ID Nombre de tarea Duration Start Finish Task Predecessors Resource Names 04 Jul '22 11 Jul '22 18 Jul '22

Mode W T F S S M T W T F S S M T W T F S S M T W T
0 CRONOGRAMA GANTT - PARCIAL 16 days Fri 01/07/22Wed 20/07/ 16 days NA
1 1 ESTRUCTURAS 16 days Fri 01/07/22 Wed 20/07/22 16 days NA
2 1.1 TRABAJOS PRELIMINARES 2 days Fri 01/07/22 Mon 04/07/22 2 days NA
3 1.1.1 DEMOLICION DE VEREDA 1 day Fri 01/07/22 Sat 02/07/22 1 day NA
4 1.1.2 LIMPIEZA DE TERRENO MANUAL 1 day Sat 02/07/22 Mon 04/07/22 3 1 day NA
5 1.1.3 TRAZO Y REPLANTEO 1 day Sat 02/07/22 Mon 04/07/22 4FF 1 day NA
6 1.2 MOVIMIENTO DE TIERRAS 3 days Mon 04/07/22 Thu 07/07/22 3 days NA
7 1.2.1 EXCAVACION MANUAL DE ZANJAS PARA ZAPATAS 1 day Mon 04/07/22 Tue 05/07/22 5 1 day NA
8 1.2.2 EXCAVACION MANUAL DE ZANJAS PARA CIMIENTOS EN 1 day Mon 04/07/22 Tue 05/07/22 7SS 1 day 16/11
TERRENO NORMAL
9 1.2.3 NIVELACION INTERIOR Y APISONADO 1 day Tue 05/07/22 Wed 06/07/22 8;7 1 day NA
10 1.2.4 RELLENO COMPACTADO CON AFIRMADO 1 day Wed 06/07/22 Thu 07/07/22 9 1 day NA
11 1.2.5 ELMINACION CON TRANSPORTE (CARGIO A MANO) 1 day Tue 05/07/22 Wed 06/07/22 7;8 1 day NA
12 1.3 OBRAS DE CONCRETO SIMPLE 5 days Thu 07/07/22 Wed 13/07/22 5 days NA
13 1.3.1 CIMIENTOS CORRIDOS 1:10 Cemento-Hormigon 30% DE PG. 2 days Thu 07/07/22 Sat 09/07/22 10 2 days NA
14 1.3.2 CONCRETO PARA SOBRECIMIENTOS F'c=145 kg/cm2 2 days Mon 11/07/22 Wed 13/07/22 15 2 days NA
15 1.3.3 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTO 1 day Sat 09/07/22 Mon 11/07/22 13 1 day NA
16 1.4 OBRAS DE CONCRETO ARMADO 11 days Thu 07/07/22 Wed 20/07/22 11 days NA
17 1.4.1 ZAPATAS 3 days Thu 07/07/22 Mon 11/07/22 3 days NA
18 1.4.1.1 CONCRETO EN ZAPATAS f'c=175 kg/cm2 1 day Sat 09/07/22 Mon 11/07/22 19 1 day NA
19 1.4.1.2 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 2 days Thu 07/07/22 Sat 09/07/22 10 2 days NA
20 1.4.2 COLUMNAS 4 days Thu 07/07/22 Tue 12/07/22 4 days NA
21 1.4.2.1 CONCRETO EN COLUMNAS f'c=175 kg/cm2 1 day Mon 11/07/22 Tue 12/07/22 22 1 day NA
22 1.4.2.2 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS 1 day Sat 09/07/22 Mon 11/07/22 23 1 day NA
23 1.4.2.3 ACERO fy=4200 kg/cm2 GRADO 60 2 days Thu 07/07/22 Sat 09/07/22 19SS 2 days NA
24 1.4.3 VIGAS 7 days Tue 12/07/22 Wed 20/07/22 7 days NA
25 1.4.3.1 CONCRETO EN VIGAS f'c=175 kg/cm2 1 day Tue 19/07/22 Wed 20/07/22 26 1 day NA
26 1.4.3.2 ENCOFRADO Y DESENCOFRADO 4 days Thu 14/07/22 Tue 19/07/22 27 4 days NA
27 1.4.3.3 ACERO fy=4200 kg/cm2 GRADO 60 en VIGAS 2 days Tue 12/07/22 Thu 14/07/22 21 2 days NA
28 2 ARQUITECTURA 5 days Wed 13/07/2Tue 19/07/2 5 days NA
29 2.1 ALBAÑILERIA 5 days Wed 13/07/22 Tue 19/07/22 5 days NA
30 2.1.1 MUROS DE LADRILLO KK 5 days Wed 13/07/22 Tue 19/07/22 14 5 days NA

Task Project Summary Rolled Up Progress Inactive Summary Start-only

Task Progress Group By Summary External Tasks Manual Task Finish-only


Proyecto: CRONOGRAMA GAN
Split Rolled Up Task External Milestone Duration-only Deadline
Fecha: Thu 12/05/22