PLAN DE UTILIZACION DEL ADELANTO PARA ADQUISICION E METERIALES E INSUMOS (FNANCIERA - PORCENTUAL)

OBRA : REHABILITACION DE LA INFRAESTRUCTURA DE LA I. E INICIAL N° 039 DEL CENTRO POBLADO PEDREGAL, DISTRITO DE TAMBOGRANDE - PROVINCIA DE PIURA - DEPARTAMENTO DE PIURA
LUGAR : PIURA - PIURA - TAMBO GRANDE
MODALIDAD : SUMA ALZADA
PLAZO : 150 DÍAS CALENDARIOS
VALOR REFERENCIAL : 2,452,498.59 inc IGV MONTO CONTRATADO : 2,207,248.74 inc IGV
FECHA DEL VALOR REFERENCIAL : 30 de Noviembre de 2020 S/0.00
ADELANTO P/MATERIALES (20.00% M.C.) : 441,449.75 inc IGV SUB PRESUPUESTO ESTRUCTURAS Y ARQUITECTURA

EXPEDIENTE TECNICO SUB. PRES. ESTRUCTURAS SUB. PRES. ARQUITECTURA ADELANTO SOLOCITADO

IU DESCRIPCIÓN UND CANTIDAD P.U. PARCIAL CANTIDAD P.U. PARCIAL CANTIDAD P.U. PARCIAL Jul-21 Ago-21 Nov-21 Dic-21 Ene-22 Feb-22 Mar-22 TOTAL SOLICITADO

43 MADERA TORNILLO p2 9,129.37 8.50 77,599.65 8,044.16 8.50 68,375.34 S/24,550.28 S/25,449.71 50,000.00

30 CALAMINON CU 06(CURVO) 1.08X180 E=0.4MM pln 265.40 120.37 31,946.20 265.40 120.37 31,946.20 S/13,691.23 S/18,254.61 31,945.84

05 PIEDRA CHANCADA 1/2" m3 254.77 100.00 25,477.00 205.76 100.00 20,575.65 S/6,005.00 S/12,249.00 S/2,321.65 20,575.65

21 CEMENTO PORTAND TIPO MS (42.5 kg) m3 4,471.00 22.00 98,362.00 2,965.67 22.00 65,244.75 S/25,015.12 S/36,039.57 S/4,190.06 65,244.75

ACERO Fy =4200 KG/CM2 (GRADO 60) kg 25,930.00 3.40 88,162.00 25,605.32 3.40 87,058.09 S/51,304.14 S/28,695.86 80,000.00
03
FIERRO LISO DE 1/2"x 6m var 471.45 26.52 12,502.85 431.06 26.52 11,431.82 S/8,798.74 8,798.74

43 MADERA CEDRO p2 3,828.15 13.90 53,211.29 3,828.15 13.90 53,211.29 S/40,000.00 40,000.00

17 LADRILLO KK TIPO IV 24X13X09 cm und 22,871.82 0.80 18,297.46 22,871.82 0.80 18,297.46 S/10,238.09 S/8,059.37 18,297.46

30 IMPRIMANTE gal 287.19 32.20 9,247.52 287.19 32.20 9,247.73 S/9,247.52 9,247.52

03 TUBO DE F° 2' X 2' und 995.78 72.56 72,253.80 995.78 72.56 72,253.80 S/50,000.00 50,000.00

COSTO DIRECTO S/ 487,059.77 284,631.85 153,010.28 S/ - S/ - S/ - S/ 106,874.54 S/ 112,672.24 S/ 87,061.05 S/ 67,502.13 S/ 374,109.96

IGV (18%) S/ 87,670.76 51,233.73 27,541.85 S/ - S/ - S/ - S/ 19,237.42 S/ 20,281.00 S/ 15,670.99 S/ 12,150.38 S/ 67,339.79

TOTAL S/ 574,730.53 335,865.58 180,552.13 S/ - S/ - S/ - S/ 126,111.96 S/ 132,953.24 S/ 102,732.04 S/ 79,652.51 S/ 441,449.75

PORCENTAJE PARCIAL 0.00% 0.00% 28.57% 30.12% 23.27% 18.04% 100.00%