MUNICIPALIDAD PROVINCIAL DE COTABAMBAS TAMBOBAMBA - APURIMAC

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO


ACTIVIDAD: "MANTENIMIENTO RUTINARIO DE CAMINOS VECINALES EN LOS TRAMOS CCASACANCHA - PACLA PACLA Y ACCESO AL SECTOR DE CCACCAHUASI
DEL DISTRITO DE TAMBOBAMBA - COTABAMBAS - APURIMAC"

ENE 22 A FEB 22 MARZO 2022 (11 dias) ABRIL 2022 (25 dias) ACUMULADO
Item Descripcion Und Metrado Precio S/. Parcial (S/.)
Parcial (S/.) Porc(%) Parcial (S/.) Porc(%) Parcial (S/.) Porc(%) Parcial (S/.) Porc(%)
01 CCASACANCHA PACLA PACLA L=2.67Km 53,657.13 36,438.97 67.91% 17,218.16 32.09% 53,657.13 100.00%
01.01 OBRAS PROVISIONALES 6,189.20 6,189.20 100.00% 6,189.20 100.00%
01.01.01 MOVILIZACION DE MAQUINARIAS HERRAMIENTAS PARA LA OBRA GBL 1.00 5,120.00 5,120.00 5,120.00 5,120.00 100.00%
01.01.02 CONSTRUCCION DE CASETA m2 36.00 29.70 1,069.20 1,069.20 100.00% 1,069.20 100.00%
01.02 OBRAS PRELIMINARES 8,008.08 8,008.08 100.00% 8,008.08 100.00%
01.02.01 LIMPIEZA DEL TERRENO MANUAL Km 36.00 173.28 6,238.08 6,238.08 100.00% 6,238.08 100.00%
01.02.02 EQUIPO DE PROTECCION INDIVIDUAL glb 1.00 1,770.00 1,770.00 1,770.00 100.00% 1,770.00 100.00%
01.03 MOVIMIENTO DE TIERRAS 20,493.85 8,933.31 43.59% 11,560.54 56.41% 20,493.85 100.00%
01.03.01 LIMPIEZA DE MATERIAL DE DERRUMBE m2 1,332.50 4.44 5,916.30 5,916.30 100.00% 5,916.30 100.00%
01.03.02 ELIMINACION DE MATERIAL DE DERRUMBE D=4Km (CON MAQUINARIm3 201.00 15.01 3,017.01 3,017.01 100.00% 3,017.01 100.00%
01.03.03 NIVELADO Y PERFILADO CON MAQUINARIA m2 2,586.25 4.47 11,560.54 11,560.54 100.00% 11,560.54 100.00%
01.04 OBRAS DE ARTE 18,966.00 13,308.38 70.17% 5,657.62 29.83% 18,966.00 100.00%
01.04.01 CUNETAS 2,109.30 2,109.30 100.00% 2,109.30 100.00%
01.04.01.0 LIMPIEZA DE CUNETAS m2 267.00 1.24 331.08 331.08 100.00% 331.08 100.00%
01.04.01.0 CORTE Y PERFILADO DE CUNETAS m2 534.00 3.33 1,778.22 1,778.22 100.00% 1,778.22 100.00%
01.04.02 ENRROCADO 16,856.70 13,308.38 78.95% 3,548.32 21.05% 16,856.70 100.00%
01.04.02.0 EXCAVACIÓN DE ZANJA C/MAQUINARIA EN TERRENO CONGLOME m3 230.00 9.83 2,260.90 2,260.90 100.00% 2,260.90 100.00%
01.04.02.0 PREPARADO Y TRANSPORTE DE PIEDRA GRANDE PARA ENROCA m3 230.00 31.68 7,286.40 7,286.40 100.00% 7,286.40 100.00%
01.04.02.0 ENROCADO CON PIEDRA GRANDE m2 460.00 15.89 7,309.40 3,761.08 51.46% 3,548.32 48.54% 7,309.40 100.00%
02 ACCESO A OCRABAMBA L=2.90Km 45,541.21 11,869.34 26.06% 33,671.87 73.94% 45,541.21 100.00%
02.01 OBRAS PROVISIONALES 5,654.60 5,654.60 100.00% 5,654.60 100.00%
02.01.01 MOVILIZACION DE MAQUINARIAS HERRAMIENTAS PARA LA OBRA GBL 1.00 5,120.00 5,120.00 5,120.00 100.00% 5,120.00 100.00%
02.01.02 CONSTRUCCION DE CASETA m2 18.00 29.70 534.60 534.60 100.00% 534.60 100.00%
02.02 OBRAS PRELIMINARES 4,889.04 4,694.10 96.01% 194.94 3.99% 4,889.04 100.00%
02.02.01 LIMPIEZA DEL TERRENO MANUAL Km 18.00 173.28 3,119.04 2,924.10 93.75% 194.94 6.25% 3,119.04 100.00%
02.02.02 EQUIPO DE PROTECCION INDIVIDUAL glb 1.00 1,770.00 1,770.00 1,770.00 100.00% 1,770.00 100.00%
02.03 MOVIMIENTO DE TIERRAS 30,078.49 30,078.49 100.00% 30,078.49 100.00%
02.03.01 LIMPIEZA DE DERRUMBE CON MAQUINARIA PESADA m2 2,940.00 4.44 13,053.60 13,053.60 100.00% 13,053.60 100.00%
02.03.02 ELIMINACION DE MATERIAL DE DERRUMBE D=4Km (CON MAQUINARIm3 161.17 15.01 2,419.16 2,419.16 100.00% 2,419.16 100.00%
02.03.03 NIVELADO Y PERFILADO CON MAQUINARIA m2 3,267.50 4.47 14,605.73 14,605.73 100.00% 14,605.73 100.00%
02.04 OBRAS DE ARTE 4,919.08 1,520.64 30.91% 3,398.44 69.09% 4,919.08 100.00%
02.04.01 CUNETAS 2,291.00 2,291.00 100.00% 2,291.00 100.00%
02.04.01.0 LIMPIEZA DE CUNETAS m2 290.00 1.24 359.60 359.60 100.00% 359.60 100.00%
02.04.01.0 CORTE Y PERFILADO DE CUNETAS m2 580.00 3.33 1,931.40 1,931.40 100.00% 1,931.40 100.00%
02.04.02 ENRROCADO 2,628.08 1,520.64 57.86% 1,107.44 42.14% 2,628.08 100.00%
02.04.02.0 EXCAVACIÓN DE ZANJA C/MAQUINARIA EN TERRENO CONGLOME m3 48.00 9.83 471.84 471.84 100.00% 471.84 100.00%
02.04.02.0 PREPARADO Y TRANSPORTE DE PIEDRA GRANDE PARA ENROCA m3 48.00 31.68 1,520.64 1,520.64 100.00% 1,520.64 100.00%
02.04.02.0 ENROCADO CON PIEDRA GRANDE m2 40.00 15.89 635.60 635.60 100.00% 635.60 100.00%

COSTO DIRECTO 99,198.34 48,308.31 48.70% 50,890.03 51.30% 99,198.34 100.00%

GASTOS GENERALES 35.33% 35,045.76 17,066.83 48.70% 17,978.92 51.30% 35,045.76 100.00%
GASTOS SUPERVISIÓN 7.21% 7,148.91 3,481.43 48.70% 3,667.48 51.30% 7,148.91 100.00%

SUB TOTAL S/. 141,393.01 68,856.57 48.70% 72,536.43 51.30% 141,393.01 100.00%

COSTOS DE EXPEDIENTE TECNICO 5.42% 5,372.00 5,372.00 0.00 0.00% 0.00 0.00% 5,372.00 0.00%
MUNICIPALIDAD PROVINCIAL DE COTABAMBAS TAMBOBAMBA - APURIMAC

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO


ACTIVIDAD: "MANTENIMIENTO RUTINARIO DE CAMINOS VECINALES EN LOS TRAMOS CCASACANCHA - PACLA PACLA Y ACCESO AL SECTOR DE CCACCAHUASI
DEL DISTRITO DE TAMBOBAMBA - COTABAMBAS - APURIMAC"

ENE 22 A FEB 22 MARZO 2022 (11 dias) ABRIL 2022 (25 dias) ACUMULADO
Item Descripcion Und Metrado Precio S/. Parcial (S/.)
Parcial (S/.) Porc(%) Parcial (S/.) Porc(%) Parcial (S/.) Porc(%) Parcial (S/.) Porc(%)
PRESUPUESTO TOTAL S/. 146,765.01 5,372.00 68,856.57 72,536.43 146,765.01
PORCENTAJE DE AVANCE % 46.92% 49.42% 100.00%
MUNICIPALIDAD PROVINCIAL DE COTABAMBAS TAMBOBAMBA - APURIMAC

CRONOGRAMA DE DESEMBOLSOS DE INSUMOS Y MANO DE OBRA


MANTENIMIENTO A NIVEL DE AFIRMADO DE PISTAS PARA PROTECCION DEL COLECTOR PRINCIPAL DEL SISTEMA DE ALCANTARRILLADO EN EL CENTRO POBLADO DE PUMAMARCA - PROVINCIA DE COTABAMBAS - DISTRITO DE TAMBOBAMBA - APURIMAC
Fecha presupuesto: 11/15/2019
SEMANA 01 SEMANA 02 SEMANA 03 SEMANA 04 SEMANA 05 SEMANA 06
Recurso Unidad Cantidad Precio S/. Parcial S/.
Parcial (S/.) Porc(%) Parcial (S/.) Porc(%) Parcial (S/.) Porc(%) Parcial (S/.) Porc(%) Parcial (S/.) Porc(%) Parcial (S/.) Porc(%)
MANO DE OBRA 106,419.13 8,707.59 8.18% 14,407.01 13.54% 30,038.70 28.23% 11,781.81 11.07% 12,371.66 11.63% 29,112.36 27.36%
OPERADOR DE EQUIPO PESADO hh 1,272.47 15.29 19,456.12 260.01 1.34% 1,479.00 7.60% 7,656.32 39.35% 2,272.31 11.68% 5,435.46 27.94% 2,353.02 12.09%
TOPOGRAFO hh 392.17 14.97 5,870.75 646.72 11.02% 3,268.79 55.68% - 1,955.24 33.30% - -
OPERARIO hh 616.55 15.29 9,426.99 1,172.29 12.44% - 2,845.32 30.18% 1,226.72 13.01% 657.22 6.97% 3,525.44 37.40%
OFICIAL hh 440.42 12.07 5,315.92 448.40 8.44% - 1,623.56 30.54% 284.83 5.36% 1,669.28 31.40% 1,289.85 24.26%
PEON hh 6,488.98 8.59 55,740.37 6,180.17 11.09% 8,488.42 15.23% 13,155.78 23.60% 4,833.88 8.67% 3,121.74 5.60% 19,960.38 35.81%
CONTROLADOR OFICIAL hh 878.95 12.07 10,608.98 1,170.80 11.04% 4,757.72 44.85% 1,208.83 11.39% 1,487.96 14.03% 1,983.67 18.70%
MATERIALES 207,727.47 28,005.40 13.48% 16,183.49 7.79% 81,736.46 39.35% 37,603.06 18.10% 15,112.02 7.27% 29,087.04 14.00%
LUBRICANTE PARA TUBERIA PVC gln 0.26 32.00 8.16 0.94 11.52% 7.22 88.48%
ALAMBRE NEGRO RECOCIDO # 16 kg 3.28 5.20 17.07 17.07 100.00%
ALAMBRE NEGRO RECOCIDO # 8 kg 30.18 5.20 156.95 39.01 24.86% 117.94 75.14%
CLAVOS PARA MADERA C/C 3" kg 203.10 5.20 1,056.11 5.20 0.49% 515.90 48.85% 506.69 47.98% 1.98 0.19% 26.34 2.49%
CLAVOS PARA MADERA C/C 4" kg 37.23 5.00 186.13 186.13 100.00%
CLAVOS PARA MADERA C/C 3" kg 37.23 5.00 186.13 186.13 100.00%
GIGANTOGRAFIA und 1.00 250.00 250.00 250.00 100.00%
ACERO DE REFUERZO FY=4200 GRADO 60 kg 169.08 4.90 828.52 828.52 100.00%
ARENA FINA m3 1.79 220.00 392.70 48.35 12.31% 344.35 87.69%
PIEDRA CHANCADA DE3/4" m3 10.50 180.00 1,890.32 1,890.32 100.00%
PIEDRA MEDIANA DE 6" m3 0.30 150.00 45.00 45.00 100.00%
ARENA GRUESA m3 8.97 180.00 1,615.48 1,615.48 100.00%
PIEDRA MEDIANA m3 1.34 80.00 106.92 106.92 100.00%
PIEDRA GRANDE m3 24.75 80.00 1,980.00 1,980.00 100.00%
ALCANTARILLA TMC D=24", E=2MM m 185.85 290.00 53,896.50 44,912.78 83.33% 8,983.72 16.67%
CACHIMBA PVC SAL DE 8" x 6" und 15.00 27.00 405.00 50.73 12.53% 354.27 87.47%
PLACA RECORDATORIA DE ALUMINIO DE 60 X 80 CM. und 1.00 650.00 650.00 650.00 100.00%
TUBERIA PVC SAP PRESION C-10 C/R. DE 1/2" x 5 m. und 15.00 12.00 180.00 22.54 12.52% 157.46 87.48%
CEMENTO PORTLAND TIPO I (42.5KG) BOL 153.12 28.00 4,287.23 458.60 10.70% 539.47 12.58% 3,289.16 76.72%
YESO kg 73.72 14.00 1,032.02 113.69 11.02% 574.62 55.68% 341.07 33.05% 2.64 0.26%
CINTA TEFLON und 15.00 1.50 22.50 2.82 12.53% 19.68 87.47%
BOTIQUIN und 1.00 360.00 360.00 360.00 100.00%
EXTINGUIDOR und 1.00 350.00 350.00 350.00 100.00%
PEGAMENTO PARA PVC AGUA FORDUIT gln 0.12 120.00 14.40 2.22 15.42% 12.18 84.58%
CAJA DE REGISTRO C° PARA DESAGUE und 30.00 35.00 1,050.00 131.25 12.50% 918.75 87.50%
CAJA DE REGISTRO C° PARA AGUA und 30.00 35.00 1,050.00 131.25 12.50% 918.75 87.50%
FLETE GLB 1.00 6,398.00 6,398.00 2,239.30 35.00% 2,239.30 35.00% 1,919.40 30.00%
MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 12,240.00 12,240.00 10,710.00 87.50% 1,530.00 12.50%
GASOLINA 84 OCTANOS gln 4.25 15.00 63.73 63.73 100.00%
HORMIGON m3 5.96 120.00 714.72 714.72 100.00%
AGUA m3 307.87 1.00 307.87 30.47 9.90% 7.31 2.37% 263.10 85.46% 6.99 2.27%
MATERIAL DE ENSEÑANZA EN SEGURIDAD DURANTE LA OBRA GLB 1.00 750.00 750.00 750.00 100.00%
TAPA METALICA PARA MEDIDOR DE AGUA DE 12" x 12" und 15.00 35.00 525.00 65.76 12.53% 459.24 87.47%
TAPA DE FºFº PARA DESAGUE DE 12" x 24" und 15.00 50.00 750.00 93.94 12.53% 656.06 87.47%
TAPA DE CONCRETO ARMADO PARA BUZON d=0.60 m, INCLUIDO und 16.00 320.00 5,120.00
5,120.00 100.00%
ANILLO
MADERA TORNILLO p2 268.02 4.50 1,206.09 1,206.09 100.00%
ROLLIZO DE EUCALIPTO DE 6" X 3 M pza 17.87 25.00 446.70 446.70 100.00%
MADERA EUCALIPTO ROLLIZO 4"X4" und 2.00 16.00 32.00 32.00 100.00%
MADERA PARA ENCOFRADO p2 456.32 4.50 2,053.46 540.00 26.30% 1,513.46 73.70%
MADERA TORNILLO CEPILLADA p2 12.00 7.20 86.40 86.40 100.00%
TRIPLAY 4 X 8 X 6 MM. pln 3.00 45.00 135.00 135.00 100.00%
PETROLEO gln 5,596.12 14.50 81,143.69 775.75 0.96% 4,334.57 5.34% 31,640.60 38.99% 25,846.70 31.85% 13,346.51 16.45% 5,199.56 6.41%
PINTURA ESMALTE gln 58.97 65.00 3,833.22 422.52 11.02% 2,134.07 55.67% 1,266.92 33.05% 9.71 0.25%
CALAMINA # 31 DE 1.83m x 0.83m x 2.7mm pza 57.23 27.00 1,545.08 1,545.08 100.00%
ZARANDA METALICA DE FIERRO CORUGADO DE 1", DE und 1.52 5,300.00 8,056.53
3.00X3.00 1,060.07 13.16% 3,763.25 46.71% 3,233.21 40.13%
MUNICIPALIDAD PROVINCIAL DE COTABAMBAS TAMBOBAMBA - APURIMAC

CRONOGRAMA DE DESEMBOLSOS DE INSUMOS Y MANO DE OBRA


MANTENIMIENTO A NIVEL DE AFIRMADO DE PISTAS PARA PROTECCION DEL COLECTOR PRINCIPAL DEL SISTEMA DE ALCANTARRILLADO EN EL CENTRO POBLADO DE PUMAMARCA - PROVINCIA DE COTABAMBAS - DISTRITO DE TAMBOBAMBA - APURIMAC
Fecha presupuesto: 11/15/2019
SEMANA 01 SEMANA 02 SEMANA 03 SEMANA 04 SEMANA 05 SEMANA 06
Recurso Unidad Cantidad Precio S/. Parcial S/.
Parcial (S/.) Porc(%) Parcial (S/.) Porc(%) Parcial (S/.) Porc(%) Parcial (S/.) Porc(%) Parcial (S/.) Porc(%) Parcial (S/.) Porc(%)
TUBERIA PVC DE U.F. DE 6" x 6m. (INC. ANILLO) und 15.00 170.00 2,550.00 319.39 12.53% 2,230.61 87.47%
ABRAZADERA DE FIERRO FUNDIDO DE 3" a 1/2" pza 15.00 29.00 435.00 54.48 12.52% 380.52 87.48%
VALVULA CORPORATION BRONCE 1/2 S/R und 15.00 12.00 180.00 22.54 12.52% 157.46 87.48%
GUANTES DE LONA PAR 22.00 10.00 220.00 220.00 100.00%
CASCO DE SEGURIDAD DE COLORES und 22.00 35.00 770.00 770.00 100.00%
GUANTES DE JEBE PAR 8.00 10.00 80.00 80.00 100.00%
MIRAS Y JALONES hm 392.17 5.00 1,960.84 216.01 11.02% 1,091.78 55.68% 650.65 33.18% 2.40 0.12%
CHALECOS CON CINTAS DE MATERIAL REFLECTIVO und 22.00 25.00 550.00 550.00 100.00%
PONCHO IMPERMEABLE PARA LLUVIA und 22.00 20.00 440.00 440.00 100.00%
ZAPATO DE CUERO CON PUNTA DE ACERO Nº 38 - 42 PAR 22.00 70.00 1,540.00 1,540.00 100.00%
CINTA DE SEÑALIZACION AMARILLA und 3.00 50.00 150.00 150.00 100.00%
CINTA DE SEÑALIZACION ROJA und 3.00 50.00 150.00 150.00 100.00%
MALLA DE SEGURIDAD PVC REFORZADA rll 2.00 100.00 200.00 200.00 100.00%
CONO GRANDE COLOR NARANJA CON CINTA REFLECTIVA und 3.00 35.00 105.00 105.00 100.00%
SEÑAL VERTICAL INFORMATIVA (Uso durante la ejecucion de obra) und 5.00 20.00 100.00 100.00 100.00%
SEÑAL VERTICAL PREVENTIVA (Uso durante la ejecucion de obra) und 5.00 20.00 100.00 100.00 100.00%
SEÑAL VERTICAL RESTRICTIVA (Uso durante la ejecucion de obra) und 5.00 20.00 100.00 100.00 100.00%
BOTAS DE JEBE 38 - 42 PAR 8.00 40.00 320.00 320.00 100.00%
LENTES DE SEGURIDAD und 22.00 10.00 220.00 220.00 100.00%
MASCARILLA ANTIPOLVO und 22.00 6.00 132.00 132.00 100.00%
EQUIPOS 8,364.84 523.29 6.26% 1,661.86 19.87% 1,800.10 21.52% 2,332.91 27.89% 790.57 9.45% 1,256.11 15.02%
HERRAMIENTAS MANUALES %MO 3,457.11 290.09 8.39% 472.28 13.66% 1,004.15 29.05% 394.34 11.41% 388.69 11.24% 907.56 26.25%
VOLQUETE DE 15 M3 hm 562.79 1.00 562.79 216.56 38.48% 314.05 55.80% 0.23 0.04% 31.95 5.68%
CAMION CISTERNA 4X2 (AGUA) 1,500 GAL. hm 182.70 1.00 182.70 97.64 53.44% 24.41 13.36% 60.65 33.20%
COMPRESORA NEUMATICA 196 HP 600-690 PCM hm 3.60 25.00 90.00 90.00 100.00%
COMPACTADOR VIBR. TIPO PLANCHA 5.8 HP hm 67.66 15.00 1,014.86 124.04 12.22% 889.02 87.60% 1.80 0.18%
RODILLO LISO VIBR AUTOP 101-135HP 10-12T hm 244.09 1.00 244.09 97.64 40.00% 24.40 10.00% 122.05 50.00%
CARGADOR S/LLANTAS 125 HP 2.5 YD3. hm 76.80 1.00 76.80 54.41 70.85% 14.27 18.58% 0.07 0.09% 8.05 10.48%
RETROEXCAVADOR S/LLANTAS 58 HP 1 YD3. hm 331.84 1.00 331.84 17.19 5.18% 97.80 29.47% 108.02 32.55% 108.83 32.80%
VIBRADOR DE CONCRETO 4 HP 2.40" hm 6.49 10.00 64.93 - 64.93 100.00%
MOTONIVELADORA DE 125 HP hm 244.09 1.00 244.09 97.64 40.00% 24.40 10.00% 122.05 50.00%
MEZCLADORA CONCRETO TAMBOR 18HP 11P3 hm 8.99 15.00 134.79 134.79 100.00%
NIVEL HE 392.17 5.00 1,960.84 216.01 11.02% 1,091.78 55.68% 648.02 33.05% 5.03 0.26%
SERVICIOS 58,405.00 16,039.83 27.46% 12,139.83 20.79% 12,139.83 20.79% 13,129.81 22.48% 4,100.70 7.02% 855.00 1.46%
SERVICIO HIGIENICO PROVISIONAL und 2.00 750.00 1,500.00 1,500.00 100.00%
MANTENIMIENTO DE MAQUINARIAS GLB 1.00 52,000.00 52,000.00 12,139.83 23.35% 12,139.83 23.35% 12,139.83 23.35% 12,139.81 23.35% 3,440.70 6.62%
ENSAYO DE CANTERA und 1.00 1,500.00 1,500.00 1,500.00 100.00%
ENSAYO DE DENSIDAD DE CAMPO (SUB RASANTE) und 33.00 30.00 990.00 990.00 100.00%
PRUEBA DE DENSIDAD DE CAMPO (BASE) und 33.00 30.00 990.00 660.00 66.67% 330.00 33.33%
DISEÑO DE MEZCLA DE CONCRETO und 2.00 450.00 900.00 900.00 100.00%
PRUEBAS DE CALIDAD DE CONCRETO (ROTURA DE BRIQUETAS) und 15.00 35.00 525.00
525.00 100.00%

COSTO DIRECTO 380,916.44 53,276.11 13.99% 44,392.19 11.65% 125,715.09 33.00% 64,847.59 17.02% 32,374.95 8.50% 60,310.51 15.83%