PROYECTO:
“PROYECTO DE VIVIENDA NUEVA AUTOCONSTRUCCION EN EL MUNICIPIO DE YACUIBA – FASE (XXX) 2021 - TARIJA"
ENTIDAD EJECUTORA:EMPRESA CONSTRUCTORA GONZALES BARJA G&B MUNICIPIO: YACUIBA PERIODO: 16/09/2021 AL 22/09/2021
INSPECTORIA DE PROYECTO: ING. MARIO B. ORTIZ GARZON. PROVINCIA: GRAN CHACO FECHA: 9/22/2021
FISCAL DE OBRA: ARQ. ERLING ARTEAGA MENDOZA DEPARTAMENTO: TARIJA
Nº COMUNIDADES: 8 COMUNIDADES
1 ALAMBRE DE AMARRE KG 582.33 10.08 5,869.89 553.00 553.00 - 5,574.24 5,574.24 94.96%
2 ALAMBRE DE COBRE Nº 10 AWG M 1040.00 3.50 3,640.00 - - - -
3 ALAMBRE DE COBRE Nº 12 AWG M 5108.00 1.95 9,960.60 - - - -
4 ALAMBRE DE COBRE Nº 14 AWG M 3103.00 1.30 4,033.90 - - - -
5 ALAMBRE GALVANIZADO Nº12 KG 110.01 19.00 2,090.19 - - - -
6 ALQUITRAN KG 260.05 11.08 2,881.35 227.50 227.50 - 2,520.70 2,520.70 87.48%
7 BOTAGUAS DE CERAMICA UNA CAIDA PZA 1483.20 3.73 5,532.34 - - - -
8 CAÑERIA DE ALUMINIO 1/2 (BRAZO DE DUCHA) PZA 40.00 20.00 800.00 - - - -
9 CAJA PARA 1 TERMICO PZA 40.00 10.02 400.80 - - - -
10 CAJA PARA 3 TERMICOS PZA 40.00 35.04 1,401.60 - - - -
11 CAJA PLASTICA CIRCULAR PZA 652.00 1.00 652.00 - - - -
12 CAJA PLASTICA RECTANGULAR PZA 652.00 2.00 1,304.00 - - - -
13 CAJA SIFONADA PVC C/REJILLA DE PISO PZA 40.00 35.00 1,400.00 - - - -
14 CAL VIVA KG 12056.03 2.28 27,487.75 - - - -
15 CALAMINA ONDULADA PREPINTADA Nº 26 M2 3472.81 35.27 122,486.01 - - - -
16 CEMENTO BLANCO KG 896.61 5.08 4,554.78 - - - -
17 CEMENTO COLA KG 15570.76 1.08 16,816.42 - - - -
18 CEMENTO PORTLAND (50 kg) BL 6622.79 51.17 338,888.16 5,775.00 5,775.00 - 295,506.75 295,506.75 87.20%
19 CERAMICA NACIONAL M2 3233.31 36.70 118,662.48 - - - -
20 CHICOTILLO PZA 80.00 9.00 720.00 - - - -
21 CIELO FALSO YESO - PVC + ACCESORIOS M2 2310.13 75.38 174,137.60 - - - -
22 CINTA AISLANTE PZA 130.45 10.01 1,305.80 - - - -
23 CLAVOS KG 277.22 10.08 2,794.38 - - - -
24 CODO PVC DE 1/2" PZA 400.00 1.70 680.00 - - - -
25 CODO PVC 5/8" PZA 1677.00 0.50 838.50 - - - -
26 CODO PVC DESAGUE 2" PZA 160.00 3.50 560.00 - - - -
27 CODO PVC DESAGUE 4" PZA 80.00 10.00 800.00 - - - -
28 COPLA PVC DE 1/2" PZA 120.00 2.00 240.00 - - - -
29 CORDEL M 520.00 1.50 780.00 455.00 455.00 - 682.50 682.50 87.50%
30 CUMBRERA PLANA PREPINTADA Nº 26 CORTE 50 M 319.20 22.14 7,067.09 - - - -
31 DUCHA PLASTICA ELECTRICA PZA 40.00 84.03 3,361.20 - - - -
32 ELECTRODOS KG 181.19 25.08 4,544.25 - - - -
33 FIERRO CORRUGADO 1/2" BR 782.54 94.00 73,558.76 665.00 665.00 - 62,510.00 62,510.00 84.98%
34 FIERRO CORRUGADO 1/4" BR 1734.38 29.22 50,678.58 1,505.00 1,505.00 - 43,976.10 43,976.10 86.77%
35 FIERRO CORRUGADO 3/8" BR 1532.10 45.20 69,250.92 1,340.50 1,340.50 - 60,590.60 60,590.60 87.49%
36 FIERRO CORRUGADO 5/16" BR 76.46 41.38 3,163.91 66.50 66.50 - 2,751.77 2,751.77 86.97%
37 FOCOS LED 18W PZA 253.00 12.00 3,036.00 - - - -
38 GRIFERIA PARA LAVAMANOS PZA 40.00 85.03 3,401.20 - - - -
39 GRIFERIA PARA LAVAPLATOS PZA 40.00 145.03 5,801.20 - - - -
40 GRIFO DE PARED 1/2" PZA 40.00 40.03 1,601.20 - - - -
41 IMPERMEABILIZANTE KG 200.00 13.00 2,600.00 - - - -
42 INODORO T/BAJO + ACCESORIOS PZA 40.00 451.80 18,072.00 - - - -
43 INTERRUPTOR PZA 253.00 15.28 3,865.84 - - - -
PROYECTO ORIGINAL DETALLE CANTIDADES DETALLE DE PAGOS (Bs.)
Nº DESCRIPCION DE INSUMOS UND.
ACTUAL ACUMULADO
CANTIDAD PRECIO UNIT. (Bs.) SUBTOTAL (Bs.) ANTERIOR ACTUAL ACUMULADO ANTERIOR (Bs.) % AVANCE
(Bs.) (Bs.)
44 LADRILLO 6H (24X18X12) PZA 125,263.16 1.45 181,631.58 109,585.00 109,585.00 - 158,898.25 158,898.25 87.48%
45 LADRILLO GAMBOTE (24X12X6) PZA 29120.00 1.60 46,592.00 - - - -
46 LAVAMANOS C/PEDESTAL + ACCESORIOS PZA 40.00 292.67 11,706.80 - - - -
47 LAVANDERIA DE CEMENTO + ACCESORIOS PZA 40.00 121.33 4,853.20 - - - -
48 LAVAPLATOS 2 FOSAS Y 1 FREGADERO + SOPAPA Y SIFON PZA 40.00 480.50 19,220.00 - - - -
49 LIJA P/PARED M 687.67 6.50 4,469.86 - - - -
50 LLAVE DE PASO 1/2" PZA 120.00 30.03 3,603.60 - - - -
51 LLAVE DE PASO 1/2" PARA DUCHA PZA 40.00 85.03 3,401.20 - - - -
52 MADERA DE CONSTRUCCION (3 USOS) P2 8418.91 4.90 41,252.66 7,366.45 7,366.45 - 36,095.61 36,095.61 87.50%
53 MARCO DE ALUMINIO LINEA 20 C/MALLA MILIMETRICA M2 229.61 220.23 50,567.01 - - - -
54 MASA ACRILICA LT 219.48 20.08 4,407.16 - - - -
55 MASA CORRIDA LT 668.84 18.08 12,092.63 - - - -
56 MEZCLADORA HR 3.41 25.00 85.25 3.41 3.41 - 85.25 85.25 100.00%
57 NIPLE PVC DE 1/2" PZA 120.00 1.50 180.00 - - - -
58 PEGAMENTO PARA PVC LT 47.20 35.08 1,655.78 - - - -
59 PERFIL TIPO C 25X50X10X1,8 MM M 3623.80 14.30 51,820.34 - - - -
60 PERFIL TIPO C 40X80X15X2 MM M 2868.85 21.56 61,852.41 - - - -
61 PINTURA LATEX LT 2220.80 25.78 57,252.22 - - - -
62 POLIESTIRENO E-1CM M2 65.59 6.00 393.54 - - - -
63 POLIETILENO 200 MICRONES M 1820.38 4.00 7,281.52 1,592.85 1,592.85 - 6,371.40 6,371.40 87.50%
64 PUERTA TABLERO DE MADERA SEMIDURA INC/MARCO 3.5"X2" C/BAR M2 426.00 851.75 362,845.50 - - - -
65 REDUCCION PVC 2" A 1 1/2" PZA 160.00 5.00 800.00 - - - -
66 SELLA ROSCA PZA 40.00 30.02 1,200.80 - - - -
67 SELLADOR DE PARED LT 754.55 16.17 12,201.07 - - - -
68 SIFON DE PVC PZA 40.00 20.00 800.00 - - - -
69 SIFON DE PVC PARA LAVANDERIA PZA 40.00 30.00 1,200.00 - - - -
70 SOCKET PLATO PZA 253.00 4.00 1,012.00 - - - -
71 TANQUE PLASTICO DE AGUA 450 LITROS C/ ACCESORIOS GLB 40.00 428.13 17,125.20 - - - -
72 TEE PVC D=1/2" PZA 200.00 3.00 600.00 - - - -
73 TEE PVC DESAGUE 2" PZA 40.00 7.50 300.00 - - - -
74 TEE PVC DESAGUE 4" PZA 80.00 13.00 1,040.00 - - - -
75 TEFLON 3/4" PZA 648.00 2.00 1,296.00 - - - -
76 TERMICO DE 20 AMP PZA 40.00 17.00 680.00 - - - -
77 TERMICO DE 25 AMP PZA 40.00 17.00 680.00 - - - -
78 TERMICO DE 32 AMP PZA 80.00 18.00 1,440.00 - - - -
79 TOMACORRIENTE DOBLE PZA 399.00 19.00 7,581.00 - - - -
80 TORNILLO Y RAMPLUG DE 2" X 6" PZA 16315.20 0.70 11,420.64 - - - -
81 TUBO PVC 1/2" (L=6M) BR 168.00 36.00 6,048.00 - - - -
82 TUBO PVC 5/8" (L=3M) BR 1350.70 4.50 6,078.15 - - - -
83 TUBO PVC DESAGUE 2" (L=4M) BR 108.00 30.28 3,270.24 - - - -
84 TUBO PVC DESAGUE 4" (L=4M) BR 192.00 69.84 13,409.28 - - - -
85 UNION UNIVERSAL 1/2" PZA 120.00 4.00 480.00 - - - -
86 VALVULA DE RETENCION DE 1/2" PZA 80.00 10.00 800.00 - - - -
87 VENTANA DE ALUMINIO LINEA 20 C/VIDRIO 4MM + ACCESORIOS M2 541.80 381.42 206,653.36 - - - -
88 VIBRADORA HR 3.41 20.00 68.20 3.41 3.41 - 68.20 68.20 100.00%
89 YESO KG 4.00 1.08 4.32 3.50 3.50 - 3.78 3.78 87.50%
TOTAL (Bs.): 2,325,073.22 TOTAL (Bs.): 0.00 675,635.15 675,635.15 29.06%
Total Literal: SEISCIENTOS SETENTA Y CINCO MIL SEISCIENTOS TREINTA Y CINCO , 15/100 BOLIVIANOS
ELABORADO:
APROBADO: V°B°
ING HORACIO RAUL SANDOVAL BURGOS ING. MARIO B. ORTIZ GARZON ARQ. ERLING ARTEAGA MENDOZA
TECNICO OPERATIVO DE AREA INSPECTOR DE PROYECTO FISCAL DE OBRA
EMPRESA CONSTRUCTORA GONZALES BARJA G&B
PROGRAMACION DE PROVISIÓN DE MATERIALES INICIAL HASTA LA FINALIZACIÓN
PROYECTO DE VIVIENDA NUEVA AUTOCONSTRUCCION EN EL MUNICIPIO DE YACUIBA – FASE (XXX) 2021 - TARIJA
PRODUCTO 1 - INFORME
PRODUCTO 2 - INFORME DE AVANCE
INICIAL AL 50% DE EJECUCION
MONTO AL 100% DE EJECUCIÓN FISICA MONTO
FISICA CANTIDAD
No DESCRIPCION DE MATERIALES UNIDAD CANT. P.U. TOTAL ( 23/09/2021 AL 03/01/2022) TOTAL %
( 16/09/2021 AL 22/09/2021) TOTAL
(Bs.) (Bs.)
MONTO MONTO
CANTIDAD CANTIDAD
(Bs.) (Bs.)
1 ALAMBRE DE AMARRE KG 582.33 10.08 5869.89 553.00 5,574.24 29.33 295.65 582.33 5869.89 100%
2 ALAMBRE DE COBRE Nº 10 AWG M 1040.00 3.50 3640.00 - 1,040.00 3,640.00 1040.00 3640.00 100%
3 ALAMBRE DE COBRE Nº 12 AWG M 5108.00 1.95 9960.60 - 5,108.00 9,960.60 5108.00 9960.60 100%
4 ALAMBRE DE COBRE Nº 14 AWG M 3103.00 1.30 4033.90 - 3,103.00 4,033.90 3103.00 4033.90 100%
5 ALAMBRE GALVANIZADO Nº12 KG 110.01 19.00 2090.19 - 110.01 2,090.19 110.01 2090.19 100%
6 ALQUITRAN KG 260.05 11.08 2881.35 227.50 2,520.70 32.55 360.65 260.05 2881.35 100%
7 BOTAGUAS DE CERAMICA UNA CAIDA PZA 1483.20 3.73 5532.34 - 1,483.20 5,532.34 1483.20 5532.34 100%
8 CAÑERIA DE ALUMINIO 1/2 (BRAZO DE DUCHA) PZA 40.00 20.00 800.00 - 40.00 800.00 40.00 800.00 100%
9 CAJA PARA 1 TERMICO PZA 40.00 10.02 400.80 - 40.00 400.80 40.00 400.80 100%
10 CAJA PARA 3 TERMICOS PZA 40.00 35.04 1401.60 - 40.00 1,401.60 40.00 1401.60 100%
11 CAJA PLASTICA CIRCULAR PZA 652.00 1.00 652.00 - 652.00 652.00 652.00 652.00 100%
12 CAJA PLASTICA RECTANGULAR PZA 652.00 2.00 1304.00 - 652.00 1,304.00 652.00 1304.00 100%
13 CAJA SIFONADA PVC C/REJILLA DE PISO PZA 40.00 35.00 1400.00 - 40.00 1,400.00 40.00 1400.00 100%
14 CAL VIVA KG 12056.03 2.28 27487.75 - 12,056.03 27,487.75 12056.03 27487.75 100%
15 CALAMINA ONDULADA PREPINTADA Nº 26 M2 3472.81 35.27 122486.01 - 3,472.81 122,486.01 3472.81 122486.01 100%
16 CEMENTO BLANCO KG 896.61 5.08 4554.78 - 896.61 4,554.78 896.61 4554.78 100%
17 CEMENTO COLA KG 15570.76 1.08 16816.42 - 15,570.76 16,816.42 15570.76 16816.42 100%
18 CEMENTO PORTLAND (50 kg) BL 6622.79 51.17 338888.16 5,775.00 295,506.75 847.79 43,381.41 6622.79 338888.16 100%
19 CERAMICA NACIONAL M2 3233.31 36.70 118662.48 - 3,233.31 118,662.48 3233.31 118662.48 100%
20 CHICOTILLO PZA 80.00 9.00 720.00 - 80.00 720.00 80.00 720.00 100%
21 CIELO FALSO YESO - PVC + ACCESORIOS M2 2310.13 75.38 174137.60 - 2,310.13 174,137.60 2310.13 174137.60 100%
22 CINTA AISLANTE PZA 130.45 10.01 1305.80 - 130.45 1,305.80 130.45 1305.80 100%
24 CODO PVC DE 1/2" PZA 400.00 1.70 680.00 - 400.00 680.00 400.00 680.00 100%
25 CODO PVC 5/8" PZA 1677.00 0.50 838.50 - 1,677.00 838.50 1677.00 838.50 100%
26 CODO PVC DESAGUE 2" PZA 160.00 3.50 560.00 - 160.00 560.00 160.00 560.00 100%
27 CODO PVC DESAGUE 4" PZA 80.00 10.00 800.00 - 80.00 800.00 80.00 800.00 100%
28 COPLA PVC DE 1/2" PZA 120.00 2.00 240.00 - 120.00 240.00 120.00 240.00 100%
29 CORDEL M 520.00 1.50 780.00 455.00 682.50 65.00 97.50 520.00 780.00 100%
30 CUMBRERA PLANA PREPINTADA Nº 26 CORTE 50 M 319.20 22.14 7067.09 - 319.20 7,067.09 319.20 7067.09 100%
31 DUCHA PLASTICA ELECTRICA PZA 40.00 84.03 3361.20 - 40.00 3,361.20 40.00 3361.20 100%
33 FIERRO CORRUGADO 1/2" BR 782.54 94.00 73558.76 665.00 62,510.00 117.54 11,048.76 782.54 73558.76 100%
34 FIERRO CORRUGADO 1/4" BR 1734.38 29.22 50678.58 1,505.00 43,976.10 229.38 6,702.48 1734.38 50678.58 100%
35 FIERRO CORRUGADO 3/8" BR 1532.10 45.20 69250.92 1,340.50 60,590.60 191.60 8,660.32 1532.10 69250.92 100%
36 FIERRO CORRUGADO 5/16" BR 76.46 41.38 3163.91 66.50 2,751.77 9.96 412.14 76.46 3163.91 100%
37 FOCOS LED 18W PZA 253.00 12.00 3036.00 - 253.00 3,036.00 253.00 3036.00 100%
38 GRIFERIA PARA LAVAMANOS PZA 40.00 85.03 3401.20 - 40.00 3,401.20 40.00 3401.20 100%
39 GRIFERIA PARA LAVAPLATOS PZA 40.00 145.03 5801.20 - 40.00 5,801.20 40.00 5801.20 100%
40 GRIFO DE PARED 1/2" PZA 40.00 40.03 1601.20 - 40.00 1,601.20 40.00 1601.20 100%
42 INODORO T/BAJO + ACCESORIOS PZA 40.00 451.80 18072.00 - 40.00 18,072.00 40.00 18072.00 100%
43 INTERRUPTOR PZA 253.00 15.28 3865.84 - 253.00 3,865.84 253.00 3865.84 100%
44 LADRILLO 6H (24X18X12) PZA 125263.16 1.45 181631.58 109,585.00 158,898.25 15,678.16 22,733.33 125263.16 181631.58 100%
45 LADRILLO GAMBOTE (24X12X6) PZA 29120.00 1.60 46592.00 - 29,120.00 46,592.00 29120.00 46592.00 100%
PROGRAMACION DE PROVISIÓN DE MATERIALES INICIAL HASTA LA FINALIZACIÓN
PROYECTO DE VIVIENDA NUEVA AUTOCONSTRUCCION EN EL MUNICIPIO DE YACUIBA – FASE (XXX) 2021 - TARIJA
PRODUCTO 1 - INFORME
PRODUCTO 2 - INFORME DE AVANCE
INICIAL AL 50% DE EJECUCION
MONTO AL 100% DE EJECUCIÓN FISICA MONTO
FISICA CANTIDAD
No DESCRIPCION DE MATERIALES UNIDAD CANT. P.U. TOTAL ( 23/09/2021 AL 03/01/2022) TOTAL %
( 16/09/2021 AL 22/09/2021) TOTAL
(Bs.) (Bs.)
MONTO MONTO
CANTIDAD CANTIDAD
(Bs.) (Bs.)
46 LAVAMANOS C/PEDESTAL + ACCESORIOS PZA 40.00 292.67 11706.80 - 40.00 11,706.80 40.00 11706.80 100%
47 LAVANDERIA DE CEMENTO + ACCESORIOS PZA 40.00 121.33 4853.20 - 40.00 4,853.20 40.00 4853.20 100%
48 LAVAPLATOS 2 FOSAS Y 1 FREGADERO + SOPAPA Y SIFON PZA 40.00 480.50 19220.00 - 40.00 19,220.00 40.00 19220.00 100%
49 LIJA P/PARED M 687.67 6.50 4469.86 - 687.67 4,469.86 687.67 4469.86 100%
50 LLAVE DE PASO 1/2" PZA 120.00 30.03 3603.60 - 120.00 3,603.60 120.00 3603.60 100%
51 LLAVE DE PASO 1/2" PARA DUCHA PZA 40.00 85.03 3401.20 - 40.00 3,401.20 40.00 3401.20 100%
52 MADERA DE CONSTRUCCION (3 USOS) P2 8418.91 4.90 41252.66 7,366.45 36,095.61 1,052.46 5,157.05 8418.91 41252.66 100%
53 MARCO DE ALUMINIO LINEA 20 C/MALLA MILIMETRICA M2 229.61 220.23 50567.01 - 229.61 50,567.01 229.61 50567.01 100%
54 MASA ACRILICA LT 219.48 20.08 4407.16 - 219.48 4,407.16 219.48 4407.16 100%
55 MASA CORRIDA LT 668.84 18.08 12092.63 - 668.84 12,092.63 668.84 12092.63 100%
57 NIPLE PVC DE 1/2" PZA 120.00 1.50 180.00 - 120.00 180.00 120.00 180.00 100%
58 PEGAMENTO PARA PVC LT 47.20 35.08 1655.78 - 47.20 1,655.78 47.20 1655.78 100%
59 PERFIL TIPO C 25X50X10X1,8 MM M 3623.80 14.30 51820.34 - 3,623.80 51,820.34 3623.80 51820.34 100%
60 PERFIL TIPO C 40X80X15X2 MM M 2868.85 21.56 61852.41 - 2,868.85 61,852.41 2868.85 61852.41 100%
61 PINTURA LATEX LT 2220.80 25.78 57252.22 - 2,220.80 57,252.22 2220.80 57252.22 100%
62 POLIESTIRENO E-1CM M2 65.59 6.00 393.54 - 65.59 393.54 65.59 393.54 100%
63 POLIETILENO 200 MICRONES M 1820.38 4.00 7281.52 1,592.85 6,371.40 227.53 910.12 1820.38 7281.52 100%
64 PUERTA TABLERO DE MADERA SEMIDURA INC/MARCO 3.5"X2" C/BARNIZ Y PINTURA + QUINCALLERIA M2 426.00 851.75 362845.50 - 426.00 362,845.50 426.00 362845.50 100%
65 REDUCCION PVC 2" A 1 1/2" PZA 160.00 5.00 800.00 - 160.00 800.00 160.00 800.00 100%
66 SELLA ROSCA PZA 40.00 30.02 1200.80 - 40.00 1,200.80 40.00 1200.80 100%
67 SELLADOR DE PARED LT 754.55 16.17 12201.07 - 754.55 12,201.07 754.55 12201.07 100%
68 SIFON DE PVC PZA 40.00 20.00 800.00 - 40.00 800.00 40.00 800.00 100%
69 SIFON DE PVC PARA LAVANDERIA PZA 40.00 30.00 1200.00 - 40.00 1,200.00 40.00 1200.00 100%
70 SOCKET PLATO PZA 253.00 4.00 1012.00 - 253.00 1,012.00 253.00 1012.00 100%
71 TANQUE PLASTICO DE AGUA 450 LITROS C/ ACCESORIOS GLB 40.00 428.13 17125.20 - 40.00 17,125.20 40.00 17125.20 100%
72 TEE PVC D=1/2" PZA 200.00 3.00 600.00 - 200.00 600.00 200.00 600.00 100%
73 TEE PVC DESAGUE 2" PZA 40.00 7.50 300.00 - 40.00 300.00 40.00 300.00 100%
74 TEE PVC DESAGUE 4" PZA 80.00 13.00 1040.00 - 80.00 1,040.00 80.00 1040.00 100%
75 TEFLON 3/4" PZA 648.00 2.00 1296.00 - 648.00 1,296.00 648.00 1296.00 100%
76 TERMICO DE 20 AMP PZA 40.00 17.00 680.00 - 40.00 680.00 40.00 680.00 100%
77 TERMICO DE 25 AMP PZA 40.00 17.00 680.00 - 40.00 680.00 40.00 680.00 100%
78 TERMICO DE 32 AMP PZA 80.00 18.00 1440.00 - 80.00 1,440.00 80.00 1440.00 100%
79 TOMACORRIENTE DOBLE PZA 399.00 19.00 7581.00 - 399.00 7,581.00 399.00 7581.00 100%
80 TORNILLO Y RAMPLUG DE 2" X 6" PZA 16315.20 0.70 11420.64 - 16,315.20 11,420.64 16315.20 11420.64 100%
81 TUBO PVC 1/2" (L=6M) BR 168.00 36.00 6048.00 - 168.00 6,048.00 168.00 6048.00 100%
82 TUBO PVC 5/8" (L=3M) BR 1350.70 4.50 6078.15 - 1,350.70 6,078.15 1350.70 6078.15 100%
83 TUBO PVC DESAGUE 2" (L=4M) BR 108.00 30.28 3270.24 - 108.00 3,270.24 108.00 3270.24 100%
84 TUBO PVC DESAGUE 4" (L=4M) BR 192.00 69.84 13409.28 - 192.00 13,409.28 192.00 13409.28 100%
85 UNION UNIVERSAL 1/2" PZA 120.00 4.00 480.00 - 120.00 480.00 120.00 480.00 100%
86 VALVULA DE RETENCION DE 1/2" PZA 80.00 10.00 800.00 - 80.00 800.00 80.00 800.00 100%
87 VENTANA DE ALUMINIO LINEA 20 C/VIDRIO 4MM + ACCESORIOS M2 541.80 381.42 206653.36 - 541.80 206,653.36 541.80 206653.36 100%
89 YESO KG 4.00 1.08 4.32 3.50 3.78 0.50 0.54 4.00 4.32 100%
PROGRAMACION DE PROVISIÓN DE MATERIALES INICIAL HASTA LA FINALIZACIÓN
PROYECTO DE VIVIENDA NUEVA AUTOCONSTRUCCION EN EL MUNICIPIO DE YACUIBA – FASE (XXX) 2021 - TARIJA
PRODUCTO 1 - INFORME
PRODUCTO 2 - INFORME DE AVANCE
INICIAL AL 50% DE EJECUCION
MONTO AL 100% DE EJECUCIÓN FISICA MONTO
FISICA CANTIDAD
No DESCRIPCION DE MATERIALES UNIDAD CANT. P.U. TOTAL ( 23/09/2021 AL 03/01/2022) TOTAL %
( 16/09/2021 AL 22/09/2021) TOTAL
(Bs.) (Bs.)
MONTO MONTO
CANTIDAD CANTIDAD
(Bs.) (Bs.)
2325073.22
2,325,073.22 BS. 675,549.90 BS. 1,649,523.31
TOTALES =
% 29.05 % 70.95
100.00
MONTO
No PRODUCTO %
(BS.)
2 PRODUCTO 2 - INFORME DE AVANCE AL 50% DE EJECUCIÓN FISICA (23/09/2021 AL 11/11/2021) 1,649,523.31 70.95
TOTAL ADQUISICION DE
2,325,073.21 100.00
MATERIALES DE CONSTRUCCION (Provision/Dotacion de Materiales)=