"Saldo de Obra del Mantenimiento Periódico del Camino Vecinal Pomacochas - Dv. Miraflores de Levanto - Gualulo; Dv.

Miraflores de Levanto - Miraflores de Levanto; Gualulo - Las Palmas, distrito de Florida, provincia Bongará, departamento
Amazonas"
04.00 REPARACION DE OBRAS DE ARTE Y DRENAJE
04.01 REPARACION DE ALCANTARILLAS
04.01.10 LIMPIEZA MANUAL DE ALCANTARILLAS
04.01.11 PINTURA EN CABEZAL DE ALCANTARILLAS

04.01.10
LIMPIEZA MANUAL DE ALCANTARILLAS 93.82 m2

TRAMO 1 POMACOCHAS - DIVISION MIRAFLORES DE LEVANTO - GUALULO


Progresivas diametro (pulg) Largo (m) % colmmatacion area (m2) Volumen (m3)
00+230 32.00 0.0254 6.00 25% 0.13 0.78
00+440 32.00 0.0254 8.60 25% 0.13 1.12
00+693 36.00 0.0254 5.50 25% 0.16 0.90
00+885 32.00 0.0254 4.00 25% 0.13 0.52
00+972 32.00 0.0254 7.30 25% 0.13 0.95
01+290 32.00 0.0254 5.80 25% 0.13 0.75
01+540 32.00 0.0254 6.50 25% 0.13 0.84
01+710 32.00 0.0254 5.40 25% 0.13 0.70
01+810 32.00 0.0254 6.00 25% 0.13 0.78
01+858 32.00 0.0254 6.10 25% 0.13 0.79
01+985 32.00 0.0254 6.10 25% 0.13 0.79
02+682 32.00 0.0254 10.00 25% 0.13 1.30
03+125 32.00 0.0254 7.10 25% 0.13 0.92
03+440 32.00 0.0254 6.50 25% 0.13 0.84
04+260 32.00 0.0254 6.30 25% 0.13 0.82
04+350 32.00 0.0254 7.80 25% 0.13 1.01
00+465 32.00 0.0254 6.10 25% 0.13 0.79
04+964 32.00 0.0254 5.50 25% 0.13 0.71
04+964 36.00 0.0254 5.50 25% 0.16 0.90
05+035 36.00 0.0254 5.80 25% 0.16 0.95
05+145 36.00 0.0254 6.10 25% 0.16 1.00
05+220 36.00 0.0254 6.70 25% 0.16 1.10
05+330 32.00 0.0254 6.50 25% 0.13 0.84
05+418 36.00 0.0254 6.70 25% 0.16 1.10
05+902 32.00 0.0254 7.80 25% 0.13 1.01
06+110 32.00 0.0254 10.00 25% 0.13 1.30
06+700 32.00 0.0254 10.00 25% 0.13 1.30
06+840 32.00 0.0254 10.00 25% 0.13 1.30
07+075 32.00 0.0254 6.50 25% 0.13 0.84
07+305 32.00 0.0254 5.40 25% 0.13 0.70
07+434 32.00 0.0254 7.50 25% 0.13 0.97
07+257 32.00 0.0254 8.90 25% 0.13 1.15
07+695 32.00 0.0254 5.50 25% 0.13 0.71
08+105 32.00 0.0254 5.40 25% 0.13 0.70
08+260 32.00 0.0254 5.90 25% 0.13 0.77
07+075 32.00 0.0254 6.50 25% 0.13 0.84
07+076 32.00 0.0254 7.50 25% 0.13 0.97
08+047 32.00 0.0254 4.40 25% 0.13 0.57
08+480 32.00 0.0254 4.80 25% 0.13 0.62
08+780 32.00 0.0254 4.60 25% 0.13 0.60
08+875 32.00 0.0254 5.00 25% 0.13 0.65
10+125 32.00 0.0254 5.80 25% 0.13 0.75
10+450 32.00 0.0254 5.90 25% 0.13 0.77

TOTAL 37.74

TRAMO 2 DIVISION MIRAFLORES DE LEVANTO - MIRAFLORES DE LEVANTO


Progresivas diametro (pulg) Largo (m) Area (m2) Area (m2) Parcial (m2)
00+124 32.00 0.0254 4.90 25% 0.13 0.64
00+265 32.00 0.0254 10.00 25% 0.13 1.30
00+507 36.00 0.0254 4.00 25% 0.16 0.66
00+792 36.00 0.0254 6.30 25% 0.16 1.03

This document was created by an application that isn’t licensed to use novaPDF.
Purchase a license to generate PDF files without this notice.
00+959 36.00 0.0254 7.40 25% 0.16 1.21
01+150 36.00 0.0254 7.50 25% 0.16 1.23
01+545 32.00 0.0254 6.90 25% 0.13 0.90
01+700 32.00 0.0254 7.00 25% 0.13 0.91

TOTAL TOTAL 7.87

This document was created by an application that isn’t licensed to use novaPDF.
Purchase a license to generate PDF files without this notice.
TRAMO 3 GUALULO - LAS PALMAS
Progresivas diametro (pulg) Largo (m) Area (m2) Area (m2) Parcial (m2)
00+103 32.00 0.0254 6.90 25% 0.13 0.90
00+300 32.00 0.0254 6.80 25% 0.13 0.88
00+538 32.00 0.0254 9.80 25% 0.13 1.27
00+660 32.00 0.0254 6.60 25% 0.13 0.86
00+726 32.00 0.0254 6.80 25% 0.13 0.88
00+830 32.00 0.0254 5.30 25% 0.13 0.69
01+176 32.00 0.0254 4.40 25% 0.13 0.57
01+306 32.00 0.0254 6.00 25% 0.13 0.78
01+398 32.00 0.0254 5.00 25% 0.13 0.65
01+585 32.00 0.0254 5.10 25% 0.13 0.66
01+823 32.00 0.0254 5.50 25% 0.13 0.71
01+958 32.00 0.0254 6.30 25% 0.13 0.82
02+078 32.00 0.0254 6.32 25% 0.13 0.82
02+340 32.00 0.0254 5.20 25% 0.13 0.67
02+664 32.00 0.0254 5.60 25% 0.13 0.73
02+883 32.00 0.0254 6.30 25% 0.13 0.82
03+210 32.00 0.0254 4.90 25% 0.13 0.64
03+344 32.00 0.0254 4.00 25% 0.13 0.52
03+580 32.00 0.0254 5.20 25% 0.13 0.67
03+654 32.00 0.0254 8.30 25% 0.13 1.08
03+779 32.00 0.0254 5.80 25% 0.13 0.75
04+047 32.00 0.0254 12.80 25% 0.13 1.66
04+601 32.00 0.0254 5.70 25% 0.13 0.74
04+637 32.00 0.0254 7.80 25% 0.13 1.01
04+818 32.00 0.0254 6.60 25% 0.13 0.86
04+918 32.00 0.0254 12.80 25% 0.13 1.66
05+023 32.00 0.0254 6.90 25% 0.13 0.90
05+110 32.00 0.0254 8.90 25% 0.13 1.15
05+198 32.00 0.0254 8.70 25% 0.13 1.13
05+315 32.00 0.0254 6.30 25% 0.13 0.82
05+349 32.00 0.0254 6.80 25% 0.13 0.88
05+382 32.00 0.0254 6.90 25% 0.13 0.90
05+475 32.00 0.0254 5.80 25% 0.13 0.75
05+517 32.00 0.0254 5.00 25% 0.13 0.65
05+577 32.00 0.0254 6.30 25% 0.13 0.82
05+637 32.00 0.0254 7.70 25% 0.13 1.00
05+714 32.00 0.0254 9.40 25% 0.13 1.22
05+783 32.00 0.0254 5.50 25% 0.13 0.71
05+962 32.00 0.0254 6.00 25% 0.13 0.78
06+146 32.00 0.0254 5.40 25% 0.13 0.70
06+222 32.00 0.0254 7.20 25% 0.13 0.93
06+300 32.00 0.0254 6.80 25% 0.13 0.88
06+354 32.00 0.0254 6.20 25% 0.13 0.80
06+433 32.00 0.0254 9.40 25% 0.13 1.22
06+646 32.00 0.0254 4.80 25% 0.13 0.62
06+713 32.00 0.0254 6.00 25% 0.13 0.78
06+748 32.00 0.0254 5.30 25% 0.13 0.69
06+779 32.00 0.0254 4.80 25% 0.13 0.62
06+821 32.00 0.0254 4.80 25% 0.13 0.62
00+700 32.00 0.0254 4.00 25% 0.13 0.52
00+759 32.00 0.0254 5.50 25% 0.13 0.71
07+891 32.00 0.0254 8.10 25% 0.13 1.05
08+065 32.00 0.0254 7.00 25% 0.13 0.91
08+166 32.00 0.0254 5.20 25% 0.13 0.67
08+263 32.00 0.0254 7.40 25% 0.13 0.96
08+303 32.00 0.0254 5.20 25% 0.13 0.67
08+371 32.00 0.0254 6.50 25% 0.13 0.84

TOTAL TOTAL 48.21

04.01.11 PINTURA EN CABEZAL DE ALCANTARILLAS 1.00 m2

TRAMOS Longitud (m) Area (m2) Altura (m) Altura (m) Parcial (m2)
05+701 0.50 0.50
0.50 0.50

This document was created by an application that isn’t licensed to use novaPDF.
Purchase a license to generate PDF files without this notice.
This document was created by an application that isn’t licensed to use novaPDF.
Purchase a license to generate PDF files without this notice.

También podría gustarte