CALCULO DEL FLETE

PROYECTO :

A-POR PESO

MATERIALES UNIDAD CANTIDAD PESO.UNIT. PESO.TOTAL


CEMENTO BL. 353.00 42.50 15,002.50
FIERRO, CLAV. ETC KG 1,380.69 1.00 1,380.69
MADERA P2 2,790.32 1.50 4,185.48
LADRILLO UN 154.00 4.50 693.00
CALAMINA UN 192.00 3.00 576.00
YESO BL 45.00 25.00 1,125.00
TAPA BUZON UN 130.00
EXPLOSIVOS KG 1.00
OTROS KG 2,000.00 1.00 2,000.00

PESO TOTAL 24,962.67

B-POR VOLUMEN

EN TUBERIA UNIDAD DE (2.20 M. x 3.00 M.) DE CARROCERIA, CON H= 1.50 M.


CAPACIDAD DEL CAMION EN TUBOS / VIAJE ML No de tubos No VIAJES
Tub, 1/2"+3/4" 4,960.00 U 3,943.00 788.60 0.16
Tub, 1" 3,360.00 U 1,150.00 230.00 0.07
Tub,1 1/2" 1,690.00 U 760.00 152.00 0.09
Tub 2:" 994.00 U 1,069.00 213.80 0.22
Tub, 3" 470.00 U
Tub 4": 259.00 U 183.00 61.00 0.24
Tub PVC SAL 2" 1,657.00 U
Tub PVC SAL 4" 432.00 U
U
U
NUMERO TOTAL DE VIAJES 0.78
REDONDEO 1.00
TUBERIA EN VOLUMEN 12

FLETE TERRESTRE

UNIDAD DE TRANSPORTE
CAPACIDAD DEL CAMION ( M3 ) 25.00
COSTO POR VIAJE S/. 900.00
CAPACIDAD DEL CAMION (KG) 10,000.00
FLETE POR KG 0.09

FLETE FLETE POR PESO =Peso Total * Flete por peso


FLETE POR PESO 2,246.64 FLETE POR VOLUMEN=No viajes*costo por viaje
FLETE POR VOLUMEN Nº DE VIAJES 3.49627
AGREGADOS
TUBERIA 900.00
COSTO TOTAL FLETE TERR. 3,146.64

RESUMEN FLETE TOTAL

AFECTO IGV
FLETE TERRESTRE 3,146.64
FLETE EN ACEMILA
FLETES TOTALES S/. 3,146.64
CALCULO DEL FLETE
PROYECTO : CONSTRUCCION DEL SISTENA DE AGUA POTABLE DEL CENTRO
POBLADO PORCON LA ESPERANZA

A-POR PESO

MATERIALES UNIDAD CANTIDAD PESO.UNIT. PESO.TOTAL


CEMENTO BL. 458.00 42.50 19,465.00
FIERRO, CLAV. ETC KG 2,328.97 1.00 2,328.97
MADERA P2 4,294.67 1.50 6,442.01
LADRILLO UN 390.00 4.50 1,755.00
CALAMINA UN 270.00 3.00 810.00
YESO BL 325.00 20.00 6,500.00
OTROS KG 2,000.00 1.00 2,000.00
PESO TOTAL 39,300.98

B-POR VOLUMEN

EN TUBERIA UNIDAD DE (2.20 M. x 3.00 M.) DE CARROCERIA, CON H= 1.50 M.


CAPACIDAD DEL CAMION EN TUBOS / VIAJE ML No de tubos No VIAJES
Tub, 1/2"+3/4" 3,390 U 16,948.00 3,389.60 1.0
Tub, 1" 521 U 2,602.81 520.56 1.0
Tub,1 1/2" 142 U 705.55 141.11 1.0
Tub 2:" 301 U 1,504.48 300.90 1.0
Tub, 3" 470 U
Tub PVC SAL 4" 30 U 90.00 30.00 1.0
Tub PVC SAL 2" 1 U 0.80 0.27 0.3

NUMERO TOTAL DE VIAJES 5.30


REDONDEO 6.00
TUBERIA EN VOLUMEN (m3) 20

FLETE TERRESTRE

UNIDAD DE TRANSPORTE
CAPACIDAD DEL CAMION ( M3 ) 25.00
COSTO POR VIAJE S/. 500.00
CAPACIDAD DEL CAMION (KG) 10,000.00
FLETE POR KG 0.05

FLETE FLETE POR PESO =Peso Total * Flete por peso


FLETE POR PESO 1,965.05 FLETE POR VOLUMEN=No viajes*costo por viaje
FLETE POR VOLUMEN Nº DE VIAJES: 10
AGREGADOS -
TUBERIA 3,000.00 - Los Agregados su costo esta considerado
COSTO TOTAL FLETE TERR. 4,965.05 puesto en obra

RESUMEN FLETE TOTAL

AFECTO IGV
FLETE TERRESTRE 4,965.05

FLETES TOTALES S/. 4,965.05