 175kg/cm2 m3 0.05 0.22 0.25 0.01 0.01 0.54
ENCOFRADO Y DESENCOFRADO DE DADOS DE
02.02.04.02 m2 3.66 14.68 16.59 0.62 0.62 36.17
CONCRETO

02.02.05 FALSO PISO

02.02.05.01 FALSO PISO DE 4" DE CONCRETO 1:10 m2 58.66 241.52 103.65 403.83

02.03 CONCRETO ARMADO

02.03.01 ZAPATAS

02.03.01.01 CONCRETO f'c= 210 kg/cm2 EN ZAPATAS m3 7.04 29.08 32.82 2.55 9.00 80.49
02.03.01.02 CONCRETO f'c= 175 kg/cm2 EN ZAPATAS m3 5.73 5.73
02.03.01.03 ENCOFRADO Y DESENCOFRADO EN ZAPATAS m3 25.80 78.60 57.45 41.52 24.00 227.37
02.03.01.04 ACERO ESTRUCTURAL TRABAJADO PARA ZAPATAS kg 194.04 741.61 1,110.78 96.73 158.40 2,301.56

02.03.02 VIGA DE CIMENTACION


CONCRETO f'c=210 kg/cm2 PARA VIGAS DE
02.03.02.01 m3 3.44 12.54 6.61 0.76 23.34
CIMENTACION
CONCRETO f'c=175 kg/cm2 PARA VIGAS DE
02.03.02.02 m3 2.01 2.01
CIMENTACION
ENCOFRADO Y DESENCOFRADO EN VIGAS DE
02.03.02.03 m2 27.50 100.28 52.88 18.41 199.07
CIMENTACION
ACERO CORRUGADO FY=4200 KG/CM2 PARA VIGAS DE
02.03.02.04 kg 362.93 1,344.83 686.76 161.10 2,555.62
CIMENTACION
METRADO DE ESTRUCTURAS - RESUMEN

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR: ING. DAVID RODRIGUEZ MINAYA

FECHA : Mar-21

ESPECIALIDAD : ESTRUCTURAS

AMBIENTE : INSTITUCION EDUCATIVA

ESTRUCTURAS

METRADO

ITEM PARTIDAS UNIDAD 2 DEMOLIC TOTAL


MODULO CERCO
MODULO MODULO CISTERN TANQUE IONES Y EXTERIO
SUM- PERIMET
01 AULA S 02 A ELEVADO DESMON RES
ADM. RICO
AULAS TAJES

02.03.03 SOBRECIMIENTO REFORZADO


CONCRETO f'c=210 kg/cm2 PARA SOBRECIMIENTO
02.03.03.01 m3 1.41 1.41
REFORZADO
CONCRETO f'c=175 kg/cm2 PARA SOBRECIMIENTO
02.03.03.02 m3 4.04 4.04
REFORZADO
ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTO
02.03.03.03 m2 11.28 8.09 19.36
REFORZADO
ACERO CORRUGADO FY=4200 KG/CM2 PARA
02.03.03.04 kg 77.38 77.38
SOBRECIMIENTO REFORZADO

02.03.04 COLUMNAS

02.03.04.01 CONCRETO EN COLUMNAS f'c=210 kg/cm2 m3 10.23 35.31 44.72 0.30 2.16 92.73
02.03.04.02 CONCRETO EN COLUMNAS f'c=175 kg/cm2 m3 4.44 4.44
02.03.04.03 ENCOFRADO Y DESENCOFRADO EN TANQUE ELEVADO m2 1.80 1.80
ENCOFRADO Y DESENCOFRADO NORMAL EN
02.03.04.04 m2 108.13 367.91 436.37 185.51 1,097.92
COLUMNAS
ACERO CORRUGADO FY=4200 KG/CM2 PARA TANQUE
02.03.04.05 kg 49.79 49.79
ELEVADO
ACERO CORRUGADO fy=4200 kg/cm2 GRADO PARA
02.03.04.06 kg 1,952.41 5,729.99 4,654.90 842.80 13,180.09
COLUMNAS

02.03.05 COLUMNETAS

02.03.05.01 CONCRETO F'C=175 KG/CM2 EN COLUMNETAS m3 1.42 5.69 4.02 3.96 15.10
ENCOFRADO Y DESENCOFRADO NORMAL EN
02.03.05.02 m2 25.64 102.57 47.46 33.44 209.11
COLUMNETAS
ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 en
02.03.05.03 kg 218.38 872.71 1,768.91 655.69 3,515.70
COLUMNETAS

02.03.06 VIGAS

02.03.06.01 CONCRETO F'C=210 KG/CM2 EN VIGAS m3 6.45 24.66 25.30 0.92 57.33
02.03.06.02 CONCRETO F'C=175 KG/CM2 EN VIGAS m3 0.98 0.98
02.03.06.03 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 58.51 250.84 263.38 7.34 10.94 591.00
02.03.06.04 ACERO CORRUGADO fy=4200 kg/cm2 PARA VIGAS kg 833.58 3,173.99 3,140.90 113.27 175.24 7,436.98

02.03.07 VIGAS DE AMARRE

02.03.07.01 CONCRETO F'C=175 KG/CM2 EN VIGAS DE AMARRE m3 0.66 2.65 2.68 5.99
ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE
02.03.07.02 m2 9.24 40.74 34.93 84.91
AMARRE
ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 EN
02.03.07.03 kg 65.89 258.56 1,868.42 2,192.86
VIGAS DE AMARRE

02.03.08 LOSAS ALIGERADAS

02.03.08.01 CONCRETO EN LOSA ALIGERADA f'c=210 kg/cm2 m3 5.72 25.45 24.40 55.58
ENCOFRADO Y DESENCOFRADO PARA LOSAS
02.03.08.02 m2 65.40 290.88 278.88 635.15
ALIGERADAS
ACERO CORRUGADO FY=4200 KG/CM2 PARA LOSA
02.03.08.03 kg 466.07 2,098.20 2,168.62 4,732.89
ALIGERADA
02.03.08.04 LADRILLO ARCILLA PARA TECHO 15X30X30 CM u 545.00 2,424.00 2,324.00 5,293.00

02.03.09 ESCALERA
02.03.09.01 CONCRETO EN LOSA ALIGERADA f'c=210 kg/cm2 m3 3.86 3.86
02.03.09.02 ENCOFRADO Y DESENCOFRADO PARA ESCALERAS m2 26.38 26.38
ACERO CORRUGADO FY=4200 KG/CM2 PARA
02.03.09.03 kg 267.57 267.57
ESCALERA

02.03.10 ESTRUCTURA DE MADERA Y COBERTURA


02.03.10.01 CORREAS DE MADERA TORNILLO DE 2"X1" m3 80.30 343.20 182.33 605.83
COBERTURA C/TEJA DE ARCILLA EN CERCO DE
02.03.10.02 ml 13.11 13.11
LADRILLO
02.03.10.03 COBERTURA DE FIBRO CEMENTO m2 75.97 341.06 172.87 589.89
METRADO DE ESTRUCTURAS - RESUMEN

PROYECTO : RECONSTRUCCIÓN DEL LOCAL ESCOLAR 1557 CON CÓDIGO LOCAL 022634

PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE CASMA REALIZADO POR: ING. DAVID RODRIGUEZ MINAYA

FECHA : Mar-21

ESPECIALIDAD : ESTRUCTURAS

AMBIENTE : INSTITUCION EDUCATIVA

ESTRUCTURAS

METRADO

ITEM PARTIDAS UNIDAD 2 DEMOLIC TOTAL


MODULO CERCO
MODULO MODULO CISTERN TANQUE IONES Y EXTERIO
SUM- PERIMET
01 AULA S 02 A ELEVADO DESMON RES
ADM. RICO
AULAS TAJES
02.03.11 LOSA DE CIMENTACIÓN
CONCRETO f'c=210 kg/cm2 PARA LOSA DE
02.03.11.01 m3 1.19 1.19
CIMENTACIÓN
ENCOFRADO Y DESENCOFRADO EN LOSA DE
02.03.11.02 m2 2.49 2.49
CIMENTACIÓN
ACERO CORRUGADO FY=4200 KG/CM2 PARA LOSA DE
02.03.11.03 kg 153.40 153.40
CIMENTACIÓN

02.03.12 LOSA MACIZA

02.03.12.01 CONCRETO f'c=210 kg/cm2 PARA LOSA MACIZA m3 1.11 1.91 3.02
02.03.12.02 ENCOFRADO Y DESENCOFRADO EN LOSA MACIZA m2 7.40 12.08 19.48
ACERO CORRUGADO FY=4200 KG/CM2 PARA LOSA
02.03.12.03 kg 174.41 161.01 335.43
MACIZA

02.03.13 PLACAS

02.03.13.01 CONCRETO f'c=210 kg/cm2 PARA MUROS DE CISTERNA m3 3.25 3.25


02.03.13.02 ENCOFRADO Y DESENCOFRADO EN CISTERNA m2 33.07 33.07
02.03.13.03 ACERO CORRUGADO FY=4200 KG/CM2 PARA CISTERNA kg 218.71 218.71

02.03.14 PEDESTALES DE CONCRETO


02.03.14.01 CONCRETO f'c= 210 kg/cm2 EN PEDESTALES m3 3.96 3.96
02.03.14.02 ENCOFRADO Y DESENCOFRADO EN PEDESATLES m2 33.44 33.44
ACERO CORRUGADO FY=4200 KG/CM2 PARA
02.03.14.03 kg 655.69 655.69
PEDESATLES

02.03.15 MUROS DE CONCRETO ARMADO


02.03.15.01 CONCRETO f'c= 210 kg/cm2 EN MUROS m3 4.80 4.80
02.03.15.02 ENCOFRADO Y DESENCOFRADO EN MUROS m2 31.98 31.98
02.03.15.03 ACERO CORRUGADO FY=4200 KG/CM2 EN MUROS kg 165.76 165.76

02.04 COBERTURA Y ESTRUCTURA METÁLICA

02.04.01 ESTRUCTURAS METALICAS


02.04.01.01 ESCALERA TIPO GATO glb 1.00 1.00 2.00
02.04.01.02 REJILLA METALICA glb 1.00 1.00
02.04.01.03 TAPA METALICA UND 1.00 1.00
02.04.01.04 BARANDA METALICA DE SEGURIDAD M 12.90 12.90
02.04.01.05 CORREA DE PROTECCION DEL TANQUE UND 1.00 1.00
COLUMNA DE ACERO A500GrB DE 250X250X4.5mm
02.04.01.06 UND 8.00 8.00
L=2.70 m
VIGA LATERAL TUBO RECT. DE 150X100X3MM ASTM A36
02.04.01.07 UND 6.00 6.00
L=5.75 m
UNION COLUMNA DE ACERO Y PEDESTAL DE C°A°
02.04.01.08 UND 8.00 8.00
C/PLANCHAS DE E=1/2"
TIJERAL T-1 TIPO ARCO DE ESTRUCTURA METALICA
02.04.01.09 UND 4.00 4.00
C/TEMPALDORES ø 3/4"COLGADORES DE ø 1/2"
APOYO DE LOS TIJERALES T-1, CON CAJON DE
02.04.01.10 UND 8.00 8.00
PLANCHAS DE 5/8"
02.04.01.11 VIGUETA METALICA DE 40X60X2 mm (CORREAS) ML 846.00 846.00
02.04.01.12 ARRIOSTRE METALICO P/VIGUETA DE 30X30X2 mm ML 38.25 38.25
SUMINISTRO DE COB. C/ALUZIBC TR4 0.4 mm
02.04.01.13 M2 235.24 235.24
(TRNASLUCIDO)
02.04.01.14 CANALETA CUADRADA DE ACERO GALVANIZADO ML 3.70 3.70
TUBERIA DE BAJADA DE CANALETA CON SUS
02.04.01.15 ML 6.30 6.30
RESPECTIVOS ACCESORIOS PVC SAP ø 4"