METRADO PRIMER NIVEL BUNGALOWS

ACERO
DiametroKg pza
ZAPATAS 5/8" 333.92 24 TOTAL ACERO POR DIAMETRO
V.CIMENTACION 3/8" 519.50 103 Diametro Kg pza
1/2" 313.24 35 1/4" 24.65 12
SOBRECIMIENTO 3/8" 204.86 41 3/8" 1145.48 227
COLUMNAS 1/4" 24.65 12 1/2" 556.48 62
3/8" 421.12 84 5/8" 908.85 65
1/2" 243.24 27
5/8" 574.93 41

CONCRETO
F'C m3 CEMENTO BLARENA GRUESAPIEDRA
m3 1/2 m3
AGUA m3
ZAPATAS 175 9.86 83.08 5.32 5.42 1.82
V.CIMENTACION 175 8.95 75.46 4.83 4.92 1.66
SOBRECIMIENTO 175 3.84 32.33 2.07 2.11 0.71
COLUMNAS 210 7.90 76.91 4.11 4.19 1.47
CERCO PERIMETRICO 175 7.04 59.35 3.80 3.87 1.30
FALSO PISO 175 16.00 134.88 8.64 8.80 2.96
TOTAL 53.59 327 20 21 7

LADRILLO DE CONCRETO NRO 12 (39*12*19cm) NTP 399.602


unidad Cantidad
MURO DE SOGA 1er u 1294
total 1294
PRECIO 2.4
LADRILLO KING KONG u 5425

METRADO AREA COMUN

LADRILLO DE CONCRETO NRO 12 (39*12*19cm) NTP 399.602


unidad Cantidad
CERCO PERMETRICO u 669
total 669

MORTERO PARA ASENTADO


m3 CEMENTO BLARENA GRUESAAGUA
m3 m3
DOSIFICACION 1.00 7.00 1.00 0.50
CERCO PERIMETRICO 0.80 5.62 0.80 0.40
MURO DE SOGA 1er 1.55 10.87 1.55 0.78
LADRILLO KING KONG 2.41 16.88 2.41 1.21
CONTRAPISO PRIMER NIVEL 3.90 27.30 3.90 1.95
CONTRAPISO SEGUNDO 4.30 30.10 4.30 2.15
TOTAL 14 98 14 7

MORTERO PARA TARRAJEO


m3 CEMENTO BLARENA FINA m3AGUA m3
DOSIFICACION 1.00 7.00 1.00 0.50
TARRAJEO DE MURO 4.64 32.45 4.64 2.32
TARRAJEO DE COLUMNAS 0.98 6.83 0.98 0.49
TARRAJEO DE VIGAS 1.00 7.00 1.00 0.50
TARRAJEO DE CIELO RASOS 1.73 12.10 1.73 0.86
TOTAL 9 65 9 5
CONSOLIDADO

TOTAL ACERO POR DIAMETRO


DiametroKg pza
1/4" 24.65 12.45
3/8" 1145.48 227.28
1/2" 556.48 62.46
5/8" 908.85 64.73

DESCRIPCION und cantidad


CEMENTO BL bls 490
ARENA GRUESA m3 m3 34
ARENA FINA m3 m3 9
PIEDRA 1/2 m3 m3 21
AGUA m3 m3 19
LADRILLO DE CONCRETO NRO 12
und
(39*12*19cm)1963
NTP 399.602
LADRILLO KING KONG und 5425
PLASTICO rollo 0.8