Está en la página 1de 3

MURO DE TABIQUE ROJO RECOCIDO 5z14x28

0,295

0.065

Espesor 1.5 cm = 0.015 m

1 M^2 / (.065x0.295) =52.15 pzas de ladrillo por m2

NUMERO DE LADRILLOS = 52.15 + 15% DESPERDICIO =59.97 PZAS

Calculo cantidad de mortero

V1=2(0.0075)(0.295)(0.155)=0.000343

V2=2(0.0075)(.05)(0.14)=0.0000525

VTOTAL= .000343+0.0000525= 0.0003955

1 M^2 / (.065x0.295) =52.15

VTOTAL/M^2 =52.15(0.0003955)=0.02063 M^3/M^2

+30% DESPERDICIO = .02063X1.3=0.02682

TABIQUE ROJO $3000.00 EL MILLAR

3000/1000= 3 POR PIEZA

MANO DE OBRA 5 PAREJAS

MAESTRO DE OBRA 300 PESOSO

ALBAÑIL 180 PESOS

PEON 120 PESOS

300/5= 60 +180+120= 360 PEOSOS

SR=360(1.9051)= 685.84 PESOS

RENDIMIENTO 7M^2 POR JORNA´L


CASTILLO-CADENA DE DESPELANTE- CADENA DE CERRAMIENTO DE 14X20

CONCRETO= 0.20x0.14=0.O28 M^3

ACERO

VARILLAS NO.3

4 VARILLAS

1m + 0.30m ganchos + 1.26% traslape = 1.32 ml(4 varillas)= 5.28 ml

PESO DE VARILLA NO.3 = 0.576 KG POR METRO LINEAL

(5.28)(0.576)= 3.04KG + 15% DESPERDICIO = 3.5 KG

$27,000.00 POR TONELADA

27000/1000= 27 PESOS POR KG

ESTRIBO VARILLA NO. 2 (ALAMBRON)

RECUBRIMIENTO 1.5 A CADA LADO

LONGITUD DE ESTRIBO

17 +17+11+11+10= 66 CM =0.66M

0.249 KG POR METRO DE VARILLA

0.66(0.249)=0.164 KG POR CADA ESTRIBO

1M/.20M= 5 + 1 VARILLA DE INICIO = 6 VARILLA

6(.164)=0.984 KG + 15% DESPERDICIO = 1.13 KG POR METRO LINEAL DE CATILLO

PRECIO 27.82 PESOS POR KG


ALAMBRE DE AMARRE

4 AMARRES DE 10 CM POR ESTRIBO

0.4 M POR ESTRIBO

0.4(6 ESTRIBOS)= 2.4 M POR METRO LIENAL

1 ML DE ALAMBRE DE AMARRE CALIBRE 19= 7.10 gr por metro = 0.0071 kg por metro

0.0071(2.4)=0.017 KG + 15 % DESPERDICIO =0.20 KG POR ML DE CASTILLO

PRECIO POR KG =32.30 PESOS