Está en la página 1de 4

Learning Lessons Independent

Evaluation
February 2011

ADB’s Emergency and Rehabilitation Assistance


on Flood-Affected Areas
Background
The climate change phenomenon has contributed to severe curricula could be revisited to incorporate teaching modules
weather disturbances over the past years. Extremely heavy on disaster preparation. Disaster training sessions covering
precipitation, along with its concomitant consequences, has basic preparation, early warning signals, and emergency
been observed in many places, and such weather condition procedures should be offered to schools and communities.
is predicted to increase in frequency in the coming years. The government and its affiliated agencies must be prepared
The effects of this heavy precipitation are aggravated by to allocate resources to prepare user-friendly training manuals
its unpredictability and unequal geographical distribution. and references, as well as to train teachers to promote
Flooding and destructive runoffs are the end results of several awareness and enhance preparedness of the people in
factors, including sustained heavy downpour, inadequate disaster-prone areas.
drainage system, poor land-use planning, clogged waterways, To optimize the positive impact of rehabilitation
and decimated watersheds and water catchment areas, assistance, efforts should be made to rebuild at every
among others. The devastations caused by floods and opportunity with disaster-resistant construction. Rehabilitation
powerful surface runoffs are similar to the effects of other efforts should always consider upgrading the infrastructure
natural disasters, although they may vary in terms of their rather than merely restoring it to pre-disaster levels. The
magnitude and impacts. What is certain, however, is the current ADB policy for emergency assistance recommends
damage these disasters can inflict on vulnerable groups that disaster response and recovery support address both
of people. immediate short-term needs and long-term rehabilitation and
This synthesis provides key lessons drawn from reconstruction requirements.
evaluations and completion reports of the Asian Development The use of simplified procedures and approaches for
Bank (ADB)-supported emergency response and rehabilitation implementation has proved effective and has enabled quick
efforts in developing member countries affected by natural implementation of emergency rehabilitation projects. The
disasters, particularly floods. Users of this brief are advised to introduction of new ideas and untested approaches into
carefully review these lessons in the context of the conditions assistance programs should be carefully considered under
of their current emergency and rehabilitation operations. emergency assistance, as emergency conditions would not
allow sufficient time to plan, build capacity, and support such
programs long enough to bring about the required change
Highlights of Lessons that would mainstream the activities. Also, under emergency
Innovations in Disaster Risk Reduction and Mitigation conditions, the capacity of the government and its associated
Education can help promote disaster mitigation, protection agencies is frequently overstretched, and may not be able to
awareness, and disaster preparedness. Countless lives have provide sufficient attention and support to such programs.
been saved by the simple power of knowledge. National
Responsiveness of Financial Management
The procedures for fund disbursements of emergency
assistance should be tailored to take into account local
conditions, and systems and procedures to prevent large
implementation delays. Emergency assistance needs more
frequent monitoring and adaptation to provide opportunities
to rectify shortcomings, particularly in the early stages of
implementation. An emergency situation often prevents
most necessary data from being made available early, and the
ADB Photo Library

urgency and concomitant rush presiding over the formulation


of an emergency project can inevitably lead to mistakes.
Hence, implementation processes should adapt iteratively to
overcome challenges and shortcomings for project delivery to
become more effective.
Wooden boats ferry people to and from their flooded houses in Cambodia
The need for adequate maintenance of all restored To optimize impacts, there should be clarity
facilities must be addressed, and necessary budgetary support of purpose of disaster response programs,
must be provided so that these facilities can face potential
i.e., to alleviate the crisis and to prevent
threats of subsequent disasters. The government should be
encouraged to budget for necessary repair and maintenance things from getting worse; hence it must not
expenditures in its recurrent budget and, where appropriate, be mistaken for poverty reduction.
to mobilize local communities to maintain rehabilitated
As one of the core objectives of emergency response
infrastructure.
assistance is the immediate restoration of functions, disaster
For emergency projects, it is more important to rank response programs must avoid the pitfalls of concentrating
alternative potential interventions through simple benefit–cost too much resource on infrastructure rehabilitation at the
ratios. The ranking will determine the most cost-effective way expense of long-term adaptation and disaster preparedness
of carrying out emergency works, with efficiency consideration interventions. Disaster response programs could be examined
in the context of resource constraints. Concise and precise by whether they were formulated for relief, recovery, or
definitions of subprojects of emergency projects will facilitate rehabilitation purposes. By categorizing interventions, the
the quantification of costs and benefits for basic economic immediate, intermediate, and long-term needs of the affected
and financial analysis. For flood restoration works, subprojects area may be better understood. While such interventions
should be coordinated and designated based on a single may have spatial and temporal characteristics that promote
functional system. Stand-alone civil works should be avoided. differentiation, inherent overlaps on the scope and timing of
their implementation need to be considered.
Optimization of Results through Prioritization,
Selectivity, and Targeting Executing agencies should carefully study all possible
effects of an area intervention to its peripheral and adjacent
In order to cope with the speed at which emergency projects
areas in order to avoid creating negative impacts to
have to be designed and organized, countries experiencing
neighboring communities. For example, executing agencies
disasters could combine good knowledge of flood disaster
frequently tend to focus their efforts on resolving politically
characteristics with a facility for rapid release of funds in an
sensitive and pressing issues, such as flooding in an urban
emergency for carrying out temporary works. Despite the
center, without giving enough attention to the effects of
tight time frame, emergency response interventions should
the interventions in adjacent or downstream areas (e.g.,
not allow the inclusion of unsustainable or economically
downstream water volume and quality, and potential erosion
or socially unjustifiable subprojects. It is also desirable that
and sedimentation). Such attention should consider the views
a comprehensive flood action plan be formulated for the
of downstream communities. It is important to recognize and
development and implementation of a water and flood
address these issues up front to the extent possible, before
strategy in the long term. As much as possible, emergency
hurriedly embarking upon solving pressing issues, which
projects should focus on immediate restoration of functions
may entail serious downstream effects that can snowball
to (i) immediately provide relief to affected communities,
into larger problems.
(ii) restore economic activities, and (iii) reduce vulnerability
to potential future disasters. One of the key issues for social Leadership and Coordination
protection and risk mitigation is identifying the vulnerable
To establish accountability and responsibility, governments
groups. While it is not an easy task to identify vulnerable
should move quickly to clarify which agency or agencies will
groups since it relies on commonly agreed criteria and
coordinate and manage the post-disaster reconstruction
accurate data, neither of which may exist, the executing
program, what it is they are empowered to do, and when its/
agency may try partnering with knowledgeable civil society
their mandate(s) begin(s) and end(s). In the overall, a strong,
organizations that operate in the affected area to identify the
vulnerable groups.
To optimize positive impacts, there should be clarity
of purpose of disaster response programs, i.e., to alleviate
the crisis and to prevent things from getting worse; hence, it
must not be mistaken for poverty reduction. The considerable
overlap between these two objectives should be carefully
addressed in the assistance program/project design. Given
that some post-disaster needs may be associated with
poverty reduction, designers of crisis-related assistance should
ADB Photo Library

be aware that interventions chosen to meet a short-term


emergency need may not be sufficient to tackle the long-term
problems of chronic poverty. A separate menu of appropriate
interventions should be formulated to address the issues of
chronic poverty. Flooded highway, south of the city of Multan in Pakistan
experienced leadership team should be recruited and
Consultation with stakeholders is
appointed to gain the full support of government agencies
and providers of assistance. Implementation of complex essential to achieve local ownership,
projects, involving a large number of central and local increase participation, and make the
agencies, requires extra efforts in coordination and follow- best use of local knowledge.
up of activities among the parties involved. Aside from close Flexible approaches and procedures to ensure consultation and
coordination among the executing agencies and providers engagement of affected communities, during preparation and
of assistance, a flood management project using a sector- implementation, are required to facilitate the speedy processing
wide approach would also require a clear organizational and timely completion of emergency projects.
environment that unequivocally defines the roles and
responsibilities of all parties involved, and an effective flow Regular, proactive communication between partners
of information from and to all concerned parties. As a rule of should be maintained to manage beneficiary and stakeholder
thumb, the institutions that ultimately own the infrastructure expectations about the pace and progress of reconstruction.
and are responsible for its operation and maintenance To facilitate this, project design and formulation should include
should assume a dynamic role in the planning, design, and lead time to ensure that beneficiaries are organized (e.g.,
implementation of the project. to support the creation of beneficiary associations if none
already exist) and are ready to participate, and for personnel
Close coordination of multiple partners of executing and implementing agencies to be ready for the
is important to ensure that works and project.
programs are complementary, with Projects that involve multiple sectors and several
minimal overlaps or gaps in support. executing agencies should be coordinated through a common
project steering committee. Regular meetings among executing
Close coordination of multiple partners is important to and partner agencies can promote interactions that, ultimately,
ensure that works and programs are complementary, with lead to smooth and successful project implementation. The
minimal overlaps or gaps in support. An integrated project use of a sector approach can be very effective in identifying
with multiple technical agencies needs full-time project appropriate subprojects that are scattered over a wide area. A
management to address implementation problems effectively mechanism needs to be in place to enable funds reallocation
and efficiently, and to communicate and facilitate decision from one sector to another as the need arises.
making across components. Carefully planned logistics
and adequate arrangements for project management and Collaboration and Partnerships
personnel are necessary for effective project implementation, There are numerous experiences illustrating the merit of
supervision, and coordination. For example, as ADB-assisted a collaborative approach involving multiple development
emergency flood projects have shown, the delegation partners. Collaboration and partnership exemplify close donor
of authority to the ADB resident mission in the country is cooperation and harmonization. Projects formulated to respond
essential for close monitoring and speedy decision making. to an emergency can provide a valuable entry point for a range
It also helps if the program has simple and well-defined of follow-up development initiatives. To derive maximum
objectives. benefits from follow-up development initiatives, there is a
need to maintain effective dialogue with the government and
Stakeholder Participation and Consultation the broader community to share and act on development
Using a participatory approach, the community consultation opportunities. The ability to respond with timely technical
process must be initiated before undertaking the actual assistance or investment projects is necessary for capitalizing on
design of flood control infrastructure in order to ensure these opportunities.
that community needs are adequately addressed to avoid
countless design revisions resulting from beneficiaries’
objections. This would also allow evaluating, from the
beginning, the beneficiaries’ perceptions of the project as a
whole, as well as their preparedness, in principle, to participate
and contribute part of their resources in return for the
expected benefits. Community participation in operations and
maintenance activities may represent a cost-effective way to
save governments’ valuable resources.
ADB Photo Library

Consultation with stakeholders is essential to achieve


local ownership, increase participation, and make the best use
of local knowledge. Consultations need to commence early
to build understanding and ownership rather than to simply
resolve difficult issues when they arise during implementation. Community people building dikes in Bangladesh
Overall References
Considering the frequency and magnitude of flood-related ADB. 1996. Performance Evaluation Report: Flood Damage Restoration
disasters, there is a need for more efficient and effective Project in Pakistan. Manila. Available at www.adb.org/Documents/
delivery of disaster response assistance. Identified lessons PERs/PE472.pdf
____. 1996. Performance Evaluation Report: Flood Rehabilitation Project
have highlighted the need for
in Bangladesh. Manila. Available at www.adb.org/Documents/PERs/
n clarity in the objectives and priorities of disaster PE466.pdf
programs to optimize outcomes; ____. 2004. Disaster and Emergency Assistance Policy. Manila. Available at
www.adb.org/Documents/Policies/Disaster_Emergency/default.asp
n establishment of accountabilities and responsibilities ____. 2006. Performance Evaluation Report: Flood Damage Rehabilitation
among mandated agencies, thereby enhancing the Project in Bangladesh. Manila. Available at www.adb.org/
coordination, management, and delivery of disaster Documents/PPERs/BAN/32501-BAN-PPER.pdf
response assistance; ____. 2007. Completion Report: Klang River Basin Environmental
Improvement and Flood Mitigation in Malaysia. Manila. Available at
n adequacy of operation and maintenance provisions www.adb.org/Documents/PCRs/MAL/26009-MAL-PCR.pdf
and regulations for restored infrastructure and facilities ____. 2007. Completion Report: Second Flood Control Sector Project
to optimize their service life; in Pakistan. Manila. Available at www.adb.org/Documents/PCRs/
PAK/28165-PAK-PCR.pdf
n formulation of tailored and responsive financial ____. 2007. Completion Report: South Java Flood Control Sector Project
systems and procedures for efficient and timely in Indonesia. Manila. Available at www.adb.org/Documents/PCRs/
implementation of disaster programs; INO/29312-INO-PCR.pdf
____. 2007. Performance Evaluation Report: Emergency Flood
n careful study of the upstream and downstream effects Rehabilitation Project in Tajikistan. Manila. Available at
of disaster response programs to avoid creating www.adb.org/Documents/PPERs/TAJ/33248-TAJ-PPER.pdf
negative impacts to neighboring communities; and ____. 2007. Performance Evaluation Report: Flood Damage Rehabilitation
Project in Kyrgyz Republic. Manila. Available at www.adb.org/
n use of innovative yet simple disaster program Documents/PPERs/KGZ/32415-KGZ-PPER.pdf
implementation approaches to ensure the ____. 2008. Completion Report: Emergency Flood Damage Rehabilitation
effectiveness of assistance. Project in Bangladesh. Manila. Available at www.adb.org/
Documents/PCRs/BAN/38625-BAN-PCR.pdf
____. 2008. Validation Report: Second Flood Control Sector Project in
ADB, along with other development partners, continues Pakistan. Manila. Available at www.adb.org/Documents/Reports/
to assess the appropriateness and applicability of disaster Validation/PAK/in215-08.pdf
responses and mitigating measures. There is a tendency ____. 2008. Validation Report: South Java Flood Control Sector Project in
for disaster programs to focus more on infrastructure Indonesia. Manila. Available at www.adb.org/Documents/Reports/
Validation/INO/in216-08.pdf
rehabilitation than on adaptation and disaster preparedness.
____. 2009. Completion Report: Tsunami Emergency Assistance Project
Needs assessment will be made more difficult by variable in Maldives. Manila. Available at www.adb.org/Documents/PCRs/
geographical characteristics, as well as the uniqueness of the MLD/39099-mld-pcr.pdf
conditions (e.g., political, economic) in each disaster situation. ____. 2009. Validation Report: Emergency Flood Damage Rehabilitation
Overall, the context of the disaster situations, as well as the Project in Bangladesh. Manila. Available at www.adb.org/
inherent constraints to or limitations of the disaster response Documents/Reports/Validation/BAN/in423-09.pdf
operations, will dictate the appropriateness and applicability ____. 2010. Validation Report: Emergency Rehabilitation Project in Kyrgyz
of proposed disaster response interventions. Republic. Manila. Available at www.adb.org/documents/reports/
validation/KGZ/in363-10.pdf

Disclaimer
The views and assessments contained herein do not necessarily reflect the Learning Lessons are synthesis of key lessons drawn from evaluation and
views of the Asian Development Bank (ADB) or its Board of Directors or the completion reports of ADB-supported projects and programs. Lessons presented
governments they represent. ADB does not guarantee the accuracy of the data in this brief are not prescriptive, and users are advised to carefully review these
and accepts no responsibility for any consequence of their use. lessons in the context of country, sector, and thematic conditions. Lessons are
extracted from the Evaluation Information System (EVIS).
About the Asian Development Bank
ADB’s vision is an Asia and Pacific region free of poverty. Its mission is to help its Contact Us
developing member countries substantially reduce poverty and improve the Independent Evaluation Department
quality of life of their people. Despite the region’s many successes, it remains Asian Development Bank
home to two-thirds of the world’s poor: 1.8 billion people who live on less than 6 ADB Avenue, Mandaluyong City
$2 a day, with 903 million struggling on less than $1.25 a day. ADB is committed 1550 Metro Manila, Philippines
to reducing poverty through inclusive economic growth, environmentally Tel +63 2 632 4100
sustainable growth, and regional integration. Fax +63 2 636 2161
Based in Manila, ADB is owned by 67 members, including 48 from www.adb.org/evaluation
the region. Its main instruments for helping its developing member countries evaluation@adb.org
are policy dialogue, loans, equity investments, guarantees, grants, and technical
assistance.

También podría gustarte