CONTRATO Nº: IVOPEY-OP- 012 -2020 - IV

CRONOGRAMA DE TRABAJO Y CURVA DE INVERSION


OBRA: CONSTRUCCION DE CERCA PERIMETRAL EN LA E.B. "ALBERTO RAVELL" V ETAPA, MUNICIPIO SAN FELIPE, ESTADO YARACUY ..

UBICACIÓN: La Patria , Municipio San Felipe , Estado Yaracuy.

LAPSO DE EJECUCION UN (01) MES


CAP DESCRIPCION SEM1 SEM 2 SEM 3 SEM 4
1 OBRAS PREPARATIVAS 2,824,908.16

2 ESTRUCTURAS 7,270,482.19

3 OBRAS ARQUITEC. 210,008,087.42 210,008,087.42 210,008,087.42 210,008,087.42 210,008,087.42 210,008,087.42 210,008,087.42 210,008,087.42 210,008,087.42 210,008,087.42 210,008,087.42 210,008,087.42 210,008,087.42

5 TRANSPORTES 36,736,891.46 36,736,891.46 36,736,891.46 36,736,891.46

6 VARIACIONES 32,079,330.71 32,079,330.71 32,079,330.71 32,079,330.71 32,079,330.71 32,079,330.71 32,079,330.71 32,079,330.71 32,079,330.71

220,103,477.77 210,008,087.42 210,008,087.42 210,008,087.42 246,744,978.88 246,744,978.88 246,744,978.88 278,824,309.59 242,087,418.13 242,087,418.13 242,087,418.13 242,087,418.13 242,087,418.13 32,079,330.71 32,079,330.71 32,079,330.71
850,127,740.03 1,019,059,246.23 968,349,672.52 338,325,410.26

SEM1 SEM 2 SEM 3 SEM 4


INVERSION SEMANAL 986,148,178.43 1,182,108,725.63 1,123,285,620.12 392,457,475.90
INVERSION ACUMULADA 986,148,178.43 2,168,256,904.06 3,291,542,524.18 3,683,999,999.99

3.5E+09
CRONOGRAMA DE INVERSIÓN

3E+09
INVERSION (Bs .)

2.5E+09

2E+09

1.5E+09

1E+09

500000000

TIEMPO (SEMANAS)