Exca Col 900 (75ml) Planilla 2 y Resum
Exca Col 900 (75ml) Planilla 2 y Resum
COTAS (m)
T/N -1.45 30.357 -40.451 -30.357 30
EXCAVACION -1.00 27.897 -27.897 0.000 29
EXCAVACION 0.00 27.897 0.000 27.897 28
27
EXCAVACION 1.00 27.897 30.437 40.451
26
T/N 1.45 30.437 0.000 0.000
25
-2 0
DISTANCIA (m
0+290.00 6.180 -6.100 -6.140 0.000
DISTANCIA (m
0+280.00 5.848 -5.853 -5.851 -6.000
DISTANCIA (m
0+270.03 5.787 -5.717 -5.752 -10.000
DISTANCIA
HOJA: 2 DE:28
C
27
26
-2 0
DISTANCIA
0+260.03 5.774 -5.784 -5.779 -9.970
COTAS (m)
T/N -1.45 30.497 -40.862 -30.497 30
EXCAVACION -1.00 28.181 -28.181 0.000 29
EXCAVACION 0.00 28.181 0.000 28.181 28
EXCAVACION 1.00 28.181 30.457 40.862
27
T/N 1.45 30.457 0.000 0.000
26
-2 0
DISTANCIA
0+250.03 5.605 -5.645 -5.625 -10.000
COTAS (m)
T/N -1.45 30.547 -40.958 -30.547 30
EXCAVACION -1.00 28.247 -28.247 0.000 29
EXCAVACION 0.00 28.247 0.000 28.247 28
EXCAVACION 1.00 28.247 30.587 40.958
27
T/N 1.45 30.587 0.000 0.000
26
-2 0
DISTANCIA
0+240.03 5.762 -5.722 -5.742 -10.000
32
31
COTAS (m)
30
29
28
27
26
-2 0
DISTANCIA
HOJA: 3 DE:
COTAS (m)
T/N -1.45 30.557 -41.071 -30.557 30
EXCAVACION -1.00 28.325 -28.325 0.000 29
EXCAVACION 0.00 28.325 0.000 28.325 28
EXCAVACION 1.00 28.325 30.547 41.071
27
T/N 1.45 30.547 0.000 0.000
26
-2 0
DISTANCIA
0+230.03 5.473 -5.483 -5.478 -10.000
COTAS (m)
T/N -1.45 30.567 -41.184 -30.567 30
EXCAVACION -1.00 28.403 -28.403 0.000 29
EXCAVACION 0.00 28.403 0.000 28.403 28
EXCAVACION 1.00 28.403 30.527 41.184 27
T/N 1.45 30.527 0.000 0.000
26
-2 0
DISTANCIA (m
0+220.03 5.247 -5.287 -5.267 -10.000
DISTANCIA
5.028 -4.948 -4.988 -10.000
SUB-TOTAL EXCAVACION TUBE
SUBCONTRATISTA :
HOJA: 4 DE:
N DE EXCAVACION
CERAS, BORDILLOS, CUNETAS Y SISTEMAS DE CONSORCIO
E PRE-COOPERATIVAS FLOR DE BASTION
TAPA, Y MARIA AUXILIADORA - PARROQUIA PASCUALES
BASTION
ASCUALES
ÓN SIN CLASIFICACIÓN
VOLUMEN VOLUMEN
PARCIAL (M3) ACUMULADO (M3)
32
31
30
29
28
27
26
25
-2 0 2
DISTANCIA (m)
0.000 0.000
31
29
27
25
-2 0 2
DISTANCIA (m)
35.973 35.970
32
31
30
29
28
27
26
-2 0 2
DISTANCIA (m)
58.015 93.990
32
31
30
29
28
27
26
-2 0 2
DISTANCIA (m)
28 HOJA: 5 DE:
27
26
-2 0 2
DISTANCIA (m)
57.482 151.470
32
31
30
29
28
27
26
-2 0 2
DISTANCIA (m)
57.020 208.490
32
31
30
29
28
27
26
-2 0 2
DISTANCIA (m)
56.835 265.330
32
31
30
29
28
27
26
-2 0 2
DISTANCIA (m)
HOJA: 6 DE:
32
31
30
29
28
27
26
-2 0 2
DISTANCIA (m)
56.100 321.430
32
31
30
29
28
27
26
-2 0 2
DISTANCIA (m)
53.725 375.160
32
31
30
29
28
27
26
-2 0 2
DISTANCIA (m)
51.275 426.440
SUB-TOTAL EXCAVACION TUBERIA 900 MM 426.440 M3
CONTRATISTA:
HOJA: 7 DE:
RUBRO
UBICACIÓN DISTANCIA COTA AREA DISTANCIA VOLUMEN VOLUMEN
ENTRE PTOS (M) Σ(xi*y(i+1) Σ(yi*x(i+1) (M2) (MTS) PARCIAL (M3) ACUMULADO (M3)
0+119.00 EXCAVACION CAMARA C2 (S/N 62 NO)
35
T/N -1.50 33.956 -50.934 50.934 30
COTAS (m)
25
T/N 1.50 33.956 43.659 50.934
20
EXCAVACION 1.50 29.106 43.656 -43.659 15
EXCAVACION -1.50 29.104 -50.934 -43.656 10
T/N -1.50 33.956 0.000 0.000 5
0
-3 -1 1 3 5
DISTANCIA (m)
0+122.00 -14.553 14.553 14.553 0.000 0.000
DISTANCIA (m)
-12.767 12.767 12.767 3.000 40.980 40.980
DISTANCIA (m)
0+204.00 -10.589 10.589 10.589 0.000 0.000
28
-3 -1 1 3 5
DISTANCIA (m)
-10.586 10.586 10.586 3.000 31.763 31.760
SUB-TOTAL EXCAVACION CAMARAS 72.740 M3
SUBCONTRATISTA : CONTRATISTA:
HOJA: 8 DE:
RUBRO
UBICACIÓN DISTANCIA COTA AREA DISTANCIA VOLUMEN VOLUMEN
ENTRE PTOS (M) Σ(xi*y(i+1) Σ(yi*x(i+1) (M2) (MTS) PARCIAL (M3) ACUMULADO (M3)
0+258.76 EXCAVACION CAMARA A18.9 (AV S/N 68 NO)
31
T/N -1.50 29.817 -44.726 44.726 30
COTAS (m)
T/N 1.50 29.817 41.846 44.726 29
EXCAVACION 1.50 27.897 41.846 -41.846
28
EXCAVACION -1.50 27.897 -44.726 -41.846
27
T/N -1.50 29.817 0.000 0.000
26
-3 -1 1 3 5
DISTANCIA (m)
0+255.76 -5.760 5.760 5.760 0.000 0.000
DISTANCIA (m)
-5.118 5.118 5.118 3.000 16.317 16.320
SUB-TOTAL EXCAVACION CAMARA A18,9 16.320 M3
RESUMEN
CAMARA C3 LIQ PLANILLA 2 39.22
CAMARA C3 PLANILLA 1 13.06
A COBRAR POR CAMARA C3 26.16
CORRECCION COLECTOR 900 MM (200ML) PLANILLA 2 1351.45
COBRADO COLECTOR 900 MM (200ML) PLANILLA 1 1103.15
A COBRAR POR COL 900MM (200ML) 248.3
COLECTOR 900 MM (75ML) AV. SN 68 NO PLANILLA 2 426.440
CAMARA C1 31.760
CAMARA C2 40.980
CAMARA 18,9 16.320
TOTAL 789.960
SUBCONTRATISTA : CONTRATISTA:
GOBIERNO AUTONOMO DESCENTRALIZADO MUNICIPAL DE GUAYAQUIL MUY ILUSTRE MUNICIPALIDAD DE GUAYAQUIL
CONTRATO: LICO-MIMG-007-2020
PAVIMENTACIÓN DE CALLES INC. ACERAS, BORDILLOS, CUNETAS Y SISTEMAS DE AA.LL., SECTOR PERIMETRAL OESTE PRE- COOPERATIVAS: FLOR
PROYECTO: DE BASTION BLOQUES: 6,8,20,21, BLOQUE 6 - 2° ETAPA, Y MARIA AUXILIADORA – PARROQUIA PASCUALES
CONTRATISTA: CONSORCIO PASCUALES BASTION
SUBCONTRATISTA
CANTIDADES PORCENTAJES
CANTIDAD
RUBRO CODIGO DESCRIPCION UNIDAD CONTRATADA
Anterior Actual Acumulado Anterior Actual Acumulado
303-2(1)E EXCAVACIÓN SIN CLASIFICACIÓN (INC. DESALOJO) M3 1,350.00 1,132.12 789.96 1,922.08 0.00% 58.52% 58.52%
Anexos:
Demostrativo
Formato de Liberacion de Campo
Memoria Fotografica
Implantacion