PRESUPUES

EMPRESA CONSULTORA:
CLIENTE: UNIVERSIDAD CONTINENTAL

PRESUPUESTO DE OBRA

1 OBRAS PRELIMINARES
1.1 TRAZO Y REPLANTEO
2 MOVIMIENTO DE TIERRAS
2.1 EXCAVACION EN MATERIAL SUELTO
2.2 EXCAVACION EN MATERIAL COMPACTO
2.3 ELIMINACION DE MATERIAL EXCEDENTE D=5km
3 ESTRUCTURAS
3.1 VACIADO DE CONCRETO CICLOPEO 1:8 + 25% P.G.
3.2 CURADO

ANALISIS DE COSTOS UNITARIOS

1.1 TRAZO Y REPLANTEO


RENDIMIENTO
MANO DE OBRA
TOPOGRAFO
OFICIAL
PEON

EQUIPO
NIVEL TOPOG.
H.M.
2.1 EXCAVACION EN MATERIAL SUELTO
RENDIMIENTO
MANO DE OBRA
PEON

EQUIPO
H.M.
MATERIALES

2.2 EXCAVACION EN MATERIAL COMPACTO


RENDIMIENTO
MANO DE OBRA
PEON

EQUIPO
H.M.

2.3 ELIMINACION DE MATERIAL EXCEDENTE D=5 km


RENDIMIENTO
MANO DE OBRA
OFICIAL
PEON

EQUIPO
CARGADOR FRONTAL
CAMION VOLQUETE 15 m3
H.M.
3.1 VACIADO DE CONCRETO CICLOPEO 1:8 + 40% P.G.
RENDIMIENTO
MANO DE OBRA
OPERARIO
OFICIAL
PEON

EQUIPO
H.M.
MEZCLADORA DE CONCRETO DE 9 -11P3

MATERIALES
CEMENTO PORTLAND TIPO I (42.5KG)
HORMIGON
PIEDRA GRANDE

3.2 CURADO
RENDIMIENTO
MANO DE OBRA
PEON

EQUIPO
H.M.

FÓRMULA POLINÓMICA

Descripción Recurso Unidad

Mano de Obra
TOPOGRAFO hh
OPERARIO hh
OFICIAL hh
PEON hh

Materiales
CEMENTO PORTLAND TIPO I (42.5KG) bolsa
HORMIGON m3
PIEDRA GRANDE m3

Equipos
HERRAMIENTAS MANUALES %MO
NIVEL TOPOG. hm
CARGADOR FRONTAL hm
CAMION VOLQUETE 15 m3 hm
MEZCLADORA DE CONCRETO DE 9 -11P3 hm

COSTO DIRECTO
GASTOS GENERALES 10 %
UTILIDAD 10 %
SUB TOTAL

IGV 18%
TOTAL

SUMATORIA COEFICIENTES

K= 0.391 MOr + 0.183 CEMr + 0.109 HOr + 0.082 PGr +0.069 MAQ_Ir + 0.1
MOo CEMo HOo PGo MAQ_Io

COD ELEMENTO IU
MO MANO DE OBRA 47
CEM CEMENTO PORTLAND TIPO I (42.5KG) 21
HO HORMIGON 38
PG PIEDRA GRANDE 5
NIVEL TOPOG. 48
CARGADOR FRONTAL 49
MAQ_I CAMION VOLQUETE 15 m3 49
MEZCLADORA DE CONCRETO DE 9 -11P3 48
HERRAMIENTAS MANUALES 37
GASTOS GENERALES 10 % 39
GGU
UTILIDAD 10 % 39
PRESUPUESTO UC-2023-I

E OBRA
UNIDAD METRADO

m2 350.00

m3 200.00
m3 150.00
m3 400.00

m3 180.00
m2 350.00

UNITARIOS

500 m2/dia
UNIDAD CUADRILLA CANTIDAD
h.h 1 0.016
h.h 1 0.016
h.h 2 0.032

h.m. 1 0.016
%m.o. 0.030
3 m3/dia
UNIDAD CUADRILLA CANTIDAD
h.h 1 2.67

0.030

2 m3/dia
UNIDAD CUADRILLA CANTIDAD
h.h 1 4.000

0.030

850 m3/dia
UNIDAD CUADRILLA CANTIDAD
h.h 1 0.009
h.h 1 0.009

h.m. 1 0.009
h.m. 5 0.047
0.030
15 m3/dia
UNIDAD CUADRILLA CANTIDAD
h.h 2 1.067
h.h 3 1.600
h.h 10 5.333

0.030
h.m 1 0.533

bolsa 3.220
m3 0.720
m3 0.540

100 m2/dia
UNIDAD CUADRILLA CANTIDAD
h.h 1 0.080

0.030

NÓMICA

Parcial S/. % AGRUPAMIENTO

S/. 84.00 0.001 0.001


S/. 2,880.00 0.040 0.040
S/. 3,568.38 0.050 0.050
S/. 21,362.98 0.299 0.299
S/. 27,895.36 0.391

S/. 13,041.00 0.183 0.183


S/. 7,776.00 0.109 0.109
S/. 5,832.00 0.082 0.082
S/. 26,649.00

S/. 836.86 0.012 0.012


S/. 47.04 0.001 0.001
S/. 640.00 0.009 0.009
S/. 2,447.06 0.034 0.034
S/. 960.00 0.013 0.013
S/. 4,930.96

S/. 59,475.32
S/. 5,947.53 0.083 0.083
S/. 5,947.53 0.083 0.083
S/. 71,370.38
S/. 12,846.67 1.000
S/. 84,217.05

+0.069 MAQ_Ir + 0.167 GGUr


MAQ_Io GGUo

COEFICIENTE %
0.391 100.00%
0.183 100.00%
0.109 100.00%
0.082 100.00%
0.95%
12.98%
0.069 49.63%
19.47%
16.97%
50.00%
0.167
50.00%
COSTO U. COSTO P. S/.

S/. 0.91 S/. 318.14

S/. 27.47 S/. 5,493.33


S/. 41.20 S/. 6,180.00
S/. 7.93 S/. 3,172.37

S/. 244.57 S/. 44,023.08


S/. 0.82 S/. 288.40
COSTO DIRECTO S/. 59,475.32
GASTOS GENERALES 10 % C.D. S/. 5,947.53
UTILIDAD 10% CD S/. 5,947.53
SUBTOTAL S/. 71,370.38
I.G.V. 18 % S/. 12,846.67
PRESUPUESTO S/. S/. 84,217.05

UNIDAD m2
COSTO TOTAL
15.000 0.24
12.000 0.192
10.000 0.32
0.752

8.400 0.134
0.752 0.023
0.157
total 0.91

UNIDAD m3
COSTO TOTAL
10.000 26.667
26.667

26.667 0.800

total 27.47

UNIDAD m3
COSTO TOTAL
10.000 40.000
40.000

40.000 1.200
1.200
total 41.200

UNIDAD m3
COSTO TOTAL
12.000 0.113
10.000 0.094
0.21

170.000 1.600
130.000 6.118
0.21 0.006
7.724
total 7.93
UNIDAD m3
COSTO TOTAL
15.000 16.000
12.000 19.200
10.000 53.333
88.533

88.533 2.656
10.000 5.333
7.989

22.500 72.450
60.000 43.200
60.000 32.400
total 244.57

UNIDAD m2
COSTO TOTAL
10.000 0.800
0.800

0.800 0.024

total 0.82

COEFICIENTES I.U. % INCIDENCIA

47 - MÁXIMO
47 - EL PORCE
0.391 47
1.000
SER MAYO
47 - LA SUMA
- EL IU 47 Y
- MÁXIMO
0.183 21 1.000
- EL IU 47 Y
- MÁXIMO

0.109 38 1.000
0.082 5 1.000

37
48
0.069 49 1.000
49
48

39
0.167 39 1.000

1.000
- MÁXIMO 8 MONOMIOS
- EL PORCENTAJE DE INCIDENCIA DE CADA MONOMIO DEBE
SER MAYOR A 5%.
- LA SUMATORIA DEBE DAR LA UNIDAD.
- EL IU 47 Y EL 39 NO SE AGRUPAN CON OTROS.
- MÁXIMO SE PUEDEN AGRUPAR 3 I.U.
- EL IU 47 Y EL 39 NO SE AGRUPAN CON OTROS.
- MÁXIMO SE PUEDEN AGRUPAR 3 I.U.
O DEBE
ANALISIS DE COSTOS UNITARIOS

PARTIDA
RENDIMIENTO UNIDAD
MANO DE OBRA UNIDAD CUADRILLA CANTIDAD COSTO TOTAL

MATERIALES UNIDAD CUADRILLA CANTIDAD COSTO TOTAL

EQUIPOS

total

PARTIDA
RENDIMIENTO UNIDAD
MANO DE OBRA UNIDAD CUADRILLA CANTIDAD COSTO TOTAL

MATERIALES UNIDAD CUADRILLA CANTIDAD COSTO TOTAL

EQUIPOS

total