MES 1 MES 2 MES 3

Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) 2 semanas 4semanas 4semanas
01 OBRAS PROVISIONALES S/ 25,318.80
01.01 TRABAJOS PRELIMINARES S/ 25,318.80 S/ 25,318.80
01.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M und 1.00 860.23 S/ 860.23 S/ 860.23
01.01.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS GLB 1.00 6,798.40 S/ 6,798.40 S/ 6,798.40
01.01.03 SEÑALIZACION Y PROTECCION DE OBRA GLB 1.00 7,060.00 S/ 7,060.00 S/ 7,060.00
01.01.04 CASETA DE ALMACEN Y GUARDIANIA m2 108.00 52.80 S/ 5,702.40 S/ 5,702.40
01.01.05 REUBICACION DE POSTES DE LUZ und 7.00 293.61 S/ 2,055.27 S/ 2,055.27
01.01.06 PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO GLB 1.00 2,842.50 S/ 2,842.50 S/ 2,842.50
02 PAVIMENTO FLEXIBLE S/ 4,090,020.30 S/ 384,699.34 S/ 1,029,808.95 S/ 882,499.48
02.01 OBRAS PRELIMINARES S/ 43,947.33 S/ 43,947.33
02.01.01 TRAZO, NIVELACION Y REPLANTEO m2 38,550.29 1.14 S/ 43,947.33 S/ 43,947.33
02.02 MOVIMIENTO DE TIERRAS S/ 554,573.21 S/ 340,752.01 S/ 213,821.20
02.02.01 CORTE DE TERRENO NATURAL H= 0.625 M. M3 26,169.83 6.22 S/ 162,776.34 S/ 78,844.79 S/ 83,931.55
02.02.02 PERFILADO, NVELACION Y COMPACTACION DE LA SUB m2 38,550.29 2.18 S/ 84,039.63 S/ 40,706.70 S/ 43,332.93
02.02.03 ELIMINACION DE MATERIAL EXCEDENTE(CARGUIO) C/V m3 31,403.80 9.80 S/ 307,757.24 S/ 221,200.52 S/ 86,556.72
02.03 PAVIMENTO S/ 3,491,499.76 S/ 815,987.75 S/ 882,499.48
02.03.01 MEJORAMIENTO DE SUBRASANTE C/ARENILLA Y OVER DE m2 38,550.29 16.69 S/ 643,404.34 S/ 643,404.34
02.03.02 SUB BASE GRANULAR E= 0.15 M. m2 38,550.29 11.07 S/ 426,751.71 S/ 172,583.41 S/ 254,168.30
02.03.03 BASE GRANULAR E= 0.20 M. m2 38,550.29 13.89 S/ 535,463.53 S/ 535,463.53
02.03.04 IMPRIMACION ASFALTICA (DOSIF. 0.40 gl/m2 - TANQUE 180m2 38,550.29 6.60 S/ 254,431.91 S/ 92,867.65
02.03.05 CARPETA ASFALTICA EN CALIENTE DE 2" m2 38,550.29 42.32 S/ 1,631,448.27
03 CONSTRUCCION DE VEREDAS S/ 1,352,055.05 S/ 38,580.71 S/ 275,434.90 S/ 476,130.87
03.01 OBRAS PRELIMINARES S/ 14,567.55 S/ 14,567.55
03.01.01 TRAZO, NIVELES Y REPLANTEO m2 12,778.55 1.14 S/ 14,567.55 S/ 14,567.55
03.02 MOVIMIENTO DE TIERRAS S/ 394,331.39 S/ 24,013.16 S/ 244,367.58 S/ 125,950.65
03.02.01 CORTE DE TERRENO MANUAL EN VEREDAS M3 1,916.08 42.31 S/ 81,069.34 S/ 17,902.81 S/ 63,166.53
03.02.02 EXCAVACION DE ZANJA PARA UÑA, ANCHO= 0.15M, PROFm 8,840.10 3.13 S/ 27,669.51 S/ 6,110.35 S/ 21,559.16
03.02.03 REFINE, NIVELACION Y COMPACTACION DE LA SUBRA m2 12,778.55 2.29 S/ 29,262.88 S/ 28,165.52 S/ 1,097.36
03.02.04 CAMA DE ARENILLA E= 0.10 M., PARA VEREDAS Y RAMP m2 12,778.55 6.27 S/ 80,121.51 S/ 58,421.93 S/ 21,699.58
03.02.05 CAMA DE AFIRMADO E= 0.10 M. PARA VEREDAS Y RAMP m2 12,778.55 11.53 S/ 147,336.68 S/ 73,054.44 S/ 74,282.24
03.02.06 ELIMINACION DE MATERIAL EXCEDENTE(CARGUIO) C/V m3 2,617.54 11.03 S/ 28,871.47 S/ 28,871.47
03.03 VEREDA DE CONCRETO S/ 800,963.69 S/ 285,655.79
03.03.01 CONCRETO F'C= 175 KG/CM2 PARA VEREDAS, INC/ A m2 10,608.12 45.41 S/ 481,714.73 S/ 170,105.51
03.03.02 CONCRETO F'C=175 KG/CM2, PARA UÑA DE 0.15M X 0.20 m3 265.20 351.69 S/ 93,268.19 S/ 32,935.33
03.03.03 CONCRETO F'C= 175 KG/CM2 PARA MARTILLOS, INC/ m2 1,341.29 45.41 S/ 60,907.98
03.03.04 CONCRETO F'C= 175 KG/CM2 P/ RAMPA DE ACCESO I m2 824.21 45.41 S/ 37,427.38
03.03.05 ENCOFRADO Y DESENCOFRADO P/VEREDAS Y MARTILL m2 3,439.65 37.11 S/ 127,645.41 S/ 82,614.95
03.04 JUNTAS Y BRUÑADOS S/ 16,315.51
03.04.01 JUNTAS CON ASFALTO E=1" m 3,384.96 4.82 S/ 16,315.51
03.05 CURADOS S/ 30,285.16
03.05.01 CURADO DE CONCRETO PARA VEREDAS, RAMPAS Y MA m2 12,778.55 2.37 S/ 30,285.16
03.06 SUMINISTRO Y NIVELACION DE CAJAS DE AGUA Y DESAGUE S/ 95,591.75 S/ 31,067.32 S/ 64,524.43
03.06.01 NIVELACION DE CAJAS PARA AGUA und 685.00 59.18 S/ 40,538.30 S/ 13,174.95 S/ 27,363.35
03.06.02 NIVELACION DE CAJAS PARA DESAGUE und 685.00 80.37 S/ 55,053.45 S/ 17,892.37 S/ 37,161.08
04 CONSTRUCCION DE SARDINELES S/ 530,384.63 S/ 10,746.13 S/ 5,332.81 S/ 292,580.36
04.01 TRABAJOS PRELIMINARES S/ 1,219.85 S/ 1,219.85
04.01.01 TRAZO, NIVELACION Y REPLANTEO m2 1,070.04 1.14 S/ 1,219.85 S/ 1,219.85
04.02 MOVIMIENTO DE TIERRAS S/ 14,859.09 S/ 9,526.28 S/ 5,332.81
04.02.01 CORTE DE TERRENO MANUAL EN SARDINEL m3 267.51 42.31 S/ 11,318.35 S/ 9,526.28 S/ 1,792.07
04.02.02 ELIMINACION DE MATERIAL EXCEDENTE(CARGUIO) C/V m3 321.01 11.03 S/ 3,540.74 S/ 3,540.74
04.03 OBRAS DE CONCRETO SIMPLE S/ 494,932.13 S/ 292,580.36
04.03.01 CONCRETO PARA SARDINELES F'C= 175 KG/CM2 m3 481.52 351.69 S/ 169,345.77 S/ 73,584.77
04.03.02 ENCOFRADO Y DESENCOFRADO DE SARDINELES m2 6,420.26 37.41 S/ 240,181.93 S/ 161,550.94
04.03.03 ACERO fy=4200 KG/CM2 GRADO 60 PARA SARDINELES kg 18,209.90 4.69 S/ 85,404.43 S/ 57,444.65
04.04 JUNTAS S/ 1,694.28
04.04.01 JUNTAS ASFALTICAS EN SARDINELES m 351.51 4.82 S/ 1,694.28
04.05 CURADOS S/ 17,679.28
04.05.01 CURADO DE SARDINELES m2 7,459.61 2.37 S/ 17,679.28
05 SEÑALIZACION S/ 94,486.27
05.01 SEÑALIZACION HORIZONTAL S/ 94,486.27
05.01.01 SEÑALIZACION DISCONTINUA EN PAVIMENTO m 4,277.87 5.61 S/ 23,998.85
05.01.02 SEÑALIZACION DE SIMBOLOS Y LETRAS ( HORIZONTA m2 2,660.17 15.06 S/ 40,062.16
05.01.03 PINTURA EN SARDINELES PERALTADOS m2 2,147.16 14.17 S/ 30,425.26
06 SEMBRADO DE AREAS VERDES S/ 174,045.50
06.01 CORTE SUPERFICIAL PARA JARDINERAS m2 11,977.91 3.16 S/ 37,850.20
06.02 ELIMINACION DE MATERIAL EXCEDENTE(CARGUIO) C/VOL m3 2,874.70 11.03 S/ 31,707.94
06.03 SEMBRADO DE AREAS VERDES m2 11,977.91 6.05 S/ 72,466.36
06.04 SEMBRADO DE PLANTONES und 2,255.00 14.20 S/ 32,021.00
07 MITIGACION DE IMPACTO AMBIENTAL S/ 10,442.92 S/ 1,576.35
07.01 REGADO CONTINUO GLB 1.00 1,576.35 S/ 1,576.35 S/ 1,576.35
07.02 LIMPIEZA FINAL DE OBRA m2 38,550.29 0.23 S/ 8,866.57

COSTO DIRECTO S/ 6,276,753.47 S/ 460,921.33 S/ 1,310,576.66 S/ 1,651,210.71

GG (8%) S/ 502,140.28 S/ 36,873.71 S/ 104,846.13 S/ 132,096.86

UTILIDADES (7%) S/ 439,372.74 S/ 32,264.49 S/ 91,740.37 S/ 115,584.75

SUB TOTAL S/ 7,218,266.49 S/ 530,059.53 S/ 1,507,163.16 S/ 1,898,892.32

IGV (18%) S/ 1,299,287.97 S/ 95,410.72 S/ 271,289.37 S/ 341,800.62

VALOR REFERENCIAL S/ 8,517,554.46 S/ 625,470.24 S/ 1,778,452.53 S/ 2,240,692.93

PORCENTAJE DE AVANCE DE OBRA (%) 7.34% 20.88% 26.31%


PORCENTAJE ACUMULADO DE AVANCE DE OBRA (%) 7.34% 28.22% 54.53%
MES 4 MES 5 MES 6
4semanas 4semanas 2 semanas

S/ 1,006,421.40 S/ 786,591.13

S/ 1,006,421.40 S/ 786,591.13

S/ 161,564.26
S/ 844,857.14 S/ 786,591.13
S/ 488,946.41 S/ 72,962.16

S/ 456,769.76 S/ 58,538.14
S/ 311,609.22
S/ 60,332.86
S/ 21,083.53 S/ 39,824.45
S/ 18,713.69 S/ 18,713.69
S/ 45,030.46
S/ 11,265.47 S/ 5,050.04
S/ 11,265.47 S/ 5,050.04
S/ 20,911.18 S/ 9,373.98
S/ 20,911.18 S/ 9,373.98
S/ 221,725.33

S/ 202,351.77
S/ 95,761.00
S/ 78,630.99
S/ 27,959.78
S/ 1,694.28
S/ 1,694.28
S/ 17,679.28
S/ 17,679.28
S/ 94,486.27
S/ 94,486.27
S/ 23,998.85
S/ 40,062.16
S/ 30,425.26
S/ 51,568.87 S/ 122,476.64
S/ 36,903.95 S/ 946.26
S/ 14,664.92 S/ 17,043.02
S/ 72,466.36
S/ 32,021.00
S/ 8,866.57

S/ 8,866.57

S/ 1,717,093.14 S/ 911,122.16 S/ 225,829.48 S/ 6,276,753.48

S/ 137,367.45 S/ 72,889.77 S/ 18,066.36

S/ 120,196.52 S/ 63,778.55 S/ 15,808.06

S/ 1,974,657.11 S/ 1,047,790.48 S/ 259,703.90

S/ 355,438.28 S/ 188,602.29 S/ 46,746.70

S/ 2,330,095.39 S/ 1,236,392.77 S/ 306,450.60

27.36% 14.52% 3.60%


81.89% 96.40% 100.00%