BLOCO A

ENTREGA
LAJE BETONAGEM PREPARAÇÃO
MATERIAL

MUROS SUPORTE

FUNDAÇÕES

PISO TÉRREO 3/5/2021


14
LAJE PISO -1 3/19/2021
24
LAJE PISO 0 4/12/2021
18
LAJE PISO 1 4/30/2021
18
LAJE PISO 2 5/18/2021
13
LAJE PISO 3 5/31/2021
18
LAJE PISO 4 6/18/2021
14
LAJE PISO 5 7/2/2021
28
LAJE PISO 6 7/30/2021
70
LAJE COBERTURA 10/8/2021
5
Teto Caixa Escadas 10/13/2021
BLOCO B

ENTREGA
LAJE BETONAGEM PREPARAÇÃO
MATERIAL

MUROS SUPORTE

FUNDAÇÕES

PISO TÉRREO 1/4/2021


17
LAJE PISO -1 1/21/2021
27
LAJE PISO 0 2/17/2021
20
LAJE PISO 1 3/9/2021
17
LAJE PISO 2 3/26/2021
21
LAJE PISO 3 4/16/2021
21
LAJE PISO 4 5/7/2021
31
LAJE PISO 5 6/7/2021
21
LAJE PISO 6 6/28/2021
22
LAJE COBERTURA 7/20/2021
BLOCO C

ENTREGA
LAJE BETONAGEM PREPARAÇÃO
MATERIAL

FUNDAÇÕES -2

MUROS SUPORTE -1

PISO TÉRREO 0

LAJE PISO -1 1

LAJE PISO 0 2

LAJE PISO 1 9/30/2021 3


12
LAJE PISO 2 10/12/2021 4
14
LAJE PISO 3 10/26/2021 5
15
LAJE PISO 4 11/10/2021 6
15
LAJE PISO 5 11/25/2021 7
15
LAJE PISO 6 12/10/2021 8
15
LAJE COBERTURA 12/25/2021 9

Teto escadas 12/25/2021