Está en la página 1de 3

VOLUMEN CONCRETO CEMENTO - AGREGADO

ARENA FINA PARA TARRAJEO RELACION CANTIDAD PARA 1 M3 DE MEZCLA

Ceme : Hormi CEMENTO ARENA VOLUMEN


DESCRIPCION UNIDAD AREA m2 espesor m VOL m3 % desperdicio VOL m3 nto gon
FACTOR
M3 FINA M3 MEZCLA M3

TARRAJEO EN MUROS EXTERIORES E INTERIORES m2 226.54 0.02 4.5308 10 5.0 1 : 5 0.1667 0.17 0.83 1.0
TARRAJEO DE SUPERFICIE DE COLUMNAS MEZCLA C:A 1:5 E=1.5CM m2 96.94 0.02 1.9388 10 3.0 1 : 5 0.1667 0.17 0.83 1.0
TARRAJEO EN SUPERFICIE DE VIGAS MEZCLA C:A 1:5 E=1.5CM m2 48.8 0.02 0.976 10 2.0 1 : 5 0.1667 0.17 0.83 1.0
VESTIDURA DE DERRAMES MEZCLAC:A 1:5 E=1.5CM, A=0.15M m 64.36 0.02 0.19308 10 1.0 1 : 5 0.1667 0.17 0.83 1.0
BRUÑAS SEGUN DETALLE (1 x 1 cm) m 46.04 0.02 10 0.0 1 : 5 0.1667 0.17 0.83 1.0
TARRAJEO EN CIELORRASO m2 128.86 0.02 2.5772 10 3.0 1 : 5 0.1667 0.17 0.83 1.0
CONTR. S/COLOREAR H=30 CM, MEZCLA C:A 1:2 E=1.5 CM m 112.7 0.02 0.6762 10 1.0 1 : 2 0.3333 0.33 0.67 1.0
CAJA REPART Y REGISTROTARRAJEO FROTACHADO, MUROS Y LOSAS EXT. e=1.5cm m2 10 1.0 1 : 5 0.1667 0.17 0.83 1.0
MEZCLA 1:5 1.15 0.02 0.023
10.92 TOTAL 16 m3 C°

HORMIGON PARA PISO RELACION CANTIDAD PARA 1 M3 DE MEZCLA

Ceme Hormi CEMENTO ARENA VOLUMEN


DESCRIPCION UNIDAD AREA m2 espesor m VOL m3 % desperdicio VOL m3 nto
:
gon
FACTOR
M3 FINA M3 MEZCLA M3

FALSO PISO DE 4" DE CONCRETO 1:10 m2 137.6 0.1016 13.98016 5 15.0 1 : 10 0.0909 0.09 0.91 1.0
CONTRAPISO 48 MM m2 6.94 0.1016 0.705104 5 1.0 1 : 5 0.1667 0.17 0.83 1.0
VEREDA CONCRETO FROTACADO e=4" BRUÑADO 1m m2 0.72 0.1016 0.073152 5 1.0 1 : 4 0.2000 0.20 0.80 1.0
SARDINEL CONCRETO F´C=175KG/CM2 m2 0.95 0.40 0.38 5 1.0 1 : 5 0.1667 0.17 0.83 1.0
CONCRETO EN COLUMNETAS F'C=175 KG/CM2 m3 0.51 0.51 5 1.0 1 : 5 0.1667 0.17 0.83 1.0
CONCRETO F'C=100 KG/CM2 EN SOLADO BIODIGESTOR m3 0.12 0.12 5 1.0 1 : 7 0.1250 0.13 0.88 1.0
CONCRETO F'c= 175 KG/CM2 CAJA REPARTICION Y REGISTRO m3 0.8 0.8 5 1.0 1 : 5 0.1667 0.17 0.83 1.0
VEREDA DE CONCRETO PULIDO F'C=175 KG/CM2 DE e=4" CON BRUÑAS DE CANTO Y
TRANSVERSALES m2 25.31 0.2 5.062 5 6.0 1 : 5 0.1667 0.17 0.83 1.0

21.63 TOTAL 27 m3 C°

ARENA GRUESA PARA CONCRETO RELACION CANTIDAD PARA 1 M3 DE MEZCLA

Ceme Hormi CEMENTO ARENA VOLUMEN


DESCRIPCION UNIDAD AREA m2 espesor m VOL m3 % desperdicio VOL m3 nto
:
gon
FACTOR
M3 FINA M3 MEZCLA M3

ACABADO DE CEMENTO PULIDO SOBRE LOSA ALIGERADA MEZCLA 1:4 (BOMBEO DE


m2 125.76 5 7.0 1 : 4 0.2000 0.20 0.80 1.0
1%) 0.0508 6.388608
PISO DE CEMENTO PULIDO C/OCRE E=2" MEZCLA 1:4 m2 105.71 0.0508 5.370068 5 6.0 1 : 4 0.2000 0.20 0.80 1.0
11.76 TOTAL 13 m3 C°
CEMENTO - AGREGADO

M3 DE MEZCLA CANTIDAD PARA EL VOLUMEN DE EZCLA

CEM VOL CEM CEM ARENA % CEM ARENA


bls MEZCLA M3 bls m3 m3 desperdicio bls m3

5.89 4.53 26.667 0.7551 3.78 5 29.0 4.0


5.89 1.94 11.411 0.3231 1.62 5 12.0 2.0
5.89 0.98 5.7445 0.1627 0.81 5 7.0 1.0
5.89 0.19 1.1364 0.0322 0.16 5 2.0 1.0
5.89 0 0.00 5 0.0 0.0
5.89 2.58 15.169 0.4295 2.15 5 16.0 3.0
11.77 0.68 7.9599 0.2254 0.45 5 9.0 1.0
5.89 0.02 0.1354 0.004 0.02 5 1.0 1.0

11 68 TOTAL 76 13
BLS M3
M3 DE MEZCLA CANTIDAD PARA EL VOLUMEN DE EZCLA
HORM
CEM VOL CEM CEM % CEM ARENA
GON
bls MEZCLA M3 bls m3 desperdicio bls m3
m3
3.21 13.98 44.882 1.2709 12.71 5 48.0 14.0
5.89 0.71 4.1501 0.1175 0.59 5 5.0 1.0
7.06 0.07 0.5167 0.0146 0.06 5 1.0 1.0
5.89 0.38 2.2366 0.0633 0.32 5 3.0 1.0
5.89 0.51 3.0018 0.085 0.43 5 4.0 1.0
4.41 0.12 0.5297 0.015 0.11 5 1.0 1.0
5.89 0.80 4.7086 0.1333 0.67 5 5.0 1.0

5.89 5.06 29.794 0.844 4.22 5 32.0 5.0

22 90 TOTAL 99 25
BLS M3
M3 DE MEZCLA CANTIDAD PARA EL VOLUMEN DE EZCLA
HORM
CEM VOL CEM CEM % CEM ARENA
GON
bls MEZCLA M3 bls m3 desperdicio bls m3
m3

7.06 6.39 45.122 1.2777 5.11 5 48.0 6.0


7.06 5.37 37.928 1.074 4.30 5 40.0 5.0
12 83 TOTAL 88 11
BLS M3

CEMENTO TOTAL: 263 BLS

AGREGADOS TOTAL:
ARENA FINA PARA TARRAJEO 13 M3
HORMIGON PARA PISO 25 M3
ARENA GRUESA PARA CONCRETO 11 M3